Intent of session
• Creating a common format for planning change initiatives and being able to use and modify for own area of responsibility
• Be able to apply the milestone planning tool
• Understand each key area of the milestone plan
Why have a Milestone Plan
• Projects/tasks for overall success to achieve site Vision are identified in detail and put into perspective
• Accountabilities, timeframes and steps to achieve the desired outcome can be assigned and tracked
• Individuals and teams can be held accountable for delivering their objectives
• Provides a means for delegating the various tasks
• A method for reviewing progression which can provide confidence of the journey towards achieving the site Vision
Creating a Milestone Plan• Utilise a prioritisation tool to establish most appropriate projects and initiatives
• Group initiatives / projects under appropriate themes
• Identify standards, measures, current state and responsibilities for each of the projects (optionally include project tracking traffic lights)
• Allocate tasks to complete the projects
• Allocate timeframes for completion of each of the tasks
• Indicate timescales to review the plan
• Communicate the plan (display visually) and update regularly (after each review)
• Incorporate into standard management reviews and audit
Milestone Plan ExampleNo Objective
Standard (Desired outcome)
Measure KPI Goal Current State OwnerSupported
ByStart Date Due Date
Project phase
Attainment of Overall
KPI
Initiative movement
Traffic light
23/1
1/09
1.Utilise Continuous Improvement function to generate a prioritised best practice plan
We have accelerated our continuous improvement journey by adopting & sharing best practice
JBO JBO 3 20%
1.1. Identify site coördinator for best practice - on hold 1.2. Describe the process and implement based on priority, aligned with ESC
1.3. ESC M&R meeting:share point/meeting,improvement workshop between plants to facilitate exchange best practices
1.4. Define per plant "what is working well/what's not1.5. Define training needs for CI
2. Implement 4 Hr reviews initially with Vtech -> Line View
ESC standard structured daily and weekly routines aligned with ESC result based platform
all 4hr meetings take place
>90% Compliance>80% Effectiveness (using audit template)
not in place only 24h review
PM
JBO,NB,supervisors,maint sup,TDP,Cing
01/12/09 01/04/10 2 15%
2.01
Create new form(s) aligned with all lines use info from V-tec ( later on lineview info included )
2.02
Inform all teamleaders and linetechnicians (purpose and qoals)
2.03
Organize training
2.04
Start implementation
2.05
Evaluation /followup and correction if needed
3.Optimise and improve our meeting matrix – incorporating the standard best practice : std day, week, month. Implement 4 nr reviews initially with Vtech -> Line View
We have incorporated CCE standard structured daily & weekly routines that are fully aligned with the ESC providing a staple platform to deliver results
Measuring by Scorecards
Fully defined meeting matrix, including purpose and individual contribution x% Compliancex% Effectiveness for key mtgs (only)
Meeting Matrix version 1 in place
PM
LMT/sups/maint
sups/TDP/PVVeghe
l
2 45%
3.01
develop dashboardmeeting aligned with ESC3.02
implement dashboard meeting3.03
GAP analysis between as is meeting matrix and to be mm3.04
implement to be meeting matrix3.05
develop audit program matrix3.06
monitor and follow up audit results with corrective actions (focus data base)monthly QESH meeting
4.Expand TPM to autonomous maintenance – improve quality of RCA’s & expand to other departments – increase number of people involved
We are the TPM centre of excellence in CCE & set the example for the rest of the group
Measuring by Scorecards
Autonomous maint - Operator level maint agreed and defined then >80% complianceRCA best practice adopted (Edm) - Electronic version in use, RCA report available, 70% compliance
Several modules already succesfully installed (production & maintenance)
JBOPM/TDP/sups/maint sup/
4 15%
4.01Expand TPM horizontally in the organisation into other departments ( start TPM in Logistics,quality,utilities,syrup ) warehouse sup
4.02 implement the TPMpractices from production into logistics4.03 Set up autonomous maintenance
a. Optimize PM plan incl aut maint (using maximo/beer) PM plan under devellopment ########b. Communicate workcouncil/all employeesc. training d. implement in skill matrix
4.04 Install Subject Matter Experts (zonals) zonals implemented JBO maint sups/TDP ########4.05 incorporate TPM/PM in engineeringprojects opgenomen in lastenboek EB4.06 improve quality RCA's trough training/coaching teamleaders TDP
Jun Jul Aug SeptApr May Oct NovMarN Dec Jan Feb
No ObjectiveStandard (Desired
outcome)Measure KPI Goal Current State Owner
Supported By
Start Date Due DateProject phase
Attainment of Overall
KPI
Initiative movement
Traffic light
23/1
1/09
1.Utilise Continuous Improvement function to generate a prioritised best practice plan
We have accelerated our continuous improvement journey by adopting & sharing best practice
JBO JBO 3 20%
1.1. Identify site coördinator for best practice - on hold 1.2. Describe the process and implement based on priority, aligned with ESC
1.3. ESC M&R meeting:share point/meeting,improvement workshop between plants to facilitate exchange best practices
1.4. Define per plant "what is working well/what's not1.5. Define training needs for CI
2. Implement 4 Hr reviews initially with Vtech -> Line View
ESC standard structured daily and weekly routines aligned with ESC result based platform
all 4hr meetings take place
>90% Compliance>80% Effectiveness (using audit template)
not in place only 24h review
PM
JBO,NB,supervisors,maint sup,TDP,Cing
01/12/09 01/04/10 2 15%
2.01
Create new form(s) aligned with all lines use info from V-tec ( later on lineview info included )
2.02
Inform all teamleaders and linetechnicians (purpose and qoals)
2.03
Organize training
2.04
Start implementation
2.05
Evaluation /followup and correction if needed
3.Optimise and improve our meeting matrix – incorporating the standard best practice : std day, week, month. Implement 4 nr reviews initially with Vtech -> Line View
We have incorporated CCE standard structured daily & weekly routines that are fully aligned with the ESC providing a staple platform to deliver results
Measuring by Scorecards
Fully defined meeting matrix, including purpose and individual contribution x% Compliancex% Effectiveness for key mtgs (only)
Meeting Matrix version 1 in place
PM
LMT/sups/maint
sups/TDP/PVVeghe
l
2 45%
3.01
develop dashboardmeeting aligned with ESC3.02
implement dashboard meeting3.03
GAP analysis between as is meeting matrix and to be mm3.04
implement to be meeting matrix3.05
develop audit program matrix3.06
monitor and follow up audit results with corrective actions (focus data base)monthly QESH meeting
4.Expand TPM to autonomous maintenance – improve quality of RCA’s & expand to other departments – increase number of people involved
We are the TPM centre of excellence in CCE & set the example for the rest of the group
Measuring by Scorecards
Autonomous maint - Operator level maint agreed and defined then >80% complianceRCA best practice adopted (Edm) - Electronic version in use, RCA report available, 70% compliance
Several modules already succesfully installed (production & maintenance)
JBOPM/TDP/sups/maint sup/
4 15%
4.01Expand TPM horizontally in the organisation into other departments ( start TPM in Logistics,quality,utilities,syrup ) warehouse sup
4.02 implement the TPMpractices from production into logistics4.03 Set up autonomous maintenance
a. Optimize PM plan incl aut maint (using maximo/beer) PM plan under devellopment ########b. Communicate workcouncil/all employeesc. training d. implement in skill matrix
4.04 Install Subject Matter Experts (zonals) zonals implemented JBO maint sups/TDP ########4.05 incorporate TPM/PM in engineeringprojects opgenomen in lastenboek EB4.06 improve quality RCA's trough training/coaching teamleaders TDP
Jun Jul Aug SeptApr May Oct NovMarN Dec Jan Feb
Milestone Planning
Objective description
Desired outcome
Measure
KPI Goal
Current state
Core element/ initiative
Details
Initiative tracking
Colour code plan & progress in timeline
area
Plan
Changed
Complete
Missed
Now
Good questions for completing MSP
• Desired outcome questions– When you have achieved this goal what would be the outcome?
• Measure questions– How could you measure the progress of achievement of this goal?– What is the measure that determines achievement of this goal?
• KPI goal questions– What level of attainment of the KPI means that this has been successful?
Suggested review frequency
• Site level – monthly/bi-monthly as part of management review
• Area level – monthly/fortnightly dependant on duration of plan
• Machine / Zone level – weekly/fortnightly incorporate into regular management routines
Incorporate compliance and internal auditing to ensure sustainability