1. Welcome - Introductions Randy Longacher, Board of Education Robert Hamm, Superintendent Hammond Construction – Jeff Tuckerman MKC Associates – Dave Zeller, Project Architect
– Steve Miller, Educational Facility Planner
2. District Update3. Ohio School Facilities Commission (OSFC) 4. Dover’s OSFC Opportunity 5. Community Input
What has been done since 2002?OSFC Assessments-2002 & 20082009 Financial Task Force Updated
DHS Staff SurveyedMeeting with Community ExpertsRenovation with New 5th Street Wing DiscussionsDHS Local Facility StudyMKC Input with Construction Options and Costs
2010 Board of Education Review of All OptionsOSFC Meeting to Discuss Funding OptionsCommunity Meeting to Gain Feedback on Renovate or NewENP Eligibility Notification from OSFCCity Council UpdateENP Application SubmittedOSFC Assessment of DHSNotification that Dover is #1 on ENP Eligibility List
2011 Staff Engagement Regarding FacilitiesReview & Selection of Architectural FirmsTimes Reporter Staff Tour of DHSMeeting with Bond CounselEnvironmental Assessment of DHSProgram of Requirements (POR)-MKC & Hammond ConstructionWork with MKC Facility Planner on How to Proceed
5
Ohio School Facilities Commission
OSFC Program initiated in 1997– Separate & Distinct State Agency
Mission:“To provide funding, management oversight, and technical assistance to local school districts for construction and renovation of school facilities in order to provide an appropriate learning environment for Ohio’s school children”
Future of the OSFC More Information: www.osfc.state.oh.us
OSFC
TerminologyOSFC: Ohio School Facilities Commission
Master Plan: District wide facility plan and associated costs
ENP: Exceptional Needs Program
Equity Rank: Determines State Share and Local Share of Project Cost
LFI: Locally Funded Initiative– Examples: Auditorium, BOE Office, Bus Garage,
Auxiliary Gymnasium
LEED Certified: Leadership in Energy and Environmental Design
OSFC
Project Delivery OSFC bases all projects on: • Condition of current facility
– Building Assessments• Projected number of students
– Enrollment Projection• Community Engagement
– Local Input
Ohio School Design Manual
Structured to provide a district with variety of options in the design of buildings
Emphasis on classroom spaces, not on extracurricular activities
Establishes building size and projected cost
OSFC
OSFC
Shares• 2009 Equity Rank #437• Dover Local Share 72%• State Share 28% • Dover was pushed ahead because of
ENP
38% State
of Ohio
Taxable Valuation Determines OSFC “Equity Rank”• Property Wealth ÷ Student Population• Dover Schools currently ranks 437 of 612 school districts• Currently Serving Equity Number approx. 400, 4-5 years
until OSFC will get to DoverState Share Local Share
Dover School Finances
Why a Bond Issue now?
OSFC funding available (ENP) Local economic development
OSFC future One year to secure local share
New academic requirements Bidding climate
Interest rates
Our Students, Staff, and Community deserve it now!
Dover’s OSFC Opportunity
First Step - ENP Plan
Exceptional Needs Program
The Exceptional Needs Program (ENP) is a building replacement program that provides school districts with the ability to protect the health and safety of their students with a new facility.
The focus of the program is to identify the facilities in most need of replacement from among the eligible applicants. The program has a single building orientation, so it will not necessarily fund a district’s entire facility needs. Districts awarded an ENP building may also participate in the Classroom Facilities Assistance Program (CFAP) or Expedited Local Partnership Program (ELPP) to complete the balance of their facility needs.
Dover’s OSFC Opportunity
Dover’s OSFC Opportunity
Heating/Ventilation Systems
Foundations Emergency Lighting Asbestos Windows Roofing Walls-Chimneys General Finishes Loose Equipment
Security/Fire Alarm Systems
Handicap Access Life Safety Issues Waters & Sewers Plumbing Interior Lighting Site Conditions Technology
Master Plan: OSFC Building Assessment Data
Dover High School
Exceptional Needs Program Site Visit Score Card Health Life Safety Structure Heating and Ventilation Electrical
Dover’s OSFC Opportunity Master Plan: Enrollment History
* Does not include full time JVS Students Source - Enrollment study by DeJong-Healy
2001-02 2002-03 2003-04 2004-05 2005-06 2006-07 2007-08 2008-09 2009-10 2010-112400
2450
2500
2550
2600
2650
2618
2528
2501
2552 2552
2482
2525
2550
2601
2636
Dover City SchoolsHistorical Enrollment
Dover’s OSFC Opportunity Master Plan: Enrollment Projection
* Does not include full time JVS Students Source - Enrollment study by DeJong-Healy
2010-11 2011-12 2012-13 2012-14 2014-15 2015-16 2016-17 2017-18 2018-19 2019-20 2020- 212450
2500
2550
2600
2650
2700
2750
2800
2850
2900
2950
2614
2688
27572781
2824 28352868 2867 2871 2884 2893
Dover City Schools Projected Enrollment
How Much Space is Needed? (Enrollment Projections)
# Students (high school)X Sq. Ft. allocation (high School)
= Total Required Square Feet building
How Much Will it Cost? (OSFC Guidelines)
Total required square feetX Cost per Sq. Ft.
= Total ENP Facilities Budget
ENP Formula - Scope & Budget
Dover’s OSFC Opportunity
Exceptional Needs Program (co funded)Project Scope:
Build 1 New 9-12 High School
• 887 Students
• 148,680 sq. ft. (co funded)
• Total building size = 148,680 + LFI sq. ft.
• Replacing total sq. ft. of 198,690
LEED Silver Certified Building Sell, abate/demo or repurpose Dover High School
Dover’s OSFC Opportunity
Dover’s OSFC Opportunity
Co-Funded Master Plan Considerations
Items OSFC Will Not Co-Fund
Potential Locally Funded Initiatives (LFI’s)
Dover’s OSFC Opportunity
LFI Examples to Consider -Purchase of Land
• Easy Access
• Utilities
• Not in Flood Plain
• Meets OSFC Acreage Requirements
• Cost Savings in Site Preparation
Dover’s OSFC Opportunity
Additional LFI Examples to Consider Additional Academic Classrooms Additional Athletic Space Auditorium Auxiliary Gym Outdoor Athletic & Music Facilities Community room Additional Locker Rooms & Storage Enhanced Technology Package Main Gym-Additional Seating
22
The Simple TruthModern education has outgrown some of the buildings where our children are preparing for the future. It makes a difference where they learn. The OSFC is working to ensure every Ohio student has a quality learning environment. Education has advanced to electronic whiteboards, portable computers, expandable networking and interactive video where students can communicate with students on other continents. Students are more likely to prosper where their environment is conducive to learning.
Dover’s OSFC Opportunity
Master Plan Option
Scope Total Budget 72% Local Share LFI’s State Share
Build One new 9-12 (Smaller than present HS)
$32,976,742
$23,743,254
To Be DeterminedSee Below
$9,233,488
Potential Locally Funded Initiatives - 100% Locally FundedAdditional Academic Classrooms Community RoomAdditional Athletic Space Additional Locker Rooms & StorageAuditorium Enhanced Technology PackageAuxiliary Gym Main Gym-Additional SeatingOutdoor Athletic & Music Facilities
Build One new Dover HS(Same size as present HS)
$45,233,488
$36,000,000
$9,233,488
Estimated Ballot Millage
Ballot Millage Calculation Par AmountFinal Maturity - yearsInterest Rate Ballot Millage
OSFC HS$26,000,000
30 Years5%
5.1 mills *
Dover HS$36,000,000
30 Years5%
6.9 mills *
Appraised Value Annual Monthly Annual Monthly$75,000 Home $117.00 $10.00 $158.00 $13.00$100,000 Home $156.00 $13.00 $211.00 $18.00$150,000 Home $234.00 $20.00 $317.00 $26.00$200,000 Home $312.00 $26.00 $422.00 $35.00
* Includes ½ mill for Maintenance
Potential Timeline
Dover City Schools
Possible Schedule - (pending voter approval of a November 2011 bond issue)
2011 2012 2013-2014
May Jun-Dec Notification of ENP Approval
BOE ResolutionBOE Election
FilingBond Issue Campaign
Planning and Programming
Planning and Programming
Schematic Design
Design Development
Construction Documents
Bid and Award
Ground Breaking
Construction
Getting Organized
Board
Core Committee
Building Advisory Committee
Sub- Committees
Dover School’s Community
INFO
RMAT
ION
/ QUE
STIO
NS
DISCUSSION / PROCESSING
RECOMM
ENDATIONS / CONSENSUS
Background
Structure Process
Facility Committee
Building Advisory Committee - Recruitment Represents Community Study Proposed Co-funded Plan for New High
School Develop Building Plan Consensus - Including LFI’s
BAC Meeting Dates
May 4, 2011 - Understanding the OSFC opportunity, LFI
discussion, and sub-committee assignmentsMay 18, 2011 - LFI sub-committee update and
discussionsJune 1, 2011 - Consensus of LFI items to include in the Dover CSD facilities projectJune 13, 2011 - Presentation of LFI findings to
Board of Education
Community InputSign Up for Building Advisory CommitteeName – Phone Number – Email Address
Your input on: •OSFC Partnership•Exceptional Needs Program (Master Plan)•Locally Funded Initiatives•General Thoughts
Directions• One response per note card• Name and contact information optional• All thoughts collected will be:
- Recorded / Database- Categorized
• Answers and conclusions- Published on web site / media
Every child……every day!!!
Dover City Schools