Business Trading Module
-
Upload
praveen013 -
Category
Documents
-
view
217 -
download
0
Transcript of Business Trading Module
-
8/3/2019 Business Trading Module
1/65
Mid & Downstream Business Training Module
HYDROCARBON PROCESSING AN OVERVIEW
LNG
PRODU
CEDWATER
G
AS
Upstream Mid and Downstream
-
8/3/2019 Business Trading Module
2/65
Mid & Downstream Business Training Module
Plant Design Cycle
Detail
Engg.
Pre-Commissioning
& Commissioning
Feasibility Study
Process Design /
Basic Engg.
FEEDStable Operation
& Performance
Testing
Trouble Shooting
& Revamp
-
8/3/2019 Business Trading Module
3/65
Mid & Downstream Business Training Module
Feasibility Study:
Conceptualization
Process Simulation
Development of Process Flow Scheme
Cost Estimation
Techno-Commercial Evaluation
Basic Engineering:
Mass and Energy Balance
Process Control Scheme
PFDs and Basic Process P&IDs
Sizing and Basic Spec. for Equipments and Instruments
-
8/3/2019 Business Trading Module
4/65
Mid & Downstream Business Training Module
Front End Engineering Design (FEED):
BEP to Project Specific Package (Residual
Engineering)
Verification of Process data for Critical items
Preparation of Specifications
Identification of Scope Splits
Identification of applicable Codes & Standards
Commissioning:
Pre-Commissioning
Commissioning
Startup and Feed charging
Performance Guarantee test run
-
8/3/2019 Business Trading Module
5/65
Mid & Downstream Business Training Module
-
8/3/2019 Business Trading Module
6/65
-
8/3/2019 Business Trading Module
7/65
Mid & Downstream Business Training Module
REVIEW STAGE:
Review of Contract Documents
Preparation of TQs
-
8/3/2019 Business Trading Module
8/65
Mid & Downstream Business Training Module
STAGE 0:
P&IDs mark up based on General Specifications,
Standards, Amendments etc.
Updation of Process Datasheets based on PFD and other
documents
Preparation of UHDs
Sizing of Utility lines
Preparation of Equipment list
Preparation of Utility summary
Preparation of Catalyst and Chemical summary
Preparation of Tie-in summary
Preparation ofLine-list
Preparation of Hazardous source list
-
8/3/2019 Business Trading Module
9/65
Mid & Downstream Business Training Module
P&IDs mark up based on General Specifications,
Standards, Amendments etc.
Licensor P&ID
Standard Details
-
8/3/2019 Business Trading Module
10/65
Mid & Downstream Business Training Module
Marked up P&ID
As per the standards, the control valve assembly with block
& bypass and Vent & Drain arrangement is shown in detail
-
8/3/2019 Business Trading Module
11/65
Mid & Downstream Business Training Module
Updation of Process Datasheets based on PFD and other
documents
-
8/3/2019 Business Trading Module
12/65
Mid & Downstream Business Training Module
Updated Process Datasheets
-
8/3/2019 Business Trading Module
13/65
Mid & Downstream Business Training Module
Preparation of UHDs
-
8/3/2019 Business Trading Module
14/65
Mid & Downstream Business Training Module
Sizing of Utility lines
-
8/3/2019 Business Trading Module
15/65
Mid & Downstream Business Training Module
Preparation of Equipment List
MUMBAI
EQ UI PM EN T S ER VI CE N O. D IM EN SI ON S I NT ER NA L EQ UI PM EN T E RE CT IO N D ES IG N CO ND IT ION I NS UL AT IO N
NO. REQD. (ID).X(TL-TL) TY PE T HICKNESS WEIGHT PRESSURE TEMP. TY PE THICKNESS
(m) (mm) (Tons ) (kg/cm2g) (C) (mm)
TOPBOTTOMTOP BOTTOM
COLUMNS
LNHTUNIT
To p =2 .0
Bottom= 2.8
TL-TL = 27.9
To p =3 .2
Bottom= 4.0
TL-TL = 36.9
PENEXUNIT
Top=1.7
Bottom= 3.2
TL-TL=26.2
TITLE : EQUIPMENT LIST
OPERATING CONDITIONMOC+C.A
PRESSURE
(kg/cm2g)
TEMP
(C)SHELL&
HEADTRAYS
125IH171Int : 15.82
Ext: FV91--DA-31701 S TRIPPER KCS + 3 mm T P 4 101
Trays,Distributor
Internalbaffles,
Vortex Breaker,
DA-31702 D EPENTA NIZER KCS + 3 mm TP 4 101
Trays,Distributor
Internalbaffles,
Vortex Breaker,
- - 70 119
STABILIZERDA-32810
DA-32811 LPGSTRIPPER
5 7 1 79
1
1 KCS+3 mm TP 4 10 - -
-TP410CS+3mm
Int : 4
Ext: FV
Int : 13.5
Ext: FV
Int : 13.5
Ext: FV
232
171
IH
80
120
60
210
179
147
119
120
- -
Trays,Distributor
Internalbaffles,
Vortex Breaker,
Trays,Distributor
Internalbaffles,
Vortex Breaker,- 45 60
ISOMERISATION PROJECT
0.75 x 21
IH
Equipment list
-
8/3/2019 Business Trading Module
16/65
Mid & Downstream Business Training Module
Equipment List contains the information such as
Equipment Number
Service
Dimensions
Internals
Material of Construction
Operating and Design Conditions
Insulation Details
Other Special requirements
Preparation of Equipment List (Continued)
-
8/3/2019 Business Trading Module
17/65
Mid & Downstream Business Training Module
Sample view of Equipment list
MUMBAI
EQUIPMENT SERVICE NO. DIMENSIONS INTERNAL EQUIPMENT ERECTION DESIGN CONDITION INSULATION
NO. REQD. (ID).X(TL-TL) TYPE THICKNESS WEIGHT PRESSURE TEMP. TYPE THICKNESS(m) (mm) (Tons) (kg/cm2g) (C) (mm)
TOP BOTTOM TOP BOTTOM
COLUMNS
LNHT UNIT
Top = 2.0
Bottom = 2.8
TL-TL = 27.9
Top = 3.2
Bottom = 4.0
TL-TL = 36.9
PENEX UNIT
Top =1.7
Bottom = 3.2
TL-TL=26.2
TITLE : EQUIPMENT LIST
OPERATING CONDITIONMOC + C.A
PRESSURE(kg/cm2g)
TEMP(C)SHELL &
HEADTRAYS
125IH171Int : 15.82
Ext : FV91--DA-31701 STRIPPER KCS + 3 mm TP 4101
Trays, Distributor
Internal baffles ,
Vortex Breaker,
DA-31702 DEPENTANIZER KCS + 3 mm TP 4101
Trays, Distributor
Internal baffles ,
Vortex Breaker,
- - 70 119
STABILIZERDA-32810
DA-32811 LPG STRIPPER
57 179
1
1 KCS+3mm TP 410 - -
-TP 410CS+3mm
Int : 4
Ext : FV
Int : 13.5
Ext : FV
Int : 13.5
Ext : FV
232
171
IH
80
120
60
210
179
147
119
120
- -
Trays, Distributor
Internal baffles ,
Vortex Breaker,
Trays, Distributor
Internal baffles ,
Vortex Breaker,- 45 60
ISOMERISATION PROJECT
0.75 x 21
IH
-
8/3/2019 Business Trading Module
18/65
Mid & Downstream Business Training Module
Preparation of Utility summary
Utility Summary summarizes the consumption / generation of utilities in
all equipments.
The utility data for consumption to be furnished with - ve value.
Similarly the utility data for generation to be furnished with +ve value.
Following are the Utilities taken into account
Electricity
Steam
Condensate
Boiler Feed Water
Cooling Water
Service Water and Portable Water
Instrument Air, Plant Air and Nitrogen
Fuel Gas and Fuel Oil
-
8/3/2019 Business Trading Module
19/65
Mid & Downstream Business Training Module
Sample View of Utility summary
-
8/3/2019 Business Trading Module
20/65
Mid & Downstream Business Training Module
Preparation of Chemical summary
TITLE : CHEMICAL SUMMARYRev.: 0
1 -- 3200 kg MRPL
2 20% Wt 6.5 m3 MRPL
3 100% 200 kg MRPL
4 100% 20 kg MRPL
5 99.9 % Min. 30 m3 MRPL
6 -- 2500 kg MRPL
7 20% Wt 25 m3 MRPL
8 -- 350 kg MRPL
Sodium Nitrate (NaNO3)
Make-up Caustic (NaOH) for Penex unit
Anhydrous Ammonia
L&T-CHIYOD BARODA, INDIA
Document No.: A-
ISOMERISATION PROJECT
Required as corrosion inhibitor for LNHT un it
First fill
quantity
required
Scope of
supply
Chemical Identification
Required for scrubbing of gases from stabiliser & during catalyst
regeneration of naphta hydrotreating reactor.
As a sulfiding agent during stat-up
% Purity Chemical Service
Required during initial start up.Anhydrous Hydrochloric Acid (HCl)
Sr. No.
For preparing neutralizing solution during regeneration
For preparing neutralizing solution during regeneration
As a promotor for penex reactor catalyst
Required to neutraiize reactor effluent gases
Perchloroethylene (C2Cl4)
DMDS
Caustic for LNHT reactor neutralisation
Soda Ash (Na2CO3)
This document summarizes the consumption of Chemicals for theprocess.
-
8/3/2019 Business Trading Module
21/65
Mid & Downstream Business Training Module
Preparation of Catalyst summary
TITLE : CATALYST SUMMARY
Bed
(m3)
Contingency
5% (m3)
2500
3200
9240
2900 9240
UOP---- Sock 3.62
2600 930
11.2520 Sock2480
6.62Sock
UOP
6.8--
7 FA-32801A Puraspec 20201200Zinc oxide
treater
ADS-11
UOP "H-8"
Catalyst
FA-32802 1800
DC-32801
Reactor
Saturation
Reactor
Sulfur guard
bed
24003
2
1
Equip. Tag
No.Sr.No.
Catalyst
SockUOP "S-12"
Catalyst1065DC-31701 UOP
ServiceEquip ID
(mm)Bed Height
(mm)
Bulk
Density
(Kg /m3)
TypeType of
Loading
4 DC-32810 Puraspec 24431100Methanator
ReactorSock7160 UOP0.34 7.14 --
5 DC-32811UOP "I-8"
Catalyst2900 882 Dense 61 UOP
6 DC-32812UOP "I-8"
Catalyst61 UOP
3720
Manufacturer
19.215
Quantity
Total
quantity
(m3)
0.91518.3
0.56 11.76
UOP0.331 6.951 6464.4
Total
quantity
(kg)
20464.0
64.05
64.05
Penex
Reactor
Penex
Reactor
3.05
3.05882 Dense
0.181 3.801
6115.2
56492.1
56492.1
This document summarizes the consumption of Catalyst for theprocess.
-
8/3/2019 Business Trading Module
22/65
Mid & Downstream Business Training Module
Preparation of Tie-in summary
Battery Limit Tie-in Summary contains the following
information for all ISBL & OSBL lines
Flow rate of all process and utility streams
going to B/L.
Operating and Design Conditions
Line Specifications
Main Properties of the Streams (Optional)
-
8/3/2019 Business Trading Module
23/65
Mid & Downstream Business Training Module
Sample view of Tie-in summary
Sr. Stream Name From To Phase Flowrates
No. L/V/M Tons/hr kg/m3 (L) Visc.Normal MW (V) cP Pressure Temperature Pressure
kg/cm2 g deg C kg/cm2 gmin/nor/max min/nor/max
(C) INCOMING UTILITY LINES:
1 MP Steam B/L HEADER V 36066.0 18.0 0.02 14/15/16 255/260/270 22
2 LP Steam B/L HEADER V 33180.0 18.0 0.02 3/3.5/4 160/175/200 10
3 HP Steam B/L HEADER V 2930.0 18.0 0.01 39/40/41 330/390/408 45
4 Instrument Air B/L HEADER V 625.0 29.0 0.02 4.5/6.5/ - - /40/ - 10.5
5 Cooling Water Supply B/L HEADER L 2378207.0 1000.0 0.60 - /4.5/ - - /33/ - 7
6 Fuel Gas B/L HEADER V 1212.0 15.5 0.01 - /4.5/5 - /40/ - 6
7 Fuel Oil B/L HEADER L 2273.0 854.0 11.50 - /13/20 - /170/ - 25
TITLE : BATTERY LIMIT TIE-IN SUMMARY
MUMBAI
Properties
Operating Conditions Design
-
8/3/2019 Business Trading Module
24/65
Mid & Downstream Business Training Module
Preparation ofLine-list
Line List contains the data related to process conditionsand the data related to mechanical design and testconditions for all the lines.
Line List is the base document utilized for verificationof major deliverables of Piping department.
Line List contains the information such as
Line Number
Line Size
Fluid Code and Piping class
From & To Location
State and Nature of the fluid Operating (Normal&Alternative) and Design
Conditions
Steam out requirements
Insulation Details
Test fluid and Test pressure
-
8/3/2019 Business Trading Module
25/65
Mid & Downstream Business Training Module
Sample View ofLine-list
TITLE : LINE LIST FOR LNHT UNIT
IDENTIFICATION LOCATION STATE
(A)
(L/V/M)
1 10-P-3170001-A1A1 606 10 P 317 0001 A1A1 FA-31701 P-3170215 L HC
2 6-P-3170002-A4A1 606 6 P 317 0002 A4A1 GA-31701A P-3170046 L HC
3 10-P-3170003-A1A1 606 10 P 317 0003 A1A1 P-3170001 P-3170216 L HC
4 6-P-3170004-A4A1 606 6 P 317 0004 A4A1 GA-31701B P-3170002 L HC
5 0.75-P-3170005-A1A1 691 0.75 P 317 0005 A1A1 P-3170002 SN-31701 L HC
6 0.75-P-3170006-A1A 691 0.75 P 317 0006 A1A SN-31701 FLARE L HC
7 0.75-P-3170007-A4A1 691 0.75 P 317 0007 A4A1 SN-31701 P-3170001 L HC
8 6-P-3170008-A4A1 606 6 P 317 0008 A4A1 P-3170002 FV-002 L HC
9 6-P-3170009-A1A1 606 6 P 317 0009 A1A1 FV-002 FA-31701 L HC
LINE NO. FROM TO
NATURE
OFFLUID
INSUL
ATION
TYPE
INSUL
ATION
THK.(MM)
SR.
NO.P&IDNO.
S
IZE
(IN
CH)
FLUID
CODE
UNITNO.
LINENO.
PIPING
CLASS
MUMBAI
-
8/3/2019 Business Trading Module
26/65
Mid & Downstream Business Training Module
Preparation of Hazardous Source List
Hazardous Source List is the base documentutilized for hazardous area classificationdrawing deliverable of Electrical department.
This document contains the information such as Inlet and Outlet streams of all equipments
State and Nature of the fluid
Composition
Max. operating temperature
Properties like Density and Molecularweight
Flammability
Flash point
Auto-ignition temperature
-
8/3/2019 Business Trading Module
27/65
Mid & Downstream Business Training Module
Sample View of Hazardous Source List
-
8/3/2019 Business Trading Module
28/65
Mid & Downstream Business Training Module
STAGE 1:
Hydraulic Check of Process lines
Sizing of Vessels
Thermal rating of Heat exchangers
PSV Sizing &Flare hydraulics
Preparation ofFlare Load Summary
Preparation of Equipment datasheets for new items
Scope demarcation for Vendor items
Updation of P&IDs based on Hydraulic results
-
8/3/2019 Business Trading Module
29/65
Mid & Downstream Business Training Module
STAGE 1 (Continued):
Updation of Pumps and Instruments datasheets based
on Hydraulics
Updation of Equipment list
Development of Control and Safeguarding Narratives
-
8/3/2019 Business Trading Module
30/65
Mid & Downstream Business Training Module
Hydraulic Check of Process lines
Loop identification in PFD
-
8/3/2019 Business Trading Module
31/65
Mid & Downstream Business Training Module
Hydraulic Check of Process lines
Collecting Inputs required for hydraulic calculations
-
8/3/2019 Business Trading Module
32/65
Mid & Downstream Business Training Module
Sample View of Hydraulic Calculation Sheet
-
8/3/2019 Business Trading Module
33/65
Mid & Downstream Business Training Module
Sizing of Vessels
Sizing of vessels is carried out based on Project
Design Criteria (Droplet size, Residence time)
Sometimes, Sizing is governed by separation of
fine entrained droplets using mesh pad, impact
separators, etc.
-
8/3/2019 Business Trading Module
34/65
Mid & Downstream Business Training Module
Sample view of Vessel Sizing calculation sheet
-
8/3/2019 Business Trading Module
35/65
Mid & Downstream Business Training Module
Thermal rating of Heat exchangers
Designing / Rating of heat exchangers is carried
out with the help of HTRI computer program.
This activity enables the designer to model heat
exchangers, allowing the designer to gauge the
performance, geometry and inherent limitations
of the shell and tube heat exchanger even before
its fabrication.
This results in lower risks of damage to the
equipment while in service.
-
8/3/2019 Business Trading Module
36/65
Mid & Downstream Business Training Module
Sample HTRI Specification Sheet
Sample HTRI Tube Layout
-
8/3/2019 Business Trading Module
37/65
Mid & Downstream Business Training Module
PSV Sizing and Flare Hydraulics
The safety of personnel and the protection of
equipments due to overpressure are the basis for the
design, sizing, and selection of pressure relieving
systems.
All systems and pressure relief devices shall be
designed based on the applicable codes (API 520,
521, etc.), industry standards and practices.
For Flare header Sizing, first we have to determine
the appropriate relief contingencies yieldingmaximum loads
Flare header size has to be large enough to prevent
excessive backpressure on the plant safety valves
and to limit gas velocity and noise to acceptable
levels.
-
8/3/2019 Business Trading Module
38/65
Mid & Downstream Business Training Module
Sample view ofFlare Hydraulics calculation sheet
-
8/3/2019 Business Trading Module
39/65
Mid & Downstream Business Training Module
Preparation ofFlare Load Summary
This document summarizes the relief load of all PSVs for theapplicable relieving cases.
-
8/3/2019 Business Trading Module
40/65
Mid & Downstream Business Training Module
Preparation of Equipment datasheets for new items
OWNER : MANGALORE REFINERY AND PETROCHEMICALS LTD.
PROJECT : LIGHT NAPHTHA ISOMERISATION BLOCK
JOB NO. : DL-4126
: A-328-30006
: 3 OF 4
Rev.
1.
2.
3.
4.
5.6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
16.
17.
18.
19.
20.
21.
22.
23.
24.
25.
26.
27.
28.
29.
30.
30.
32.
33.
34.
35.
36.37.
38.
39.
40.
41.
APVD.DOC. NO.
SHEET DATE
L&T-CHIYODALIMITED,Baroda
VESSEL DATASHEET
MATERIAL
kg/cm2g @
IBR IS APPLICABLE
mm
225 (NOTE-1)
NO
100
YES
%
FA-32850
HOT COLD PP THICKNESS : 120
YES
HEMISPHERICAL
ITEM NO.
SERVICE
NO. REQD.
POSITION
OTHER
NO YES
IF YES THEN STEAM PRESS. / TEMP.
VESSEL TRIM A2A
kg/cm2g
C
mm
YES
2:1 ELLIPSE
NO YES
REFER UOP STD. DRG. 3-122
3
C
TORISPHERICAL
mm
C
915.4
kg/cm2g
kg/m3
mm
mm
mm
min
TL-TL LENGTH OF BOOT
NO
NO
1400
4100
N.A.
N.A.
@ 153
STEAM CONDENSATE
kg/h
kg/m3
kg/h
C
GAS/
VAPOR
LIQ.
TEMPERATURE
PRESSURE
MW
QUANTITY
DENSITY
QUANTITY
STEAM OUT CONDITION
VORTEX BREAKER
IF YES THEN TYPE
DESIGN TEMPERATURE
VACUUM CONDITION
DEMISTER
IF YES THEN TYPE
IF YES THEN
INSULATION
CORROSION ALLOWANCE
SPECIAL SERVICE
INSIDE DIAMETER
RJB
12/4/2004
IF YES THEN TYPE
HEAD TYPE
INSIDE DIAMETER OF BOOT
FLUID
REV.
MADE
NORMAL HOLD UP TIME
OPERATING CONDITIONS
4
18
40861 (Note-4)
RHDCHKD.
NO
5
VERTICAL
CLEAN MP CONDENSATE FLASH VESSEL
1
151.6
4605 (Note-4)
2.63
DESIGN PRESSURE 10
TL-TL LENGTH
YES
DESIGN CONDITIONS
CODE / REGULATION
DENSITY
0
NPK
-
8/3/2019 Business Trading Module
41/65
-
8/3/2019 Business Trading Module
42/65
Mid & Downstream Business Training Module
Updation of P&IDs based on Hydraulic results
Licensor P&ID
-
8/3/2019 Business Trading Module
43/65
-
8/3/2019 Business Trading Module
44/65
Mid & Downstream Business Training Module
Updation of Pumps and Instruments datasheets based
on Hydraulics
Licensor Datasheet
-
8/3/2019 Business Trading Module
45/65
Mid & Downstream Business Training Module
Updated Pumps datasheets based on Hydraulics
-
8/3/2019 Business Trading Module
46/65
Mid & Downstream Business Training Module
Development of Control Narratives
This narrative describes the plant control systems by
instrumentation.
The purpose of this document are as follows :
(1) To explain control systems to those who may
not be familiar with instrumentation symbols
or functional logic diagrams.
(2) To define purpose and algorithm of eachcontrol system.
Pump auto start systems will be also covered in this
document.
-
8/3/2019 Business Trading Module
47/65
Mid & Downstream Business Training Module
Development of Safeguarding Narratives
The purpose of this narrative is to thoroughly
explain the safeguarding scheme and its
significance. Based on the same it is possible to
understand how safeguarding scheme works and
how it will be depicted in Cause and Effect
diagram or Safeguarding Matrix.
-
8/3/2019 Business Trading Module
48/65
Mid & Downstream Business Training Module
Sample of Cause and Effect Diagram
P-5105BHPSTEAMVALVE
P-5105AHPBFWPUMP
P-51203HPBFWPUMP
P-51402AMPBFWPUMP
P-51206AHPBFWPUMP
P-51206BHPBFWPUMP
P-51206CHPBFWPUMP
P-51206DHPBFWPUMP
COMMONTRIPALARM
CAUSE CLOSE TRIP TRIP TRIP TRIP TRIP TRIP TRIP ALARM ACTION
TAG NO. DESCRIPTIONPEFS NO.
51UZA-2103
51UZA-2102
51UZA-2104
51UZA-2100
51UZA-2105
51UZA-2106
51UZA-2107
51UZA-2108
51UZA-2100
TAG NO.
51LZA-2008 D-0098-51-25-0006 X X X X X 51LZA-2008
51LZA-2011 D-1651-51-50-0018 X X X X X 51LZA-2011
51LZA-2008 D-0098-51-25-0006 X X X X X X X X X 51LZA-2008
51LZA-2011 D-1651-51-50-0018 51LZA-2011
51LZA-2008 D-0098-51-25-0006 51LZA-2008
51LZA-2011 D-1651-51-50-0018 X X X X X X X X X 51LZA-2011
V-51203 LEVEL LOW LOW
V-51210 LEVEL LOW LOW
V-51203 LEVEL LOW LOW
V-51210 LEVEL LOW LOW
EFFECT
51UZA-2100 V-51203 / V-51201 SGS
DESCRIPTION
SAFE GUARDING MATRIX UNIT 51
V-51210 LEVEL LOW LOW
V-51203 LEVEL LOW LOW
Cause Section
Effect Section
-
8/3/2019 Business Trading Module
49/65
Mid & Downstream Business Training Module
STAGE 2:
Interface Activities
Updation of Control & Safeguarding narratives and issue
for HAZOP Study
Updation of Utility summary
Updation ofLine list
-
8/3/2019 Business Trading Module
50/65
Mid & Downstream Business Training Module
Interface Activities
Vendor Document Review
Review of Engineering Drawings
Review of Plot Plan
3D-Model Review
Review of DCS Graphics
-
8/3/2019 Business Trading Module
51/65
Mid & Downstream Business Training Module
Vendor Document Review
Some of the Critical points to be reviewed in EngineeringDrawings are:
Consistency of Process data as per process datasheetssuch as Operating & Design Conditions, MOC, Special
service requirements, etc.
Review of other technical aspects
(a) Meeting all Specifications as per requirement.
(b) Expected Utility consumption figures.
(c) Guarantee figures, if any.
(d) Other technical requirements specified in therequisition.
(e) Fulfilment of Scope of Supply.
-
8/3/2019 Business Trading Module
52/65
Mid & Downstream Business Training Module
Review of Engineering Drawings
Some of the Critical points to be reviewed in EngineeringDrawings are:
Consistency of Process data as per process datasheetssuch as Operating & Design Conditions, MOC, Specialservice requirements, etc.
Number of Nozzles
Sizes of Nozzles
Checking location and orientation of all nozzles
especially nozzles for Temperature, Pressure and
Level Instruments as per Project requirements
-
8/3/2019 Business Trading Module
53/65
Mid & Downstream Business Training Module
Review of Plot Plan
Some of the Critical points to be reviewed in Plot plan are:
Consistency of equipments shown in plot plan withEquipment List, PFD and P&IDs.
Are the distances between equipment kept minimum withrespect to pressure drop?
Are the height of Towers and vessels enough toprovide NPSH of pumps?
Are the equipment located symmetrically such as column andreboilers?
Is there enough space around columns, towers andreactors for removal of internals?
Is there enough space to remove tube bundle of heatexchangers?
Are the equipments arranged considering safetyaspects especially for Fired heaters, Compressors andTanks?
-
8/3/2019 Business Trading Module
54/65
Mid & Downstream Business Training Module
3D-Model Review
Some of the Critical points to be considered in 3D-modelreview are:
Is piping arranged to provide straight runrequirement such as inlet of tower?
Are CV sets placed as per Project requirements such as
closeness to equipment, at high or low level, etc., if
any?
Are symmetrical piping considered for AFCs?
Are the valves located at operable location from the
nearest platform or grade?
Is piping arranged to keep special bending radius
requirements, if any?
-
8/3/2019 Business Trading Module
55/65
-
8/3/2019 Business Trading Module
56/65
Mid & Downstream Business Training Module
STAGE 2 (Continued):
Updation of Control & Safeguarding narratives and issue
for HAZOP Study
Updation of Utility summary
Updation ofLine list
-
8/3/2019 Business Trading Module
57/65
Mid & Downstream Business Training Module
STAGE 3:
Safety Studies / Analysis
Updation of P&IDs based on Safety Studies
recommendation
Preparation of Precommisioning manual
Preparation of Operating manual
-
8/3/2019 Business Trading Module
58/65
Mid & Downstream Business Training Module
Safety Studies / Analysis
HAZOP Study
SIL Study
FIREPRAN Study
-
8/3/2019 Business Trading Module
59/65
Mid & Downstream Business Training Module
HAZard and OPerability study is a technique to examine a
system, part by part, in a very systematic manner, to find
out the cause and consequence of every conceivable
deviation in the normal operation of the system as well
as during emergencies, start-ups and shutdowns. The
method enables prediction of all possible ways in which a
hazard or an operating problem could arise, whether thedesign takes preventive care of them and if not,
recommends changes (Action) as may be necessary.
HAZOP Study
-
8/3/2019 Business Trading Module
60/65
Mid & Downstream Business Training Module
SIL
Measurement of confidence level for performance of safetyfunction is called the Safety Integrity Level(SIL)
Safety integrity of a system can be defined as The probability (likelihood) of a safety-related systemperforming the required safety function under all the stated
conditions within a stated period of time SIL is a measure of the reliability of the safety function
performing to specification.
The SIL is based on the accepted risk level and ranges from 1to 4
Probability of FailureSafety
IntegrityLevel (SIL)
Mode of Operation On demand(average probability of failure to perform
its design function upon demand)
Mode of Operation continuous(probability of dangerous failure per
hour)
4 > 10-5
to < 10-4
> 10-9
to < 10-8
3 > 10-4 to < 10-3 > 10-8 to < 10-7
2 > 10-3
to < 10-2
> 10-7
to < 10-6
1 > 10
-2
to < 10
-1
> 10
-6
to < 10
-7
-
8/3/2019 Business Trading Module
61/65
Mid & Downstream Business Training Module
FIREPRAN study
FIRE PRotection &ANalysis is a new technique employed atthe design phase of a facility or installation to achieve thefollowing objectives
Overview the role of the facility and its significance to the
overall operation. Review the facilitys Fire and Explosion Strategy (FES) in the
context of the role of the facility and its significance to theoverall company.
Analyze threats to loss of containment or other potentialsources of combustion events.
Assess release event consequences and explosion scenarios
Review and assess adequacy of threat control measures,mitigation and recovery measures.
Make recommendation for risk reduction measures toachieve levels as low as reasonably practicable (ALARP).
-
8/3/2019 Business Trading Module
62/65
-
8/3/2019 Business Trading Module
63/65
Mid & Downstream Business Training Module
Critical Area identification
Area in red needs tobe given extensive
consideration for fireprotection systems
-
8/3/2019 Business Trading Module
64/65
Mid & Downstream Business Training Module
Updation of P&IDs based on Safety Studies
recommendation
Preparation of Precommisioning manual
Preparation of Operating manual
STAGE 3 (Continued):
-
8/3/2019 Business Trading Module
65/65
Mid & Downstream Business Training Module