By: Date: Federal Aviation Administration Surveillance and Broadcast Services ASAS in NextGen...
-
date post
21-Dec-2015 -
Category
Documents
-
view
218 -
download
1
Transcript of By: Date: Federal Aviation Administration Surveillance and Broadcast Services ASAS in NextGen...
By:
Date:
Federal AviationAdministrationSurveillance and
Broadcast Services
ASAS in NextGen
Roberta Massiah
April 24, 2007
2 2Federal AviationAdministration
Surveillance and Broadcast ServicesApril 24, 2007
Agenda
• Transition to NextGen• Initial Applications• Benefits• Future Applications
– Balancing – Prioritization – Qualitative Score Sheet
• Next Steps
3 3Federal AviationAdministration
Surveillance and Broadcast ServicesApril 24, 2007
Realizing NextGenNextGen
NextGen
Trajectory-Based Operations
Aircraft Data Communications
Performance-Based
Operations and Services
Separation Management
Collaborative TFM
Precision Navigation
Weather Integration
Surveillance Services
Network-Centric
Information Sharing
Trajectory-Based Operations
Aircraft Data Communications
Performance-Based
Operations and Services
Separation Management
Collaborative TFM
Precision Navigation
Weather Integration
Surveillance Services
Network-Centric
Information Sharing
Key Near-Term Investments Key Near-Term Investments
ERAM EnhancementsAutomated Problem Resolution
Concept DemonstrationsTrajectory-Based Ops/High Density
Infrastructure Robust Flow of Information
TFM-M EnhancementsTime-Based Metering
Terminal EnhancementsMerging and Spacing Tools
RNP/RNAV ExpansionPrecise Navigation
Data CommunicationsFlight Intent Downlink
ADS-BAircraft Separation
SWIM/Net-Enabled WeatherNet-Centric Information Sharing
ERAM EnhancementsAutomated Problem Resolution
Concept DemonstrationsTrajectory-Based Ops/High Density
Infrastructure Robust Flow of Information
TFM-M EnhancementsTime-Based Metering
Terminal EnhancementsMerging and Spacing Tools
RNP/RNAV ExpansionPrecise Navigation
Data CommunicationsFlight Intent Downlink
ADS-BAircraft Separation
SWIM/Net-Enabled WeatherNet-Centric Information Sharing
ERAM
TFM-M
STARS/CARTS
RNP/RNAV
Airspace Mgmt Program
Initial ADS-B
Initial SWIM
ERAM
TFM-M
STARS/CARTS
RNP/RNAV
Airspace Mgmt Program
Initial ADS-B
Initial SWIM
Current ProgramsCurrent Programs
4 4Federal AviationAdministration
Surveillance and Broadcast ServicesApril 24, 2007
Background: Initial ADS-B ServicesFY2007- FY2010
Services: ASAS / RFG Conversion
Surveillance Broadcast Services (en route, terminal, surface)
- Airport surface surveillance (ADS-B-APT)
- ATC surveillance in non-radar airspace (ADS-B-NRA)
- ATC surveillance in radar areas (ADS-B-RAD)
- Aircraft derived data for ground tools (ADS-B-ADD)
Traffic Information Broadcast Services - Enhanced traffic situational awareness during flight operations (ATSA-AIRB)
Flight Information Broadcast Services Not applicable
Link to Initial Services and Applications Detail
5 5Federal AviationAdministration
Surveillance and Broadcast ServicesApril 24, 2007
Background: Initial ADS-B ApplicationsFY2007- FY2010
FAA Applications: ASAS / RFG Conversion
Enhanced Visual Acquisition - Enhanced traffic situational awareness during flight operations (ATSA-AIRB)
Enhanced Visual ApproachesIncludes:• Merging and Spacing• Cockpit Display of Traffic Information (CDTI) Assisted Visual Separation (CAVS)
- Enhanced visual separation on approach (ATSA-VSA)• Merging and Spacing and CAVS are not applicable
Final Approach and Runway Occupancy Awareness
- Enhanced traffic situational awareness on the airport surface (ATSA-SURF)
Airport Surface Situational Awareness - Enhanced traffic situational awareness on the airport surface (ATSA-SURF)
Conflict Detection - Enhanced traffic situational awareness during flight operations (ATSA-AIRB)
Link to Initial Services and Applications Detail
6 6Federal AviationAdministration
Surveillance and Broadcast ServicesApril 24, 2007
Sample Initial Applications
Enhanced Visual Acquisition
Climb/descent rate
Selected Target
Selected Target Info
Closure Rate
RangeIndication
Enhanced Visual Approach
7 7Federal AviationAdministration
Surveillance and Broadcast ServicesApril 24, 2007
Quantified Benefits for Initial Applications
FAA Application Outcome
Risk Adjusted Benefit
(BY07$M)
Radar Airspace ATC Surveillance
Surveillance cost avoidance $1,225.9
More efficient spacing on approach in IMC and MVMC by reducing the spacing buffer
$1,519.3
Increased safety on the surface by controllers $14.2
More efficient ATC management of surface movement $87.0
Enhanced Visual Acquisition and Conflict Detection Fewer aircraft-to-aircraft conflicts $569.2
Weather and NAS Status Situational Awareness
Fewer encounters with hazardous weather $1,052.6
More efficient routes in adverse weather $12.2
Fewer aircraft-to-terrain conflicts $749.4
Enhanced Visual Approach - Initial Application More efficient spacing on approach in VMC $1,356.8
Enhanced Visual Approach - CAVS Continuation of visual approaches in marginal conditions $603.3
Enhanced Visual Approach - Merging and Spacing Increased ability to perform continuous descent
approaches$2,329.6
ADS-B ATC Automation Integration
Airport Surface Situational Awareness More efficient movement on surface by pilots $782.7
Final Approach and Runway Occupancy Awareness Increased safety on the surface by pilots $313.7
Total $10,615.9
8 8Federal AviationAdministration
Surveillance and Broadcast ServicesApril 24, 2007
Future ApplicationsFAA Applications: ASAS / RFG Conversion
CDTI / MFD Assisted Visual Separation Not applicable
Merging and Spacing Not applicable
In-Trail Procedure in Oceanic Airspace - In-trail procedure in oceanic airspace (ATSA-ITP)1,2
- In-trail procedure in oceanic airspace (ASEP-ITP)1
Approach Spacing for Instrument Approaches
Not applicable
Enhanced Sequencing and Merging - Sequencing and merging operations (ASPA-S&M)1,2
- Sequencing and merging operations (ASEP-S&M)1
Independent Closely Spaced Parallel Approaches
Not applicable
1 – ASAS Application; 2 – RFG Application
Link to Future Applications Detail
9 9Federal AviationAdministration
Surveillance and Broadcast ServicesApril 24, 2007
Future ApplicationsFAA Applications: ASAS / RFG Conversion
Airborne Conflict Management - Self separation in segregated free flight airspace (SSEP-FFAS)1
- Self separation in managed airspace (SSEP-MAS)1
- Organized track system (SSEP-FFT)1
Paired Approach Not applicable
Not applicable - Enhanced crossing and passing operations (ASPA-C&P) 1,2
Not applicable - Lateral crossing and passing (ASEP-LC&P)1
Not applicable - Vertical crossing and passing (ASEP-VC&P)1
Not applicable - In-trail follow (ASEP-ITF)1
1 – ASAS Application; 2 – RFG Application
Link to Future Applications Detail
10 10Federal AviationAdministration
Surveillance and Broadcast ServicesApril 24, 2007
Selection Approach
System Effectiveness
Lifecycle Cost
• Research, design, and development cost
•Construction cost
•Production cost
•System operation cost
•Maintenance and support cost
•Retirement, material recycling, and disposal cost
• System performance
•Availability, dependability, reliability, maintainability, and supportability
•Constructability
•Human Factors
•System quality
•Disposability
•Other technical factors
11 11Federal AviationAdministration
Surveillance and Broadcast ServicesApril 24, 2007
Prioritization
Deploy
DiscoverDecide
Develop
Steps we take to screen the many ideas we could pursue and narrow them down to the select portfolio(s) we will pursue with our limited resources
The work we do as we execute the selected array of applications, which taken together, produce the capabilities we need
Activities to ensure that the innovations we develop are effectively applied to produce value for the airspace users
All the things we do to explore and understand our applications,
opportunities, the directions we could choose to pursue in
addressing our airspace needs
Scorecard
Simulation
Concept Exploration
Air to Air Applications
Capacity Cost Avoidance
Efficient Spacing
Efficient Routes in Adverse Weather
Efficient ATC Surface
Management
Efficient Pilot
Surface Movement
Efficiency Subscore
Reduced A/C to A/C
Conflicts
Reduced Hazardous Weather
Encounters
Reduced A/C to Terrain Conflict
Improved Search
and Rescue Services
Increased Medevac Access
Safety Subscore
Improved Separation Standards
Reduced Legacy Investment
ATC PilotUser
ANSP
Risk Rating
Likelihood Consequence:
Assessment: Additional risk assessment should be based on the Likelihood and Consequence tables below. Choose a level of Likelihood (A – E) based on the probability of the risk occurring (A being the lowest and E the highest). Then, rate the impact of the risk occurrence (1 being the lowest and 5 the highest).
Regulatory Impact Environmental Impact Political Impact
ANSP
ANSP Subscore
Payback Period
Aircraft Retrofit
User
Avionics Upgrade User Cost Subscore
Description: Insert operational description of the proposed application
Score
3.0 Risk
1.0 User Demand: State whether the application demand is by the user, an ANSP, or both.
Safety
ATC Workforce Automation Impact
Surface Safety
Efficiency
2.0 Reward Criteria:
Business Case Benefits Criteria
Business Case Cost Criteria
Application: Insert application name, including RFG / ASAS Conversion (if applicable)
E
D
C
B
A
1 2 3 4 5
Low Medium High
Lik
elih
oo
d
Consequence Will effectively avoid or mitigate this risk based on standard practices
Low/ Not Likely
A
Have usually mitigated this type of risk with minimal oversight in similar cases
Minor/ Low Likelihood
B
May mitigate this risk, but workarounds will be required
Moderate/ Likely
C
Cannot mitigate this risk, but a different approach might
Significant/ Highly Likely
D
Cannot mitigate this type of risk; no known processes or alternatives are available
High/ Near Certainty
E
Existing Approach…DescriptionLevel
Will effectively avoid or mitigate this risk based on standard practices
Low/ Not Likely
A
Have usually mitigated this type of risk with minimal oversight in similar cases
Minor/ Low Likelihood
B
May mitigate this risk, but workarounds will be required
Moderate/ Likely
C
Cannot mitigate this risk, but a different approach might
Significant/ Highly Likely
D
Cannot mitigate this type of risk; no known processes or alternatives are available
High/ Near Certainty
E
Existing Approach…DescriptionLevel
Cannot achieve major program milestones; re-baseline required
Unacceptable performance; workarounds not available
5 – HighProgram success in doubt
Program critical path affected; workarounds available; major program milestones not affected.
Unacceptable performance; workarounds available; significant design or process change needed
4 – SignificantProgram success could be jeopardized
Some key dates missed; workarounds available; critical path not affected.
Moderate performance shortfall; workarounds available; minor design/process change needed
3 – ModerateLimited impact to program success
Schedule slip but able to meet key dates with additional activities or effort; critical path not affected
Minor performance shortfall within acceptable limits; no design or process change needed
2 – MinorProgram success not impacted
Program schedule will still be metTechnical goals will still be met1 – Low Program success not impacted
ScheduleTechnicalImpact
Cannot achieve major program milestones; re-baseline required
Unacceptable performance; workarounds not available
5 – HighProgram success in doubt
Program critical path affected; workarounds available; major program milestones not affected.
Unacceptable performance; workarounds available; significant design or process change needed
4 – SignificantProgram success could be jeopardized
Some key dates missed; workarounds available; critical path not affected.
Moderate performance shortfall; workarounds available; minor design/process change needed
3 – ModerateLimited impact to program success
Schedule slip but able to meet key dates with additional activities or effort; critical path not affected
Minor performance shortfall within acceptable limits; no design or process change needed
2 – MinorProgram success not impacted
Program schedule will still be metTechnical goals will still be met1 – Low Program success not impacted
ScheduleTechnicalImpact
12 12Federal AviationAdministration
Surveillance and Broadcast ServicesApril 24, 2007
Prioritization (continued)
Test
Test
Test
DIS
CO
VE
R
DE
CID
E
DE
PL
OY
DE
VE
LO
P
Concept
Requirements
Design
Development
High Level
Low Level
High Level
Low Level
Portfolio Investment
PlanPlans,
Schedules, Resources, Progress Tracking
Low Level
High Level
•Vision
•Strategic Roadmaps
•Con Ops
•Deployment Plans
•Pilots
Verification
Validation
Delivery
In-Service
13 13Federal AviationAdministration
Surveillance and Broadcast ServicesApril 24, 2007
Generic Scorecard
Capacity Cost Avoidance
Efficient Spacing
Efficient Routes in Adverse Weather
Efficient ATC Surface
Management
Efficient Pilot
Surface Movement
Efficiency Subscore
Reduced A/C to
A/C Conflicts
Reduced Hazardous Weather
Encounters
Reduced A/C to Terrain Conflict
Improved Search
and Rescue Services
Increased Medevac Access
Safety Subscore
Improved Separation Standards
Reduced Legacy Investment
ATC PilotUser
ANSP
Risk Rating
Likelihood Consequence:
Assessment: Additional risk assessment should be based on the Likelihood and Consequence tables below. Choose a level of Likelihood (A – E) based on the probability of the risk occurring (A being the lowest and E the highest). Then, rate the impact of the risk occurrence (1 being the lowest and 5 the highest).
Regulatory Impact Environmental Impact Political Impact
ANSP
ANSP Subscore
Payback Period
Aircraft Retrofit
User
Avionics Upgrade User Cost Subscore
Description: Insert operational description of the proposed application
Score
3.0 Risk
1.0 User Demand: State whether the application demand is by the user, an ANSP, or both.
Safety
ATC Workforce Automation Impact
Surface Safety
Efficiency
2.0 Reward Criteria:
Business Case Benefits Criteria
Business Case Cost Criteria
Application: Insert application name, including RFG / ASAS Conversion (if applicable)
E
D
C
B
A
1 2 3 4 5
Low Medium High
Lik
eli
ho
od
Consequence Will effectively avoid or mitigate this risk based on standard practices
Low/ Not Likely
A
Have usually mitigated this type of risk with minimal oversight in similar cases
Minor/ Low Likelihood
B
May mitigate this risk, but workarounds will be required
Moderate/ Likely
C
Cannot mitigate this risk, but a different approach might
Significant/ Highly Likely
D
Cannot mitigate this type of risk; no known processes or alternatives are available
High/ Near Certainty
E
Existing Approach…DescriptionLevel
Will effectively avoid or mitigate this risk based on standard practices
Low/ Not Likely
A
Have usually mitigated this type of risk with minimal oversight in similar cases
Minor/ Low Likelihood
B
May mitigate this risk, but workarounds will be required
Moderate/ Likely
C
Cannot mitigate this risk, but a different approach might
Significant/ Highly Likely
D
Cannot mitigate this type of risk; no known processes or alternatives are available
High/ Near Certainty
E
Existing Approach…DescriptionLevel
Cannot achieve major program milestones; re-baseline required
Unacceptable performance; workarounds not available
5 – HighProgram success in doubt
Program critical path affected; workarounds available; major program milestones not affected.
Unacceptable performance; workarounds available; significant design or process change needed
4 – SignificantProgram success could be jeopardized
Some key dates missed; workarounds available; critical path not affected.
Moderate performance shortfall; workarounds available; minor design/process change needed
3 – ModerateLimited impact to program success
Schedule slip but able to meet key dates with additional activities or effort; critical path not affected
Minor performance shortfall within acceptable limits; no design or process change needed
2 – MinorProgram success not impacted
Program schedule will still be metTechnical goals will still be met1 – Low Program success not impacted
ScheduleTechnicalImpact
Cannot achieve major program milestones; re-baseline required
Unacceptable performance; workarounds not available
5 – HighProgram success in doubt
Program critical path affected; workarounds available; major program milestones not affected.
Unacceptable performance; workarounds available; significant design or process change needed
4 – SignificantProgram success could be jeopardized
Some key dates missed; workarounds available; critical path not affected.
Moderate performance shortfall; workarounds available; minor design/process change needed
3 – ModerateLimited impact to program success
Schedule slip but able to meet key dates with additional activities or effort; critical path not affected
Minor performance shortfall within acceptable limits; no design or process change needed
2 – MinorProgram success not impacted
Program schedule will still be metTechnical goals will still be met1 – Low Program success not impacted
ScheduleTechnicalImpact
14 14Federal AviationAdministration
Surveillance and Broadcast ServicesApril 24, 2007
Scoring GuidelinesScore = 0 Score = 10
1.0 Demand
- Minimal sponsorship by user and ANSP - Strong sponsorship by user and ANSP
- Low probability of implementation success - High probability of implementation success
- Speculative improvement to airspace environment - Predictable positive impact on airspace environment
2.0 Reward Criteria
Business Case Benefits Criteria
- Marginal airspace / surface efficiency contribution in high density environment
- Considerable airspace / surface efficiency contribution in high density environment
- Minimal surface / airspace safety contribution in high density environment
- Significant surface / airspace safety contribution in high density environment
- Nominal cost avoidance - Considerable cost avoidance
Business Case Cost Criteria
- Rough estimate of application payback period is greater than 10 years
- Rough estimate of application payback period is less than 5 years
- Rough estimate of incremental cost for application
User:
-Avionics costs are greater than $100K/aircraft
-Aircraft retrofit cost are greater than $500K/aircraft
ANSP:
-ATC workforce increase greater than 3 per shift
-ATC automation lifecycle costs greater than $10M
- Rough estimate of incremental cost for application
User:
-Avionics costs are less than $40K/aircraft
-Aircraft retrofit cost are less than $100K/aircraft
ANSP:
-ATC workforce increase less than 1 per shift
-ATC automation lifecycle costs less than $1M
3.0 Risk
- High regulatory impact - Low regulatory impact
- High negative environmental impact - Low negative environmental impact
- Negative political impact - Positive political impact
15 15Federal AviationAdministration
Surveillance and Broadcast ServicesApril 24, 2007
Deciding the ‘Right’ Application To Invest In
Standards and Rulemaking, $4.2,
5%
Program Management, $3.3,
4%
Implementation, $57.9, 73%
Ops Support, $6.6, 8%
Systems Engineering, $8.0,
10%
Application Score Risk
1 26 G
2 22 G
3 20 Y
4 20 R
5 11 R
16 16Federal AviationAdministration
Surveillance and Broadcast ServicesApril 24, 2007
Next Steps
• Developing applications to the point of implementation
• Measuring value in demonstration trials
• Leverage activities across international community to maximize value