Business Planning Criteria
Transcript of Business Planning Criteria
8/8/2019 Business Planning Criteria
http://slidepdf.com/reader/full/business-planning-criteria 1/41
Network Rail
Business Planning Criteria
March 2006
8/8/2019 Business Planning Criteria
http://slidepdf.com/reader/full/business-planning-criteria 2/41
2
Network Rail Business Planning Criteria
Contents
Introduction .....................................................................................................................................3 Part 1: Strategy .........................................................................................................................4 1 Corporate strategy.....................................................................................................................5 2 Stakeholder and statutory requirements...................................................................................9 Part 2: Asset management....................................................................................................11 3 Asset management framework...............................................................................................12 4 Utilisation and output specification..........................................................................................13 5 Asset policies ...........................................................................................................................17 6 Investment regulations.............................................................................................................21 7 Asset plans...............................................................................................................................28 Part 3: Appendices.................................................................................................................31 Appendix 1: Supporting documents...........................................................................................32 Appendix 2: Integrated Risk Management Process.................................................................33 Appendix 3: Regulatory targets..................................................................................................34 Appendix 4: How the criteria are applied in practice.................................................................36 Appendix 5: 26 strategic routes..................................................................................................38 Appendix 6: Route classification................................................................................................39 Appendix 7: Draft network capability parameters .....................................................................40
8/8/2019 Business Planning Criteria
http://slidepdf.com/reader/full/business-planning-criteria 3/41
3
Network Rail Business Planning Criteria
IntroductionNetwork Rail has a pivotal role in a complex
industry, with responsibility for the operation,
maintenance, renewal and, in conjunction with train
operators and funders, the development or
enhancement of the national rail network. As a
consequence, the way in which we look after ourassets affects a wide range of people. For
example, it is important for train operators,
passengers and freight users that we operate and
maintain the network in a way which allows their
services to run safely, efficiently and reliably. In
addition, there are wider benefits to society and the
environment to be gained from delivering an
effective national rail network that provides an
integrated, socially inclusive and sustainable
transport system.
Our aim is to carry out the asset management
activities that support these responsibilities in a way
that provides demonstrable value for money to
passenger and freight operators and to the ultimatecustomers of the railway – the fare paying
passengers, freight users and the taxpayer. We are
committed to integrating environmental
management with the safe and efficient operation of
the railway and treat all legal obligations as the
minimum standard.
PurposeThe purpose of this document is to help our
employees and industry partners understand:
• the context in which investment and other
decisions are made to meet our obligations
• the criteria to be applied in making these
decisions in accordance with Condition 7 of our
network licence (including the priority and timing
of maintenance and renewal works and the parts
of the network where this will be carried out)
• where constraints exist (e.g. the availability of
funding, access to the network or resources to
carry out the work), how activities should be
prioritised and trade-offs made
• how we engage with our stakeholders on the
development of these plans and ultimately
improve the value delivered by the rail network.
ScopeThe criteria detailed in this document apply to all
assets that are owned and managed by NetworkRail that constitute the national rail network, and
cover design, installation, maintenance and renewal
– both at an individual asset and at a system level.
This document does not specifically address
operational issues. Our operating policies set out
how the services on the route will be delivered
safely and reliably, including the contribution made
by the production of a resilient timetable. The
Railway Operational Code (ROC) sets out the
arrangements for the day-to-day management and
control of the network and includes both network-
wide sections and route sections reflecting the
specific circumstances of the route.
The Business Planning Criteria is the primary
document for outlining the principles by which we
deliver our asset management responsibilities.
There are a number of other documents that areimportant in this process, as outlined in Appendix 1.
Additional information on the key principles
contained in these documents and the context
within which they are used are referenced
throughout this document as appropriate. In
addition, some of the content of these documents
has been duplicated here to minimise the need for
the reader to access multiple documents. During
2006 it is our intention to replace these references
with hyperlinks and remove much of this duplicated
text.
This document has been updated following the
consultation issued in 2005 and subsequentdiscussion with stakeholders. Although it is not
subject to further consultation before being
established it will continue to be developed in the
light of further discussion with these stakeholders.
In particular we would hope to simplify the
document considerably with the detail being
updated separately as the issues become more
widely understood and accepted. To this end users
of this document are invited to send their views and
feedback to:
Director, Planning & Regulation
Network Rail
40 Melton Street
LondonNW1 2EE
This document is available on the Network Rail
website (www.networkrail.co.uk).
8/8/2019 Business Planning Criteria
http://slidepdf.com/reader/full/business-planning-criteria 4/41
4
Network Rail Business Planning Criteria
Part 1: Strategy
8/8/2019 Business Planning Criteria
http://slidepdf.com/reader/full/business-planning-criteria 5/41
5
Network Rail Business Planning Criteria
1 Corporate strategy1.1 Our strategyThe successful delivery of our asset management
responsibilities requires a robust and consistent
framework that defines the actions we take to
optimise the overall cost of the railway and the
services to passengers and freight users. Deliverymust be achieved within the available funds and be
consistent with the reasonable requirements of our
stakeholders. Our strategy to achieve these aims is
as follows:
• we will continue our focus on passenger and
workforce safety and strive to maintain the
position where rail travel is one of the safest forms
of transport
• we plan to deliver all existing contractual and
regulatory commitments, except where analysis
and consultation demonstrates that better value
for the available funds would be obtained by
agreeing changes to the required outputs
• our future plans for the network will be developed,following consultation, in a manner that meets the
reasonable requirements of our customers,
funders and other key stakeholders. These plans
will be sufficiently transparent to enable key
stakeholders to plan their own activities with a
reasonable degree of assurance
• to continue working with ORR, DfT and Transport
Scotland on the development of a long-term
strategy for the network
• as it is generally in the long-term interests of the
industry, and where funding constraints and
industry processes allow, we will manage our
business on an optimised whole life, whole
railway cost basis, and avoid compromising the
future affordability and performance of the
network. Where funding or deliverability
constraints necessitate a departure from this
approach, consideration will be given to the
impact on passengers and freight users and to
minimising the impact on future costs or outputs
• we will continue to seek refinements to the
regulatory and contractual regime which (a)
incentivise and empower our employees to ‘do
the right thing’, (b) provide them with appropriate
levers to enable them to do this, and (c) provide
for proportionate and targeted monitoring
enforcement which allows the business to focus
on delivery without excessive intervention
•
we will continue to enhance the value of therailway by improving the efficient delivery of our
investment in the network. Where possible we
will seek to be the delivery provider of choice, but
where appropriate we will establish processes
that facilitate third party delivery and financing of
options to help grow the railway
• we will work with the rest of the industry to
understand our environmental impacts, identify
good practice and plan improvements.
Imbalances in the cost and revenue streams
between various industry partners will invariably
result in initiatives being progressed that may have
a disproportionate effect on another part of the
industry. It is important, therefore, that when
considering the cost and benefit analysis of any
option to deliver the required outputs, the net
industry impact is the key driver of decisions.
Where the industry framework presents obstacles to
this we will seek to address these with our industrypartners and ORR.
Underpinning the way we work and to deliver our
strategy we have identified six values that we live
by:
• safety • customer focus
• integrity • excellence
• self-confidence • dependability.
We have also defined the behaviours that govern
the way that we approach our work. They are
translated into the way we conduct ourselves in our
day-to-day work through the attitudes and
behaviours we display:
• enthusiasm • pride
• teamwork • can do / will do.
1.2 The delivery of this strategyThe effective development of plans to implement
this strategy requires a holistic approach to all
aspects of asset management, and the systems we
are putting in place address the following
dimensions:
• systematic – wherever appropriate we use an
objective, evidence based approach promoting
consistent, repeatable and transparent decisions
and actions. This approach is applied at allphases of an asset’s lifecycle
• systemic – we consider the assets from a
system perspective, avoiding the optimisation of
individual assets in isolation
• risk-based – resources are allocated and
priorities set using a common set of risk assessed
management principles (see Appendix 2)
• optimal – we establish the optimum trade-off
between competing factors such as reliability,
cost and risk associated with the assets over their
lifecycles
• sustainable – wherever funding or resource
constraints allow we make sure that the future
cost base or capability of the network is not
compromised as a result of the delivery of short-
term objectives.
1.2.1 The planning criteria that underpin thedelivery of this strategyThe operation of this strategy requires a
comprehensive understanding of the criteria that
must be considered when developing and
implementing our asset management activities, and
the systematic organisation of these activities. This
will deliver:
8/8/2019 Business Planning Criteria
http://slidepdf.com/reader/full/business-planning-criteria 6/41
6
Network Rail Business Planning Criteria
• assets that are managed effectively
• optimal use of resources to achieve the required
outputs
• compliance with legal, regulatory and statutory
requirements
• risks that are actively managed
•
plans that are sustainable beyond the currentcontrol period
• decision-making processes that are transparent
to our customers and funders.
The determination of the network outputs is a
complex and iterative process that requires an
understanding of a number of interrelated issues.
We have put in place an asset management
framework (described in Part 2) that enables us to
manage these interrelated issues in a manner that
supports the effective and efficient delivery of our
corporate strategy
Asset information
The availability of fit-for-purpose asset information isessential to the effective and efficient delivery of our
asset management systems. We currently have
access to a wide range of asset information to
support the discharge of these responsibilities, and
in recent years we have made considerable
improvements to our processes and systems.
However, as with many organisations responsible
for managing a large and diverse asset base, some
of our existing data remains dispersed and of an
inconsistent or undefined quality. Our Asset
Information Strategy is designed to overcome these
inadequacies and enable the effective and efficient
provision of the required data.
Unit costsThe development of appropriate unit cost
information is critical to the understanding of our
cost drivers by the company and our stakeholders.
It is particularly important when seeking to optimise
maintenance and renewal strategies, to
demonstrate compliance with efficiency targets, in
controlling activity volumes and for benchmarking
purposes. We have prioritised development of
improved unit cost information in order to maximise
our understanding of the highest value repeatable
activities, particularly in maintenance, track and
signalling renewals.
Both inter-company and intra-company
benchmarking play an important role in monitoring
and improving the operation of our processes so
that we are able to drive continuous improvements
in efficiency and performance. Intra-company
benchmarking is being enhanced by the further
development of better analysis tools and techniques
and more appropriate data specifications.
1.3 Customer reasonable requirementsIn developing the network we seek to understand
and meet the reasonable requirements of train
operators, other providers of services relating to
railways and funders. We use the criteria set out
below to assess if a requirement is reasonable.
Where a scheme is to be funded or delivered by
Network Rail all three criteria must be met for it to
progress.
1.3.1 Financial criteria
A requirement is regarded as reasonable subject toit satisfying any of the following conditions:
• it can be achieved at no extra net cost (i.e.
including future maintenance or operational
liabilities) to Network Rail or
• it can be achieved at no extra net cost to Network
Rail, as it forms part of a scheme which we are
expected to undertake for the renewal or
enhancement of the network or
• the customer or funder commits to pay extra
funds, or procure the payment of additional funds
to Network Rail, based on the cost of delivering
and financing the enhancement, including a
return which is commensurate with the risks
carried by Network Rail or• the funding for the expenditure involved is
explicitly provided for at an access charges
review
and it is not unduly difficult for Network Rail to
finance the scheme taking account of the other
financing requirements of its regulated business.
Where relevant, we will work with our customers
and funders to help secure additional sources of
funding for development of the network.
1.3.2 Compatibility with existingcommitmentsA requirement is regarded as reasonable subject to
it satisfying each of the following conditions:
• it does not conflict with the existing access rights
of other operators, including local output
commitments
• it is not designed to give unfair advantage over
other bidders in future franchise negotiations
• it does not impede our ability in the future to
deliver the published strategy on any route
(including performance objectives for the route)
• it is consistent with our obligations under the
network licence and statutory duties under the
Railways Act or other law
• we are able to operate the revised infrastructure
or service in a safe and efficient manner,
consistent with our safety case and existing
processes and procedures.
Where a proposed scheme does conflict with an
existing route strategy, consideration would be
given to amending the strategy, subject to
discussion with our funders and other operators on
the route.
1.3.3 Deliverability criteriaIn order to avoid the possibility of diverting
resources used to support the safe, efficient and
reliable running of the scheduled services a
8/8/2019 Business Planning Criteria
http://slidepdf.com/reader/full/business-planning-criteria 7/41
7
Network Rail Business Planning Criteria
requirement is regarded as reasonable subject to it
satisfying each of the following conditions:
• the requirement is clearly defined and its scope
and timescale for delivery are realistic
• the output is measurable, ensuring that all parties
can agree delivery has been achieved• Network Rail has, or can obtain, the necessary
resources to implement the scheme
• network access can be made available
• delivering the scheme does not unacceptably
compromise our ability to deliver the existing
programme of works on the route.
Where there are constraints on our ability to deliver
a scheme that is proposed by our stakeholders, or
to support a third party delivered scheme, we will
work closely with the stakeholder to identify options
for relieving these constraints. In some
circumstances this may necessitate a proposal
being deferred until the resource constraints are
alleviated.
1.4 Proposed changes to network capacityor capabilityWhere a proposed investment will result in a
material physical change to the infrastructure (for
example a change to the network layout as a result
of the removal of a cross-over) or a material change
to the operation of the network (for example a line
speed increase) we seek approval for the change
through the Network Change process, under Part G
of the Network Code. This process requires
detailed consultation with funders and train
operators and consideration of the likely impact on
their businesses of the proposed change. For each
change proposal a business case is prepared. Theproposed Network Change is only considered
where industry value is enhanced: for example, any
infrastructure cost savings are in excess of
additional costs generated elsewhere, or additional
infrastructure costs are less than industry benefits.
Where relevant it is also necessary to take account
of any compensation payable under the industry
processes.
A Network Change may also have a significant
impact on a station and therefore require a Station
Change, which has a separate consultation
process. Proposed investment to the network could
also be the result of a Vehicle Change, consulted
and accepted through the processes under Part F
of the Network Code.
1.5 Dealing with surpluses and deficits1.5.1 Use of surplusesAs part of the Access Charges Review 2003 (ACR)
the Office of Rail Regulation (ORR) set Network
Rail’s access charges so that meeting the
regulator’s efficiency and output assumptions would
result in an expected level of profit which can be
used to reduce the expected increase in the
company’s debt. The company aims at least to
meet these efficiency and output assumptions and
outperformance of these assumptions may
therefore result in additional profit compared to that
which was assumed in the review. ORR has
indicated that Network Rail is best placed to
determine the use of any such outperformance in
consultation with key stakeholders, particularly DfT
and Transport Scotland. ORR has therefore askedus to set out the criteria which would be applied in
deciding between the alternative options during the
third control period. In determining the extent of any
additional profits that would arise from
outperformance we would need to take account of
the following:
• Costs. The value of scope and unit cost
efficiency savings achieved in meeting the ACR
outputs when compared against ORR’s
expenditure assumptions. However, deferral of
expenditure to future control periods would not be
treated as outperformance. Such deferrals may
be optimal, but the company would not expect to
be paid twice for this work when it needs to becarried out and it is therefore necessary to make
sure that some debt headroom is retained.
• Income. The degree to which we exceed the
ACR property and other single till income
forecasts. However, in some cases, additional
receipts may be accelerated from future control
periods and, in these circumstances, the
additional income would not be treated as
outperformance. In other cases, we would take
the opportunity to use developers’ funds to
improve station condition or facilities – we are
discussing with ORR how the resultant financial
benefits may be shared with developers and the
appropriate treatment of these improvements in
the Regulatory Asset Base (RAB).• Net effect. We would need to consider the net
effect of additional revenues, cost savings and
RAB additions to determine the overall level of
additional profit from outperformance. The
structure of charges is designed so that additional
variable track access charges arising from
incremental traffic flows are intended broadly to
offset any additional costs across the network as
a whole and it is therefore necessary to take
account of the change in net costs. Any additions
to the RAB would be treated in the same way as
additional income. Potential downwards
adjustments to the RAB where required outputs
have not been delivered would also be taken into
account.
• Outputs. Beating the ACR outputs will not
necessarily lead to additional profits in CP3 but
will improve the affordability of the rail network in
future control periods.
• Timescale. Outperformance should be assessed
over the entire control period. We are committed
to delivering the overall output requirements
within the available funds during the control
period as a whole. Outperformance in one year
may be offset by underperformance in
subsequent years. A realistic assessment of the
likely level of outperformance over the control
8/8/2019 Business Planning Criteria
http://slidepdf.com/reader/full/business-planning-criteria 8/41
8
Network Rail Business Planning Criteria
period cannot be made until at least the third year
of the control period. Even in the third year of the
control period, it is appropriate for us to take a
prudent view of the potential for improvements in
efficiency or additional costs.
If there is expected to be a significant element ofadditional profits in CP3 from the above, we would
then consider the most appropriate use of that
surplus based on the following priorities.
An overriding principle is that where Network Rail
considers it necessary to reduce the level of debt for
financeability reasons or to make certain that the
company is able to comply with its obligations; any
additional profits will be used to reduce debt.
Relevant obligations would include Condition 12
(ring-fencing) and Condition 29 (level of financial
indebtedness) of our network licence. If these
constraints do not apply, the following issues would
then be considered to determine how any additional
profits should be used.
If there is no financeability or compliance issue then
we believe that at least a proportion of any
additional profit from outperformance should be
used to fund worthwhile investments that either
reduce future cost or improve the outputs from the
railway. Potential schemes would have to have a
positive industry business case (determined as
explained in other sections of this document).
Before committing to any significant investments,
we would expect to discuss the matter with the two
principal funders, Department for Transport (DfT)
and Transport Scotland, and with ORR. The two
Governments are likely to have slightly different
preferences for any additional investment and thesewishes will be taken into account in the choice of
possible schemes. For example, at the time of
writing we understand that DfT’s initial preference is
for investment to increase the capacity of the
network and that Transport Scotland’s preference is
for investment to reduce journey times on key
routes. The final decision on how we re-invest our
profits will have to rest with Network Rail. We would
also seek to use our investments to leverage other
sources of funding taking account of available
opportunities. Given the potential time horizon for
such investments, this may involve some
expenditure in future control periods – in this case
the relevant funds would be set aside so that this
can be treated consistently at the next periodic
review.
If the level of additional profit from outperformance
exceeds the value of worthwhile investments which
it is appropriate to fund from any outperformance
then we will use the surplus to reduce our debt.
Network Rail has substantial debts which it has
inherited or due to the levels of expenditure that was
necessary to address previous underinvestment in
the network. This is also reflected in the value of
Network Rail’s RAB. Reducing debt (and
increasing the level of headroom between the level
of debt and the RAB) can help to improve the
financial stability of the business, our ability to
withstand potential future cost shocks, and the
longer term affordability of the railway. Reductions
in debt will benefit the company’s overall financial
position and therefore our main funders. The
impact on the respective funding requirements inScotland and England and Wales would be a matter
for discussion as part of the periodic review
process.
1.5.2 Remedial plansWe are determined to deliver the required outputs
within the available funds through improvements in
efficiency due to procurement savings, rigorous
financial control, improved planning and increased
quality of what we deliver. It must be recognised,
however, that precise plans for achieving efficiency
targets several years away will not generally be
available. Where the required efficiency savings
cannot reasonably be expected to be achieved, a
remedial plan will be developed and reflected in ouroverall plans. In developing this plan the same
principles as used for prioritising expenditure in
general would be followed and the options would be
evaluated by considering the whole railway cost and
benefits delivered. As a general principle, therefore,
our continued priority would be to seek to achieve
an appropriate balance between infrastructure costs
and the value of services provided on each route.
Actions to achieve the necessary reduction in
expenditure in line with these principles would
include:
• the potential non-achievement of efficiency
targets would be subject to a rigorous challenge
and further opportunities sought, includinginitiatives to reduce further the costs of
maintenance and renewal activities and the
scope of individual schemes, where this does not
compromise the required outputs
• further expenditure savings could be realised by
the deferral of renewal activities or by allowing
asset condition to deteriorate where there is no
immediate impact on contractual or regulatory
outputs. When considering this option the whole-
life cost impact would need to be determined to
confirm that the future cost of the railway is not
compromised
• we would re-examine the route infrastructure and
service balance to identify any further
opportunities to amend route reliability and
capability (with corresponding adjustments to
existing contractual commitments as appropriate)
where such a course of action would realise
whole railway cost savings.
Any remedial plans would be developed following
engagement with our stakeholders as part of our
normal planning processes and be reflected in our
annual business plans. They would therefore be
subject to review by ORR to confirm that they are
consistent with the requirements in Condition 7.
8/8/2019 Business Planning Criteria
http://slidepdf.com/reader/full/business-planning-criteria 9/41
9
Network Rail Business Planning Criteria
2 Stakeholder and statutoryrequirementsThe effective delivery of our asset management
responsibilities requires close cooperation with train
operators and other stakeholders. It also highlights
the need for a comprehensive understanding of
their expectations, encompassing both contractualand regulatory obligations, and their aspirations for
the development of the network.
2.1 Key stakeholdersOur immediate customers are the passenger and
freight train operators. On generic industry-wide
issues, passenger operators are often represented
by the Association of Train Operating Companies
(ATOC). However, our own focus also needs to be
on our ultimate customer – passenger and freight
users. Our approach is to work closely with
operators to focus jointly on the final users of the
railway, which are often represented by Passenger
Focus, London TravelWatch, the Rail Freight Group
(RFG) and the Freight Transport Association (FTA).
The main funders of network outputs are the
Department for Transport (DfT) and Transport
Scotland. Other funders include Welsh Assembly
Government, Transport for London (TfL), the
Passenger Transport Executives (PTEs), local and
county councils, the European Union (EU) and third
parties. Our many suppliers have a key role in the
quality, cost and reliability of the rail infrastructure
and we are working closely with them to deliver
improvements in effectiveness and efficiency.
We are subject to independent economic and safety
regulation by the Office of Rail Regulation (ORR).
Effective stakeholder consultation is essential to the
development of our investment plans. We achieve
this via a series of regular bilateral and cross-
industry meetings with these stakeholders. These
communication channels are discussed in more
detail throughout this document.
2.2 Contractual and regulatorycommitmentsOur obligations arise from various commitments that
are described below.
2.2.1 Contractual commitments
Our contractual commitments to the passenger andfreight train operators and funders are documented
in the track access agreements, the associated
Network Code and various agreements to provide
enhancements to the network. The Network Code
provides a common set of rules that apply to all
parties to regulated track access contracts. It forms
a set of conditions for access to the network, setting
out the protection for, and obligations of, Network
Rail and train operators. Network Rail and train
operators are responsible for the development of
the Network Code (subject to regulatory protection
by the ORR) to make sure that it provides an
effective basis for their partnership in improving the
overall performance of the railway. We have
developed template enhancement contracts that are
intended to simplify arrangements and provide for a
reasonable allocation of risk.
2.2.2 Reasonable requirements under
Condition 7 of the network licenceCondition 7 of the network licence places a number
of requirements on Network Rail in respect of our
stewardship of the network, including its operation,
maintenance, renewal, improvement, enhancement
and development. The overall purpose of these
requirements is that we carry out these activities in
accordance with best practice and in a timely,
efficient and economical manner so as to satisfy the
reasonable requirements of persons providing
railway services and funders in respect of the quality
and capability of the network. The ORR established
the main elements of our reasonable requirements
through the 2003 ACR and this includes a series of
measures of network capability, performance,
serviceability and condition. A summary of thesemeasures can be found in Appendix 3. We are
required to develop detailed plans consistent with
these reasonable requirements.
We are also required to understand and meet the
reasonable requirements of train operators, other
providers of services relating to railways and
funders. Defining these requirements includes
discussion with train operators about the future
capacity, capability and reliability of the parts of the
network on which they run their services. The
criteria that need to be considered when assessing
if a requirement is reasonable are set out in Section
1.3. Following the Rail Review our reasonable
requirements include those of the Secretary of Stateand Transport Scotland, with these requirements
represented by the regulatory outputs agreed with
ORR. We are working with the ORR, DfT and
Transport Scotland to develop these arrangements
for the 2008 Periodic Review. Network Rail and
ORR recently agreed amendments to Condition 7 in
the light of the company’s new responsibilities
following the Rail Review. These changes clarify
our role in relation to the facilitation of overall
industry performance and the development of Route
Utilisation Strategies.
2.2.3 Other regulatory requirementsThe stewardship requirements arising from
condition 7 of the network licence are underpinned
and supplemented by a number of other licence
conditions, including:
• Condition 9 (timetabling) – we must plan
investment on the network in a timely and efficient
manner to enable reliable timetable information to
be provided to passengers
• Condition 10 (non-discrimination) – in carrying
out our activities we must not unduly discriminate
between particular persons or between any
classes or descriptions of persons
8/8/2019 Business Planning Criteria
http://slidepdf.com/reader/full/business-planning-criteria 10/41
10
Network Rail Business Planning Criteria
• Condition 24 (asset register) – this requires us to
establish and maintain a register of relevant
assets, including their condition, capability and
capacity
• Condition 25 (dependent persons) – the
principles and procedures that we apply in our
dealings with potential or actual providers orfunders of railway services and facilities
• Condition 26 (disposal of land) – the principles
and procedures that cover the disposal of land
• Condition 28 (Management Incentive Plan) –
specifies the matters that Network Rail must have
regard to when developing its Management
Incentive Plan, including the achievement of the
purpose of Conditions 7 and 25.
2.2.4 Safety and environmentalrequirementsWe have a duty to make certain that all our
activities, including those undertaken to meet our
asset management responsibilities, meet our
obligations under health and safety law to achieve alevel of safety risk that is As Low As Reasonably
Practicable (ALARP). We are also subject to a
number of statutory environmental obligations that
affect our stewardship of the network.
2.2.5 European RequirementsEuropean originated legislation is increasingly
defining the standards and legislation which applies
to the UK railway network. The 1st and 2nd
Railway Packages are currently being transposed
into British law, with the 3rd Railway Package under
discussion in Brussels. The European Rail Agency
(ERA) has now been set up and is responsible for
drafting new Technical Standards of Interoperability
(TSIs) in addition to reviewing existing standards.Although ERA undertakes cost benefit analysis,
these standards may still have cost implications for
the UK railway network. Once these TSIs have
been developed there is often a second stage in the
development whereby Euronorms (EN) are
produced to further define the outputs of the
standards. The development of these can be
crucial to the UK as there is no requirement to carry
out any cost benefit analysis during their drafting.
Once published in the European Journal, TSIs
apply to all new and major upgrades of designated
High Speed and designated Conventional
Infrastructure. In addition, a condition of the
European Commission is that any scheme it
contributes to must be built to TSI requirements.
8/8/2019 Business Planning Criteria
http://slidepdf.com/reader/full/business-planning-criteria 11/41
11
Network Rail Business Planning Criteria
Part 2: Asset management
8/8/2019 Business Planning Criteria
http://slidepdf.com/reader/full/business-planning-criteria 12/41
12
Network Rail Business Planning Criteria
3 Asset managementframeworkThe effective and efficient implementation of our
corporate strategy requires an asset infrastructure
that meets our customers’ and funders’
requirements, in terms of capacity, capability,
reliability and cost. Our asset managementframework, and the investment planning process
that underpins it, provides a structured approach to
this challenge.
Figure 1, below, identifies the four key components
of this framework.
Utilisation and output definition – this is the
mechanism by which we establish our regulatory
and contractual commitments at a route level. It
also provides a platform for:
• consideration of our customers’ and funders’
aspirations for amendments to the existing
capacity, capability or performance of the
network, using the criteria of fundability,
compatibility and deliverability described above
• consideration of opportunities to change the
capacity or capability of a route where analysis
and consultation demonstrates that better value
for the available funds would be obtained.
The output of this process is a route specification
that defines the required capacity, capability and
performance of the route, providing clarity to
customers and funders and for the establishment of
the asset maintenance and renewal regimes to
deliver these outputs.
Asset policies – these are in place for each of our
asset groups and describe the maintenance and
renewal regimes necessary to deliver the defined
route capacity and capability. They are
differentiated by route type where appropriate,
reflecting the volume and nature of the traffic
carried. These policies address the risks that asset
failure or degradation may have on the delivery of
our required outputs, identified as part of the
integrated risk management process, and balance
current funding availability with the long-term
sustainability of the network. An understanding of
the feasibility and cost of delivering various output
scenarios is necessary as this underpins the
development of the route specification.
Investment regulations – consideration of achange to a route specification, an amendment to
an asset policy or an individual investment decision
requires a robust, objective and transparent process
to assess the value delivered. Our investment
regulations set out the methodology for assessing
this value and the sources of data used in the
appraisal. These regulations provide details of the
sources of funds available to us for investment in
the network and the rules governing the draw down
of these funds. The approach we have adopted
secures consistency and is designed to provide
visibility to our customers and funders of the criteria
we have used to determine the value of an
investment or a change in route capacity and
capability and therefore the rationale for ourproposed course of action.
Asset plans – the result of the application of our
asset policies are our forward expenditure plans,
covering operations, maintenance and renewal, and
enhancement activities. Our investment plans are
summarised in our annual business plan. This sets
out our planned activities, expenditure and output
forecasts, generally over a 10-year planning
horizon, identifying the assumptions on which the
plan is based. These plans are structured to
provide stakeholders with sufficient detail to enable
them to plan their own activities with a reasonable
degree of assurance. A similar process is used to
support the production of our submissions for the2008 Periodic Review.
The effective implementation of this asset
management framework to develop robust asset
plans requires an understanding of the context
within which they are being developed, particularly
by our stakeholders. There are a number of factors
that our planning process must address, including:
• the iterative nature of much of our decision
making, for example where major infrastructure
renewal schemes provide the opportunity to
rationalise or enhance the operation of the
network, and hence the outputs that may be
delivered
• facilitating the delivery of changes to the capacity
or capability of the network required by
stakeholders outside of the access charges
review cycle.
The remainder of this document has been
structured to explain how these factors are
considered. Appendix 4 provides an illustration of
how this framework supports the application of our
planning criteria.
Figure 1 Key elements of the asset management
framework
InvestmentRegulations
InvestmentRegulations
E
na
ble
rs
Corporate strategyCorporate strategy
Asset plansAsset plans
Utilisation and outputdefinition
Utilisation and outputdefinition
DeliveryDelivery
Asset policiesAsset policiesInvestmentRegulations
InvestmentRegulations
E
na
ble
rs
E
na
ble
rs
Corporate strategyCorporate strategy
Asset plansAsset plans
Utilisation and outputdefinition
Utilisation and outputdefinition
DeliveryDelivery
Asset policiesAsset policies
Corporate strategyCorporate strategy
Asset plansAsset plans
Utilisation and outputdefinition
Utilisation and outputdefinition
DeliveryDelivery
Asset policiesAsset policies
8/8/2019 Business Planning Criteria
http://slidepdf.com/reader/full/business-planning-criteria 13/41
13
Network Rail Business Planning Criteria
4 Utilisation and outputspecificationTo exploit opportunities on the network to improve
overall value for our customers, funders and rail-
users requires an understanding of the output
requirements at a local level. Our move to route-
based planning is designed to facilitate this process,with the key components illustrated in the figure
below.
This section identifies the key benefits to Network
Rail and our stakeholders of route-based planning
and explains how these route plans are developed,
including:
• how we identify our funders’, customers’ and
passengers’ aspirations for the route in question,
including the role that Route Utilisation Strategies
(RUSs) play in this
• the criteria that are used to develop our longer-
term strategy for the route
•
the production of route specifications that willdeliver the desired strategy and how these
specifications are used with our asset policies to
produce plans for the section of the network
under review.
4.1 The move to route-based planning4.1.1 The key benefitsThe implementation of route-based planning is
designed to:
• improve the way we plan our business by
establishing a framework built around the
required outputs. This could, therefore, involve
incremental improvements in some areas and
reductions in other areas, subject to theestablished industry processes, rather than
automatically maintaining the capability on a like-
for-like basis
• deliver a clear route-by-route specification of the
outputs required in order to develop improved
operating and asset management plans to deliver
the outputs required
• facilitate the examination of changes in route
outputs where this will deliver improved value for
money for the rail industry and society in general
• create an environment where investment
opportunities are considered in an efficient,
consistent and systematic way and within a
framework that maintains clarity as to the over-
arching objectives and strategy for the network at
a route level
• provide greater transparency of our plans to our
customers to allow them to plan their businesses
more effectively and to improve the dialogue with
customers and wider stakeholders to refine andimprove both our customers' and our own plans
• create a coherent and transparent link from
stakeholder and customer requirements
(including the HLOS – the High Level Output
Specification) through to our operating,
maintenance, renewals & enhancement plans.
4.1.2 The segmentation of the network intostrategic routesOur ‘units’ of the network for planning purposes are
the 26 strategic routes that are illustrated in
Appendix 5. The composition of these routes in part
reflects the relevant markets of our customers and
is consistent with those used previously by the SRA
as part of its RUS analysis process.
The network is also differentiated by route type,
reflecting the volume and general nature of the
traffic carried, see Appendix 6. This approach
provides an effective means of identifying the
differing reliability and performance requirements of,
for example, high intensive routes carrying inter-city
traffic from those with a more infrequent service.
This allows for asset policies to be differentiated by
the type and nature of traffic carried and make
certain that decisions on routes with similar usage
characteristics are managed in a consistent manner
across the network.
Even at this level of disaggregation of the networkthe routes are not homogenous in terms of the
railway infrastructure, operations, asset condition
and operational characteristics. In order to support
more accurate and granular cost modelling, and
better route planning in general, we have therefore
developed a set of around 300 Strategic Route
Sections (SRS). These are contiguous subsections
of the strategic routes which are both meaningful to
external stakeholders and are more ‘homogenous’
pieces of infrastructure. All of the pieces of the
network within each SRS have the same route
classification (Primary, Secondary, London and
South East, Rural and Freight), and also broadly the
same traffic and capability characteristics.
The geographic scope of these routes is kept under
review to make sure that they remain relevant to our
customers and funders.
A key aim of our approach is to deliver plans that
provide the information required by operators and
funders to enable them to plan their activities with a
reasonable degree of assurance. Each route plan
sets out what is expected of the route, including:
Figure 2 Route-based planning
Asset policies
Route specifications and plansRoute specifications and plans
Route strategiesRoute strategies
Contractualcommitments
High LevelOutput
Specification
Customeraspirations
RouteUtilisationStrategies
Asset policies
Route specifications and plansRoute specifications and plans
Route strategiesRoute strategies
Contractualcommitments
High LevelOutput
Specification
Customeraspirations
RouteUtilisationStrategies
8/8/2019 Business Planning Criteria
http://slidepdf.com/reader/full/business-planning-criteria 14/41
14
Network Rail Business Planning Criteria
• route output targets
• expenditure, activity and network access
assumptions
• any agreed change in capacity or capability that
will be delivered over the life of the plan
• the planned utilisation of that capacity.
The strategic route is becoming the bedrock of our
planning process and our route plans provide the
backdrop against which individual stewardship
decisions are made. Our Investment Board and
Renewal Investment Panel will authorise individual
schemes against the specification and principles set
out in the route plans and asset policies.
Effective route-based planning requires close
collaboration between each of the key functions
within Network Rail, in particular Planning &
Regulation, Engineering, Maintenance, MP&I and
Operations and Customer Services. Our Route
Strategy Planning Groups (RSPGs) have
representatives from each of these functions.These groups are responsible for providing clarity
on the required current and future outputs from the
network and stations on each route, and for
ensuring that the forward route investment
programme is developed to deliver these outputs in
an effective, efficient and consistent manner,
optimising whole life costs within funding and other
constraints. It is a cross-functional forum that
discharges its accountabilities through the
mechanisms of formal meetings, reviews and
workshops. The emphasis is on considering issues
early in the planning life-cycle to improve direction
and the quality of decision-making. Formal
authorisation is, however, through the Renewals
Investment Panels and Investment Board asdescribed in our Investment Regulations.
Our forward route investment programmes are also
discussed on a quarterly basis with train operators
at the Route Investment Review Group (RIRG)
meetings. The purpose of these meetings is:
• for Network Rail to set out its forward asset
renewal programme and any plans we have to
change the capacity/capability of the route
• to identify any firm plans that other industry
stakeholders have to enhance the
capacity/capability of the route
• to explore how these plans may be amended to
meet the reasonable requirements of operators
on the route, either funded by Network Rail’s own
funds, the Network Rail Discretionary Fund
(NRDF) or by the operator or other funders.
In addition, there are a number of forums for a
consideration of broader strategic issues, as
discussed below.
4.2 Input analysis4.2.1 Route Utilisation StrategiesThe Route Utilisation Strategy (RUS) process was
established by the SRA. The initial programme of
RUSs was focussed on areas of the network where
there is a potential to generate greatest benefits,
where there is a significant mix of traffic causingissues not capable of resolution within a single
passenger franchise specification or track access
variation and where congestion exists with
significant levels of reactionary delay. To do this,
the analysis and appraisal sought to understand
which options maximise the net industry and
societal benefits rather than that of any individual
organisation or group affected.
A consequence of the Rail Review is that we have
taken on responsibility for drawing up RUSs in
which these priorities are assessed. Work on these
RUSs is now much more closely integrated with the
development of our own plans and we are
developing these in conjunction with the rest of theindustry. The current programme is primarily aimed
at informing the programme of franchise
replacements and the development of the HLOS. It
is intended that the RUS programme will evolve to
address other key decision points such as major
asset renewals. The need to appraise options from
an industry and societal perspective continues
under the Network Rail programme of RUSs. The
RUSs provide a key input to the franchise process
enabling consistency between the franchise
specification and the plans for the network.
The development of RUSs requires close
collaboration with the DfT and Transport Scotland to
understand their requirements for the routes inquestion. As a consequence, a Planning and
Franchising Steering Group has been established,
with representation from the DfT and Network Rail,
and a similar group has been established with
Transport Scotland. These groups are responsible
for overseeing the overall programme for the
preparation of RUSs, overseeing the development
of the RUS process and ensuring that the process
integrates with wider industry planning, including the
franchise specification.
It is also important to work closely with the rest of
the industry. A Rail Industry Planning Group has
therefore been established, chaired by Network
Rail. Representation includes the DfT, Transport
Scotland, PTEG, Passenger Focus, ATOC, freight
operators, Rail Freight Group, TfL and the Welsh
Assembly Government (WAG). Its purpose is not to
review individual RUSs; rather it is to consider the
overall programme and approach to RUSs. Where
appropriate, it may also discuss multi-route issues
such as freight and long distance strategies. In
addition, each individual RUS also has its own
stakeholder group, which includes representation
from the relevant funders and operators.
8/8/2019 Business Planning Criteria
http://slidepdf.com/reader/full/business-planning-criteria 15/41
15
Network Rail Business Planning Criteria
The key stages in the development of a RUS (as
set out in the RUS Technical Guide) are as follows:
• seeking clarity from the DfT of its high level
specification for the route which is expected to
draw input from stakeholders and Regional
Planning Assessments• carrying out a detailed baseline exercise for the
route, understanding asset condition and
capability, freight and passenger demand, and
infrastructure and train operator performance
• undertaking a gap analysis, considering the
strategies and plans of funders and operators on
the route
• generating options to meet the gaps, using a
toolkit of possible solution types and stakeholder
suggestions
• structuring and packaging these options where
appropriate
• filtering and reviewing the list of options
• assessing and evaluating the remaining options
to identify those requiring full appraisal• carrying out a socio-economic cost/benefit
appraisal in accordance with the agreed criteria
(this is set out in Section 6.2.2)
• selecting solutions consistent with the route
utilisation objective, and refining them into a
coherent strategy.
Throughout this process we consult with rail industry
stakeholders and the wider community to make
sure that aspirations are understood and, where
appropriate, included in the study. Representatives
of the RUS stakeholders are informed on a regular
and frequent basis of progress with the study and
participate in determining further action as
appropriate.
A RUS may recommend actions from all industry
parties and Government, not just Network Rail. For
example: fare changes, service changes, rolling
stock changes as well as infrastructure changes
could all be recommended. Those actions that fall
to Network Rail are delivered through Network
Rail’s business processes including the route-based
planning process and via inclusion in the
appropriate route specification. Some options may
require additional funding prior to Network Rail
agreeing to implement the scheme.
Extensive information on the RUS programme, the
methodology, and the individual RUSs is contained
on Network Rail’s website.
4.2.2 Other inputs to be consideredThe RUS methodology also provides a process of
review for other inputs to be considered, including
where:
• an established RUS is not definitive or has
identified issues that require further consideration
• a RUS has not yet been, or is not currently
planned to be, carried out
• a RUS is established for the route but as it was
carried out some time ago the issues addressed
at the time need to be reviewed
• a third party has an aspiration for the route that
warrants a re-examination of the strategy for the
route (e.g. Crossrail, EWS’s ‘Big Freight Railway’
strategy) or• the HLOS has identified something specific
relating to a route.
Cost/benefit analysis of any option under
consideration is carried out using the approach set
out in Section 6.2.2. In carrying out this analysis we
consider opportunities to improve overall network
value by amending existing outputs. In the longer-
term the infrastructure cost model will be used to
cost potential scenarios. Potential options are
discussed with customers and funders as
appropriate and any network change proposals are
progressed as set out in Section 1.4.
4.3 Route strategies, specifications andcapabilities
4.3.1 Route strategiesThis input analysis is used to define the strategy for
the route, identifying specific links between key
inputs and the resultant strategy. This strategy sets
out the overall intent for the route in terms of:
• the underlying assumptions considered in the
development of this strategy, including traffic
growth
• any proposed changes in capacity or capability
and when these changes are likely to be
implemented
• any key changes in train services or service
patterns• any proposed changes to network access
• those changes that are linked to specific franchise
issues
• any proposed changes in service reliability
• any proposed changes to station facilities along
the route (car parking etc)
• those factors or dependencies that may impact
on the delivery of the proposed strategy
• any unresolved issues that require further
consideration.
The strategy also sets out a framework against
which potential investment options can be tested for
strategic fit with the proposed purpose and
objectives for the route.
The strategy for each of our routes and the
underlying planning assumptions are published in
our annual business plans. We make clear within
this document those aspects of our plans that are
firm, and those that are currently aspirational.
8/8/2019 Business Planning Criteria
http://slidepdf.com/reader/full/business-planning-criteria 16/41
16
Network Rail Business Planning Criteria
4.3.2 Route specifications and plansThe route specification provides clarity on those
aspects of the strategy for the route that are to be
delivered and by when. Its purpose is to:
• provide a statement of the required outputs of the
network at a route level in order to give clarity ofrequired capability to those developing operating,
maintenance and investment plans
• provide clarity to customers, funders and other
external stakeholders of the current and future
capability expected on the network at a route level
to allow them to plan their businesses
• provide clarity to customers and funders and
other external stakeholders of what Network Rail
is funded to deliver on the route.
The route specification sets out:
• current route capability, capacity, performance
and operational requirements
• the expected current and future demand on aroute (in terms of train path requirements and its
translation into equivalent annual tonnage)
• the future required capability, capacity,
performance and operational requirements of the
route and the timescale by which these changes
must be made.
The overall specification of the routes reflects the
fact that each route is not homogeneous and
consequentially our asset management and service
delivery policies are differentiated within the route. It
is against this specification that renewal,
maintenance and (where appropriate) enhancement
plans are developed (as set out in Section 5) and
identified in our annual business plan (as explainedin Section 7).
4.3.3 Route capabilityIt is acknowledged that the current method of
defining route capability has limitations, particularly
with regard to understanding the ability of some
routes to deliver additional freight services. In
addition, there are a limited number of routes on the
network where there is a discrepancy between the
actual and published capability of the route. As a
consequence we are:
• discussing with industry partners a revised
definition of infrastructure that will deliver
increased clarity on the capability of the network
and provide a mechanism to improve industry
efficiency. Our initial work on this is described in
Appendix 7
• we are developing plans to strengthen our
internal processes for managing the Sectional
Appendix (as this is the current repository for
infrastructure capability), together with its
maintenance and distribution
• where there is a difference between actual and
published capability we are working to eliminate
these discrepancies. As part of the freight RUS
process we will be receiving the detailed industry
freight traffic forecasts. Through further
discussions with industry colleagues we aim to
understand the cost implications arising from the
forecast traffic levels. This information will be
identified by each route and form a key input into
the freight RUS process.
8/8/2019 Business Planning Criteria
http://slidepdf.com/reader/full/business-planning-criteria 17/41
17
Network Rail Business Planning Criteria
5 Asset policiesAsset policies provide the pivotal link between our
strategy for meeting our stakeholder/statutory
requirements and how we manage our asset base.
Policies are in place for each asset type, setting out
the maintenance and renewal regimes that will
deliver the required network and route outputs forthe funding available. Assets are designed,
constructed, inspected, maintained and replaced in
accordance with these policies. These policies
have been developed over a number of years and
reflect our extensive asset management
experience.
The framework within which these policies are
developed, and the individual asset policies
themselves, are currently being updated. This is in
part to make sure that the criteria against which we
operate our asset management systems are
consistent with the company’s overall risk
management framework. In identifying areas for
attention, we examined best practice within thecompany, in other businesses and the Institute of
Asset Management’s publicly available specification
on good practice in asset management (BSI PAS
55). Our policies will provide an important input to
our submission for the 2008 Periodic Review.
The relationship between our asset policies and
those factors that influence their development is
illustrated in the figure below.
This section sets out:
• the principles by which we are developing and
implementing our asset policies and how they
remain aligned with our strategy for the
management of the network
• the supporting information that underpins the
effective development and delivery of these
policies
• those aspects of our policies that do not meet the
principle of minimising whole life costs and the
implications of this.
5.1 A risk-based approachOur approach is centred on a risk-based
methodology, used to identify those factors that may
impede the delivery of our corporate objectives.
The effective management of these risks is
achieved by the allocation of resources and the
setting of priorities, and this is documented in our
asset management processes and policies. The
principle purpose of these documents and how they
contribute to the delivery of the required outputs is
explained below.
5.1.1 Network Rail’s asset management
policy
Network Rail’s asset management policy sets outthe framework and key principles against which our
functional policies (i.e. policies for track, signalling
equipment etc) are developed and maintained, as
follows:
• asset policies shall be developed to meet the
capability and functional requirements, defined by
the route or network specification, taking account
of any current funding and deliverability
constraints. Where such constraints limit our
ability to deliver these requirements on a whole
railway, minimum whole life cost basis, short term
decisions shall be designed to minimise the
variance from this preferred approach and enable
its re-establishment when such constraints are
overcome. Consideration must be given at all
times to the impact of these decisions on
passengers and freight users
Figure 3 Asset policy framework
Utilisation and output specification
Asset inventory,condition and costs
Functional assetpolicies
Functional assetpolicies
Network Rail’s assetmanagement policy
Network Rail’s assetmanagement policy
WorkbanksWorkbanks
Regulatorycommitments
Safety andenvironment
Legislation
Fundingavailable
Supplier resource
Workforce resourceand skill base
Investment plans
Utilisation and output specification
Asset inventory,condition and costs
Functional assetpolicies
Functional assetpolicies
Network Rail’s assetmanagement policy
Network Rail’s assetmanagement policy
WorkbanksWorkbanks
Regulatorycommitments
Safety andenvironment
Legislation
Fundingavailable
Regulatorycommitments
Safety andenvironment
Legislation
Fundingavailable
Regulatorycommitments
Safety andenvironment
Legislation
Fundingavailable
Supplier resource
Workforce resourceand skill base
Investment plans
8/8/2019 Business Planning Criteria
http://slidepdf.com/reader/full/business-planning-criteria 18/41
18
Network Rail Business Planning Criteria
• assets shall be managed compliant with relevant
statutory and legislative requirements
• company standards, specifications and standard
functional procedures shall be created and
maintained to bring into day-to-day effect the aims
of the asset policies
•
sufficient relevant asset information shall bemaintained to support the defined needs of both
internal and external stakeholders
• proposed changes to functional asset policies
shall be subject to a risk and economic
assessment that will take into account the impact
of the change on industry partners, including any
proposed changes to network access. In most
circumstances these changes shall only be
progressed where they improve overall industry
value
• clear economic and performance criteria shall be
identified for the major asset interventions that
drive expenditure and deliver outputs (i.e.
inspection, maintenance and renewal). These
criteria should be based on an assessment ofrisks associated with the delivery of the required
outputs, using the methodology identified in the
company integrated risk management framework
• before commencement of the business
processes for renewal, the opportunity for change
(enhancement or reduction) of an asset or asset
system shall be considered by reference to the
capability and functionality as defined in the route
specification
• the decision on timing of individual asset
replacement shall include consideration of
replacement timing of other assets at a location.
When economically justified, a mixture of life
extension and premature replacement shall be
pursued in order to achieve overall railwaysystem best value including consideration of the
impact on train service delivery of repeat
interventions
• wherever practical and economic, materials used
for assets and their construction and life cycle
management shall be from sustainable sources
and accord with Network Rail’s Corporate Social
Responsibility policy
• as far as is reasonably practical, new and
renewed assets shall be designed to minimise
subsequent need for attention requiring human
intervention or co-existence with train movements
or exposed live electrical equipment
• the design of assets or asset systems shall
comply with the company ergonomics policy and
standards to deliver optimum operability and
maintainability, thereby minimising loss of
functionality performance or capability through
human error or human performance limitations
• the use of standard designs, products and
technique shall be maximised to avoid
unnecessary diversity and complexities of training
and competence for constructors, operators and
maintainers
• new asset products shall be identified, developed
and approved only where overall business
performance improvement outweighs the risks
and costs of diversification
• the design and construction of new and renewed
assets shall minimise reliance on repetitive
human examination and subjective assessment.
Centralised remote monitoring by technical
instrumentation of current status and aspects ofcondition shall be a requirement for new or
renewed assets or asset systems
• enhancement or change of assets or their
management, within the maintenance period of
their life cycle shall be effected only as a
consequence of changed use or required
capability following a business risk and
opportunity evaluation taking into account the
whole railway system
• asset examination technology and techniques
shall be operated to support an overall
engineering maintenance strategy of measuring
deterioration trend and arranging intervention on
a planned basis before loss of asset functionality
or capability. This will enable the progressivereplacement of traditional ‘find and fix’ reactive
maintenance with ‘predict and prevent’ active
management.
5.1.2 Functional asset policiesFor each asset group a functional asset policy is in
place (these are currently being updated as part of
the 2008 Periodic Review submission). Assets are
designed, constructed, inspected, maintained and
removed in accordance with these policies. These
functional policies identify the individual asset types
covered and set out how each of the policy
statements identified in Section 5.1.1 is being
addressed.
In drawing up these policies, consideration is given
to the following:
• the physical condition of the assets, age profile
and suitability for the desired usage
• asset deterioration mechanisms, and failure
modes and effects
• how the asset interacts with other infrastructure
assets
• asset-related risks identified as part of the
integrated risk management process
• the potential costs and delivery risks of delivering
a variety of likely route or network outputs both
during and beyond the current control period
• asset lifecycle costs for alternative maintenance
and renewal regimes and the likely long term
impact of these regimes on future costs and
network sustainability
• network access required and the likely impact on
train operators
• supplier resources
• the potential cost and benefit impact on
passengers and freight users of alternative
regimes
• where appropriate, the potential wider social cost
and benefit impact of these regimes.
8/8/2019 Business Planning Criteria
http://slidepdf.com/reader/full/business-planning-criteria 19/41
19
Network Rail Business Planning Criteria
A key challenge is to identify the optimal
maintenance and renewal trade-off (i.e. the asset
condition level, or proxy for condition, where
ongoing maintenance is not cost-effective and the
asset should be renewed). Opportunities to
improve the safety of the network using funds
explicitly identified for this purpose at the 2003Access Charges Review are also considered when
developing these policies.
Where appropriate, the policies are differentiated by
route type, reflecting the volume and general nature
of the traffic carried, as described in Section 4.1.2.
Route-specific modifications are made to our asset
policies where this improves the alignment between
activities and outputs.
Functional policy assumptions and justification
Each functional asset policy is supported by
information that sets out the basis on which the
policy has been based. This provides a summary of
the policy options that were considered and theprocess by which the chosen policy was selected,
and includes:
• the assumptions made in developing the policy
• the outputs which the asset supports and the
risks which the policy is designed to mitigate
against
• the key interfaces with other assets
• an assessment of current asset condition (or
proxy for condition) and key drivers of asset
degradation and failure
• the policy options that were considered and the
rationale for the selected policy
• any key dependencies in terms of future
technology developments or changes in materialor labour costs
• where the policy is sub-optimal in terms of whole
life costs, the longer term cost impact and the
balance between cost and the delivery of current
outputs.
Proposed changes to these policies are supported
by financial analysis to make sure that the benefits
delivered are commensurate with any additional
costs that may be incurred. This includes schemes
to deliver our safety and environment plan, for which
the incremental outputs, costs and benefits to be
delivered must be clearly identified.
Changes are initially assessed using the whole
railway financial analysis as set out in Section 6.2.1.
The net present value is determined over the life of
the asset, which can generally range from 15 years
for telecom assets to 50 to 100 years for major
structures. Where the proposal would not increase
the cost of the railway in the next or subsequent
control periods the policy change would proceed
subject to any funding constraints during the current
control period.
Where a proposal has a more significant initial cost
impact its implementation may require additional
Government funding. Under these circumstances
the overall societal impact must be assessed using
the approach identified in Section 6.2.2. The
outcome of this analysis will be discussed with
ORR, before any further action is taken.
Decision support toolsThe development of asset policies to deliver the
required route capacity and capability necessitates
an understanding of how assets degrade and what
causes this degradation. It is important to recognise
that the relationships between inputs (in the form of
activity undertaken) and outputs (asset condition
and serviceability) are complex and few of the
output forecasts can be assessed purely through
formulaic models. A number of different techniques
are used in the production of our long-term
forecasts, according to the nature of the assets
involved, the extent of understanding of the way in
which they degrade and the availability of data on
asset type, installation date (age), usage, condition
and rates of degradation. These techniques are notmutually exclusive and the forecasts in most asset
categories involve elements of more than one of
these methods. However, as these tools are an aid
to decision making, it is necessary to apply an
element of judgement in their application.
The output of these decision support tools are used
within the Infrastructure Cost Model where
appropriate. This is discussed in Section 7.
Key decision support tools include:
• track (T-SPA – Track Strategic Planning
Application and IMM – Infrastructure and
Maintenance Model)• civils (SCMI – Structures Condition Marking index
and SACP – Structures Annual Cost Profile)
• signalling (SICA – Signalling Infrastructure
Condition Assessment).
These cover the major components of our
maintenance and renewal expenditure and are well
developed, although they may require further
improvement to refine their application or calibration.
For the other asset categories, significant work is
required to develop decision support tools. We
intend to work closely with the ORR on the
development of these tools where appropriate in
advance of the 2008 Periodic Review.
Policies to be produced
Policies have been produced for each of our asset
groups, i.e. track, civils (incorporating operational
property), signalling, electrification and plant, and
telecoms.
In addition we are considering developing an
enabling policy relating to our involvement with the
specification of rolling stock. This is intended to
consider both Network Rail owned rolling stock and
that operated by train operators. The latter is
particularly important as for a number of years the
8/8/2019 Business Planning Criteria
http://slidepdf.com/reader/full/business-planning-criteria 20/41
20
Network Rail Business Planning Criteria
lack of integration between rolling stock specification
and acceptance and network management has led
to a situation that has inflated both rolling stock and
network management costs. In part this has
resulted from an inadequate consideration of train
and network interfaces, poorly understood
acceptance processes and late changes beingrequired to the infrastructure or retrofitting of trains.
Although a number of problems have been
addressed, the consideration of whole railway
issues consistently at an early stage in the process
is still crucial.
We are working on this issue with train operators
and other stakeholders, via the System Interface
Committees, and believe that the model adopted by
the airline industry provides a basis for further
consideration. In this model we would, in
consultation with the DfT, specify the base
engineering specification of the vehicle (including
bogie design, wheels, brakes, power, weight etc).
This specification would be developed inconjunction with rolling stock manufacturers and
would be based on balancing train design,
production and maintenance costs with
infrastructure management costs. Other aspects of
the design of the rolling stock would be for the TOC
and manufacturer to determine. This is being taken
forward as part of the reform of the Network Code.
5.1.3 Standards, specifications and thedevelopment of workbanksThe asset policies provide the mechanism to
determine the default position with regard to the
actions that should be carried out, based on asset
age, condition or performance etc. It is the
application of the asset policies that drives thedevelopment of the forward maintenance and
renewal programmes (known as workbanks). As a
consequence we supplement our high-level policy
documents where appropriate with standards,
specifications and work instructions. These provide
more specific information for determining the
appropriate action on individual assets following
routine inspection or asset failure. They identify
when continued maintenance is likely to be
uneconomic and renewal should be considered.
Where an asset renewal is required they specify the
product that must be installed or the design
parameters for any new product, as appropriate.
They may also identify the competencies required to
carry out these tasks.
The criteria considered for including a scheme in the
workbank for a route take account of:
• operational impact if no action is carried out, for
example line closure, imposition of temporary
speed restrictions etc, including an assessment of
our ability to meet operators’ access rights
• activities necessary to maintain (or achieve) the
required asset specification
• degradation rates increasing the maintenance
workload and future renewal costs.
The content of these workbanks are reviewed on a
regular basis to test for the consistent application of
the asset policies and associated standards. This
review process also provides important feedback to
enable the suitability of the current policies to be
assessed and identify where potential changes may
be required.
5.2 The impact of funding restrictionsFunding restrictions over many years have resulted
in asset policies that have met short-term
imperatives at the expense of increased future
costs. Our current high cost base is in part due to
this. As stated above, wherever possible our
policies are based upon optimised whole life asset
management costs and we continue to drive
improvements in efficiency that improves
affordability. However, where funding constraints
limit our ability to operate on this basis, it is
necessary to maintain a balance between short-
term savings and the future affordability of the
railway. The main areas where a whole lifeapproach is not applied fully at present include:
• civils – an optimised whole life cost policy
necessitates preventative maintenance being
carried out, for example painting to preserve the
fabric of a metal bridge. Funding constraints
restrict our current policy, referred to during the
2003 Access Charges Review as policy B, to
allowing structures to deteriorate until repair or
replacement is necessary to maintain operational
requirements. At the time of intervention, we then
carry out work sufficient to achieve lowest long-
term costs for the structure
• track – funding and access constraints limit our
opportunities to bring forward, from the nextcontrol period renewal items that may provide
work volumes that are more economical to
deliver. However, where this can be done
efficiently within the available funds and without
causing excessive disruption, we will do so; and
• telecoms – funding constraints have delayed the
roll out of the Fixed Telecoms Network and GSM-
R. This has left existing legacy transmission and
radio systems requiring expenditure to be
committed for life extension work.
8/8/2019 Business Planning Criteria
http://slidepdf.com/reader/full/business-planning-criteria 21/41
21
Network Rail Business Planning Criteria
6 Investment regulationsWhen considering an investment in the network it is
important that a consistent approach is followed in
identifying and assessing the benefits that we
expect to be delivered by the scheme (the value for
money and affordability criteria).
The rules and procedures governing these
decisions are set out in detail in our Investment
Regulations. This section identifies the key
principles that are contained within these
regulations and how they are applied, including:
• the sources of funds available to the business
and the rules governing the draw down of these
funds
• the methodology we adopt to assess the eligibility
of a scheme, primarily in terms of value for money
• details of our authorisation process, including how
this is designed to minimise and mitigate the risks
associated with delivering such schemes on an
operational railway.
Additional information relating to the application of
these criteria can be found in ORR’s “Policy
Framework for Investments: Conclusions” (October
2005) and “Implementing the policy framework for
investments: guidelines on arrangements and key
processes” (March 2006).
6.1 Funding for investment schemesFunding for schemes is dependent upon the type of
investment scheme under consideration, as shown
in Figure 4. The rules governing the drawdown of
these funds are specific to the fund in question and
are discussed in detail below.
1. Enhancement schemes that are self financing in terms
of income generation or cost saving.
An investment scheme may be a combination of
condition-led renewal, capacity/capability
enhancement and third party funded
enhancements. For such schemes the rules
outlined below apply to the appropriate component
of the overall scheme.
6.1.1 Expenditure allowanceThe majority of Network Rail’s investment on the
network is funded by our regulatory expenditure
allowance. This allowance is determined through
the five-yearly access charges review that provides
funds via track access charges, direct grant, and
agreed adjustments to the RAB, to deliver the
network outputs as agreed with the ORR. There
are three types of scheme that are eligible for the
use of this fund.
Condition-led maintenance and renewalsThese consist of maintenance regimes or individual
asset renewal schemes that result from the
application of current asset policies and standards.
These must satisfy the following criteria:
• the scheme is consistent with the current asset
policy and relevant standards (see Section 5)
• the capacity/capability provided by the
maintained/renewed asset is consistent with the
requirements as set out in the route specification,
and the RUS where relevant (see Section 4).
As the asset policy, the relevant standards and the
route specification are subject to a financial analysis
that has to balance a number of issues at both routeand network level (as explained in Sections 4 and
5), an individual cost/benefit analysis of each
scheme that reflects the application of the policy is
not generally necessary. However, a financial
analysis must be carried out where the following
conditions apply:
• the investment scheme is at variance with the
existing asset policy or standard, or
• the asset policy provides guidance only or
identifies a range of options that can be
considered, or
• the scheme is inconsistent with the current output
specification or contractual commitment related to
the route.
These schemes are assessed by determining the
value delivered against a reference base-case, asset out in Section 6.2.1. The appraisal period is the
life of the asset. Where an asset does not have a
defined life an appraisal period of 25 years is used.
Where an amendment to an existing policy or
standard is proposed, the base-case is the
application of the current policy/standard. Where
the existing policy allows for a range of options, the
base-case is generally the lowest cost option.
Figure 4 Funding source by scheme type
Scheme type Funding source
Expenditure RAB adjustments Network Rail’s ThirdAllowance or grant funding own funds party funds
Condition-led maintenance and renewals
Network enhancements 1
Safety & Environment
Third party funded schemes
8/8/2019 Business Planning Criteria
http://slidepdf.com/reader/full/business-planning-criteria 22/41
22
Network Rail Business Planning Criteria
Network enhancements
The criteria governing the draw down of expenditure
allowance funds for an investment initiative
associated with a network enhancement are as
follows:
•
the enhancement scheme was a fundedrequirement in the final conclusions following the
access charges review
• the proposed investment initiative is consistent
with the identified strategy and business case for
the scheme as defined at the time of the access
charges review.
Where these circumstances apply no further
cost/benefit appraisal is required.
Where the proposed initiative would imply a material
change in the overall scheme (and with the
agreement of ORR) the scheme value is
determined on the basis of a socio-economic
cost/benefit appraisal, as set out in Section 6.2.2.The base-case against which the value is compared
is the current scheme strategy. Where appropriate,
any substantial changes in the proposed approach
in the light of this assessment would be discussed
with ORR and the relevant funder.
Safety and Environment plan
Safety enhancement schemes are designed to
reduce industry risk to tolerable levels where there
is a quantifiable safety or environmental benefit net
of any cost, but no other business efficiency saving.
Network Rail has a limited funding provision from
the ORR to undertake safety and environment
enhancements to the network (or exceptionally its
processes). The funding is usually for site specificenhancements where the risk is not As Low As
Reasonably Practicable (ALARP) and Network Rail
is not currently funded to manage the risk down
effectively.
Individual schemes are assessed on the basis of
their value, see Section 6.2.3.
In general, environmental projects are national
initiatives, agreed with ORR and designed to
address compliance with legislation introduced
since the previous access charges review.
6.1.2 Regulatory Asset Base adjustments orgrant fundingAdjustments to the RAB (or the provision of grants
from Government or other public sector bodies)
provide a mechanism for funding investment
schemes that were not funded by the last charges
review. Any scheme that is proposing funding for all
or part of the investment via this mechanism must
satisfy the ORR criteria that determine if such an
adjustment is appropriate. Although there are some
variations in the criteria, dependent on the size of
the scheme (see below) all schemes must
demonstrate that:
• Government support the ongoing financial
commitment arising from a RAB addition
• the proposed scheme enhances the economic
value of the network
• the expenditure has been efficiently incurred
• the outputs specified within the scheme have
been delivered.
Where the expenditure does not add to the
economic value of our assets we will explain:
• why the proposed RAB addition represents an
efficient whole-industry solution and why we
should fund the scheme and
• how the proposal will add economic value to the
rail network
Schemes may be developed on either an emerging
or fixed cost basis. Where the latter is chosen, the
level of contingency is agreed between Network
Rail and the funder and is dependent upon the risks
associated with the delivery of the scheme, as setout in ORR’s “Policy Framework for Investments:
Conclusions” (October 2005). For schemes where
there is limited interaction with the operational
railway or for schemes costing less than £5 million
the contingency will be a maximum of 10 per cent.
For other schemes the contingency will generally
not exceed 15 per cent, with a maximum of 25 per
cent in exceptional circumstances.
Major network enhancements
There are circumstances under which the DfT or
Transport Scotland may wish Network Rail to
implement a major enhancement scheme that was
not funded at the previous access charges review.
A letter of support from the DfT or TransportScotland and formal agreement from the ORR is
required concerning the provision of the grant or an
agreement in principle to an adjustment to the RAB
for Network Rail to progress the scheme.
Where the DfT or Transport Scotland decide not to
proceed with such a scheme, Network Rail’s
scheme development costs to date will be added to
the RAB providing ORR is content that they have
been efficiently incurred.
Network Rail Discretionary Fund
It is important that opportunities are taken to
enhance the capacity and capability of the rail
network where this will deliver value for money,
delivery resources are available and it can be
delivered efficiently. We have agreement from the
DfT, Transport Scotland and ORR to the creation of
a programme of small enhancement schemes up to
a total expenditure of £200 million over the four year
period 2005/06 to 2008/09 – the Network Rail
Discretionary Fund (NRDF). Funding will be via an
adjustment to the RAB in April 2009.
For a scheme to be eligible for this fund, it must
meet the criteria as determined by the DfT, as
follows:
8/8/2019 Business Planning Criteria
http://slidepdf.com/reader/full/business-planning-criteria 23/41
23
Network Rail Business Planning Criteria
• it must provide a business case with a positive net
present value as defined by the Benefit Cost
Ratio indicator for Government (as set out in
Section 6.2.2). This analysis uses the socio-
economic cost/benefit approach to take account
of the economic impacts that are expected to be
delivered by the scheme• the amount to be logged to the RAB for each
scheme must not exceed £5 million (without the
prior agreement of ORR, and following discussion
with DfT or Transport Scotland). This allows
schemes with a total cost in excess of £5 million
to be eligible, where costs in excess of £5 million
are funded by Network Rail or a third party.
It is expected that many schemes will involve
incremental enhancements linked to renewals as
this is likely to provide the greatest value for money
and the minimum disruption to existing rail users.
However, stand-alone schemes are also possible.
The method for determining the scheme cost, usedin assessing the amount that will be logged up to
the RAB, is dependent on how the scheme is being
delivered, as follows:
• for stand-alone schemes, the scheme cost is that
determined at the completion of GRIP stage 5
(including risk and contingency allowances)
• for enhancements/improvements linked to a
renewal scheme the percentage of the overall
scheme cost which is attributable to the
enhancement/improvement is identified at GRIP
stage 3. This percentage would then be applied
to the actual scheme cost in order to determine
the amount to be added to the RAB.
Where a decision is taken not to proceed with a
scheme, Network Rail’s scheme development costs
will be added to the RAB providing they have been
efficiently incurred.
Schemes are generally prioritised on the basis of
their Benefit Cost Ratio, see Section 6.2.2.
The fund is not generally intended to support
enhancements where the financial benefits to
individual stakeholders, or a group of stakeholders,
are sufficient to warrant them funding the scheme
directly. Therefore where the benefits accrue wholly
to a single third party it would generally be funded
as a third party scheme. Similarly, where a scheme
would generate sufficient additional income or cost
savings for Network Rail we would progress the
scheme using our own funds, as set out below.
We take a lead role in identifying opportunities to
enhance network value, and details of the schemes
we are considering for this fund are set out in our
route plans, published annually as part of our
business plan suite of documents. This provides
the opportunity for other stakeholders to comment
on and provide input to our plans. In some cases,
however, the greatest value will be obtained from
schemes that are identified at short notice.
We will consult with passenger and freight
operators, and where appropriate other
stakeholders, on proposed NRDF schemes.
As the principles under which this fund is to be
managed have been agreed with ORR, prior
approval is not required before an individual
scheme can be progressed. However, it is
expected that the independent regulatory reporters
will assess a representative sample of schemes to
check for compliance with the criteria. As set out in
ORR’s “Policy Framework for Investments:
Conclusions” (October 2005) we will provide ORR
with:
• a quarterly summary report, setting out actual and
budgeted NRFD expenditure and showing
progress in achieving outputs
• at year-end include details of NRDF schemes inour regulatory accounts.
6.1.3 Network Rail’s own fundsThere are three categories of schemes that Network
Rail may consider investing its own money in, as
defined below:
• schemes designed to increase the
capacity/capability of the network that may in the
future result in additional track access or station
lease income (for example the provision of an
additional station platform or the conversion of
signals to allow bi-directional operation). They
may be stand-alone schemes or part of a larger
condition-led renewal initiative• investments that can be justified through savings
in Schedule 8 performance payments and
investments in assets, plant or equipment that will
reduce the future cost of maintaining or operating
the railway
• commercial schemes designed to generate
income for the business, e.g. a retail scheme at a
station where the capital outlay will be recovered
through increased rental income from retail units,
or capacity/capability schemes that generate
track access revenue from open access
operators.
For a scheme to be considered it must provide a
positive net present value (see Section 6.2.1).
Where the payback period for the scheme extends
beyond the end of the current control period and the
scheme provides sufficient revenue (or cost
reduction) to cover the associated return on the
RAB, ORR have agreed the principle of Network
Rail adding the expenditure to the RAB. Any
scheme that generates sufficient income and/or cost
savings in less than 20 years are eligible for
inclusion under this category of scheme. Generally,
specific approval from the Government for such a
scheme being added to the RAB is not required as
8/8/2019 Business Planning Criteria
http://slidepdf.com/reader/full/business-planning-criteria 24/41
24
Network Rail Business Planning Criteria
there should be no additional call on Government
funds. We will provide details of expenditure and
income generated (or costs saved) for such
schemes as part of our annual regulatory accounts.
Hypothecated gains
In consideration for Network Rail land, developerswill commonly offer a mixture of cash and
enhancements to railway assets – typically station
buildings and surrounds. We receive the full benefit
of cash, but the benefits of enhanced assets
typically accrue to other parties such as the Station
Facility Operator (SFO). We are in discussion with
ORR on the regulatory treatment of these benefits
and are proposing that the net value of the
enhanced asset is added to the RAB so that we are
incentivised appropriately. We want to reach
agreement with ORR for this approach but
nevertheless will agree to development deals that
provide worthwhile railway enhancements.
Our plans for the next control period (CP4) willinclude projections for income as well as assumed
investment in facilities where this provides better
value for money.
ORR are currently consulting on this issue and on a
mechanism for sharing with developers the value
that will be generated by our granting of property
rights to a third party.
6.1.4 Third party fundsThird party funded schemes are those that are
funded by an organisation other than Network Rail.
The scheme may be delivered by Network Rail or
directly by the third party.
Where a scheme is to be funded by a third-party it is
not necessary for that body to satisfy Network Rail
of the value delivered by the scheme. However, the
scheme must be compatible with the existing
strategy for the route, as set out in the tests for
‘reasonableness’ in Section 1.3. In addition, where
Network Rail is to deliver the scheme we must be
able to deliver it without compromising our other
delivery commitments.
Schemes may be developed on either an emerging
or fixed cost basis, generally at the discretion of the
third party. Where the latter is chosen, the level of
contingency is agreed between Network Rail and
the funder and will be dependent upon the risks
associated with the delivery of the scheme, as set
out in ORR’s “Policy Framework for Investments:
Conclusions” (October 2005).
Where the scheme can be delivered more efficiently
by bringing forward renewals from future years, the
third party would pay for the financing cost of the
accelerated renewal. The cost of the renewal would
generally be added to the RAB if the renewal is in a
future control period. No adjustment to the RAB will
be necessary for renewals brought forward from
within the current control period.
Any additional operational and maintenance costs
up to the end of the current control period that we
will incur as a result of the scheme will be funded by
the scheme funder. Longer-term operational,
maintenance and renewal costs would be included
in our periodic review submissions. ORR are
currently consulting on this issue and on a rebatemechanism to enable funders to recover an
appropriate proportion of their additional costs from
beneficiaries.
Risk funds
Risks associated with third party funded schemes
are allocated to the body best able to manage and
mitigate them. However we are proposing that
most liabilities are capped (for both third parties and
Network Rail) and we have established two funds
as follows:
• a Network Rail Fee Fund (NRFF): a ring-fenced
fund where payments from third parties to cover
our own costs and liabilities are put into the fundand the fund is drawn upon as necessary. Any
surplus that we derive from our charges to third
parties will be retained within the fund. We have
contributed £10 million to this fund. This provides
an incentive to manage effectively liabilities that
might arise
• an Industry Risk Fund (IRF), funded by third party
contributions based on a proportion of scheme
costs. This is intended to act as an insurance
against low-probability, high-impact risks.
If liability caps are breached and the NRFF and IRF
are both exhausted, Network Rail would finance any
additional costs until the next periodic review, at
which time there would be an addition to the RAB.This is subject to Government support, as set out in
ORR’s “Implementing the policy framework for
investments: guidelines on arrangements and key
processes” (March 2006).
We have drawn up a set of template agreements
with model terms and conditions, under Part G of
the Network Code. These will provide third parties
with transparency on risk allocation, payments to
Network Rail and our obligations and accountability.
We will provide ORR with quarterly reports on all
schemes with access to these funds.
6.2 Value for money assessmentWhere a value for money assessment is required
the approach used is dependent upon the source of
funds, as follows:
• where the scheme is to be funded by Network
Rail a whole railway financial analysis is required
or
• where the scheme will be funded by a public
grant or an adjustment to the RAB a socio-
economic cost/benefit appraisal must be carried
out.
8/8/2019 Business Planning Criteria
http://slidepdf.com/reader/full/business-planning-criteria 25/41
25
Network Rail Business Planning Criteria
For all schemes the costs and benefits are
compared to a base case (i.e. ‘do minimum’), which
should include:
• committed and funded future plans
• the achievement of required policies and
standards• activities required to meet contractual, regulatory
and statutory requirements.
6.2.1 Whole railway financial analysisThe net costs and benefits that are expected to be
delivered by a proposed scheme are risk adjusted
to obtain ‘expected values’ and discounted to obtain
a net present value (NPV). The NPV is assessed
as:
• the revenue and any other financial benefits
delivered by the scheme (including changes in
schedule 4 and 8 payments) less
• the cost of implementing the scheme, including
any ongoing maintenance and operational costs.
In general only schemes with a positive NPV are
progressed. However, schemes with a marginal
business case may be progressed where there are
significant non-monetary benefits.
For commercial property related revenue generating
schemes the real internal rate of return (IRR) must
be in excess of 10.5 per cent. This hurdle rate is
based on our cost of capital, including a premium to
reflect the commercial risks of such investments.
For all other schemes a real discount rate of 6.5 per
cent (reflecting the agreed rate of return on the
RAB) would be used to determine the NPV over thelife of the asset (or a period agreed with ORR were
an adjustment to the RAB is proposed – see
Section 6.1.3).
With the exception of capacity enhancement
schemes, the impact on industry stakeholders is not
addressed separately as the regulatory regime is
designed so that this analysis takes account of the
financial impact on other railway parties, primarily
through schedules 4 and 8, the Network Code and
its equivalent for stations and depots. Where it is
apparent that the impact on other parties would not
be covered adequately by this regime additional
analysis would be undertaken and we would consult
with ORR, and DfT or Transport Scotland as
appropriate.
6.2.2 Socio-economic cost/benefit appraisalFor RAB or public grant funded schemes, or
enhancement schemes funded through the access
charges review the assessment must include
consideration of the societal and financial benefits,
using an approach agreed with the DfT and
Transport Scotland. This includes consideration of:
• overall passenger journey time
• environmental and safety benefits arising from
modal shift from car or lorry to rail
• reliability and crowding for rail users
• employment and regeneration impacts.
All benefits and costs of the options under
consideration are quantified in real monetary terms,where possible, using net present values, discount
rates and appraisal period as defined by HM
Treasury (The Green Book 2003). Discount rates
are currently 3.5 per cent for the first thirty years of
the appraisal, at 3.0 per cent for years 31-75 and
2.5 per cent thereafter until 125 years – this is the
Social Time Preference rate, reflecting the value
society attaches to present, as opposed to future,
consumption.
Scheme costs include monetised risk and
contingency. In addition optimism bias is added to
correct the historically observed tendency to
underestimate costs. In accordance with DfT and
Transport Scotland guidance, cost estimates atGRIP stage 3 are uplifted by 40 per cent and by 6
per cent at GRIP stage 5 (these figures are currently
under review by DfT and Transport Scotland).
We apply the principle of proportionality to the
appraisal process, with the methodology adopted
based upon the value and complexity of the scheme
under consideration (below £1 million, between £1
million and £5 million, and above £5 million). This is
to limit the analysis overhead on low cost or
relatively straightforward schemes.
Network Rail’s Route Utilisation Strategies
Technical Guide provides a comprehensive
explanation of the data sources and benefit analysismethodology used when considering major
investments. For schemes that are to draw down
on the NRDF a simplified methodology has been
agreed with the DfT, Transport Scotland and ORR,
(The Appraisal Guidance for the Network Rail
Discretionary Fund).
Appraisal Summary Table
The Appraisal Summary Table (AST) is used by
DfT and Transport Scotland to compare the cost
and benefit of each option to enable comparison
between options to be made. The five sections of
the AST cover the five broad Government
objectives for transport of: environment; safety;
economy; accessibility; and integration.
Where possible the costs and benefits of options
are quantified in monetary terms. Non-monetary
(qualitative) impacts are used for assessing the
environment, accessibility and integration sections
of the AST. Their impacts are appraised using a
five point qualitative scale. The non-monetary
impact is used when assessing the relative merits of
options that have a similar economic value or to
assist in prioritising schemes where funding or
resource constraints exist.
8/8/2019 Business Planning Criteria
http://slidepdf.com/reader/full/business-planning-criteria 26/41
26
Network Rail Business Planning Criteria
Transport Economic Efficiency table
A monetary assessment of the benefits delivered by
each option is carried out using the Transport
Economic Efficiency (TEE) table. The value of the
scheme is determined by calculating the net present
value of benefits delivered. This is defined as:
net revenues – private sector costs + subsidies +
rail user benefits + non-user benefits.
This analysis includes consideration of:
• net revenue changes to TOCs and Network Rail
• the cost of capital (where Network Rail will initially
fund the scheme and recover costs via an
adjustment to the RAB)
• welfare benefits such as journey time, reliability,
rolling stock or station ambience changes to rail
users divided by business and non business rail
users
• benefits to non rail users and society, for example
environmental benefits arising from modal shift ofusers from another transport mode.
For both DfT and Transport Scotland appraisals all
benefits and costs expressed in monetary values
use 2002 as the price base. This allows the results
of the scheme to be compared to all other
appraisals completed in accordance with
DfT/Transport Scotland criteria. The appraisal
period follows HM Treasury and DfT guidance and
should cover the period over which any liabilities
(actual or contingent) fall on the funder’s budget.
All options should be appraised over the same
period. If there is no exact life (such as the life of
the asset before first renewal) then the appraisalperiod is set at 60 years.
The overall measure of value for money used by the
DfT, Transport Scotland and Network Rail is the
Benefit Cost Ratio (BCR) which is set out in the
TEE table. The BCR is defined as:
NPV (as defined above) .
present value of costs (PVC) to Government
Guidance on the use of the minor discretionary fund
from the DfT is that:
• most, if not all, schemes should provide high
value (i.e. with a BCR of greater than 2.0)
• some schemes may provide a medium level of
value for money (where the BCR is between 1.5
and 2)
• very few schemes should provide low value for
money (with a BCR of between 1.0 and1.5) – and
such schemes must deliver other benefits
• there should be no schemes providing a poor
level of value for money (a BCR of less than 1.0).
In addition to providing an absolute measure of the
value for money provided by a scheme, the BCR is
also used to prioritise schemes where the number
of eligible schemes exceeds the funding available.
Sensitivity analysis
Sensitivity analysis is used to test the vulnerability of
the options to future unavoidable uncertainties.
These are likely to include uncertainty associatedwith the achievement of either the levels of benefit
or base demand, usage or patronage profile.
Examples of option sensitivity tests include:
• reducing all option benefits such as performance
savings by 15 per cent or 40 per cent
• removing growth from the values used to
monetise the benefits
• the identification of the switching value, i.e. the
level to which the cost must increase or the
benefits decrease for the NPV to move from
positive to negative
• using various patronage scenarios as well as the
central case for the demand profile.
Sensitivities in costs may also be considered.
However risk should already be addressed in the
cost profile as a result of including an appropriate
optimism bias in the appraised cost.
6.2.3 Safety business case assessmentA financial analysis is carried out over the life of the
asset to determine the NPV, using a discount factor
of 6.5 per cent.
Safety benefits are defined as the safety benefits
achieved in terms of the equivalent fatalities
prevented less any safety disbenefits delivered by
the scheme. In assessing if a risk is ALARP,
Network Rail uses the Value of Preventing a Fatality(VPF) as a means of applying a monetary value to
the benefits delivered. The VPF applies to
equivalent fatalities and is the threshold value
attached to reducing the risk by one fatality, 10
major injuries, or 200 minor injuries. More details on
how this methodology is applied and on the current
monetary value assigned to the VPF can be found
in Network Rail’s Railway Safety Case.
6.3 Governance processOur Investment regulations set out the governance
process applicable for all types of investment
schemes.
Authorisation of investment schemes in Network
Rail is delegated to investment panels, depending
on the scheme type and the forecast level of
expenditure. All panels share the responsibility to
ascertain that:
• the scheme is consistent with asset policies and
route or network strategies
• the appropriate scheme development and
implementation processes have been adhered to
• roles and responsibilities have been clearly
defined
8/8/2019 Business Planning Criteria
http://slidepdf.com/reader/full/business-planning-criteria 27/41
27
Network Rail Business Planning Criteria
• adequate budget provision for the scheme is
available
• the efficiency target for scheme has been
achieved
• the scheme is deliverable.
We have developed an approach to managinginvestment schemes to minimise and mitigate the
risks associated with delivering such schemes on
an operational railway – the Guide to Railway
Investment Projects (GRIP). The approach is
based upon best practice within Network Rail and
other industries that undertake major infrastructure
projects as well as practice recommended by the
major professional bodies. It covers the investment
lifecycle from inception through to the post-
implementation realisation of benefits, as follows.
Funding is in discrete stages to limit the risk of
committing resources to the wrong scheme. The
authorisation process provides a check mechanism
(budget and funding availability, consistency with
asset and route policy etc.) to deliver the continued
effective operation of this process.
We are in the process of reviewing our GRIP
documentation.
Figure 5 Key stages of the investment lifecycle
1
Outputdefinition
2
Pre-feasibility
4
Single optionselection
5
Detaileddesign
6Construction
test &commission
7
Schemehand back
8
Projectclose out
3
Optionselection
1
Outputdefinition
1
Outputdefinition
2
Pre-feasibility
2
Pre-feasibility
4
Single optionselection
4
Single optionselection
5
Detaileddesign
5
Detaileddesign
6Construction
test &commission
6Construction
test &commission
7
Schemehand back
7
Schemehand back
8
Projectclose out
8
Projectclose out
3
Optionselection
3
Optionselection
8/8/2019 Business Planning Criteria
http://slidepdf.com/reader/full/business-planning-criteria 28/41
28
Network Rail Business Planning Criteria
7 Asset plansHaving developed asset policies that are designed
to deliver the required network outputs within the
applicable constraints, the activity and expenditure
plans are produced by applying these policies.
There are two key outputs of this planning process:
our annual business plan and our periodic reviewsubmissions. This section describes:
• the models we are developing to produce activity
and expenditure forecasts
• the role of our annual business plan and the
process by which it is produced
• how these plans are used to develop our periodic
review cost submissions.
7.1 Modelling tools7.1.1 Infrastructure cost modelWe are currently developing the first version of an
Infrastructure Cost Model (ICM). This is intended to
be a strategic planning tool to produce forecasts of
activity volumes, expenditure and outputs fordifferent specifications of usage and capability. The
ICM will cover all elements of our business,
including operating, maintenance and renewals
expenditure. It will provide, for the first time, an
integrated model across all asset types and will
improve our ability to analyse the costs of specific
segments of the network.
The ICM will, wherever possible, derive ‘bottom up’
estimates of activity volumes as functions of the key
cost drivers and based upon the application of our
asset policies. These cost drivers include the
volumes of different types of assets, their
associated capacities and capabilities, and the level
and type of traffic that uses them. The model will
reflect the existing level of understanding of asset
degradation relationships and cost drivers, which
varies across our asset portfolio, drawing on
existing decision support tools. The forecast costs
of delivering these activity volumes will be informed
by progressive improvements in unit cost data,
following the standardisation of our cost data
collection processes. The model will incorporate
high level input – output relationships, quantifying
the impact of different levels of activity, expenditure
and traffic usage on key network output measures,
including measures of asset condition and failure
rates.
Transparency, consistency and ease of audit will all
be key principles guiding the development of the
model. The first version of the model, which will be
completed in spring 2006, will be used to produce
our first cost submission for the 2008 access
charges review in June 2006. It will also link in to
the wider industry Network Modelling Framework
being developed for the DfT.
The model will continue to be developed and refined
over time, serving as a focus for, and a driver of,
progressive improvements in the understanding of
core relationships including asset degradation rates,
the trade-offs between maintenance and renewal,
the relationship between unit costs and possession
regimes, and the relationships between activity input
and asset condition and performance outputs.
7.1.2 Performance model
We are currently developing the first version of amodelling tool to help us produce longer term
forecasts of network performance. The model will
forecast the effects on performance of three types of
change:
• in asset condition and failure rates, based on
outputs from the ICM
• in traffic levels on the network, based on
relationships between the capacity utilisation
index and delay
• other changes, for example those affecting the
robustness of the timetable, such as
improvements in incident management. The
model will not itself forecast the effects of these
changes, but will enable the estimated effects ofthese changes to be consolidated in a transparent
and consistent manner.
The primary output of the model will be delay
minutes and (for passenger operators) PPM, at
operator level.
7.2 Annual business planOur route investment plans result from the
application of our asset policies, adjusted where
necessary (primarily in terms of the timescale for
delivery) to reflect current business priorities. These
are detailed in our annual business plan and set out
the actions we are undertaking to make certain that
the capacity and capability of each route are asagreed with our stakeholders via the processes set
out in Section 4. We also identify our plans to
improve the effectiveness of our asset management
activities, our income projections and our plans for
financing the required expenditure.
Within the plan we identify the following for each of
our 26 strategic routes:
• our high-level strategy for the route
• the current capability for the route, and the timing
of any change in this capability
• forecast maintenance, renewal and enhancement
activities and costs
• the assumptions we have made (traffic growth
etc) in developing these plans.
It is important that our plans are sufficiently
transparent to enable our stakeholders to plan their
own activities with a reasonable degree of
assurance. Business planning guidelines are
provided to support the production of appropriate
and consistent plans. These guidelines set out the
procedures and processes for the development of
the plan and contain key assumptions that should
be used in the preparation of the plan.
8/8/2019 Business Planning Criteria
http://slidepdf.com/reader/full/business-planning-criteria 29/41
29
Network Rail Business Planning Criteria
7.2.1 Demand forecastingA key set of assumptions used as an input to our
Business Plan is a demand forecast; or, more
precisely, the train service growth expected over the
next 10 years. This informs two principal elements
of the plan: maintenance and renewal costs and
performance. It is important that the forecasts usedin the plan are seen in context. The eventual level
of train services run on the network in future years
will of course be the outcome of a number of
decision-making processes, notably the HLOS, the
2008 Periodic Review, RUSs, enhancement
projects which are funded separately and
franchising decisions.
For passenger services, forecasts for the first two
years of the plan are based known service changes,
via the timetable development process and
discussions with TOCs. In some cases, train
service changes (especially significant ones) can be
anticipated further ahead than this. For example,
some franchise plans contain commitments tocertain service changes. The longer term forecast
is based on top-down forecasts of future growth in
passenger demand. This involves forecasting
unconstrained passenger demand, expressed in
terms of passenger-miles. We then make
assumptions as to what proportion of this growth will
need to be accommodated by means of increasing
train services, whether by running more trains or
lengthening existing ones.
The short to medium term forecasts for freight
services are also based on known service changes
through the usual timetable development process
and discussions with FOCs. The Freight RUS that
is currently underway will look in some detail at longterm freight forecasts. Unconstrained growth
forecasts are being prepared by the rail freight
industry and the Freight RUS will consider these
forecasts and how (or to what extent) the growth
can be accommodated on the network. Freight
traffic forecasts in future business plans will be
largely based on the conclusions of the Freight
RUS. However, as these growth forecasts have not
been finalised, our 2006 Business Plan has
considered growth at a commodity level, based on a
combination of historical trends, the draft forecasts
from the industry and judgement as to the likely
effects of capacity constraints.
7.2.2 Target settingOur business planning processes are designed so
that the disaggregation of output targets to the
appropriate component parts of the organisation are
set at a level that enables us to meet our contractual
and regulatory outputs. In addition, these planning
processes are used to validate and amend our
portfolio of asset investment initiatives, to facilitate
the optimum delivery of these outputs.
SMART (i.e. Specific, Measurable, Achievable,
Realistic and Time-related) targets are set at a
network, functional and area level as appropriate.
Wherever possible, asset condition and
performance targets are set at a delivery (i.e. Area)
level. Local target setting is based upon asset
population, outputs delivered previously and the
likely outcome of current asset and other initiatives.
These targets include asset reliability, train service
reliability and the number of broken rails. Networktargets cover those asset condition measures
where a disaggregation to area level would not
assist in the development of local delivery plans.
The move to route-based planning is improving
significantly our ability to set Area targets, and
provide appropriate budget provision for their
delivery. Functional targets are set at a level
necessary to achieve the required cost and
efficiency levels.
7.2.3 The translation of the workbank intoannual plansThe application of the asset policies (described in
Section 5) will identify the workbank necessary to
deliver the defined route specification. For manyitems within the workbank the policies will have
identified the point by which ongoing maintenance
will no longer be economic and a renewal should be
considered. Our annual work plans, and
corresponding budget and resource allocation, are
targeted at delivering the appropriate elements of
these workbanks.
A risk-based approach is used to prioritise delivery
of the defined work, based upon the following
hierarchy:
• protecting expenditure on safety critical schemes
• maintaining defined capability of the route
• meeting targets for operational performance andasset condition.
Other factors considered when determining the
scheduling of a scheme include:
• the availability of resources (both internal and
external) to deliver the work
• the cost and benefit impact of deferring the
scheme, particularly where reductions in unit
costs are imminent
• the packaging of works to minimise service
disruption and network access costs and to
improve delivery efficiency.
Where resource constraints limit our ability to deliver
items of work a mitigation plan is developed to
eliminate any safety impact and minimise any
impact on the delivery of contracted services until
the work can be rescheduled.
8/8/2019 Business Planning Criteria
http://slidepdf.com/reader/full/business-planning-criteria 30/41
30
Network Rail Business Planning Criteria
7.2.4 Review processIn addition to the routine reviews of the contents of
the proposed workbanks described in Section 5, a
more formal review takes place on an annual basis.
This review, led by asset heads, provides an
additional challenge to the content of the asset
investment portfolio. It assesses the consistentimplementation of asset policies, the likely impact of
the resultant plans on performance and other output
measures, overall deliverability issues and the
appropriate budget provision to support the delivery
of these plans.
Regular reviews are also carried out by the
Executive Directors to monitor progress against the
plan, with a key focus on the resilience of our plans
and the achievement of our efficiency and
performance targets. Reviews are also held with
Area and functional teams across the organisation
on their plans to deliver these targets. In addition,
the Renewal Investment Panel authorises individual
elements of the asset renewal programme,considering the deliverability of the overall
programme, its affordability and if it meets our
efficiency challenges.
As our planning processes mature the linkage
between the annual business plan and the
necessary adjustments that are required to be
made during its implementation throughout the year
will be improved. This enables the plan to become
‘live’, in that it is amended to reflect what is
happening throughout the year. The availability of
an up-to-date plan against which progress can be
assessed facilitates the monitoring process and will
reduce considerably the effort needed to create
annual plans in future years.
7.3 Periodic review submissionsThe 2008 Periodic Review for Control Period 4 will
determine Network Rail’s access charges for the
five year period from April 2009 to March 2014.
This review has been initiated with the publication of
the ORR’s first consultation document (August
2005) and the initial assessment of our revenue
requirements (December 2005). Network Rail will
be providing the ORR with our initial draft cost
submission in June 2006, with a further cost
submission with our 2007 Business Plan. The
criteria set out in this document and the
methodology we have adopted to applying this
criteria are pivotal to the development of our plans
as an input to this process, allowing us translate the
regulatory requirements into required action plans
and assessing options for value for money.
As described above, the route specifications define
the required capability, capacity, performance and
operational requirements of the route and the
timescale by which these changes must be made.
The Infrastructure Cost Model will be used to assist
in forecasting the cost of delivering these plans, with
the asset policies providing the basis for estimating
activity and expenditure forecasts associated with
the delivery of the required route and network
outputs. These policies are adjusted, and funding
re-allocated between asset groups, based upon the
contribution of each asset group to the delivery of
the required route and network outputs. This
process assists in determining:
• the cost of delivering the outputs required during
the next control period (including defined network
enhancements) based upon current asset policies
• the likely long-term cost and sustainability
implications of these policies
• options to reduce long-term costs (measured in
terms of net present value) by additional
investment in asset management during the
forthcoming control period.
The latter is particular important as it enables
funders to consider the value delivered by route
capacity or capability enhancements with those
delivered by improved long-term infrastructure
management policies. Although the format of ourcost submission is still under review with the ORR it
is likely to include a detailed description of our plans
and the underlying assumptions so that they can be
reviewed by ORR, including:
• our corporate objectives
• a forecast of our likely position at the end of the
current control period
• our base plan, i.e. what we are seeking to deliver
and our delivery plans
• the outputs that these plans will achieve, e.g.
capacity, safety and performance
• the assumptions that underpin this plan
• maintenance and renewal activities and spend by
asset type• our operational costs and single till income
• our funding requirements and proposed financing
arrangements
• details of any enhancement options that have not
been included in our base plan.
8/8/2019 Business Planning Criteria
http://slidepdf.com/reader/full/business-planning-criteria 31/41
31
Network Rail Business Planning Criteria
Part 3: Appendices
8/8/2019 Business Planning Criteria
http://slidepdf.com/reader/full/business-planning-criteria 32/41
32
Network Rail Business Planning Criteria
Appendix 1: SupportingdocumentsThe following documents contain additional
information relevant to the application of our
Business Planning Criteria.
A1.1 Network Rail documents• Our Integrated Risk Management Process
provides the framework against which risks to the
delivery of our corporate objectives are identified
and managed.
• The Railway Safety Case describes our activities
and health and safety responsibilities as
infrastructure controller and demonstrates how
risks on our infrastructure are controlled. This
covers those activities undertaken to meet our
asset management responsibilities.
• OurCorporate Responsibility Report provides
a review of our efforts to be a good neighbour, a
responsible employer, and a custodian of an
important part of Britain's natural environment.
• Our Environmental Policy sets out our
environmental aims and the commitments we
have made to integrate environmental
management with the safe and efficient operation
of the railway.
• Route Utilisation Strategies (RUSs) play an
important role in the planning activity for the rail
industry and the RUS Technical Guide sets out
how Network Rail develops these strategies with
other industry parties.
• Asset policies set out the engineering
stewardship regimes for each of our asset types,
identifying the point at which continued
maintenance is likely to be uneconomic and
detailing the appropriate action to be taken.Proposed changes to the asset policies are
evaluated using the criteria set out in this
document.
• Our investment regulations comprise the
following two elements:
o the appraisal criteria set out the criteria
used to assess proposed changes to
the infrastructure and reflect the
principles set out in this document
o the Guide to Railway Investment
Projects (GRIP) identifies the actions
that must be carried out at each stage
of the investment lifecycle
• Our annual Business Plan sets out our plans for
improving the effectiveness of our assetmanagement activities and our expenditure plans
for the next 10 years. It identifies the principles
and assumptions under which these annual plans
are drawn up. It also incorporates our plans for
each of the 26 strategic routes.
• Our Asset Information Strategy (AIS) sets out
our strategy for the provision of fit for purpose
asset information to support the delivery of our
asset management responsibilities.
• In line with the Customer Sponsored
Enhancement consultation that we have
undertaken with the industry, we have developed
a suite of template agreements that we intend to
use with customers for their schemes. A brief
summary of each of these agreements is
contained in our Template ConsultationAgreement for Customers undertakingRailway Projects.
• The Land Disposal Licence Condition identifies
the screening process we adopt with regard to
land disposals that do not need the consent of the
ORR.
All of these documents are either made available to
industry group members where appropriate or will
be available on our website.
A1.2 External document list
• ORR’s “Policy Framework for Investments:
Conclusions” (October 2005)
• ORR’s “Implementing the policy framework forinvestments: guidelines on arrangements and key
processes” (March 2006)
• DfT “Appraisal Guidance for Network Rail
Discretionary Fund Schemes” (January 2006) –
www.dft.gov.uk
• HM treasury “The Green Book: Appraisal and
Evaluation in Central Government” (2003)
• DfT value for money guidance – www.dft.gov.uk
• DfT appraisal rules – www.webtag.org.uk
• Scottish Transport appraisal rules – www.scot-
tag.org.uk.
8/8/2019 Business Planning Criteria
http://slidepdf.com/reader/full/business-planning-criteria 33/41
33
Network Rail Business Planning Criteria
Appendix 2: Integrated RiskManagement ProcessA2.1 PrinciplesIn order to increase the certainty of meeting our
corporate objectives we have implemented a
comprehensive, structured and robust framework. It
is designed to make sure that key risks aremanaged and our processes provide transparency
on how they are being managed.
A2.2 Process overviewOur integrated risk management process can be
summarised by the following six basic steps:
• corporate objectives – identify the objectives that
could be impacted by the action or process under
consideration
• identify risks – determine what could go wrong or
what opportunities could be missed
• assess and prioritise – assess how exposed we
are and determine what should we tackle first
• identify mitigation – determine what, if anything,
we should do, or do differently
• implement – carry out the appropriate action
• monitor – determine if we are delivering the
expected results.
A2.3 Risk identificationRisk owners are identified based upon their
accountability for the action under consideration. It
is their responsibility to assign and allocate priority
risks to plan managers. These managers are
responsible for developing and implementing action
plans to mitigate the risks and monitoring progress
on the completion of the plan. Risk identification
may be carried out during:
• the development or update of asset policies
• the consideration of material changes in capacity
or capability of the network
• prior to and during renewal, enhancement or
maintenance projects
• the development of annual business plans.
A2.4 Assessment and prioritisationHaving identified the risk, a ranking system is used
to determine prioritisation based upon a numerical
assessment of its impact on the business and the
likelihood of it occurring,
i.e. Risk ranking = Impact + Frequency
A2.4.1 ImpactThe assessment of impact is based upon its effect
on our corporate objectives, covering:
•
finance• safety
• performance
• capability
• asset stewardship
• business performance
• customers and stakeholder.
When determining the impact, the primary business
objective is identified, i.e. which of the above will the
risk impact on more than the others.
The range of impact scores is from 1 to 5. For
example, for capability the loss of a major route for 5
hours would receive an impact score of 1, whereas
the loss of such a route for 5 days would beallocated a score of 4. Similar guidance is provided
for each of the above objectives.
A2.4.2 FrequencyFrequency is an estimate of the potential for the
maximum credible impact occurring.
A2.5 Identify mitigationThe risk ranking (the sum of the impact and
frequency scores) is used to determine the action
that should be carried out to manage and control
the risk, using the following approach.
Figure 7 Frequency scoring
Frequency Description Score
More than or equal to five per year Recurring 5
Less than five per year
More than or equal to one per year Expected 4
Less than one per year
More than or equal to one in five years Possible 3
Less than one in five years
More than or equal to one in 25 years Unlikely 2
Less than one in 25 years Remote 1
Figure 6 Identification of actions for risk control
Risk region Rating Safety risk Other risk
Unacceptable 7-10 Additional controls will be introduced to Additional controls will be introduced to reduce the
region reduce the risks to the tolerable region risks to the tolerable region (or lower) unless it is
(or lower) demonstrably not cost effective to do so
Tolerable 5-6 Additional controls will be introduced to Additional controls will be introduced to reduce the
region reduce the risks risk unless the cost is risk unless the cost is disproportionate to the benefit
disproportionate to the benefit (i.e. ALARP)
Broadly 2-4 Action not usually required unless Further action not usually required
acceptable region reasonably acceptable practicable
measures are available
8/8/2019 Business Planning Criteria
http://slidepdf.com/reader/full/business-planning-criteria 34/41
34
Network Rail Business Planning Criteria
Appendix 3: Regulatory targetsNetwork Rail’s regulatory targets for the third control
period (CP3), April 2004 – March 2009, were set in
the ACR 2003: Final Conclusions. These targets,
summarised below, are distinct from Network Rail’s
internal targets, which are the company’s way of
managing the assets to achieve agreed regulatorytargets, and from incentives, which provide a means
of additional remuneration to Network Rail if it
improves on certain baseline levels of performance.
These targets have been translated into values,
which Network Rail believes are to be met on a
measure by measure basis. In addition, using a
methodology agreed with DfT, Transport Scotland
and ORR, we have disaggregated these targets
and produced indicative outputs for England and
Wales and Scotland. These are set out in figure 9.
Note that condition assessments are based oninspections during the year stated and previous
years, hence do not necessarily describe the
condition of the asset base at the year taken as the
baseline.
Figure 8 Regulatory targets for the five year period 2004/05 to 2008/09
Name of measure Regulatory targets
Total Network Rail attributed delay (million minutes) 2004/05: 12.3
2005/06: 11.3
2006/07: 10.6
2007/08: 9.8
2008/09: 9.1
Train delay minutes/100 train kms 2004/05: 2.34(franchised passenger operators) 2005/06: 2.12
2006/07: 1.97
2007/08: 1.80
2008/09: 1.65
Broken rails Reduction in the number of broken rails to no more than
300 per annum by 2005/06. No increase thereafter.
Track geometry Reduction in the number of L2 exceedences per track mile
to no greater than 0.9 by 2005/06. No increase thereafter.
Track geometry (standard deviations) - the regulatory
target is to maintain 2003/04 levels.
Temporary speed restrictions Annual reduction required.
Structures and electrification Condition and serviceability to return to 2001/02 levels.
Other measures Other asset condition and serviceability measures to showno deterioration from 2003/04 levels.
Network capability Maintain the capability of the network for broadly existing
use at April 2001 levels (subject to network changes
authorised under the Network Code).
8/8/2019 Business Planning Criteria
http://slidepdf.com/reader/full/business-planning-criteria 35/41
35
Network Rail Business Planning Criteria
Figure 9 Values of regulatory targets and disaggregated indicative outputs for the period 2004/05 to 2008/09
Measure Regulatory target Indicative outputs
England Scotland
& Wales
Total Network Rail attributed 2006/07: 10.6 9.713 0.887
Delay (million minutes) 2007/08: 9.8 8.980 0.820
2008/09: 9.1 8.338 0.762Train delay minutes/100 train 2006/07: 1.97 1.99 1.74
kms (franchised passenger 2007/08: 1.80 1.82 1.59
operators) 2008/09: 1.65 1.67 1.46
M1 Broken rails Reduction to no more than 300 broken rails per annum 270 30
by 2005/06. No increase thereafter.
M3 Track geometry 35m top (vertical) 50% 62.4% 61.2% 69.8%
90% 89.2% 88.7% 92.4%
100% 97.0% 96.9% 97.9%
35m alignment (horizontal) 50% 72.7% 73.2% 69.3%
90% 92.9% 92.9% 92.9%
100% 96.5% 96.5% 96.7%
70m top (vertical) 50% 63.6% 63.1% 67.1%
90% 92.3% 92.3% 92.4%
100% 95.3% 95.3% 95.2%
70m alignment (horizontal) 50% 79.5% 79.8% 77.7%
90% 95.8% 95.8% 95.8%
100% 97.2% 97.2% 97.3%
M5 Level 2 exceedances Reduction in the number of L2 exceedences to no 0.93 0.70
per track mile greater than 0.9 by 2005/06. No increase thereafter.
M4 Temporary speed Annual reduction required from 2003/04 level of 1091 108
restrictions 1,199 TSRs (track, structures and earthworks)
M6 Earthwork Covered by “other asset condition and serviceability” 37 10
failures and derailments with no deterioration from 2003/04 levels.
M8 Bridge condition Condition1 and serviceability to return to 2001/02 levels 2.0 2.0
which was approximately 2.0, but the full target cannot be
firmly established until all bridges have undergone Structures
Condition Monitoring Index, anticipated to be in 2007/08.
M9 Signalling failures Covered by “other asset condition and serviceability” 25,150 2,948
with no deterioration from 2003/04 levels i.e. 28,098
signalling failures at 59 million train km per annum.
M10 Signalling asset Covered by “other asset condition and serviceability” 2.5 2.5
condition with no deterioration from 2003/04 levels
M11 AC traction power No deterioration from number of incidents reported in 97 10
incidents causing train delays 2001/02
M12 DC traction power No deterioration from number of incidents reported in 30 NA
incidents causing train delays 2001/02
M13 AC Feeder stations and Condition1 and serviceability to return to 2001/02 levels, 2.18 1.61
track sectioning points i.e. 2.1.
M14 DC Traction substations Condition1 and serviceability to return to 2001/02 levels 2.3 NA
M15 AC Traction contact Condition1 and serviceability to return to 2001/02 levels 1.83 1.61
systems
M16 DC Traction contact Condition1 and serviceability to return to 2001/02 levels 1.8 NA
systems
M17 Station condition index Covered by “other asset condition and serviceability” with 2.29 2.02
no deterioration from 2003/04 levels
M18 Station facility score No regulatory target - -
M19 Light maintenance Covered by “other asset condition and serviceability” with
depots – condition index no deterioration from 2003/04 levels 2.7 2.7
8/8/2019 Business Planning Criteria
http://slidepdf.com/reader/full/business-planning-criteria 36/41
36
Network Rail Business Planning Criteria
Appendix 4: How the criteria areapplied in practiceThis section provides an illustration of how our
business planning criteria are being applied. The
scenario examined is an asset renewal scheme and
addresses three key questions: why we are carrying
out work on this asset in this location, why at thistime and why to this specification.
There are three components of the decision making
framework against which these considerations will
be addressed:
• the asset policy
• the route specification
• the annual business plan.
This framework enables us to make individual
decisions that collectively address the complex and
interrelated issues that govern the management of
the infrastructure, and in a manner that best
supports the effective and efficient delivery of our
corporate strategy. Individual renewal decisions
must be seen in this broader context.
A4.1 Asset policyThis addresses when, how and why we would carry
out work on this type of asset in this sort of location.
It also partly addresses: why at this time.
The asset policy (and corresponding standards)
identifies the inspection and maintenance regime for
the asset type under consideration and identifies:
• the frequency of inspection and maintenance
•
the information that should be collected duringinspection
• the tasks that must be carried out during
maintenance
• the age/condition/usage criteria that should be
used to identify if the asset should be renewed.
For example, for a switch and crossing the criteria
used when considering the most appropriate action
to take will include: the condition of the ballast,
recent performance history, current levels of
maintenance necessary to maintain geometry and
component condition.
The following factors will have been explicitly
addressed by the development and application ofthis policy:
• the risk that this asset imposes on our business in
terms of delivering the required route and network
outputs (Section 5.1.2)
• the optimum maintenance/renewal interface (i.e.
the point at which the asset should be renewed
as ongoing maintenance is considered not to be
cost effective). This is based upon an
assessment of the whole life cost of managing the
asset (Section 5.1.1)
• the type and nature of the traffic on the route and
its forecast change over time (Section 5.1.2)
• an assessment of the overall impact on the
delivery of our output commitments of varying the
funding available for each asset group (Section
7.3).
The corresponding renewal item will be contained
within a workbank; detailing when the work shouldbe completed by and any necessary mitigation
measures should the work be deferred beyond this
date (5.1.3).
A4.2 Route specificationThis addresses the question: why to this
specification.
The required capacity/capability of the route
containing the asset to be renewed is defined by the
route specification. This is based upon
consideration of:
• the current and future contractual and other
commitments, and changes to capacity/capabilityagreed with customers and funders via the RUS
process (Section 4.2)
• analysis of opportunities to grow the value of the
route by considering the cost implications of asset
management policies and the value of services
provided (Section 1.1)
• consideration of customers’ reasonable
requirements for enhancements to the current
route specification (Section 1.4).
For component or minor renewal no further analysis
would generally be carried out and the renewed
asset would be designed to meet the requirements
of the route capacity/capability as currently
specified.
For major renewal, system replacement or where
the route specification indicates that enhancement
opportunities should be explored, a more detailed
consideration would be given to the design
specification. This is likely to include an
assessment of the impact on overall industry value
of varying the design of the renewed asset, and
hence the route capacity/capability that would be
delivered.
For example, consideration may be given to
enhancing the capacity/capability of a route by
increasing the line speed through a switch and
crossing that is due for renewal. The potential value
delivered by this ‘enhanced renewal’ would be
determined by consideration of the financial and
socio-economic benefits using the methodology set
out in Section 6.2. Where these benefits outweigh
the additional cost, and subject to industry
consultation and funding availability, the asset
would be renewed to the higher specification.
Network Rail would generally draw down on the
Network Rail Discretionary Fund (Section 6.1.2) to
cover the additional cost of delivering the elevated
line speed.
8/8/2019 Business Planning Criteria
http://slidepdf.com/reader/full/business-planning-criteria 37/41
37
Network Rail Business Planning Criteria
Conversely, proposed major work on a bridge
where future traffic flows no longer justify
maintaining existing capability may warrant
consideration with industry partners of the financial
and socio-economic impact of a reduction in route
capability or a diversion of existing freight services.
A4.3 Annual business planThis addresses: why this actual timing for the
renewal.
The application of the asset policy will identify that
an asset renewal is required and provide a target
date by which this renewal should be achieved.
The route specification would assist in determining
the required capacity/capability of the renewed
asset. The actual timing of the renewal work is
determined using a risk-based approach that takes
into account a number of additional factors, as set
out in Section 7.2.2. These include:
• prioritising safety critical schemes• maintaining defined capability of the route;
• meeting targets for operational performance and
asset condition
• the availability of resources (both internal and
external) to deliver the work
• the packaging of works to minimise service
disruption and network access costs and to
improve delivery efficiency.
8/8/2019 Business Planning Criteria
http://slidepdf.com/reader/full/business-planning-criteria 38/41
38
Network Rail Business Planning Criteria
Appendix 5: 26 strategic routes
Figure 10 26 planning routes and 8 operational routes
8/8/2019 Business Planning Criteria
http://slidepdf.com/reader/full/business-planning-criteria 39/41
39
Network Rail Business Planning Criteria
Appendix 6: Route classification
Figure 11 Route classification
8/8/2019 Business Planning Criteria
http://slidepdf.com/reader/full/business-planning-criteria 40/41
40
Network Rail Business Planning Criteria
Appendix 7: Draft networkcapability parametersA7.1 Track and route mileageThis parameter defines the amount of mileage on
the network.
Tracks are shown in the Sectional Appendix astrack layout diagrams. Different types of track are
shown by full, dashed and dotted lines (usually
denoting running lines used by passenger trains,
other running lines, and sidings).
Individual tracks are held in GEOGIS as either
running lines, sidings or closed tracks. Statistics are
produced to show the number of miles of track
(expressed as Single Track Miles, being the sum of
the extents of the individual tracks), either for
running lines or sidings, and the number of miles of
route (Route Miles, being the sum of the extents of
the routes), for the open network.
A7.2 Length capabilityWe have described this capability by the following
components which contribute to the overall
understanding of the impact of length as a measure.
Possible measures to be considered include:
• platform length – recognising that the capabilities
can equally apply to the passenger business, the
length of the platforms over a route can define the
maximum level of train which a passenger train
company can operate
• loop length – to deliver an appropriate level of
train performance across all operators, there are
loops positioned at strategic places across the
network which enables the maximisation ofcapacity – the length of these loops will define the
potential length of freight trains which may require
use of these loops
• junctions length – the physical length of the route
which is available across a junction which is used
as a measure so that trains do not extend across
other signalled areas
• signal section length – this is part of the loop and
junction length issue, and involves each of the
signal section lengths for the part of the unit of the
network we are considering. This is particularly
relevant where the signals are relatively close
together and freight trains are routinely longer
than a signal section length.
A7.3 Linespeed capabilityThis parameter defines the maximum speed at
which trains can travel on a track.
In some locations, a different maximum permissible
speed applies to different types of train (differential
speeds). The Sectional Appendix defines which
types of train the different speeds apply to. On
tracks used in both directions, speeds may be
defined separately for each direction.
The speeds in the Sectional Appendix are not all
held in GEOGIS, as only 4 different speeds for a
track can be stored, which are:
• maximum permissible speed (normal)
• maximum permissible speed (raised)
•
maximum permissible speed (wrong direction) or• maximum permissible speed (override) (not now
used).
Where more than two different speeds apply in the
normal traffic direction, only two may be held in
GEOGIS, one of which is always the highest speed;
and where more than one different speed applies in
the ‘wrong’ traffic direction, only one may be held in
GEOGIS, which is always the highest speed.
Moreover, the types of trains to which the speeds
apply are not held in GEOGIS.
A7.4 Gauge capability
This parameter defines the maximum size of vehicle
that is permitted on a route.
Gauge codes (e.g. W6) are assigned to vehicles
and routes, and a vehicle is permitted to travel over
a route if the vehicle gauge is within the route
gauge. The gauge code for a vehicle is derived
from the dimensions of the vehicle; the gauge code
for a route is derived from the dimensions of the
structures. Tables in the Sectional Appendix show
which passenger vehicles and locomotives are
permitted on which routes.
A spreadsheet holds the freight gauge (W6 to W10)
for each route.
A7.5 Route Availability (RA)This parameter defines the maximum weight of
vehicle that is permitted on a route.
RA numbers are assigned to vehicles and routes,
and in general terms, a vehicle is permitted to travel
over a route if the vehicle RA is less than or equal to
the route RA, but there are exceptions. The RA
number for a vehicle is derived from its maximum
axle loads and axle spacing; the RA number for a
route is derived from the strength of the under-track
structures. RA numbers for routes are shown in the
Sectional Appendix. Tables in the Sectional
Appendix show which passenger vehicles and
locomotives are permitted on which routes. A
spreadsheet holds the route availability for each
route.
8/8/2019 Business Planning Criteria
http://slidepdf.com/reader/full/business-planning-criteria 41/41
41
A7.6 Electrified track capabilityThis parameter defines the type of electrification on
a track.
Electrified tracks are defined in some of the
sectional diagrams in the Sectional Appendix.
Tables in the Sectional Appendix show whichelectric multiple units and locomotives are permitted
on which routes. GEOGIS holds codes for the
electrification type at track level in the Age of Road
files.
A7.7 Total tonnage capabilityThis is an important component of infrastructure
capability, but there is no straightforward
methodology to quantify this. We are exploring the
following approach:
• using ACTRAFF to measure total tonnage
currently running on routes (and possibly total
tonnage running at April 2001, subject to data
limitations)• identifying routes that could accommodate more
tonnage than the current level (possibly sub-
divided by band according to the potential level of
additional tonnage)
• identifying a process by which the remaining
routes could be examined regarding their
potential to accommodate more tonnage that the
current level (prioritised according to customer
aspirations and routes identified through the RUS
process).
A7.8 Gradient profileThis parameter defines the gradient on a route (and
at track level at locations where different tracks have
different gradients). Gradient is expressed as ‘1 inx’, or ‘level’, and the direction of the rising gradient is
defined. Five Mile diagrams (where available) show
the value and direction of the gradient.