Bulletin Vol 2 Issue 7 - Welcome to Entracon · Landscaping Installation of Public Lighting...

11
www.entracon.com.au the bulletin ENTRACON BIANNUAL UPDATE Volume 2, Issue 7 SPRING / SUMMER 2014/2015 Entracon 51 Melverton Drive Hallam Victoria 3803 Ph: 03 8786 3700 Fax: 03 8786 3722 Email: pro- [email protected] In this issue… Current Projects Lake Endevour Dam Upgrade Parkes, NSW Nine Mile Creek Reservoir Upgrade Longwood, Vic Boronia Retarding Basin Boronia, Vic Orde Hill Reservoir Upgrade, Mt Macedon, Vic St Georges Dam Creswick, VIC Wilsons Reservoir Upgrade Bullarook Booran Rd Reservoir Demolition Glenhuntly, Vic Completed Projects Dandenong Creek Rehabilitation Heathmont, Vic Charles Mutton Reserve Stormwater Fawkner, Vic Sunbury Landfill / Transfer Station Sunbury, Vic Jack Madigan Reserve Williamstown, VIC Burdens Park Springvale South Napier Conservation Park Strathmore, Vic Lake Endeavour Dam Upgrade, Parkes, NSW Lake Endeavour Dam is located on the Billabong Creek, approximately 25km east of Parkes. The dam was built in 1940 and when full covers an area of around 55 hectares, and holds 2400 ML Lake Endeavour Dam is the key water reservoir for the Parkes Shire and has performed and operated in a satisfactory manner for the past 76 years. However, the spillway capacity is now considered inadequate by mod- ern standards and requires strengthening and flood security works to be carried out . The upgrade works involve strengthening the Dam embankment and spillway training wall to ensure long term stability and integrity of the structure. Increased flood security will be achieved by widening/deepening the existing relief spillway and raising the current embankment crest. This infrastructure upgrade will maintain Lake Endeavour as a key water resource for the Parkes Shire for many decades to come

Transcript of Bulletin Vol 2 Issue 7 - Welcome to Entracon · Landscaping Installation of Public Lighting...

Page 1: Bulletin Vol 2 Issue 7 - Welcome to Entracon · Landscaping Installation of Public Lighting Construction of Drainage and pit structures Construction of Retaining walls Top soiling

www.entracon.com.au

the bulletin

ENTRACON BIANNUAL UPDATE

Volume 2, Issue 7

SPRING / SUMMER 2014/2015

Entracon

51 Melverton Drive Hallam Victoria 3803

Ph: 03 8786 3700 Fax: 03 8786 3722

Email: [email protected]

In this issue…

Current Projects

Lake Endevour Dam Upgrade Parkes, NSW Nine Mile Creek Reservoir Upgrade Longwood, Vic

Boronia Retarding Basin Boronia, Vic

Orde Hill Reservoir Upgrade, Mt Macedon, Vic

St Georges Dam Creswick, VIC

Wilsons Reservoir Upgrade Bullarook

Booran Rd Reservoir Demolition Glenhuntly, Vic

Completed Projects

Dandenong Creek Rehabilitation Heathmont, Vic

Charles Mutton Reserve Stormwater Fawkner, Vic

Sunbury Landfill / Transfer Station Sunbury, Vic

Jack Madigan Reserve Williamstown, VIC

Burdens Park Springvale South Napier Conservation Park Strathmore, Vic

Lake Endeavour Dam Upgrade, Parkes, NSW

Lake Endeavour Dam is located on the Billabong Creek, approximately 25km east of Parkes. The dam was built in 1940 and when full covers an area of around 55 hectares, and holds 2400 ML Lake Endeavour Dam is the key water reservoir for the Parkes Shire and has performed and operated in a satisfactory manner for the past 76 years. However, the spillway capacity is now considered inadequate by mod-ern standards and requires strengthening and flood security works to be carried out . The upgrade works involve strengthening the Dam embankment and spillway training wall to ensure long term stability and integrity of the structure. Increased flood security will be achieved by widening/deepening the existing relief spillway and raising the current embankment crest. This infrastructure upgrade will maintain Lake Endeavour as a key water resource for the Parkes Shire for many decades to come

Page 2: Bulletin Vol 2 Issue 7 - Welcome to Entracon · Landscaping Installation of Public Lighting Construction of Drainage and pit structures Construction of Retaining walls Top soiling

www.entracon.com.au

2014/15 Current projects

Volume 2, Issue 7

Lake Endeavour Dam Upgrade, Parkes, NSW

Client:

Parkes Shire Council

Project Design:

NSW Water Design Contract Sum: $ 8.0M

Key Aspects

Deep excavation Large scale construction works Working within an operating

dam environment

Works Include

Construction of Auxiliary Fuse Plug Relief Spillway

Embankment Strengthening Works Relocation of Existing and installation of

new instrumentation Service spillway training wall concrete

strengthening works Service spillway training wall post

tensioning works Upgrade of outlet works Reinforced concrete conduit

strengthening works

Page 3: Bulletin Vol 2 Issue 7 - Welcome to Entracon · Landscaping Installation of Public Lighting Construction of Drainage and pit structures Construction of Retaining walls Top soiling

www.entracon.com.au

2014/15 Current projects

Volume 2, Issue 7

Nine Mile Creek Reservoir Upgrade, Longwood, Vic

Client:

Goulburn Valley Water

Project Design:

SKM

Contract Sum: $ 1.6M

Key Aspects

Remoteness of site Accessibility to works Large concrete pours Construction tolerances

Works Include

Removal/decommissioning of existing pipework and fittings including grouting of pipes.

Design and construction of coffer dam and all associated temporary works

Construction of earthen zoned embankment Construction of concrete and rock gabion spillway including

culverts and guard railing. Construction of access track

The Nine Mile Creek reservoir is about 150km north of Melbourne and provides the town of Longwood with its water supply. The dam is currently operated at less than full capacity and is in poor condition with excessive seepage and embankment instability. The project involves works to upgrade and im-prove the stability of the existing reservoir embankment and overall dam safety to ensure that a relia-ble supply of water is provided to the Longwood township.

Page 4: Bulletin Vol 2 Issue 7 - Welcome to Entracon · Landscaping Installation of Public Lighting Construction of Drainage and pit structures Construction of Retaining walls Top soiling

www.entracon.com.au

2014/15 Current projects

Volume 2, Issue 7

Boronia Retarding Basin, Boronia, Vic

Client:

Knox City Council

Project Design:

Knox City Council Contract Sum: $ 1.5M

Key Aspects

Working in a live drainage asset Protection of existing gum trees Site access and proximity to

major road

Works Include

Bulk Earthworks Concrete Paving Design, construction and certification of timber boardwalks Landscaping Installation of Public Lighting Construction of Drainage and pit structures Construction of Retaining walls Top soiling and seeding of lawn areas.

Knox City Council has been working closely with Melbourne Water for the past 2 years to identify ways to improve the storage capacity of the retarding basin for flood protection of residents, without losing a much –valued park site . In its current form the Retarding Basin and surrounding drainage has a higher risk of reaching its full capacity and flooding overland. The upgrade works will signifi-cantly reduce the risk to as low as 2% .Comptetion of the project will see an improved useability of the park with creation of a ‘meadow’ and wetland garden, feature trees, wider paths and a multipur-pose plaza space.

Page 5: Bulletin Vol 2 Issue 7 - Welcome to Entracon · Landscaping Installation of Public Lighting Construction of Drainage and pit structures Construction of Retaining walls Top soiling

www.entracon.com.au

2014/15 Current projects

Volume 2, Issue 7

Orde Hill Reservoir Upgrade, Mt Macedon, Vic

Client:

Western Water

Project Design:

GHD Contract Sum: $ 0.5M

Key Aspects

Limited access to work site Poor weather conditions Poor ground conditions Significant Asbestos removal

Works Include

Clearing, Topsoil and Grassing Chimney Filter Works Outlet Filter Protection Works Concrete Pits, hinged lockable lid. Drainage Blanket Upgrade Subsurface Drainage Excavate toe drain, stockpile and reinstate drain. Surface Drainage Rock line road side drain including lining, groin drains, toe

drain,

The Orde Hill Reservoir, located on the Willimingongon Creek, Mt Macedon has a capacity of 250 million litres. This reservoir is used to harvest and store water before it is transferred to Rosslynne Reservoir and/or the Graham Brock Reservoir, Woodend, where it is treated and distributed to customers as drinking water. On completion, the upgrade works will ensure Western Water meets ANCOLD guidelines for dam safety and the integrity of the Orde Hill reservoir will be improved and re-duce the risk of dam failure.

Page 6: Bulletin Vol 2 Issue 7 - Welcome to Entracon · Landscaping Installation of Public Lighting Construction of Drainage and pit structures Construction of Retaining walls Top soiling

www.entracon.com.au

2014/15 Current projects

Volume 2, Issue 7

St Georges Dam, Creswick, Vic

Client:

Parks Victoria

Project Design:

SMEC Australia Contract Sum: $ 1.6M

Key Aspects

Poor Site access Poor ground conditions Deep excavation Flood water level management Extreme weather conditions

St Georges Lake Dam is located outside the township of Creswick. In late 2010 severe storms resulted in water levels creeping dangerously close to the crest of the dam wall. This close call reinforced the need fort eh 1-00 year old structure to gain and urgent upgrade. The new design of the dam and the spillway being constructed will reduce the volume of water held by the lake, therefore improving safety during high rainfall and flood events.

Works Include

Dewatering of the reservoir and water control management during construction;

Clearing, grubbing and off-site disposal of vegetation and other obstructions to the work;

Decommissioning of the piezometers and outlet works Removal of pedestrian footbridge over the primary spillway; Stripping and stockpiling of top soil; Excavation of the embankment Construction of the new spillway; Construction of the rockfill weir downstream of the secondary

spillway chute; Construction of pedestrian access from the south to north

extents of the site; Landscaping and grassing of all areas

Page 7: Bulletin Vol 2 Issue 7 - Welcome to Entracon · Landscaping Installation of Public Lighting Construction of Drainage and pit structures Construction of Retaining walls Top soiling

www.entracon.com.au

2014/15 Current projects

Volume 2, Issue 7

Wilson reservoir Upgrade, Bullarook Vic

Client:

Central Highlands

Water

Project Design:

MWH

Contract Sum: $3 M

Key Aspects

High Bushfire Risk Protection of Heritage Buildings Maintaining water level in reser-

voir while under construction High Rainfall Risk

Works Include

Chimney Filter / Drains with Weighting Buttress. Filter Cutoff trench Outlet works, including Concrete encasement, brickwork

and discharge channel Cured in Place Pipe (CIPP) New auxiliary spillway including Cutoff and Riprap Crest capping materials and {Piezometer Extensions Establishment and monitoring or temporary deformation

monitoring survey points Salvage of existing outlet works structure brickwork Construction of embankment swale drain

Wilsons Reservoir is and earthen dam, immediately upstream of Beales Reservoir, and was constructed in 1891 with a capacity of 1010ML. The old dam was 285m log and up to 10 m high. To comply with ANCOLD’s 1 in 100,000 year flood requirements, Entracon has been engaged to up-grade the spillway, outlet pipeline, earthen embankment including the installation of sand filters, addition of a full height berm to meet ANCOLD guidelines, new auxiliary spillways and improved site drainage

Page 8: Bulletin Vol 2 Issue 7 - Welcome to Entracon · Landscaping Installation of Public Lighting Construction of Drainage and pit structures Construction of Retaining walls Top soiling

www.entracon.com.au

2014/15 Current projects

Volume 2, Issue 7

Booran Rd Reservoir Demolition, Glenhuntly Vic

Client:

Glen Eira City Council

Project Design:

TGM Group

Contract Sum: 0.7M

Key Aspects

Concrete demolition within a residential area Noise control Pedestrian/ Traffic Management Proximity of site to main road.

Works Include

Mass concrete demolition Demolition of Earth embankments Bulk Earthworks Stormwater protection Tree and stump removal Protection of assets. Site dewatering

The former Melbourne Water Reservoir located on Booran Road occupies 1.6Ha and has been unused for well over 30 years. Glen Eira city council are now redeveloping this land into a passive recreational space for use by the local community. Whilst the majority of the concrete wall will be demolished, the reservoir walls along the east and north side will be retained as will the central sluice gate, which controlled water levels in the reservoir, as a link to the past history of the site,. Both of these will become key components in the park design.

Page 9: Bulletin Vol 2 Issue 7 - Welcome to Entracon · Landscaping Installation of Public Lighting Construction of Drainage and pit structures Construction of Retaining walls Top soiling

www.entracon.com.au

2014/15 completed projects

Volume 2, Issue 7

Client:

Moreland City Council

Project Design:

Spiire

Contract Sum: $1M

Key Aspects Publicity of Project Public/Pedestrian Management and

Control Connection to MWC asset Heavy Rock excavation

Works Included Excavation for pipelines and foundations, including

dewatering, topsoil stripping and site levelling Excavation and installation of valve pits and buffer

storage tanks Excavation of diversion pump stations: sump pit and wet

well onstruction of Raingarden and underground day storage Installation of GPT

Charles Mutton Reserve Stormwater, Fawkner, Vic

Client:

City of Moonee Valley

Project Design:

AECOM

Contract Sum: $0.8M

Key Aspects Heavy rains delaying progress Conflicts with existing services Redesign of pipe runs to avoid services Deep excavation Limited site access

Works Included Bulk earthworks Removal of existing services Stormwater Drainage pipes 250m Storm Trap underground Levee Installation Installation of Irrigation System Construction of rock riffle Landscaping and planting

Napier Conservation Park, Strathmore, Vic

Page 10: Bulletin Vol 2 Issue 7 - Welcome to Entracon · Landscaping Installation of Public Lighting Construction of Drainage and pit structures Construction of Retaining walls Top soiling

www.entracon.com.au

2014/15 completed projects

Volume 2, Issue 7

Works Include

Installation of driven piles Construction of the upper and lower concrete slabs/platforms Construction of the vertical concrete wall between the upper

and lower concrete slabs Construction of the steel roof including its supporting columns Installation of roof drainage Installation of lighting and GPO items Installation of works site drainage system.

Client:

Hume City Council

Project Design:

Form Structures

Contract Sum: $0.7M

Client:

Hobsons Bay City

Council

Project Design:

Spiire Australia Contract Sum: $ 0.95M

Key Aspects

Deep compaction New to Australia -

First construction methodology using RIC7000 Poor ground conditions

Jack Madigan Reserve, Williamstown, Vic

Sunbury Landfill/Transfer Station, Sunbury, Vic

Works Included Bulk Earthworks Deep Compaction Landscape works Grassing and lawn areas Landscape feature rock work

Key Aspects

Large scale concrete construction Remoteness of site Ground conditions

Page 11: Bulletin Vol 2 Issue 7 - Welcome to Entracon · Landscaping Installation of Public Lighting Construction of Drainage and pit structures Construction of Retaining walls Top soiling

2014/15 Other News

www.entracon.com.au Volume 2, Issue 7

New to the Entracon Fleet

Sean Durston-Ryan Project Engineer

Welcome

Entracon was proud to be part of the winning team, along with designers Spiire Australia, Moreland City Council and Melbourne Water. Moreland City Council identified the need for revitalisation of Charles Mutton Reserve and the opportuni-ty to future proof the site against drought. The final design included a stormwater diversion system and underground storage tank, distribution I infrastructure including rising main and pumps, 500kL above ground storage tanks, raingarden to treat sediments and nutrients, irrigation storage to provide volume for irrigation cycles and UV disinfection to treat pathogens. The expected water harvest of 20ML/year will reduce the sites reliance on potable water

by 70%, reduce stormwater runoff to nearby Merri Creek and provide a significantly increased amenity for users.

SIAV Awards 2014—Stormwater Victoria Merit Award - Excellence in Infrastructure Charles Mutton Stormwater Harvesting Scheme

Entracon is on the move ….. Entracon has outgrown our office space and early in the new year will be moving to our new address at 105 Fox Drive, Dandenong South Vic 3175. Please make sure to update your records.

Due to the ever increasing demand on our excavators, a second PC450LC-8 has been added to our fleet.