Building Excellence IV Capital Levy Projects Under ...
Transcript of Building Excellence IV Capital Levy Projects Under ...
![Page 1: Building Excellence IV Capital Levy Projects Under ...](https://reader033.fdocuments.in/reader033/viewer/2022052706/628ed4ac95e93c1dd81e32f8/html5/thumbnails/1.jpg)
Project Slide Number
Arbor Heights Elementary School 2
Cascadia Elementary School & Robert Eagle Staff Middle School 13
Genesee Hill Elementary School 21
Hazel Wolf K-8 at Pinehurst 33
Olympic Hills Elementary School 43
Seattle New World School at TT Minor 51
New Thornton Creek Building 61
January 22, 2016
Building Excellence IV Capital Levy Projects Under Construction
![Page 2: Building Excellence IV Capital Levy Projects Under ...](https://reader033.fdocuments.in/reader033/viewer/2022052706/628ed4ac95e93c1dd81e32f8/html5/thumbnails/2.jpg)
Building Excellence IV Capital Levy Arbor Heights Elementary School
Site: Maintaining temporary erosion sedimentation control (TESC) measures.
South Building: Exterior - Fluid applied air-barrier ongoing. Completed welding of southeast and southwest steel stair towers. Interior - Spray-foam insulation ongoing floor 1. Hanging Gypsum wall board (GWB) floor 1. HVAC, plumbing, fire-sprinkler and electrical rough-in ongoing floors 1, 2, and 3.
Arbor: Structural frame erection is complete.
North Building: Exterior and interior light-gauge metal stud wall framing is ongoing floors 2 and 3. Hollow-metal (HM) frame installation ongoing at floors 2 and 3. Membrane roofing ongoing at the cafeteria, kitchen, and gymnasium roof.
![Page 3: Building Excellence IV Capital Levy Projects Under ...](https://reader033.fdocuments.in/reader033/viewer/2022052706/628ed4ac95e93c1dd81e32f8/html5/thumbnails/3.jpg)
Arbor Heights Elementary School Site Plan
July 1, 2015 July 10, 2015
![Page 4: Building Excellence IV Capital Levy Projects Under ...](https://reader033.fdocuments.in/reader033/viewer/2022052706/628ed4ac95e93c1dd81e32f8/html5/thumbnails/4.jpg)
Arbor Heights Elementary School Aerial View from the South
December 30, 2015
![Page 5: Building Excellence IV Capital Levy Projects Under ...](https://reader033.fdocuments.in/reader033/viewer/2022052706/628ed4ac95e93c1dd81e32f8/html5/thumbnails/5.jpg)
Arbor Heights Elementary School South Wing – Southeast Stair Tower
January 15, 2016
![Page 6: Building Excellence IV Capital Levy Projects Under ...](https://reader033.fdocuments.in/reader033/viewer/2022052706/628ed4ac95e93c1dd81e32f8/html5/thumbnails/6.jpg)
Arbor Heights Elementary School South Wing – Exterior Air Barrier Application
January 19, 2016
![Page 7: Building Excellence IV Capital Levy Projects Under ...](https://reader033.fdocuments.in/reader033/viewer/2022052706/628ed4ac95e93c1dd81e32f8/html5/thumbnails/7.jpg)
Arbor Heights Elementary School South Wing – First Floor Wall Spray Foam Insulation
January 15, 2016
![Page 8: Building Excellence IV Capital Levy Projects Under ...](https://reader033.fdocuments.in/reader033/viewer/2022052706/628ed4ac95e93c1dd81e32f8/html5/thumbnails/8.jpg)
Arbor Heights Elementary School South Wing – Kindergarten Room 123 Gypsum Wall Board (GWB)
January 19, 2016
![Page 9: Building Excellence IV Capital Levy Projects Under ...](https://reader033.fdocuments.in/reader033/viewer/2022052706/628ed4ac95e93c1dd81e32f8/html5/thumbnails/9.jpg)
Arbor Heights Elementary School South Wing – Second Floor Corridor
January 19, 2016
![Page 10: Building Excellence IV Capital Levy Projects Under ...](https://reader033.fdocuments.in/reader033/viewer/2022052706/628ed4ac95e93c1dd81e32f8/html5/thumbnails/10.jpg)
Arbor Heights Elementary School North Wing – Commons Exterior Wall Framing
January 19, 2016
![Page 11: Building Excellence IV Capital Levy Projects Under ...](https://reader033.fdocuments.in/reader033/viewer/2022052706/628ed4ac95e93c1dd81e32f8/html5/thumbnails/11.jpg)
Arbor Heights Elementary School North Wing – Gymnasium
January 19, 2016
![Page 12: Building Excellence IV Capital Levy Projects Under ...](https://reader033.fdocuments.in/reader033/viewer/2022052706/628ed4ac95e93c1dd81e32f8/html5/thumbnails/12.jpg)
Arbor Heights Elementary School North Wing – Library
January 19, 2016
![Page 13: Building Excellence IV Capital Levy Projects Under ...](https://reader033.fdocuments.in/reader033/viewer/2022052706/628ed4ac95e93c1dd81e32f8/html5/thumbnails/13.jpg)
Building Excellence IV Capital Levy Cascadia Elementary School and Robert Eagle Staff Middle School
Site: Maintaining TESC measures. Preparing SW parking lots for asphalt paving late January/early February, depending on weather.
ES: Ongoing steel erection. Poured concrete slab on second floor metal deck. HVAC, plumbing, fire-sprinkler and electrical rough-in ongoing.
MS: On-going steel erection. HVAC, plumbing, fire-sprinkler and electrical rough-in ongoing rough-in. Poured stem walls for murals.
![Page 14: Building Excellence IV Capital Levy Projects Under ...](https://reader033.fdocuments.in/reader033/viewer/2022052706/628ed4ac95e93c1dd81e32f8/html5/thumbnails/14.jpg)
Cascadia Elementary School & Robert Eagle Staff Middle School Site Plan
![Page 15: Building Excellence IV Capital Levy Projects Under ...](https://reader033.fdocuments.in/reader033/viewer/2022052706/628ed4ac95e93c1dd81e32f8/html5/thumbnails/15.jpg)
Cascadia Elementary School & Robert Eagle Staff Middle School Aerial Photo
December 30, 2015
![Page 16: Building Excellence IV Capital Levy Projects Under ...](https://reader033.fdocuments.in/reader033/viewer/2022052706/628ed4ac95e93c1dd81e32f8/html5/thumbnails/16.jpg)
Cascadia Elementary School & Robert Eagle Staff Middle School Elementary School - Steel Erection, Looking North
January 12, 2016
![Page 17: Building Excellence IV Capital Levy Projects Under ...](https://reader033.fdocuments.in/reader033/viewer/2022052706/628ed4ac95e93c1dd81e32f8/html5/thumbnails/17.jpg)
Cascadia Elementary School & Robert Eagle Staff Middle School Elementary School - Steel Erection, Looking Northwest
January 12, 2016
![Page 18: Building Excellence IV Capital Levy Projects Under ...](https://reader033.fdocuments.in/reader033/viewer/2022052706/628ed4ac95e93c1dd81e32f8/html5/thumbnails/18.jpg)
Cascadia Elementary School & Robert Eagle Staff Middle School Elementary School - Slab-On-Metal-Deck Poured at 2nd Floor, Looking South
January 12, 2016
![Page 19: Building Excellence IV Capital Levy Projects Under ...](https://reader033.fdocuments.in/reader033/viewer/2022052706/628ed4ac95e93c1dd81e32f8/html5/thumbnails/19.jpg)
Cascadia Elementary School & Robert Eagle Staff Middle School Middle School - Slab-On-Grade Poured, Looking Southwest
January 12, 2016
![Page 20: Building Excellence IV Capital Levy Projects Under ...](https://reader033.fdocuments.in/reader033/viewer/2022052706/628ed4ac95e93c1dd81e32f8/html5/thumbnails/20.jpg)
Cascadia Elementary School & Robert Eagle Staff Middle School Middle School - Steel Erection, Looking South
January 12, 2016
![Page 21: Building Excellence IV Capital Levy Projects Under ...](https://reader033.fdocuments.in/reader033/viewer/2022052706/628ed4ac95e93c1dd81e32f8/html5/thumbnails/21.jpg)
Building Excellence IV Capital Levy Genesee Hill Elementary School
Site: Formed/poured curb at access road and stem wall at stair; installing fire department connection (FDC).
Area 1: Interior - Ceramic tile in bathrooms complete, vinyl wall covering is ongoing; casework install is complete; metal siding install is ongoing; T-bar ceiling grid install is ongoing; began installing electrical trim and ceiling lights.
Area 2: Interior - Installation of gypsum wall board (GWB) is ongoing; window frames/glazing is ongoing; electrical rough-in and sprinkler system is complete.
Area 3: GWB finishing process ongoing; interior painting ongoing; plumbing and electrical rough-in ongoing; installation of salvaged masonry is complete; window frames and glazing ongoing; casework at childcare complete.
Area 4: GWB installation and finishing process ongoing; mechanical, plumbing and electrical rough-in ongoing; prepping decking, structure and ductwork for painting.
![Page 22: Building Excellence IV Capital Levy Projects Under ...](https://reader033.fdocuments.in/reader033/viewer/2022052706/628ed4ac95e93c1dd81e32f8/html5/thumbnails/22.jpg)
Genesee Hill Elementary School Site Plan
![Page 23: Building Excellence IV Capital Levy Projects Under ...](https://reader033.fdocuments.in/reader033/viewer/2022052706/628ed4ac95e93c1dd81e32f8/html5/thumbnails/23.jpg)
Genesee Hill Elementary School Aerial Photo
![Page 24: Building Excellence IV Capital Levy Projects Under ...](https://reader033.fdocuments.in/reader033/viewer/2022052706/628ed4ac95e93c1dd81e32f8/html5/thumbnails/24.jpg)
Genesee Hill Elementary School Areas 1 North Elevation – Resuming Installation of Metal Siding
![Page 25: Building Excellence IV Capital Levy Projects Under ...](https://reader033.fdocuments.in/reader033/viewer/2022052706/628ed4ac95e93c1dd81e32f8/html5/thumbnails/25.jpg)
Genesee Hill Elementary School Area 1 Mechanical Basement – Ongoing Plumbing Rough-in to Equipment
![Page 26: Building Excellence IV Capital Levy Projects Under ...](https://reader033.fdocuments.in/reader033/viewer/2022052706/628ed4ac95e93c1dd81e32f8/html5/thumbnails/26.jpg)
Genesee Hill Elementary School Area 1 Level 2 Intermediate Data Room – Ongoing Terminate Data Cable
![Page 27: Building Excellence IV Capital Levy Projects Under ...](https://reader033.fdocuments.in/reader033/viewer/2022052706/628ed4ac95e93c1dd81e32f8/html5/thumbnails/27.jpg)
Genesee Hill Elementary School Area 1 Level 2 – Octagonal Shaped Paneling Installation Ongoing
![Page 28: Building Excellence IV Capital Levy Projects Under ...](https://reader033.fdocuments.in/reader033/viewer/2022052706/628ed4ac95e93c1dd81e32f8/html5/thumbnails/28.jpg)
Genesee Hill Elementary School Area 1 Level 2 – Bathroom Fixture Installation Ongoing
![Page 29: Building Excellence IV Capital Levy Projects Under ...](https://reader033.fdocuments.in/reader033/viewer/2022052706/628ed4ac95e93c1dd81e32f8/html5/thumbnails/29.jpg)
Genesee Hill Elementary School Area 1 Level 3 – Vinyl Wall Covering Installation Ongoing
![Page 30: Building Excellence IV Capital Levy Projects Under ...](https://reader033.fdocuments.in/reader033/viewer/2022052706/628ed4ac95e93c1dd81e32f8/html5/thumbnails/30.jpg)
Genesee Hill Elementary School Area 2 – Main Entrance to Building
![Page 31: Building Excellence IV Capital Levy Projects Under ...](https://reader033.fdocuments.in/reader033/viewer/2022052706/628ed4ac95e93c1dd81e32f8/html5/thumbnails/31.jpg)
Genesee Hill Elementary School Area 2 Level 2 – Library Window/Glazing Ongoing
![Page 32: Building Excellence IV Capital Levy Projects Under ...](https://reader033.fdocuments.in/reader033/viewer/2022052706/628ed4ac95e93c1dd81e32f8/html5/thumbnails/32.jpg)
Genesee Hill Elementary School Area 3 – Installing Doors at North/South Connecting Corridor
![Page 33: Building Excellence IV Capital Levy Projects Under ...](https://reader033.fdocuments.in/reader033/viewer/2022052706/628ed4ac95e93c1dd81e32f8/html5/thumbnails/33.jpg)
Building Excellence IV Capital Levy Hazel Wolf K-8 at Pinehurst
Site: Natural Gas, Water and Power installation complete. Electrical transformer set and to be energized next week. General site clean up.
Building A: Area (A1) Exterior and interior wall metal stud framing ongoing. HVAC, plumbing, fire-sprinkler and electrical rough-in ongoing. Green roof concrete pour. Area (A2) Exterior wall metal stud installation complete. Exterior wall sheathing and air barrier application ongoing. Window installation started. Interior wall metal stud framing complete. Wall cover inspections complete. Gypsum wall board activities started. HVAC, plumbing, fire-sprinkler and electrical rough-in nearing completion. Area (A3) Green roof dried-in. Placement of concrete floor slab complete and protected.
Building B: Placement of concrete floor slab on grade pending weather. Structural welding and bolting completed. Roofing ongoing.
Building C: Concrete slab on grade continues to be covered and protected. Metal roof deck welding complete. Roof insulation complete, roofing ongoing. Exterior wall metal stud framing started.
![Page 34: Building Excellence IV Capital Levy Projects Under ...](https://reader033.fdocuments.in/reader033/viewer/2022052706/628ed4ac95e93c1dd81e32f8/html5/thumbnails/34.jpg)
Hazel Wolf K-8 at Pinehurst Site Plan
![Page 35: Building Excellence IV Capital Levy Projects Under ...](https://reader033.fdocuments.in/reader033/viewer/2022052706/628ed4ac95e93c1dd81e32f8/html5/thumbnails/35.jpg)
Hazel Wolf K-8 at Pinehurst Aerial Photo
![Page 36: Building Excellence IV Capital Levy Projects Under ...](https://reader033.fdocuments.in/reader033/viewer/2022052706/628ed4ac95e93c1dd81e32f8/html5/thumbnails/36.jpg)
Hazel Wolf K-8 at Pinehurst Area A1 – Admin HVAC Ducting
January 12, 2016
![Page 37: Building Excellence IV Capital Levy Projects Under ...](https://reader033.fdocuments.in/reader033/viewer/2022052706/628ed4ac95e93c1dd81e32f8/html5/thumbnails/37.jpg)
Hazel Wolf K-8 at Pinehurst Area A2 – Air Barrier “Blueskin” Installation
January 12, 2016
![Page 38: Building Excellence IV Capital Levy Projects Under ...](https://reader033.fdocuments.in/reader033/viewer/2022052706/628ed4ac95e93c1dd81e32f8/html5/thumbnails/38.jpg)
Hazel Wolf K-8 at Pinehurst Area A2 – Air Barrier and Window Installation
January 13, 2016
![Page 39: Building Excellence IV Capital Levy Projects Under ...](https://reader033.fdocuments.in/reader033/viewer/2022052706/628ed4ac95e93c1dd81e32f8/html5/thumbnails/39.jpg)
Hazel Wolf K-8 at Pinehurst Area A2 – Air Barrier Window Detail
January 13, 2016
![Page 40: Building Excellence IV Capital Levy Projects Under ...](https://reader033.fdocuments.in/reader033/viewer/2022052706/628ed4ac95e93c1dd81e32f8/html5/thumbnails/40.jpg)
Hazel Wolf K-8 at Pinehurst Area A2 – Third Floor Classroom
January 12, 2016
![Page 41: Building Excellence IV Capital Levy Projects Under ...](https://reader033.fdocuments.in/reader033/viewer/2022052706/628ed4ac95e93c1dd81e32f8/html5/thumbnails/41.jpg)
Hazel Wolf K-8 at Pinehurst Area C – Metal Steel Stud Framing and Blocking
January 13, 2016
![Page 42: Building Excellence IV Capital Levy Projects Under ...](https://reader033.fdocuments.in/reader033/viewer/2022052706/628ed4ac95e93c1dd81e32f8/html5/thumbnails/42.jpg)
Hazel Wolf K-8 at Pinehurst Area A2, A3, and B – looking Northwest
January 12, 2016
![Page 43: Building Excellence IV Capital Levy Projects Under ...](https://reader033.fdocuments.in/reader033/viewer/2022052706/628ed4ac95e93c1dd81e32f8/html5/thumbnails/43.jpg)
Building Excellence IV Capital Levy Olympic Hills Elementary School
Site: Geothermal well drilling ongoing. 40 wells complete, out of 80 total. Forecasting well drilling to be complete March 2016. Maintaining TESC measures throughout site.
Building: Started formwork for footings.
![Page 44: Building Excellence IV Capital Levy Projects Under ...](https://reader033.fdocuments.in/reader033/viewer/2022052706/628ed4ac95e93c1dd81e32f8/html5/thumbnails/44.jpg)
Olympic Hills Elementary School Site Plan
![Page 45: Building Excellence IV Capital Levy Projects Under ...](https://reader033.fdocuments.in/reader033/viewer/2022052706/628ed4ac95e93c1dd81e32f8/html5/thumbnails/45.jpg)
Olympic Hills Elementary School Aerial Photo
January 1, 2016
![Page 46: Building Excellence IV Capital Levy Projects Under ...](https://reader033.fdocuments.in/reader033/viewer/2022052706/628ed4ac95e93c1dd81e32f8/html5/thumbnails/46.jpg)
Olympic Hills Elementary School Geothermal Well Drilling, Looking West
January 13, 2016
![Page 47: Building Excellence IV Capital Levy Projects Under ...](https://reader033.fdocuments.in/reader033/viewer/2022052706/628ed4ac95e93c1dd81e32f8/html5/thumbnails/47.jpg)
Olympic Hills Elementary School Footing Excavation and Formwork Prep, Looking West
January 13, 2016
![Page 48: Building Excellence IV Capital Levy Projects Under ...](https://reader033.fdocuments.in/reader033/viewer/2022052706/628ed4ac95e93c1dd81e32f8/html5/thumbnails/48.jpg)
Olympic Hills Elementary School Forming Footings, Looking Northwest
January 13, 2016
![Page 49: Building Excellence IV Capital Levy Projects Under ...](https://reader033.fdocuments.in/reader033/viewer/2022052706/628ed4ac95e93c1dd81e32f8/html5/thumbnails/49.jpg)
Olympic Hills Elementary School Bio-Detention Looking South at Southwest Corner of Site
January 13, 2016
![Page 50: Building Excellence IV Capital Levy Projects Under ...](https://reader033.fdocuments.in/reader033/viewer/2022052706/628ed4ac95e93c1dd81e32f8/html5/thumbnails/50.jpg)
Olympic Hills Elementary School Overall Site Looking Southeast
January 13, 2016
![Page 51: Building Excellence IV Capital Levy Projects Under ...](https://reader033.fdocuments.in/reader033/viewer/2022052706/628ed4ac95e93c1dd81e32f8/html5/thumbnails/51.jpg)
Building Excellence IV Capital Levy Seattle World School at T.T. Minor
Area A – Administration Office, Student Services, Health Clinic and Library: Installation of seismic glu-lam beam installation ongoing. Interior steel door frames delivered to the jobsite. Admin wood framing started. Area A overhead mechanical, plumbing, fire-sprinkler and electrical rough-in work ongoing. Exterior masonry work started.
Area B – Multipurpose, Kitchen, Boiler Room: Steel erection ongoing, structural wood and framing of the Kitchen ongoing SIP roof panel installation ongoing.
Area C – Classrooms: MEP installation ongoing, underground utility complete, CMU block wall installation complete interior steel stud framing ongoing, Fire Sprinkler installation ongoing bathroom plumbing rough in ongoing. Interior door frames on site.
![Page 52: Building Excellence IV Capital Levy Projects Under ...](https://reader033.fdocuments.in/reader033/viewer/2022052706/628ed4ac95e93c1dd81e32f8/html5/thumbnails/52.jpg)
Seattle World School at T.T. Minor Site Plan
Area C
Area B
Area A
Area C
Area B
Area A
![Page 53: Building Excellence IV Capital Levy Projects Under ...](https://reader033.fdocuments.in/reader033/viewer/2022052706/628ed4ac95e93c1dd81e32f8/html5/thumbnails/53.jpg)
Seattle World School at T.T. Minor Site – Exterior Masonry Tuck Pointing, Repair, Clean and Seal
January 19, 2016
![Page 54: Building Excellence IV Capital Levy Projects Under ...](https://reader033.fdocuments.in/reader033/viewer/2022052706/628ed4ac95e93c1dd81e32f8/html5/thumbnails/54.jpg)
Seattle World School at T.T. Minor Site – North Mobilization Area SIP Roof Panel Prep Area
January 19, 2016
![Page 55: Building Excellence IV Capital Levy Projects Under ...](https://reader033.fdocuments.in/reader033/viewer/2022052706/628ed4ac95e93c1dd81e32f8/html5/thumbnails/55.jpg)
Seattle World School at T.T. Minor Area A – Glu-lam Installation Ongoing
January 19, 2016
![Page 56: Building Excellence IV Capital Levy Projects Under ...](https://reader033.fdocuments.in/reader033/viewer/2022052706/628ed4ac95e93c1dd81e32f8/html5/thumbnails/56.jpg)
Seattle World School at T.T. Minor Area A – Admin Interior Wood Framing Started
January 19, 2016
![Page 57: Building Excellence IV Capital Levy Projects Under ...](https://reader033.fdocuments.in/reader033/viewer/2022052706/628ed4ac95e93c1dd81e32f8/html5/thumbnails/57.jpg)
Seattle World School at T.T. Minor Area B – New Commons/Kitchen Structural Glu-Lam Installation
January 19, 2016
![Page 58: Building Excellence IV Capital Levy Projects Under ...](https://reader033.fdocuments.in/reader033/viewer/2022052706/628ed4ac95e93c1dd81e32f8/html5/thumbnails/58.jpg)
Seattle World School at T.T. Minor Area B – New Commons/Kitchen SIP Roofing Ongoing
January 19, 2016
![Page 59: Building Excellence IV Capital Levy Projects Under ...](https://reader033.fdocuments.in/reader033/viewer/2022052706/628ed4ac95e93c1dd81e32f8/html5/thumbnails/59.jpg)
Seattle World School at T.T. Minor Area C – Restroom Plumbing Rough-in Ongoing
January 19, 2016
![Page 60: Building Excellence IV Capital Levy Projects Under ...](https://reader033.fdocuments.in/reader033/viewer/2022052706/628ed4ac95e93c1dd81e32f8/html5/thumbnails/60.jpg)
Seattle World School at T.T. Minor Area C – Interior Steel Door Frames Delivered
January 19, 2016
![Page 61: Building Excellence IV Capital Levy Projects Under ...](https://reader033.fdocuments.in/reader033/viewer/2022052706/628ed4ac95e93c1dd81e32f8/html5/thumbnails/61.jpg)
Building Excellence IV Capital Levy New Thornton Creek Building
Building A: Staging steel for steel erection.
Building B: Ongoing roofing for library. Ongoing exterior sheathing and interior framing on first and second floor. Ongoing ductwork on second floor. Began electrical rough-in on second. Ongoing plumbing rough-in on first floor. Ongoing rough-in for electrical and fire.
Building C: Began installing gypsum wall board (GWB) at classrooms. Completed insulation and brick veneer. Completed installation of windows and flashing. Ongoing roofing to complete final roof. Began install electrical panels in electrical closet. Began installing storefront doors.
Building D: Completed erecting structural steel and placing steel decking for roof for Covered Play Area.
![Page 62: Building Excellence IV Capital Levy Projects Under ...](https://reader033.fdocuments.in/reader033/viewer/2022052706/628ed4ac95e93c1dd81e32f8/html5/thumbnails/62.jpg)
New Thornton Creek Building Key Plan
Building C
Building B
Building A
D
![Page 63: Building Excellence IV Capital Levy Projects Under ...](https://reader033.fdocuments.in/reader033/viewer/2022052706/628ed4ac95e93c1dd81e32f8/html5/thumbnails/63.jpg)
New Thornton Creek Building Aerial Photo
January 15, 2016
![Page 64: Building Excellence IV Capital Levy Projects Under ...](https://reader033.fdocuments.in/reader033/viewer/2022052706/628ed4ac95e93c1dd81e32f8/html5/thumbnails/64.jpg)
New Thornton Creek Building Building A – Concrete Slab-on-grade for Administration Area
![Page 65: Building Excellence IV Capital Levy Projects Under ...](https://reader033.fdocuments.in/reader033/viewer/2022052706/628ed4ac95e93c1dd81e32f8/html5/thumbnails/65.jpg)
New Thornton Creek Building Building B – Exterior Sheathing on First & Second Floor
![Page 66: Building Excellence IV Capital Levy Projects Under ...](https://reader033.fdocuments.in/reader033/viewer/2022052706/628ed4ac95e93c1dd81e32f8/html5/thumbnails/66.jpg)
New Thornton Creek Building Building B – Stairs from Library Office to Mechanical Mezzanine
![Page 67: Building Excellence IV Capital Levy Projects Under ...](https://reader033.fdocuments.in/reader033/viewer/2022052706/628ed4ac95e93c1dd81e32f8/html5/thumbnails/67.jpg)
New Thornton Creek Building Building B – Second Floor Interior Framing
![Page 68: Building Excellence IV Capital Levy Projects Under ...](https://reader033.fdocuments.in/reader033/viewer/2022052706/628ed4ac95e93c1dd81e32f8/html5/thumbnails/68.jpg)
New Thornton Creek Building Building B – Second Floor Mechanical Penetration for Ductwork to First Floor
![Page 69: Building Excellence IV Capital Levy Projects Under ...](https://reader033.fdocuments.in/reader033/viewer/2022052706/628ed4ac95e93c1dd81e32f8/html5/thumbnails/69.jpg)
New Thornton Creek Building Building B – Second Floor HVAC Ductwork Installation
![Page 70: Building Excellence IV Capital Levy Projects Under ...](https://reader033.fdocuments.in/reader033/viewer/2022052706/628ed4ac95e93c1dd81e32f8/html5/thumbnails/70.jpg)
New Thornton Creek Building Building C – Installation of Cap Sheet on Roof
![Page 71: Building Excellence IV Capital Levy Projects Under ...](https://reader033.fdocuments.in/reader033/viewer/2022052706/628ed4ac95e93c1dd81e32f8/html5/thumbnails/71.jpg)
New Thornton Creek Building Building C – Insulation in Interior Walls
![Page 72: Building Excellence IV Capital Levy Projects Under ...](https://reader033.fdocuments.in/reader033/viewer/2022052706/628ed4ac95e93c1dd81e32f8/html5/thumbnails/72.jpg)
New Thornton Creek Building Building C – Installing Gypsum Wall Board (GWB)
![Page 73: Building Excellence IV Capital Levy Projects Under ...](https://reader033.fdocuments.in/reader033/viewer/2022052706/628ed4ac95e93c1dd81e32f8/html5/thumbnails/73.jpg)
New Thornton Creek Building Building C – Installing Moisture Resistant GWB in Bathroom
![Page 74: Building Excellence IV Capital Levy Projects Under ...](https://reader033.fdocuments.in/reader033/viewer/2022052706/628ed4ac95e93c1dd81e32f8/html5/thumbnails/74.jpg)
New Thornton Creek Building Building C – Installing Electrical Panels in Electrical Closet