Building for Learning Project Photo Progress Report 6 February 2010– March 2010 Project...

16
Building for Learning Project Photo Progress Report 6 February 2010– March 2010 Project commencement 21 st September 2009

Transcript of Building for Learning Project Photo Progress Report 6 February 2010– March 2010 Project...

Page 1: Building for Learning Project Photo Progress Report 6 February 2010– March 2010 Project commencement 21 st September 2009.

Building for Learning ProjectPhoto Progress Report 6

February 2010– March 2010

Project commencement 21st September 2009

Page 2: Building for Learning Project Photo Progress Report 6 February 2010– March 2010 Project commencement 21 st September 2009.

Aluminium doors and windows plus Hebel Bricks ready for March construction 2010.

Director Marg Crisp inspecting new roof areas.

Page 3: Building for Learning Project Photo Progress Report 6 February 2010– March 2010 Project commencement 21 st September 2009.

Structural Engineer Mark and Builder Graeme Connelly with Site Foreman Al - inspections

February 2010

Page 4: Building for Learning Project Photo Progress Report 6 February 2010– March 2010 Project commencement 21 st September 2009.

Plaster Jerry’s back and happy to be here!!The first sheet ready for March 2010.

Page 5: Building for Learning Project Photo Progress Report 6 February 2010– March 2010 Project commencement 21 st September 2009.

Getting ready for Hebel Bricks (trend setting sunny’s Jeremy), brick work and windows in - March 2010.

Page 6: Building for Learning Project Photo Progress Report 6 February 2010– March 2010 Project commencement 21 st September 2009.

With about 8 days using a crane to put materials onto the 1st Floor, we are certainly getting the attention of the

Wodonga public. Main St - March 2010.

Page 7: Building for Learning Project Photo Progress Report 6 February 2010– March 2010 Project commencement 21 st September 2009.

David ‘the render man’ – doin’ the business!!!March 2010.

Page 8: Building for Learning Project Photo Progress Report 6 February 2010– March 2010 Project commencement 21 st September 2009.

Hebel Building Brick being added to all 1st floor external areas - March 2010.

Page 9: Building for Learning Project Photo Progress Report 6 February 2010– March 2010 Project commencement 21 st September 2009.

Bricks continue on our stairway (to heaven ???) March 2010.

Page 10: Building for Learning Project Photo Progress Report 6 February 2010– March 2010 Project commencement 21 st September 2009.

Lift Shaft and Stairway close to the top - March 2010.

Page 11: Building for Learning Project Photo Progress Report 6 February 2010– March 2010 Project commencement 21 st September 2009.

Yep!!! Power tools haven’t taken over everything just yet - March 2010.

Page 12: Building for Learning Project Photo Progress Report 6 February 2010– March 2010 Project commencement 21 st September 2009.

Wall insulation and plaster - March 2010.

Page 13: Building for Learning Project Photo Progress Report 6 February 2010– March 2010 Project commencement 21 st September 2009.

Plaster going in, air-conditioners going on and hands up if your happy? Kos - March 2010.

Page 14: Building for Learning Project Photo Progress Report 6 February 2010– March 2010 Project commencement 21 st September 2009.

External Painting starts - March 2010.

Page 15: Building for Learning Project Photo Progress Report 6 February 2010– March 2010 Project commencement 21 st September 2009.

No knife to cut the cake for ‘Trainee Painter’ Reg, use the Putty Knife – Happy 86th Birthday - March 2010.

Internal room painting starts downstairs

Page 16: Building for Learning Project Photo Progress Report 6 February 2010– March 2010 Project commencement 21 st September 2009.

Old stormwater pipes replaced - March 2010.

Jerry – still smiling but can you keep on them all because we getting closer to the finish

date!!!