Business Trading Module

download Business Trading Module

of 65

Transcript of Business Trading Module

  • 8/3/2019 Business Trading Module

    1/65

    Mid & Downstream Business Training Module

    HYDROCARBON PROCESSING AN OVERVIEW

    LNG

    PRODU

    CEDWATER

    G

    AS

    Upstream Mid and Downstream

  • 8/3/2019 Business Trading Module

    2/65

    Mid & Downstream Business Training Module

    Plant Design Cycle

    Detail

    Engg.

    Pre-Commissioning

    & Commissioning

    Feasibility Study

    Process Design /

    Basic Engg.

    FEEDStable Operation

    & Performance

    Testing

    Trouble Shooting

    & Revamp

  • 8/3/2019 Business Trading Module

    3/65

    Mid & Downstream Business Training Module

    Feasibility Study:

    Conceptualization

    Process Simulation

    Development of Process Flow Scheme

    Cost Estimation

    Techno-Commercial Evaluation

    Basic Engineering:

    Mass and Energy Balance

    Process Control Scheme

    PFDs and Basic Process P&IDs

    Sizing and Basic Spec. for Equipments and Instruments

  • 8/3/2019 Business Trading Module

    4/65

    Mid & Downstream Business Training Module

    Front End Engineering Design (FEED):

    BEP to Project Specific Package (Residual

    Engineering)

    Verification of Process data for Critical items

    Preparation of Specifications

    Identification of Scope Splits

    Identification of applicable Codes & Standards

    Commissioning:

    Pre-Commissioning

    Commissioning

    Startup and Feed charging

    Performance Guarantee test run

  • 8/3/2019 Business Trading Module

    5/65

    Mid & Downstream Business Training Module

  • 8/3/2019 Business Trading Module

    6/65

  • 8/3/2019 Business Trading Module

    7/65

    Mid & Downstream Business Training Module

    REVIEW STAGE:

    Review of Contract Documents

    Preparation of TQs

  • 8/3/2019 Business Trading Module

    8/65

    Mid & Downstream Business Training Module

    STAGE 0:

    P&IDs mark up based on General Specifications,

    Standards, Amendments etc.

    Updation of Process Datasheets based on PFD and other

    documents

    Preparation of UHDs

    Sizing of Utility lines

    Preparation of Equipment list

    Preparation of Utility summary

    Preparation of Catalyst and Chemical summary

    Preparation of Tie-in summary

    Preparation ofLine-list

    Preparation of Hazardous source list

  • 8/3/2019 Business Trading Module

    9/65

    Mid & Downstream Business Training Module

    P&IDs mark up based on General Specifications,

    Standards, Amendments etc.

    Licensor P&ID

    Standard Details

  • 8/3/2019 Business Trading Module

    10/65

    Mid & Downstream Business Training Module

    Marked up P&ID

    As per the standards, the control valve assembly with block

    & bypass and Vent & Drain arrangement is shown in detail

  • 8/3/2019 Business Trading Module

    11/65

    Mid & Downstream Business Training Module

    Updation of Process Datasheets based on PFD and other

    documents

  • 8/3/2019 Business Trading Module

    12/65

    Mid & Downstream Business Training Module

    Updated Process Datasheets

  • 8/3/2019 Business Trading Module

    13/65

    Mid & Downstream Business Training Module

    Preparation of UHDs

  • 8/3/2019 Business Trading Module

    14/65

    Mid & Downstream Business Training Module

    Sizing of Utility lines

  • 8/3/2019 Business Trading Module

    15/65

    Mid & Downstream Business Training Module

    Preparation of Equipment List

    MUMBAI

    EQ UI PM EN T S ER VI CE N O. D IM EN SI ON S I NT ER NA L EQ UI PM EN T E RE CT IO N D ES IG N CO ND IT ION I NS UL AT IO N

    NO. REQD. (ID).X(TL-TL) TY PE T HICKNESS WEIGHT PRESSURE TEMP. TY PE THICKNESS

    (m) (mm) (Tons ) (kg/cm2g) (C) (mm)

    TOPBOTTOMTOP BOTTOM

    COLUMNS

    LNHTUNIT

    To p =2 .0

    Bottom= 2.8

    TL-TL = 27.9

    To p =3 .2

    Bottom= 4.0

    TL-TL = 36.9

    PENEXUNIT

    Top=1.7

    Bottom= 3.2

    TL-TL=26.2

    TITLE : EQUIPMENT LIST

    OPERATING CONDITIONMOC+C.A

    PRESSURE

    (kg/cm2g)

    TEMP

    (C)SHELL&

    HEADTRAYS

    125IH171Int : 15.82

    Ext: FV91--DA-31701 S TRIPPER KCS + 3 mm T P 4 101

    Trays,Distributor

    Internalbaffles,

    Vortex Breaker,

    DA-31702 D EPENTA NIZER KCS + 3 mm TP 4 101

    Trays,Distributor

    Internalbaffles,

    Vortex Breaker,

    - - 70 119

    STABILIZERDA-32810

    DA-32811 LPGSTRIPPER

    5 7 1 79

    1

    1 KCS+3 mm TP 4 10 - -

    -TP410CS+3mm

    Int : 4

    Ext: FV

    Int : 13.5

    Ext: FV

    Int : 13.5

    Ext: FV

    232

    171

    IH

    80

    120

    60

    210

    179

    147

    119

    120

    - -

    Trays,Distributor

    Internalbaffles,

    Vortex Breaker,

    Trays,Distributor

    Internalbaffles,

    Vortex Breaker,- 45 60

    ISOMERISATION PROJECT

    0.75 x 21

    IH

    Equipment list

  • 8/3/2019 Business Trading Module

    16/65

    Mid & Downstream Business Training Module

    Equipment List contains the information such as

    Equipment Number

    Service

    Dimensions

    Internals

    Material of Construction

    Operating and Design Conditions

    Insulation Details

    Other Special requirements

    Preparation of Equipment List (Continued)

  • 8/3/2019 Business Trading Module

    17/65

    Mid & Downstream Business Training Module

    Sample view of Equipment list

    MUMBAI

    EQUIPMENT SERVICE NO. DIMENSIONS INTERNAL EQUIPMENT ERECTION DESIGN CONDITION INSULATION

    NO. REQD. (ID).X(TL-TL) TYPE THICKNESS WEIGHT PRESSURE TEMP. TYPE THICKNESS(m) (mm) (Tons) (kg/cm2g) (C) (mm)

    TOP BOTTOM TOP BOTTOM

    COLUMNS

    LNHT UNIT

    Top = 2.0

    Bottom = 2.8

    TL-TL = 27.9

    Top = 3.2

    Bottom = 4.0

    TL-TL = 36.9

    PENEX UNIT

    Top =1.7

    Bottom = 3.2

    TL-TL=26.2

    TITLE : EQUIPMENT LIST

    OPERATING CONDITIONMOC + C.A

    PRESSURE(kg/cm2g)

    TEMP(C)SHELL &

    HEADTRAYS

    125IH171Int : 15.82

    Ext : FV91--DA-31701 STRIPPER KCS + 3 mm TP 4101

    Trays, Distributor

    Internal baffles ,

    Vortex Breaker,

    DA-31702 DEPENTANIZER KCS + 3 mm TP 4101

    Trays, Distributor

    Internal baffles ,

    Vortex Breaker,

    - - 70 119

    STABILIZERDA-32810

    DA-32811 LPG STRIPPER

    57 179

    1

    1 KCS+3mm TP 410 - -

    -TP 410CS+3mm

    Int : 4

    Ext : FV

    Int : 13.5

    Ext : FV

    Int : 13.5

    Ext : FV

    232

    171

    IH

    80

    120

    60

    210

    179

    147

    119

    120

    - -

    Trays, Distributor

    Internal baffles ,

    Vortex Breaker,

    Trays, Distributor

    Internal baffles ,

    Vortex Breaker,- 45 60

    ISOMERISATION PROJECT

    0.75 x 21

    IH

  • 8/3/2019 Business Trading Module

    18/65

    Mid & Downstream Business Training Module

    Preparation of Utility summary

    Utility Summary summarizes the consumption / generation of utilities in

    all equipments.

    The utility data for consumption to be furnished with - ve value.

    Similarly the utility data for generation to be furnished with +ve value.

    Following are the Utilities taken into account

    Electricity

    Steam

    Condensate

    Boiler Feed Water

    Cooling Water

    Service Water and Portable Water

    Instrument Air, Plant Air and Nitrogen

    Fuel Gas and Fuel Oil

  • 8/3/2019 Business Trading Module

    19/65

    Mid & Downstream Business Training Module

    Sample View of Utility summary

  • 8/3/2019 Business Trading Module

    20/65

    Mid & Downstream Business Training Module

    Preparation of Chemical summary

    TITLE : CHEMICAL SUMMARYRev.: 0

    1 -- 3200 kg MRPL

    2 20% Wt 6.5 m3 MRPL

    3 100% 200 kg MRPL

    4 100% 20 kg MRPL

    5 99.9 % Min. 30 m3 MRPL

    6 -- 2500 kg MRPL

    7 20% Wt 25 m3 MRPL

    8 -- 350 kg MRPL

    Sodium Nitrate (NaNO3)

    Make-up Caustic (NaOH) for Penex unit

    Anhydrous Ammonia

    L&T-CHIYOD BARODA, INDIA

    Document No.: A-

    ISOMERISATION PROJECT

    Required as corrosion inhibitor for LNHT un it

    First fill

    quantity

    required

    Scope of

    supply

    Chemical Identification

    Required for scrubbing of gases from stabiliser & during catalyst

    regeneration of naphta hydrotreating reactor.

    As a sulfiding agent during stat-up

    % Purity Chemical Service

    Required during initial start up.Anhydrous Hydrochloric Acid (HCl)

    Sr. No.

    For preparing neutralizing solution during regeneration

    For preparing neutralizing solution during regeneration

    As a promotor for penex reactor catalyst

    Required to neutraiize reactor effluent gases

    Perchloroethylene (C2Cl4)

    DMDS

    Caustic for LNHT reactor neutralisation

    Soda Ash (Na2CO3)

    This document summarizes the consumption of Chemicals for theprocess.

  • 8/3/2019 Business Trading Module

    21/65

    Mid & Downstream Business Training Module

    Preparation of Catalyst summary

    TITLE : CATALYST SUMMARY

    Bed

    (m3)

    Contingency

    5% (m3)

    2500

    3200

    9240

    2900 9240

    UOP---- Sock 3.62

    2600 930

    11.2520 Sock2480

    6.62Sock

    UOP

    6.8--

    7 FA-32801A Puraspec 20201200Zinc oxide

    treater

    ADS-11

    UOP "H-8"

    Catalyst

    FA-32802 1800

    DC-32801

    Reactor

    Saturation

    Reactor

    Sulfur guard

    bed

    24003

    2

    1

    Equip. Tag

    No.Sr.No.

    Catalyst

    SockUOP "S-12"

    Catalyst1065DC-31701 UOP

    ServiceEquip ID

    (mm)Bed Height

    (mm)

    Bulk

    Density

    (Kg /m3)

    TypeType of

    Loading

    4 DC-32810 Puraspec 24431100Methanator

    ReactorSock7160 UOP0.34 7.14 --

    5 DC-32811UOP "I-8"

    Catalyst2900 882 Dense 61 UOP

    6 DC-32812UOP "I-8"

    Catalyst61 UOP

    3720

    Manufacturer

    19.215

    Quantity

    Total

    quantity

    (m3)

    0.91518.3

    0.56 11.76

    UOP0.331 6.951 6464.4

    Total

    quantity

    (kg)

    20464.0

    64.05

    64.05

    Penex

    Reactor

    Penex

    Reactor

    3.05

    3.05882 Dense

    0.181 3.801

    6115.2

    56492.1

    56492.1

    This document summarizes the consumption of Catalyst for theprocess.

  • 8/3/2019 Business Trading Module

    22/65

    Mid & Downstream Business Training Module

    Preparation of Tie-in summary

    Battery Limit Tie-in Summary contains the following

    information for all ISBL & OSBL lines

    Flow rate of all process and utility streams

    going to B/L.

    Operating and Design Conditions

    Line Specifications

    Main Properties of the Streams (Optional)

  • 8/3/2019 Business Trading Module

    23/65

    Mid & Downstream Business Training Module

    Sample view of Tie-in summary

    Sr. Stream Name From To Phase Flowrates

    No. L/V/M Tons/hr kg/m3 (L) Visc.Normal MW (V) cP Pressure Temperature Pressure

    kg/cm2 g deg C kg/cm2 gmin/nor/max min/nor/max

    (C) INCOMING UTILITY LINES:

    1 MP Steam B/L HEADER V 36066.0 18.0 0.02 14/15/16 255/260/270 22

    2 LP Steam B/L HEADER V 33180.0 18.0 0.02 3/3.5/4 160/175/200 10

    3 HP Steam B/L HEADER V 2930.0 18.0 0.01 39/40/41 330/390/408 45

    4 Instrument Air B/L HEADER V 625.0 29.0 0.02 4.5/6.5/ - - /40/ - 10.5

    5 Cooling Water Supply B/L HEADER L 2378207.0 1000.0 0.60 - /4.5/ - - /33/ - 7

    6 Fuel Gas B/L HEADER V 1212.0 15.5 0.01 - /4.5/5 - /40/ - 6

    7 Fuel Oil B/L HEADER L 2273.0 854.0 11.50 - /13/20 - /170/ - 25

    TITLE : BATTERY LIMIT TIE-IN SUMMARY

    MUMBAI

    Properties

    Operating Conditions Design

  • 8/3/2019 Business Trading Module

    24/65

    Mid & Downstream Business Training Module

    Preparation ofLine-list

    Line List contains the data related to process conditionsand the data related to mechanical design and testconditions for all the lines.

    Line List is the base document utilized for verificationof major deliverables of Piping department.

    Line List contains the information such as

    Line Number

    Line Size

    Fluid Code and Piping class

    From & To Location

    State and Nature of the fluid Operating (Normal&Alternative) and Design

    Conditions

    Steam out requirements

    Insulation Details

    Test fluid and Test pressure

  • 8/3/2019 Business Trading Module

    25/65

    Mid & Downstream Business Training Module

    Sample View ofLine-list

    TITLE : LINE LIST FOR LNHT UNIT

    IDENTIFICATION LOCATION STATE

    (A)

    (L/V/M)

    1 10-P-3170001-A1A1 606 10 P 317 0001 A1A1 FA-31701 P-3170215 L HC

    2 6-P-3170002-A4A1 606 6 P 317 0002 A4A1 GA-31701A P-3170046 L HC

    3 10-P-3170003-A1A1 606 10 P 317 0003 A1A1 P-3170001 P-3170216 L HC

    4 6-P-3170004-A4A1 606 6 P 317 0004 A4A1 GA-31701B P-3170002 L HC

    5 0.75-P-3170005-A1A1 691 0.75 P 317 0005 A1A1 P-3170002 SN-31701 L HC

    6 0.75-P-3170006-A1A 691 0.75 P 317 0006 A1A SN-31701 FLARE L HC

    7 0.75-P-3170007-A4A1 691 0.75 P 317 0007 A4A1 SN-31701 P-3170001 L HC

    8 6-P-3170008-A4A1 606 6 P 317 0008 A4A1 P-3170002 FV-002 L HC

    9 6-P-3170009-A1A1 606 6 P 317 0009 A1A1 FV-002 FA-31701 L HC

    LINE NO. FROM TO

    NATURE

    OFFLUID

    INSUL

    ATION

    TYPE

    INSUL

    ATION

    THK.(MM)

    SR.

    NO.P&IDNO.

    S

    IZE

    (IN

    CH)

    FLUID

    CODE

    UNITNO.

    LINENO.

    PIPING

    CLASS

    MUMBAI

  • 8/3/2019 Business Trading Module

    26/65

    Mid & Downstream Business Training Module

    Preparation of Hazardous Source List

    Hazardous Source List is the base documentutilized for hazardous area classificationdrawing deliverable of Electrical department.

    This document contains the information such as Inlet and Outlet streams of all equipments

    State and Nature of the fluid

    Composition

    Max. operating temperature

    Properties like Density and Molecularweight

    Flammability

    Flash point

    Auto-ignition temperature

  • 8/3/2019 Business Trading Module

    27/65

    Mid & Downstream Business Training Module

    Sample View of Hazardous Source List

  • 8/3/2019 Business Trading Module

    28/65

    Mid & Downstream Business Training Module

    STAGE 1:

    Hydraulic Check of Process lines

    Sizing of Vessels

    Thermal rating of Heat exchangers

    PSV Sizing &Flare hydraulics

    Preparation ofFlare Load Summary

    Preparation of Equipment datasheets for new items

    Scope demarcation for Vendor items

    Updation of P&IDs based on Hydraulic results

  • 8/3/2019 Business Trading Module

    29/65

    Mid & Downstream Business Training Module

    STAGE 1 (Continued):

    Updation of Pumps and Instruments datasheets based

    on Hydraulics

    Updation of Equipment list

    Development of Control and Safeguarding Narratives

  • 8/3/2019 Business Trading Module

    30/65

    Mid & Downstream Business Training Module

    Hydraulic Check of Process lines

    Loop identification in PFD

  • 8/3/2019 Business Trading Module

    31/65

    Mid & Downstream Business Training Module

    Hydraulic Check of Process lines

    Collecting Inputs required for hydraulic calculations

  • 8/3/2019 Business Trading Module

    32/65

    Mid & Downstream Business Training Module

    Sample View of Hydraulic Calculation Sheet

  • 8/3/2019 Business Trading Module

    33/65

    Mid & Downstream Business Training Module

    Sizing of Vessels

    Sizing of vessels is carried out based on Project

    Design Criteria (Droplet size, Residence time)

    Sometimes, Sizing is governed by separation of

    fine entrained droplets using mesh pad, impact

    separators, etc.

  • 8/3/2019 Business Trading Module

    34/65

    Mid & Downstream Business Training Module

    Sample view of Vessel Sizing calculation sheet

  • 8/3/2019 Business Trading Module

    35/65

    Mid & Downstream Business Training Module

    Thermal rating of Heat exchangers

    Designing / Rating of heat exchangers is carried

    out with the help of HTRI computer program.

    This activity enables the designer to model heat

    exchangers, allowing the designer to gauge the

    performance, geometry and inherent limitations

    of the shell and tube heat exchanger even before

    its fabrication.

    This results in lower risks of damage to the

    equipment while in service.

  • 8/3/2019 Business Trading Module

    36/65

    Mid & Downstream Business Training Module

    Sample HTRI Specification Sheet

    Sample HTRI Tube Layout

  • 8/3/2019 Business Trading Module

    37/65

    Mid & Downstream Business Training Module

    PSV Sizing and Flare Hydraulics

    The safety of personnel and the protection of

    equipments due to overpressure are the basis for the

    design, sizing, and selection of pressure relieving

    systems.

    All systems and pressure relief devices shall be

    designed based on the applicable codes (API 520,

    521, etc.), industry standards and practices.

    For Flare header Sizing, first we have to determine

    the appropriate relief contingencies yieldingmaximum loads

    Flare header size has to be large enough to prevent

    excessive backpressure on the plant safety valves

    and to limit gas velocity and noise to acceptable

    levels.

  • 8/3/2019 Business Trading Module

    38/65

    Mid & Downstream Business Training Module

    Sample view ofFlare Hydraulics calculation sheet

  • 8/3/2019 Business Trading Module

    39/65

    Mid & Downstream Business Training Module

    Preparation ofFlare Load Summary

    This document summarizes the relief load of all PSVs for theapplicable relieving cases.

  • 8/3/2019 Business Trading Module

    40/65

    Mid & Downstream Business Training Module

    Preparation of Equipment datasheets for new items

    OWNER : MANGALORE REFINERY AND PETROCHEMICALS LTD.

    PROJECT : LIGHT NAPHTHA ISOMERISATION BLOCK

    JOB NO. : DL-4126

    : A-328-30006

    : 3 OF 4

    Rev.

    1.

    2.

    3.

    4.

    5.6.

    7.

    8.

    9.

    10.

    11.

    12.

    13.

    14.

    15.

    16.

    17.

    18.

    19.

    20.

    21.

    22.

    23.

    24.

    25.

    26.

    27.

    28.

    29.

    30.

    30.

    32.

    33.

    34.

    35.

    36.37.

    38.

    39.

    40.

    41.

    APVD.DOC. NO.

    SHEET DATE

    L&T-CHIYODALIMITED,Baroda

    VESSEL DATASHEET

    MATERIAL

    kg/cm2g @

    IBR IS APPLICABLE

    mm

    225 (NOTE-1)

    NO

    100

    YES

    %

    FA-32850

    HOT COLD PP THICKNESS : 120

    YES

    HEMISPHERICAL

    ITEM NO.

    SERVICE

    NO. REQD.

    POSITION

    OTHER

    NO YES

    IF YES THEN STEAM PRESS. / TEMP.

    VESSEL TRIM A2A

    kg/cm2g

    C

    mm

    YES

    2:1 ELLIPSE

    NO YES

    REFER UOP STD. DRG. 3-122

    3

    C

    TORISPHERICAL

    mm

    C

    915.4

    kg/cm2g

    kg/m3

    mm

    mm

    mm

    min

    TL-TL LENGTH OF BOOT

    NO

    NO

    1400

    4100

    N.A.

    N.A.

    @ 153

    STEAM CONDENSATE

    kg/h

    kg/m3

    kg/h

    C

    GAS/

    VAPOR

    LIQ.

    TEMPERATURE

    PRESSURE

    MW

    QUANTITY

    DENSITY

    QUANTITY

    STEAM OUT CONDITION

    VORTEX BREAKER

    IF YES THEN TYPE

    DESIGN TEMPERATURE

    VACUUM CONDITION

    DEMISTER

    IF YES THEN TYPE

    IF YES THEN

    INSULATION

    CORROSION ALLOWANCE

    SPECIAL SERVICE

    INSIDE DIAMETER

    RJB

    12/4/2004

    IF YES THEN TYPE

    HEAD TYPE

    INSIDE DIAMETER OF BOOT

    FLUID

    REV.

    MADE

    NORMAL HOLD UP TIME

    OPERATING CONDITIONS

    4

    18

    40861 (Note-4)

    RHDCHKD.

    NO

    5

    VERTICAL

    CLEAN MP CONDENSATE FLASH VESSEL

    1

    151.6

    4605 (Note-4)

    2.63

    DESIGN PRESSURE 10

    TL-TL LENGTH

    YES

    DESIGN CONDITIONS

    CODE / REGULATION

    DENSITY

    0

    NPK

  • 8/3/2019 Business Trading Module

    41/65

  • 8/3/2019 Business Trading Module

    42/65

    Mid & Downstream Business Training Module

    Updation of P&IDs based on Hydraulic results

    Licensor P&ID

  • 8/3/2019 Business Trading Module

    43/65

  • 8/3/2019 Business Trading Module

    44/65

    Mid & Downstream Business Training Module

    Updation of Pumps and Instruments datasheets based

    on Hydraulics

    Licensor Datasheet

  • 8/3/2019 Business Trading Module

    45/65

    Mid & Downstream Business Training Module

    Updated Pumps datasheets based on Hydraulics

  • 8/3/2019 Business Trading Module

    46/65

    Mid & Downstream Business Training Module

    Development of Control Narratives

    This narrative describes the plant control systems by

    instrumentation.

    The purpose of this document are as follows :

    (1) To explain control systems to those who may

    not be familiar with instrumentation symbols

    or functional logic diagrams.

    (2) To define purpose and algorithm of eachcontrol system.

    Pump auto start systems will be also covered in this

    document.

  • 8/3/2019 Business Trading Module

    47/65

    Mid & Downstream Business Training Module

    Development of Safeguarding Narratives

    The purpose of this narrative is to thoroughly

    explain the safeguarding scheme and its

    significance. Based on the same it is possible to

    understand how safeguarding scheme works and

    how it will be depicted in Cause and Effect

    diagram or Safeguarding Matrix.

  • 8/3/2019 Business Trading Module

    48/65

    Mid & Downstream Business Training Module

    Sample of Cause and Effect Diagram

    P-5105BHPSTEAMVALVE

    P-5105AHPBFWPUMP

    P-51203HPBFWPUMP

    P-51402AMPBFWPUMP

    P-51206AHPBFWPUMP

    P-51206BHPBFWPUMP

    P-51206CHPBFWPUMP

    P-51206DHPBFWPUMP

    COMMONTRIPALARM

    CAUSE CLOSE TRIP TRIP TRIP TRIP TRIP TRIP TRIP ALARM ACTION

    TAG NO. DESCRIPTIONPEFS NO.

    51UZA-2103

    51UZA-2102

    51UZA-2104

    51UZA-2100

    51UZA-2105

    51UZA-2106

    51UZA-2107

    51UZA-2108

    51UZA-2100

    TAG NO.

    51LZA-2008 D-0098-51-25-0006 X X X X X 51LZA-2008

    51LZA-2011 D-1651-51-50-0018 X X X X X 51LZA-2011

    51LZA-2008 D-0098-51-25-0006 X X X X X X X X X 51LZA-2008

    51LZA-2011 D-1651-51-50-0018 51LZA-2011

    51LZA-2008 D-0098-51-25-0006 51LZA-2008

    51LZA-2011 D-1651-51-50-0018 X X X X X X X X X 51LZA-2011

    V-51203 LEVEL LOW LOW

    V-51210 LEVEL LOW LOW

    V-51203 LEVEL LOW LOW

    V-51210 LEVEL LOW LOW

    EFFECT

    51UZA-2100 V-51203 / V-51201 SGS

    DESCRIPTION

    SAFE GUARDING MATRIX UNIT 51

    V-51210 LEVEL LOW LOW

    V-51203 LEVEL LOW LOW

    Cause Section

    Effect Section

  • 8/3/2019 Business Trading Module

    49/65

    Mid & Downstream Business Training Module

    STAGE 2:

    Interface Activities

    Updation of Control & Safeguarding narratives and issue

    for HAZOP Study

    Updation of Utility summary

    Updation ofLine list

  • 8/3/2019 Business Trading Module

    50/65

    Mid & Downstream Business Training Module

    Interface Activities

    Vendor Document Review

    Review of Engineering Drawings

    Review of Plot Plan

    3D-Model Review

    Review of DCS Graphics

  • 8/3/2019 Business Trading Module

    51/65

    Mid & Downstream Business Training Module

    Vendor Document Review

    Some of the Critical points to be reviewed in EngineeringDrawings are:

    Consistency of Process data as per process datasheetssuch as Operating & Design Conditions, MOC, Special

    service requirements, etc.

    Review of other technical aspects

    (a) Meeting all Specifications as per requirement.

    (b) Expected Utility consumption figures.

    (c) Guarantee figures, if any.

    (d) Other technical requirements specified in therequisition.

    (e) Fulfilment of Scope of Supply.

  • 8/3/2019 Business Trading Module

    52/65

    Mid & Downstream Business Training Module

    Review of Engineering Drawings

    Some of the Critical points to be reviewed in EngineeringDrawings are:

    Consistency of Process data as per process datasheetssuch as Operating & Design Conditions, MOC, Specialservice requirements, etc.

    Number of Nozzles

    Sizes of Nozzles

    Checking location and orientation of all nozzles

    especially nozzles for Temperature, Pressure and

    Level Instruments as per Project requirements

  • 8/3/2019 Business Trading Module

    53/65

    Mid & Downstream Business Training Module

    Review of Plot Plan

    Some of the Critical points to be reviewed in Plot plan are:

    Consistency of equipments shown in plot plan withEquipment List, PFD and P&IDs.

    Are the distances between equipment kept minimum withrespect to pressure drop?

    Are the height of Towers and vessels enough toprovide NPSH of pumps?

    Are the equipment located symmetrically such as column andreboilers?

    Is there enough space around columns, towers andreactors for removal of internals?

    Is there enough space to remove tube bundle of heatexchangers?

    Are the equipments arranged considering safetyaspects especially for Fired heaters, Compressors andTanks?

  • 8/3/2019 Business Trading Module

    54/65

    Mid & Downstream Business Training Module

    3D-Model Review

    Some of the Critical points to be considered in 3D-modelreview are:

    Is piping arranged to provide straight runrequirement such as inlet of tower?

    Are CV sets placed as per Project requirements such as

    closeness to equipment, at high or low level, etc., if

    any?

    Are symmetrical piping considered for AFCs?

    Are the valves located at operable location from the

    nearest platform or grade?

    Is piping arranged to keep special bending radius

    requirements, if any?

  • 8/3/2019 Business Trading Module

    55/65

  • 8/3/2019 Business Trading Module

    56/65

    Mid & Downstream Business Training Module

    STAGE 2 (Continued):

    Updation of Control & Safeguarding narratives and issue

    for HAZOP Study

    Updation of Utility summary

    Updation ofLine list

  • 8/3/2019 Business Trading Module

    57/65

    Mid & Downstream Business Training Module

    STAGE 3:

    Safety Studies / Analysis

    Updation of P&IDs based on Safety Studies

    recommendation

    Preparation of Precommisioning manual

    Preparation of Operating manual

  • 8/3/2019 Business Trading Module

    58/65

    Mid & Downstream Business Training Module

    Safety Studies / Analysis

    HAZOP Study

    SIL Study

    FIREPRAN Study

  • 8/3/2019 Business Trading Module

    59/65

    Mid & Downstream Business Training Module

    HAZard and OPerability study is a technique to examine a

    system, part by part, in a very systematic manner, to find

    out the cause and consequence of every conceivable

    deviation in the normal operation of the system as well

    as during emergencies, start-ups and shutdowns. The

    method enables prediction of all possible ways in which a

    hazard or an operating problem could arise, whether thedesign takes preventive care of them and if not,

    recommends changes (Action) as may be necessary.

    HAZOP Study

  • 8/3/2019 Business Trading Module

    60/65

    Mid & Downstream Business Training Module

    SIL

    Measurement of confidence level for performance of safetyfunction is called the Safety Integrity Level(SIL)

    Safety integrity of a system can be defined as The probability (likelihood) of a safety-related systemperforming the required safety function under all the stated

    conditions within a stated period of time SIL is a measure of the reliability of the safety function

    performing to specification.

    The SIL is based on the accepted risk level and ranges from 1to 4

    Probability of FailureSafety

    IntegrityLevel (SIL)

    Mode of Operation On demand(average probability of failure to perform

    its design function upon demand)

    Mode of Operation continuous(probability of dangerous failure per

    hour)

    4 > 10-5

    to < 10-4

    > 10-9

    to < 10-8

    3 > 10-4 to < 10-3 > 10-8 to < 10-7

    2 > 10-3

    to < 10-2

    > 10-7

    to < 10-6

    1 > 10

    -2

    to < 10

    -1

    > 10

    -6

    to < 10

    -7

  • 8/3/2019 Business Trading Module

    61/65

    Mid & Downstream Business Training Module

    FIREPRAN study

    FIRE PRotection &ANalysis is a new technique employed atthe design phase of a facility or installation to achieve thefollowing objectives

    Overview the role of the facility and its significance to the

    overall operation. Review the facilitys Fire and Explosion Strategy (FES) in the

    context of the role of the facility and its significance to theoverall company.

    Analyze threats to loss of containment or other potentialsources of combustion events.

    Assess release event consequences and explosion scenarios

    Review and assess adequacy of threat control measures,mitigation and recovery measures.

    Make recommendation for risk reduction measures toachieve levels as low as reasonably practicable (ALARP).

  • 8/3/2019 Business Trading Module

    62/65

  • 8/3/2019 Business Trading Module

    63/65

    Mid & Downstream Business Training Module

    Critical Area identification

    Area in red needs tobe given extensive

    consideration for fireprotection systems

  • 8/3/2019 Business Trading Module

    64/65

    Mid & Downstream Business Training Module

    Updation of P&IDs based on Safety Studies

    recommendation

    Preparation of Precommisioning manual

    Preparation of Operating manual

    STAGE 3 (Continued):

  • 8/3/2019 Business Trading Module

    65/65

    Mid & Downstream Business Training Module