Buried Instln Pract for FOC Technical Presentation

17
Presented by: Kamran Bashir Inspector I - Telecom

Transcript of Buried Instln Pract for FOC Technical Presentation

Page 3: Buried Instln Pract for FOC Technical Presentation

Placement methods for direct buried cable are essentially the

same as those used for placing direct buried copper cable.

However, it must be kept in mind that fiber cable is a high capacity

transmission medium which can have its transmission

characteristics degraded when subjected to excessive pulling

force, sharp bends, or crushing forces.

Fiber optic cables are more susceptible to performance degradation due to tight bending than copper cables. The minimum bend radius of each cable is relative to the cable diameter. A general guide line is that a cable under tension should not be exposed to a bend radius less than 20 times the cable diameter and a cable with no tension not to be exposed to a bend radius less than 10 times the cable diameter.

Standard FOC cable has maximum recommended pulling tension

of 600 lbs.

Page 8: Buried Instln Pract for FOC Technical Presentation

IV. Plowing vs. Trench:

In general, the most desirable and economical method of cable placement in open area such as desert area is plowing. Here there will be fewer obstacles to impede the progress of the plowing equipment.

Advantages of Plowing:

Speed of installation in open areas.

Less ground disturbance than may be caused by trenching.

Disadvantages of Plowing:

Large size and high cost of equipment.

Requires skilled equipment operators, quality supervision, and equipment in good condition.

Possibility of damaging cables or under ground utilities.

Page 9: Buried Instln Pract for FOC Technical Presentation

In urban or sub-urban areas where

there can be many obstacles such as

underground utilities, side walk and

paved road crossings, trenching has

advantages.

Advantages of Trenching:

Lower cost of equipment.

Digging operation is separate from

cable placement.

Better depth control.

Less risk of damaging underground

utilities.

Provides the opportunity to place

conduit at the same time.

Disadvantages of Trenching:

Slower rate of cable placement than

with plow.

Not suitable for all soil, sands and

terrain conditions .

Page 10: Buried Instln Pract for FOC Technical Presentation

The “figure-eight” configuration should be used

to prevent kinking and twisting when the cable

must be unreeled. The “figure-eight” should be

approximately 4.5 to 9.0 meters in length. Each

loop should be approximately 1.5 meters to 4.5

meters in diameter.

Page 11: Buried Instln Pract for FOC Technical Presentation

PLOWING (typical trench dimension)

When plowing in fiber optic cable a

warning orange terra tape is placed 12”

below the surface of the ground directly

above the cable. Both the cable and

the warning tape are normally plowed

in at the same time.

Page 12: Buried Instln Pract for FOC Technical Presentation

TRENCHING:

When trenching ensure an orange marker tape is placed flat in the trench above

all open trench for direct buried fiber optic cables. The marker tape is to be

placed approximately 300 mm below grade.

Page 16: Buried Instln Pract for FOC Technical Presentation

SATIP-T-624

CONT’N – APPLICABLE S TA N DA R D S F O R F O C - O S P

SAIC-T-5408