Back to contents Back to contents Building Handover Documents This Power Point Presentation is compiled from using, experience in construction, skills in building management and knowledge gained from studying guidelines. Special thanks are due in no small part to BSRIA. Open the powerpoint in slide screen go to page 2 and click on a section and it takes you there, when finished in that section click on back to Fresh Eyes Facilities Assistance FM solutions made easy

Transcript of Building Handover Documents v14

Page 1: Building Handover Documents v14

Back to contentsBack to contents

Building Handover Documents

This Power Point Presentation is compiled from using, experience in construction, skills in building management and knowledge gained from studying guidelines. Special thanks are

due in no small part to BSRIA. Open the powerpoint in slide screen go to

page 2 and click on a section and it takes you there, when finished in that section click on

back to contents and it does what it says.

Fresh Eyes Facilities AssistanceFM solutions made easy

Page 2: Building Handover Documents v14

Back to contentsBack to contents

Building Handover Documents

• 1. The User Guide• 2. O&M Information• 3. Computer Aided FM• 4. Record Drawings• 5. Statutory Examination and Insurance• 6. Familiarisation And Training Sessions• 7. Commissioning Information• 8. Plant and System Warranties• 9. Defects Period• 10. Storage and Access of Information• 11. Documentation to be held• 12. Regulatory Reform (Fire Safety) Order

2005 should cover• 13. Construction (Design and Management)

Regulations 2007 (CDM)

Page 3: Building Handover Documents v14

Back to contentsBack to contents

1. The User Guide

• 1.1 Emergency Procedures• 1.2 The Building Health And Safety File• 1.3 Catering• 1.4 Facilities Management• 1.5 Security• 1.6 Space Planning

– 1.6.2 Floor Plate Usage• 1.7 Directories• 1.8 Out Of Hours contacts• 1.9 Support Services

– 1.9.1 FM– 1.9.2 ICT– 1.9.3 HR

• 1.10 Guided Tour– 1.10.1Photo– 1.10.2 Video– 1.10.3 Booklet

Page 4: Building Handover Documents v14

Back to contentsBack to contents

1. The User Guide1.1 Emergency Procedures

Page 5: Building Handover Documents v14

Back to contentsBack to contents

1. The User Guide1.2 Building Health & Safety File

• 1.2.1. General • 1.2.2. Nature of Project • 1.2.3. Principals • 1.2.4. Contractors and Suppliers • 1.2.5. Drawings • 1.2.6. Documents • 1.2.7. Construction Methods and

Materials • 1.2.8. Residual Risks & Fire Strategy • 1.2.9. Manuals and Procedures • 1.2.10. Services and Utilities

Page 6: Building Handover Documents v14

Back to contentsBack to contents

• 2.1 Maintenance Strategy• 2.2 Legislations covering O&Ms• 2.3 The Content of O&M Manuals• 2.4 Type of O&M Manual• 2.5 O&M Strategy• 2.6 Users of O&M Manuals• 2.7 Sources of Information• 2.8 The Content of O&M Manuals• 2.9 Contents, structure and layout• 2.10 Specification of manuals for

Building Services

2. O&M InformationContents

Page 7: Building Handover Documents v14

Back to contentsBack to contents

2. O&M Information• 2.1 Maintenance Strategy

– Building– Plant– Environment

• 2.2 Legislations covering O&Ms– 2.2.1 Construction (Design and Management)

Regulations 2007• See Below CDM

– 2.2.2 Control of Substances Hazardous to Health Regulations 2002 (COSHH)

• Risk Assessment– of Legionellosis

» IF Present» Written Scheme for minimising» Specification of below with» Water Treatment Regime» Flow Rates» static and dynamic pressures» thermal capacity» system volumes» operating temperatures» set points

Page 8: Building Handover Documents v14

Back to contentsBack to contents

2. O&M Information» Storage capacity» Design turnover» Cold Water Cisterns» Hot Water Storage» Semi Storage Plant» Heat Recovery Time» Hot Water Storage» Semi-storage Plant» Key Areas in Building Services» Evaporative Condensers» Cooling Towers» Hot & Cold Water Services» Spray Humidifiers» Sprinkler Systems» O&M's should» be available for each water system» be detailed» In easily understood terms» O&M procedures that» enable operators to

Page 9: Building Handover Documents v14

Back to contentsBack to contents

2. O&M Information» carry out duties safely» and effectively» Manuals should» include equipment fitted» represent the system as currently in

operation» include system drawings» include schematics» manufacturers instructions for

operating» system parameters» Capabilities» throughputs» design temperatures» total volume of the entire water

circuit» cooling tower ponds» recirculation pipe work» heat exchange pipe work

Page 10: Building Handover Documents v14

Back to contentsBack to contents

2. O&M Information» should all be known and recorded» Water treatment program» in use» dosing method» dosing equipment» means to confirm treatment» quantity» frequency» chemicals» records to confirm above» Records» results of system monitoring» actions required» confirmation actions carried out» Details of normal parameters» out of specification situations» corrective actions

Page 11: Building Handover Documents v14

Back to contentsBack to contents

2. O&M Information» changes» cleaning» disinfection procedures» Detailed Maintenance Schedule» time intervals» checks» Water and System Plant» Checked» Inspected» Overhauled» Cleaned» Records made» Method» Details

– Hazardous substances» Employees likely to be exposed to» Form in which they occur

Page 12: Building Handover Documents v14

Back to contentsBack to contents

2. O&M Information» Measures taken to adequately

control exposure» information provided by supplier» using substance in accordance to

instructions» Statement» substance poses little or no risk» group of little or no risk

– Risk to health» Significant Findings» Comprehensive record» process or activity» used or produced» how staff may be exposed» Substances» liable to be exposed» form in which they occur» gas

Page 13: Building Handover Documents v14

Back to contentsBack to contents

2. O&M Information» liquid» vapor» powder» under normal circumstances» unforeseen» incident» accident» emergency» uncontrolled release» extent to which - considered» prevention» submission» identification of liable to be exposed» employees » groups» preventative measures» achieve adequate control» use of protective equipment» personal» respiratory

Page 14: Building Handover Documents v14

Back to contentsBack to contents

2. O&M Information» Control measures» Commissioning» Monitoring» Testing» refining» validating» air monitoring» need» atmospheric sampling» measurement» frequency» PPE» Why selected type» including repertory» to secure control» conclusions reached on the risk» employees» other people

Page 15: Building Handover Documents v14

Back to contentsBack to contents

2. O&M Information» Health Surveillance» need» groups» persons» Review» When» by whom» frequency

– 2.2.3 Electricity at Work Regulations 1989

• Precautions against Risk– of Injuries– Fatalities

• use of electricity in work activities• for

– Engineers– Technicians

Page 16: Building Handover Documents v14

Back to contentsBack to contents

2. O&M Information– Involved in

» Design» Construction» Operation» maintenance

– use of electrical equipment

• Satisfied by compliance or– Institution of Electrical Engineers (IEE)

wiring Regulations for Electrical Installations (BS7671)

– Under IEE– Employers have responsibility to

» test» maintain» Electrical equipment in a safe

condition

Page 17: Building Handover Documents v14

Back to contentsBack to contents

2. O&M Information– 2.2.4 Environment Protection Act

1990• Places Obligation on those who -

controlled waste– produce– carry– keep– treat– dispose of

• and must– prevent from illegally - their waste

» keeping» treating» disposing

– prevent waste from escaping– only transfer waste

» to an authorized person» to an authorized transporter

– waste is accompanied by written description

Page 18: Building Handover Documents v14

Back to contentsBack to contents

2. O&M Information• Building Owners must

– Have a procedure» Handling» Disposal» Building Services» Refrigerants» waste oil» chemicals» fluorescent tubes» Record of waste transfer» Waste handler details» Waste transporter

• Environmental Protection (Duty of Care) Regulations 1991

– Allows a Season ticket of Transfer» Weekly / Daily Collections» Maximum 12 months

Page 19: Building Handover Documents v14

Back to contentsBack to contents

2. O&M Information

– 2.2.5 Factories Act 1961• Largely Superseded by H&S@W Act• And Workplace (H,S, Welfare) Regulations

– 2.2.6 Regulatory Reform (Fire Safety) Order 2005

• Largely replaced 118 pieces of previous legislation• Notably Fire Precautions Act 1971• Revocation of Fire

Precautions(Workplace)regulations 1997• Places responsibility for fire safety on responsible

person• See Separate Section Below

– Details of– 2.2.7 Fire Safety Information

• Guidance in Appendix G of Approved Documents B Volume 2 states

• Fire Safety means information relating to the design and Construction... and services, fittings and equipment provided in or in connection with the building, or extension which will assist the responsible person to operate and maintain the facility with reasonable fire safety

Page 20: Building Handover Documents v14

Back to contentsBack to contents

2. O&M Information• Information to be submitted at completion or

occupancy• must be available to any nominated risk

assessor• Further Guidance from

– BS 5588-12:2004– Fire Precautions in the design, construction

and use of Buildings– Managing Fire Safety (Annex A Fire Safety

Manual)

– 2.2.8 Management of Health and Safety at Work Regulations 1999

• Risk Assessments should include– A record of the Preventative and Protective

measures in place to control risk– What action, if any needs to be taken to

reduce risks– Proof that a suitable and sufficient assessment

has been made

• Demonstration by employers that Risk Assessments have been made

– Record of findings– record of recommendations– Record of Revisions

Page 21: Building Handover Documents v14

Back to contentsBack to contents

2. O&M Information• Review and modify Risk Assessments

– Nature of work changes– Change to employees– Reveal Near Misses– Reveal Defects in plant or equipment– Regular review

» Based on nature of Risk and degree of likely change

– 2.2.9 Offices, Shops and Railways Premises Act 1963

– 2.2.10 Pressure Systems and Transportable Gas Containers Regulations 1989

• PSS Regs. 2000– steam at any pressure– Pressurised Gasses and Fluids kept under

pressure greater than 0.5bar gauge and will flash to gas if released to the atmosphere

– Pressurised Hot Water if above 110 deg c– Compressed air above 0.5 bar gauge

• Pressure Systems defined as– Pipe work systems

Page 22: Building Handover Documents v14

Back to contentsBack to contents

2. O&M Information– Related protection devices

» Where pressure is +2 bar– Pipe work systems which are or will be

joined to the portable gas container– Systems that contain one or more

pressure vessels with capacity <250 bar liters

– Refrigerated systems with power input <25kW

– All Steam systems• specific requirements from

– Manufacturers– Designers– to provide

» sufficient information to allow the system to be operated and maintained safely

» Test Certificates» Certificates of Conformity» From Manufacturers» From Examination Bodies» Maximum and minimum design

temperatures and pressures» Flow and Discharge capacities» capacity of pressure vessels

Page 23: Building Handover Documents v14

Back to contentsBack to contents

2. O&M Information• Written Scheme of Examination

– Planned scheme for future examination» Parts» Pressure systems» appropriate intervals

– Responsibility of Owner or user to define– Identification of the items of plant or

equipment within the system– those parts to be examined– nature of the examination required

» inspection» testing» Recording» on any protective device

– Preparatory work needed for the item to be examined safely

– The nature of any examination needed before the system is first used

– Maximum interval between examinations

Page 24: Building Handover Documents v14

Back to contentsBack to contents

2. O&M Information– the critical parts of the system which if

modified or repaired should be examined» by a competent persons before the

system is used– Name of competent person certifying the

written scheme of examination– The date of the Certification

– 2.2.11 Provision and Use of Works Equipment Regulations 1998

• Under section 2 of H&S@W

• Provide & Maintain– Machinery– Equipment– other plant– In a safe condition

• to ensure Systems of work are safe• Requires employers to

– Ensure equipment is appropriate for its task

– Provide information and instruction for work equipment

– ensure work equipment is adequately maintained

Page 25: Building Handover Documents v14

Back to contentsBack to contents

2. O&M Information• Information to be provided

– written instructions– Explaining Operation

» normal conditions» Abnormal conditions» Emergency conditions

• Covers and includes building services equipment

– All H& aspects arising from the use of the work equipment

– any limitations on these uses– any foreseeable difficulties that could

arise– the methods to deal with them

– 2.2.12 Workplace Health, Safety and Welfare Regulations 1992

• Suitable working environment• adequate welfare facilities for all• onus on employer

Page 26: Building Handover Documents v14

Back to contentsBack to contents

2. O&M Information– suitable system of maintenance of

» heating systems» Ventilation systems» emergency lighting» escalators and moving walkways» sanitary appliances» washing facilities» drinking water systems» window cleaning equipment

– suitable record of maintenance» implemented» validated

– 2.2.13 Disability Discrimination act 2005

• gave disabled people rights– Employment– education– access to goods– access to facilities

Page 27: Building Handover Documents v14

Back to contentsBack to contents

2. O&M Information– access to services– buying and renting property

• Rights covering– unlawful for operators of transport vehicles to

discriminate– making it easier for DP to rent property and for

tenants to make disability related adaptations– Requiring public bodies to promote equality of

opportunity for DP– extending protection to cover people who have HIV,

Cancer, Multiple Sclerosis from the moment they are diagnosed

– Ensuring that discrimination law covers all the activities of the public sector

• requiring business– to take steps to tackle physical features that act as a

barrier to those who want access– 2.2.14 The Notification of Cooling Towers and

Evaporation Condensers Regulations 1992• notify local authorities

– where equipment is situated– potential growth of

» Legionella Pueumophila bacterium

Page 28: Building Handover Documents v14

Back to contentsBack to contents

2. O&M Information– 2.2.15 The Control of Noise at Work

Regulations 2005• Code of practice L108 states

– You should record the major findings of your risk assessment and you action plan

– The major findings are you estimate of daily personal noise exposure and peak noise exposure

– your analysis of the risks and whether they are as low as reasonably practicable

– any other information on which you based the evaluation of risk and the decisions on actions required under the Noise Regs.

– The record will provide some evidence for the decisions that you made to comply with the law.

– A minimum adequate record will include details of - - - -

• of– The workplace area, jobs or people included in the

assessment, including a description of the work– The date of the assessment done– The daily personal noise exposure of the employees

or groups of 4employees concerned– The information use to determine noise

exposure– If noise measurements have been made,

relevant details of the measurements, including the person(s) responsible for carrying them out

– Any further information used to evaluate risk– the name of the person(s) responsible for

making the risk assessment

Page 29: Building Handover Documents v14

Back to contentsBack to contents

2. O&M Information– Your action plan to control noise risk

• Approved Code of Practice L108– States that an up-to-date health record for each

individual whilst under health surveillance– to include

» Identification details of the employee» The employees history of exposure to noise» The outcome of previous health surveillance in

terms of» fitness» the work» any restrictions» The person in charge of the audiometric

program should maintain records of the program including

» Any questionnaires completed» the Audiograms themselves» any assessments made of the results

– Visiting service records must be maintained by employer, separate from HR Records

– Retain all employee health records whilst employed

Page 30: Building Handover Documents v14

Back to contentsBack to contents

2. O&M Information• 2.3 The Content of O&M Manuals

– The Type required or warranted by the installations and needs of the end user

– The operating and maintenance strategy envisaged for the installation

– the categories of user for whom the manual is being written

– The likely sources of information• 2.4 Type of O&M Manual

– specification• meets the needs of end user• guidance on likely competence of the potential users

– Details of training and qualification where appropriate

– Combination• Function• system based structured information• Arranged

– Logical– Hierarchical structure

Page 31: Building Handover Documents v14

Back to contentsBack to contents

2. O&M Information• Laid down in

– BS 4884 part 1 :a992 Specification for Presentation of Essential Information

– Part 2 : 1993 Guide to content– Part3 : 1993 Guide to Presentation

– Now looking more towards• Low energy• Passive energy recovery

– Client to ensure• Designers intent on building use

– Function -based• User operation of local systems

– OHPs– Room lighting– local environment controls

– Reference• Building Controls Industry Association (BCIA)• Usable Buildings Trust UBT• Building Services Research Information

Association (BSRIA)

Page 32: Building Handover Documents v14

Back to contentsBack to contents

2. O&M Information– System Based Manuals

• points to each building service• Class A

– Basic Record Drawings– Manufacturers Literature– Manufacturers Manuals

• Class B– Record Drawings– Manufacturers Operating Instructions– Manufacturers Operating Manuals– Test Certificates– Parts List

• Class C– Purpose and Planning Information– Technical Documents

» Record Drawings– Full Operating Instructions for each

system– Detailed Maintenance Instructions– Detailed Maintenance Schedules– Parts Lists

Page 33: Building Handover Documents v14

Back to contentsBack to contents

2. O&M Information– Modification Instructions– Disposal Instructions

• Class D– Purpose and Planning Information– Technical Documents

» Record Drawings– Full Operating Instructions for each

system– Detailed Maintenance Instructions– Detailed Maintenance Schedules– Parts Lists– Modification Instructions– Disposal Instructions– Commissioning Process

» Procedures» Results» Tests undertaken

– Warranties» Plant» Systems

Page 34: Building Handover Documents v14

Back to contentsBack to contents

2. O&M Information• Class A&B

– Prepared by Installer– Complies with H&S@W Act 1974

• Class C&D– Comprehensive Documents– Capable of being used without further

supporting documentation

• 2.5 O&M Strategy– Consideration of

• Building owner• Building users' legal obligations• Running Building Services• To help fulfill these obligations

– Client to work with Design Team• establish a brief

– Specific information required• Building services Designer

– environmental Services– Operation and Maintenance requirements

Page 35: Building Handover Documents v14

Back to contentsBack to contents

2. O&M Information– Involve Maintenance Expertise

• Identify needs– Building Plant and Services

• achieve Objectives of building owner– conditions– limitations– Environmental conditions required– Occupancy times– Implication of plant failure– labour and resources for maintenance

– Amount of information needed• by whom• for what purpose• in what detail• what competence of users

– How to be presented• Paper• Electronic• Both

Page 36: Building Handover Documents v14

Back to contentsBack to contents

2. O&M Information• Training to be given

– Maintenance Plan• How to achieve• cost limitations• Planned Life• Risk Analysis• Plant breakdown policy• The availability of plant for

maintenance• Specialist support needed/available• Client image

– Floodlights etc– Water features– Grounds– Building Cleanliness– car park image

• 2.6 Users of O&M Manuals– Categories

• Occupiers of buildings

Page 37: Building Handover Documents v14

Back to contentsBack to contents

2. O&M Information– differing requirement

» Interests» Abilities» Expertise

– General overview

• Managing and operating buildings– differing requirement

» Interests» Abilities» Expertise

– detailed design concept– Operational Capacity– Maintenance program

• Maintainers of Buildings– differing requirement

» Interests» Abilities» Expertise

– technical details» plant» O&M requirements

Page 38: Building Handover Documents v14

Back to contentsBack to contents

2. O&M Information– Presentation– Training– Availability– Searchability– Extracted– Consider separate Manuals for the above

groups• or electronically segment the system

• 2.7 Sources of Information– Design engineers

• Set out operating philosophy of each engineering service

– Purpose– the method of control– emergency provisions– safety considerations– design criteria– design intent

Page 39: Building Handover Documents v14

Back to contentsBack to contents

2. O&M Information– Equipment Manufacturers and Suppliers

• Literature• Produced in line with BS4940:1994 Technical

Information on Construction Products and Services, Guide to Content and Arrangement

– Identification» Product type

» Quality» description» Standards» Guarantees

– Description» Composition» Manufacturer» Size» weight

– Performance» Energy consumption

– Applications» Uses» Resources Required

Page 40: Building Handover Documents v14

Back to contentsBack to contents

2. O&M Information– Construction

» preparation» installation» protection» Safety

– Operation» Maintenance resource» Operations» Maintenance» Cleaning» Protection» Safety

– Installation Contractors• provide a working system in

accordance with design specification– integrating equipment into a functional

scheme• information on chosen manufacturer

Page 41: Building Handover Documents v14

Back to contentsBack to contents

2. O&M Information• details of systems

– operations– Performance– testing– commissioning results– variations on design criteria

– Integration of the differing types of information

• Sources• types• Formats

• 2.8 The Content of O&M Manuals– BS4884 lists 9 categories of information

• The purpose of the installation• Installation records• description of the installation• How the installation is to be used• How to keep the installation operational• Maintenance schedules• how the installation may be changed• Disposal of the installation

Page 42: Building Handover Documents v14

Back to contentsBack to contents

2. O&M Information• 2.9 Contents, structure and layout

– 2.9.1 Contractual and legal guides• Name and Address of installation• Details of the local and public

authority consents• details of the teams

– Design– Consultants– Installation contractor– associated sub-contractors

• dates of the installation– Start– Handover (PC)– expiry of the defects liability period

• Information on all Guarantees effecting components

– systems– plant– expiry dates– Contacts

» names» addresses

Page 43: Building Handover Documents v14

Back to contentsBack to contents

2. O&M Information» telephone numbers

• Each item of plant and equipment the O&M should have

– Test certificates– Manufacturers guarantees and warranties– insurance inspection reports– safety and fire certificates

• Hazard and safety statement– any Known feature which may produce a

hazard– operational characteristic which may produce

a hazard– any known hazards against which protection

can be provided– any mandatory requirements relating to

safety– any other safety precautions which should

be observed– any other relevant warning

Page 44: Building Handover Documents v14

Back to contentsBack to contents

2. O&M Information– 2.9.2 Overall Purpose

• general overview• should include

– Parameters and conditions within which it has been designed to operate a system

– Type of each utility require to operate a system– intended method of control– should be as brief as possible

– 2.9.3 Description• of each engineering system installed• should include

– The system type (i.e. cold water supply)– System Location and what it serves– What the system depends upon in order to

function– Design Data

» Basic design parameters» basic assumptions made during design

– Reasons for selecting particular plant

Page 45: Building Handover Documents v14

Back to contentsBack to contents

2. O&M Information– expected service life– planned operational efficiency

– 2.9.4 Equipment schedule• Type• model number• serial number of all components items• names of their respective manufacturers or

suppliers

– 2.9.5 Parts identification and recommended spares

• Identifying replaceable assemblies• sub assemblies and components

Page 46: Building Handover Documents v14

Back to contentsBack to contents

2. O&M Information– 2.9.6 Spares policy

• guide to setting up a spares facility• recommended stock levels• Prepared after consultation with

building user– Consequences of failure– risk to core business– period of acceptable down time

• prepared after consolation with suppliers

– on above

– 2.9.7 Commissioning Data• Measured Data• Measurement points• Test Equipment used• Details of calibration certificates• A statement of whether design requirements

were achieved

Page 47: Building Handover Documents v14

Back to contentsBack to contents

2. O&M Information• Certificates

– Plant data» model» type» serial number

– 2.9.8 Operation• Instructions for each engineering system• Suppliers recommendations for

– spares– running spares

» wear and tear» deterioration

– Items held in stock by supplier» for purchase» for refurbishment replacement

– safe operation– efficient operation– Normal operation– Emergency condition

• A recommended strategy for operation and control

Page 48: Building Handover Documents v14

Back to contentsBack to contents

2. O&M Information• an outline of the general operating

mode• Control Data

– location– effect– object– sequence– limits of capability– modes– set points

• Standard operating and emergency procedures and sequences for

– Start up– Running– Shutdown– Photographs– Videos recording

• Interlocks between plant items• Operating Procedures for stand-by plant• Precautions necessary to overcome known

hazards

Page 49: Building Handover Documents v14

Back to contentsBack to contents

2. O&M Information• The means by which any potentially hazardous

plan can be made safe• Target figures for both energy consumption and

energy costs• forms for recording plant running hours, energy

consumption and energy costs– 2.9.9 Maintenance Instructions

• Manufacturer's recommendations and instructions for maintenance

• detailed for each item of plant and equipment installed

• Clear distinction to be made– planned tasks (preventative maintenance)– work done on a corrective basis

• on each– the Isolation and return to service of plant

and equipment– adjustments calibration and testing– Dismantling and re-assembly– the exchange of components and

assemblies– dealing with hazards that may arise during

maintenance

Page 50: Building Handover Documents v14

Back to contentsBack to contents

2. O&M Information– The nature of deterioration and checks for

defects– Special

» tools» test equipment» ancillary services

– 2.9.10 Maintenance Schedule• All preventative maintenance tasks• based on manufacturers

recommendations• other authoritative sources

– statutory– mandatory

• to include– inspections– examinations– tests– adjustments calibrations– lubrication– periodic overhaul

Page 51: Building Handover Documents v14

Back to contentsBack to contents

2. O&M Information• frequency to be specific (either)

– time intervals– running hours– completed operations

• Complete maintenance cycle• Source of schedule to be stated• Local authority of supply authority should also

be noted

– 2.9.11 Modification Information• Authorised Changes• effecting

– safety– reliability– operation– maintenance

• system or component parts• permitted modifications allowed• space in the manual for recording

modifications• system to have modifications recorded in

every copy of the manuals wherever located

Page 52: Building Handover Documents v14

Back to contentsBack to contents

2. O&M Information– 2.9.12 Fault Finding

• logical diagnosis• correction of faults

– 2.9.13 Lubrication• schedule of all plant requiring lubrication

• manufacturers– recommendation

» type» method of application» frequency of application

– product name– generic reference ( BS)– any special requirements

» storage» transport» handling» insertion

– 2.9.14 Disposal instructions• any known dangers likely to arise during

disposal of specific items of the plant or equipment

Page 53: Building Handover Documents v14

Back to contentsBack to contents

2. O&M Information• precautions• safety measures• methods of safely disposing or destroying the

equipment or parts– packaging– insulation– fluids

• Sources from which further information can be obtained

• recycling information for the specific item of plant

– 2.9.15 names and address of manufacturers

• manufacturers• Suppliers• names• addresses• telephone• fax• email

Page 54: Building Handover Documents v14

Back to contentsBack to contents

2. O&M Information• contact names• websites• Local Stockiest

– spare parts– replicable assemblies– complete units

• Alphabetical order– 2.9.16 Index of plans and drawings

• Index of all AS-Fitted drawings• identified

– by number– by title

• schedule of issuer

– 2.9.17 Emergency information• Contracts in the event

– of fire– of theft– of burglary– failure of

» Gas

Page 55: Building Handover Documents v14

Back to contentsBack to contents

2. O&M Information» Electricity» water» Failures» leaks» ingress due to flood

– Failure or breakdown of plant» lifts» boilers» pumps

• Location of– fire fighting equipment– hydrants– rising mains

• Hazards particular to the building

– 2.9.18 Manufactures literature• complete set• Description of the product as purchased• the cost and date of purchase• performance- behavioral characteristic of the

equipment in use• applications (suitable for use)

Page 56: Building Handover Documents v14

Back to contentsBack to contents

2. O&M Information• Operation and maintenance details• labor, plant, materials and spatial recourses

required• Methods of operations and control• Cleaning and Maintenance requirements• protective measures• labour safety and welfare associated with the

equipment• public safety considerations• non provision of information should be

treated as a breach of contract

• 2.10 Specification of manuals for Building Services– Format for Operating and maintenance

manuals• influenced by

– type– manual required– the content– sequence of presentation– users– how it is to be used

Page 57: Building Handover Documents v14

Back to contentsBack to contents

3. Computer Aided FM

• Asset Database• Record of Breakdowns and Maintenance• Record of H&S Information• Emergency Information• Standard and Emergency Operating

Procedures• Service Levels• Contract Management• Stock & Inventory Control• Schematic Viewer• Search Engine

Page 58: Building Handover Documents v14

Back to contentsBack to contents

• 4.1 Style• 4.2 M& E Record

– 4.2.1 Electrical Installation– 4.2.1.2 Schematic

– 4.2.2 Mechanical Installations• 4.2.2.1Layout drawings

– 4.2.2 Mechanical Installations» 4.2.2.2Schematic Drawings

4. Record DrawingsContents

Page 59: Building Handover Documents v14

Back to contentsBack to contents

4. Record Drawings• 4.1 Style

– Workable• AutoCAD or alternative

– Recorded• PDF

– Schematic displays• 4.2 M& E Record

– 4.2.1 Electrical Installation• 4.2.1.1 Layout drawings

» Underground Cables

» Location» Route» Depth» Colour

– Cables Trunking Visible– Cable Trunking Concealed– Cable

» Path» Origin» Destination

Page 60: Building Handover Documents v14

Back to contentsBack to contents

4. Record Drawings» Loading» Conductor Metal» Conductor Size» Insulation type» Insulation Colour» Number of Cores in Cable» Number of Cables in Trunking

– HV/LV Switchboards– Primary Cable Trunking Distribution

Routes– Distribution Switch Gear– Distribution Boards– Trunking and Ladders in Switchrooms and

plantrooms– Single & 3 Phase wiring and Cable routes

» Sub Routes– Electrical Equipment

» Isolators» starters» socket outlets» control equipment» Other

Page 61: Building Handover Documents v14

Back to contentsBack to contents

4. Record Drawings– Sections through

» Ceiling voids» Risers

– Lighting Configuration» Distribution Boards» Switch Locations» circuit identification

– Emergency Lighting» Luminaries» Supply Circuits

– Lighting Conductors and air terminals– Earth Electrodes and test Clamps– Earth Tapes– Main Earthing Terminal– Cables providing specialist earth circuits– Telephone (voice) and IT (data) Cable– Concealed Cabling

» Within Building structure» Buried Underground

Page 62: Building Handover Documents v14

Back to contentsBack to contents

4. Record Drawings» Depths» Point of entry to building» Telephone» Power» IT

• 4.2.1.2 Schematic– Electrical System

» Cable» Size» Type» Number of cores

– Fire Alarm Systems– Emergency Lighting– Security System

» Intruder Alarms» CCTV system

– Public Address Systems– Factory Equipment

Page 63: Building Handover Documents v14

Back to contentsBack to contents

4. Record Drawings– 4.2.2 Mechanical Installations

• 4.2.2.1Layout drawings– Mechanical Services

» Pipework» Size» Route» Duct» Size» Route

– Plant Rooms» Plant Layout» Identity» Rating

– Concealed Services» in Building Structure» underground» Depth» Point of Entry to Building» Water» Gas» Sewers

Page 64: Building Handover Documents v14

Back to contentsBack to contents

4. Record Drawings– Isolating and Control Valves

» Identification» Location» Regulating Method

– Regulating Dampers» Location» Identification» Access Point

– Fire Smoke Dampers» Location» Identification» Access Point

– Acoustic Silencers» Locations

– Air plant location & Identification» Distribution» Grilles» Diffusers» Terminal units

– Details of Vibration Dampers

Page 65: Building Handover Documents v14

Back to contentsBack to contents

4. Record Drawings• 4.2.2.2Schematic Drawings

– HVAC» Locations & ID» Heating» Ventilating» Air Conditioning» Piping» Flow rates» Temperatures» Pressures» Pluming system» Flow rates» Temperatures» Pressures

– Control Systems» Sensors» Field Controllers» Outstations» Control Panels

Page 66: Building Handover Documents v14

Back to contentsBack to contents

4. Record Drawings– Equipment

» Cable» Origin» Route» destination of each cable» Conductor» Size» Number of cores» Spare cores» Insulations» Type» Rating» Number of BS or codes» Cable Identification» Joints and draw boxes» Power supply cables» Fuse rating reference» Sensors» Location and type» Factory Built Equipment

Page 67: Building Handover Documents v14

Back to contentsBack to contents

5. Statutory Examination and Insurance

• Lifting Equipment• Pressure systems

– Boilers– Air Receivers

• Transportable Gas Containers

Page 68: Building Handover Documents v14

Back to contentsBack to contents

6. Familiarisation And Training Sessions

• Classroom• Tour of Building• Handouts and Manuals• Demonstration of System

Operation• Training Records

Page 69: Building Handover Documents v14

Back to contentsBack to contents

7. Commissioning Information

• 7.1 Building Services Certificates– 7.1.1 Mechanical System

• Escalator Test Certificate– HSE Guidance Note PM45

• Escalator Reports of Thorough Examination– BS 5266 part 1

• Lift Installation type test certificate for locking device, governors, buffers and doors

– BS5655 part 10

• Lift Makers High voltage test– BS 5655 part 10

• Lift Installation test Certificate– BS 5655 part 10

• Lifting Equipment reports of thorough examination

– HSE Form F2530

• Air Condition system test Certificates• Air Conditioning System Performance test

certificates

Page 70: Building Handover Documents v14

Back to contentsBack to contents

7. Commissioning Information (Cont.)

• Ventilation System Test Certificates• Heating System Test Certificates• Pressure System Test Certificates

– HSC L122• Pressure Vessels and systems written schemes

of examination– HSC L122

• Pipework System Test Certificates– HVCA TR/6 & TR/20

• Drainage System Test Certificates– Approved Document H

• Water distribution systems, and flushing, cleaning and chemical closing certificate

– BS 6700• Chlorination certificates for drinking water

systems– BS 6700

Page 71: Building Handover Documents v14

Back to contentsBack to contents

7. Commissioning Information (Cont.)

• Sprinkler system test certificate– BS 5306 part2 loss Prevention Council

Certificate

• LPCB certificates of conformity for sprinkler installation

– Loss Prevention Standard 1048-1 issue 4

• Fire Hose-reel test certificate• Smoke extraction System Test Certificates• Escape Route Pressurisation System Test

Certificates– BS 5588 Part 4

• Fire Appliance Certificates– BS5306

– 7.1.2 Electrical System• IEE Electrical system

– BS 7671

• Emergency Lighting Test Certificate– BS 566 part 1

Page 72: Building Handover Documents v14

Back to contentsBack to contents

7. Commissioning Information (Cont.)

• LPCB Certificate of Conformity for fire detection and alarm systems

– Loss Prevention Standard 1014

• Security Alarm Test Certificate• Fire Alarm Test Certificate

– BS 5839 part 1

• Lightning protection System Test Certificates– BS 6651

• Public Address System Test Certificates– BS 6259

• CCTV System Test Certificates– BS EN 50132-7

• High Voltage System Test Certificates• Standby Generator System Test Certificates• Building Management System Test Certificates• Manufacturers Test Certificates for Electrical

Equipment such as Distribution Boards

Page 73: Building Handover Documents v14

Back to contentsBack to contents

7. Commissioning Information (Cont.)

• Specialist System Test Certificates for systems such as

– UPS– Telephones– Document Handling– Data Cabling

Page 74: Building Handover Documents v14

Back to contentsBack to contents

8. Plant and System Warranties

Page 75: Building Handover Documents v14

Back to contentsBack to contents

9. Defects Period

• Reporting Method– Nature of Defect– Subsequent damage to plan and

systems– Correspondence copy– Dates of

• Events• Actions• Correspondence

Page 76: Building Handover Documents v14

Back to contentsBack to contents

10. Storage and Access of Information

• Where• Nature• Assessment• Second Copy• Business Continuity Plan• Inspection

Page 77: Building Handover Documents v14

Back to contentsBack to contents

11. Documentation to be held

• Document------------------------- - - Legislation and standards

• Pressure Vessel and system records– Pressure systems safety Regulations 2000

• Pressure vessel and system written scheme of examination

– Pressure systems safety Regulations 2000• Maintenance record for system which control a

working environment, such as Heating and Ventilation System

– Workplace (Health and Safety & Welfare) Regulations 1992

• Legionella Risk assessment records– Legionnaires Disease. The control of Legionella Bacteria

Approved Code of Practice and Guidance• Record Contain a written scheme for the minimising of the

Legionella risk and the results of the written scheme• Legionnaires Disease. The control of Legionella Bacteria

Approved Code of Practice and Guidance– Copy of notification to local authorities of installation or wet

cooling towers and evaporative condensers• Notification of Cooling Towers and evaporative Condenser

Regulations 1992– Chemical and Bacteriological test results for drinking water

cisterns greater than 1000 liters' ( no stat)

Page 78: Building Handover Documents v14

Back to contentsBack to contents

11. Documentation to be held (Cont.)

• Workplace (Health and Safety & Welfare) Regulations 1992; BS6700

– Chlorination Certificates for Drinking Water (not stat)• Workplace (Health and Safety & Welfare) Regulations

1992; BS6700– Source Protection policy and license to use water supplied by a

borehole• National Rivers Authority• Noise Assessment Records

– Control of Noise at Work Regulations 2005• Fire Risk Assessment

– Fire Safety Order 2005• A Log detailing smoke extract tests

– Fire Safety Order 2005 BS 5588• A Log detailing fire hose reels and the test for portable

fire extinguishers– Fire Safety Order 2005 BS 5306

• A Log detailing escape-route pressurisation tests– Fire Safety Order 2005; BS5577-4

Page 79: Building Handover Documents v14

Back to contentsBack to contents

11. Documentation to be held (Cont.)

• Fire Training Log Book– training– special duties– fire drills– all to Fire Safety Order 2005

• Asbestos awareness report– Control of Asbestos at Work Regulations 2002

• A Log detailing emergency lighting test and examinations– BS 5266-1

• Examination certificates and reports– lifts

• All to Lifting Operations Lifting Equipment Regulations 1998

– lifting equipment• All to Lifting Operations Lifting Equipment

Regulations 1998– pressure systems

• Pressure Safety Systems 2000– pressure vessels

• Pressure Safety Systems 2000

Page 80: Building Handover Documents v14

Back to contentsBack to contents

11. Documentation to be held (Cont.)

• Risk basements for plant and systems– Management of Health and Safety at

Work Regulations 1999 – If not covered by COSHH Regulations

• Building Services operating and maintenance information including emergency procedures– Section 2and 6 of the Health and Safety at Work Act

1974– Construction (Design and Management) Regulations

2007– Building Regulations Part L.2 2006

• Record drawings for building services installation– Section 2and 6 of the Health and Safety at Work Act

1974• Record of installation and earthling tests

– Institute of Electrical Engineers Wiring Regulations 16th Edition 1991 BS 7671

• Record of tests carried out on electrical appliances (not stat to keep)

Page 81: Building Handover Documents v14

Back to contentsBack to contents

11. Documentation to be held (Cont.)

– Electricity at Work Regulations 1989• Water authority discharge of water

certificates– Water Authority and National River Authority

• Inventory of refrigerants– COSHH 2002– Environmental Protection Act 1990

• Record of waste disposal– Environmental Protection Act 1990

• Documentation for Wayleaves and adopted roads

• Building Log Book• Building Regulations Partl.2 2006

Page 82: Building Handover Documents v14

Back to contentsBack to contents

12. Regulatory Reform (Fire Safety) Order 2005 should

cover• Specified place to keep records• Details of any significant findings from the

fire risk assessment and any action taken• Testing and checking of Escape routes

– Finial exit locking mechanisms such as panic devices

– Emergency Exit devices– Electromagnetic devices

• Testing of– Fire Warning systems– Weekly alarm tests– Periodic maintenance by a competent person

• Recording of False Alarms• Testing and Maintenance of Emergency

Lighting System

Page 83: Building Handover Documents v14

Back to contentsBack to contents

12. Regulatory Reform (Fire Safety) Order 2005 should

cover (Cont.)• Testing and Maintenance of

– Fire Extinguishers– Hose Reels– Fire Blankets– Fire Suppression systems– Smoke Control Systems

• Recording and Training– relevant people– Fire Evacuation Drills

• Policy and Implementation– Planning– Organising– Monitoring– Audit– Review

• Fire And Rescue System to help– Fire Rescue Service– Maintenance of– Audit of

Page 84: Building Handover Documents v14

Back to contentsBack to contents

12. Regulatory Reform (Fire Safety) Order 2005 should

cover (Cont.)• In Multi user building

– Arrangements– Coordinated– Emergency Plan– Overall Control by you and your staff

• Fire Safety Systems– Alterations– Tests– Repairs– Maintenance– Including passive systems - fire doors

• Responsible Persons– Qualifications– Status– Of those who carry out

• Tests• inspections

Page 85: Building Handover Documents v14

Back to contentsBack to contents

12. Regulatory Reform (Fire Safety) Order 2005 should

cover (Cont.)• Results of Periodic Safety -

– Audits– Reviews Inspections– Tests– remedial action

• Incidents– Circumstances– Potential to cause accident– Monitor subsequent remedial actions– Reviews Inspections– Tests– remedial action

• Incidents– Circumstances– Potential to cause accident– Monitor subsequent remedial actions

• Record of Building Use– Fire Protection– Fire Prevention

• High Risk Areas• Details of

Page 86: Building Handover Documents v14

Back to contentsBack to contents

13. Construction (Design and Management) Regulations 2007

(CDM)• Aim

– Improve H&S of persons involved in; Construction, operation, maintenance of a structure and its services

• The Client must Appoint– Competent person

• To act as CDM Coordinator• CDM Coord to act as H&S advisor in planning• Health & safety Plan

– Pre Contract– Post contract

• to allocate time and resource to achieve cdm regs.

– Competent Principle Contractor• to act as H&S Coordinator in Construction

– Provide known information on condition of premises or site