Building for Learning Project Photo Progress Report Month of April 2010 Project commencement 21 st September 2009

description

Building for Learning Project Photo Progress Report Month of April 2010 Project commencement 21 st September 2009. Don’t ask a man to do something you wouldn’t do yourself right Kassi !!! Another Blue-Tongue Lizard saved. Hang on a minute!!! - PowerPoint PPT Presentation

Transcript of Building for Learning Project Photo Progress Report Month of April 2010

Page 1: Building for Learning Project Photo Progress Report  Month of April 2010

Building for Learning ProjectPhoto Progress Report

Month of April 2010

Project commencement 21st September 2009

Page 2: Building for Learning Project Photo Progress Report  Month of April 2010

Don’t ask a man to do something you wouldn’t do yourself right Kassi !!!

Another Blue-Tongue Lizard saved.

Page 3: Building for Learning Project Photo Progress Report  Month of April 2010

Hang on a minute!!! That’s not right – I’m sure Rod said not to build that

there!!!

Al (Site Foreman), stirred but not shaken,

sought of that ‘James Bond’ 007

temperament about him.

April 2010.

Page 4: Building for Learning Project Photo Progress Report  Month of April 2010

Stairway progressing – roof added.

Page 5: Building for Learning Project Photo Progress Report  Month of April 2010

Toilets and wet areas water proofed.

Page 6: Building for Learning Project Photo Progress Report  Month of April 2010

Lights begin installed – windows cleaned

Page 7: Building for Learning Project Photo Progress Report  Month of April 2010

Plaster added to Lecture Theatre.

Page 8: Building for Learning Project Photo Progress Report  Month of April 2010

New electrical sub-station installed April 2010.

Page 9: Building for Learning Project Photo Progress Report  Month of April 2010

Sign writing and doors trims added.

Page 10: Building for Learning Project Photo Progress Report  Month of April 2010

Scaffolding coming down on High St and Hebel still going at rear

Page 11: Building for Learning Project Photo Progress Report  Month of April 2010

Changes to student classroom adviceTV monitors installed

Page 12: Building for Learning Project Photo Progress Report  Month of April 2010

End