Building a high capacity wireless network for the future

29
Building a High-Capacity Wireless Network for the Future

Transcript of Building a high capacity wireless network for the future

Page 1: Building a high capacity wireless network for the future

Building a High-Capacity Wireless Network for the Future

Page 2: Building a high capacity wireless network for the future

50,000 Gamers = 800+ Mbps

Page 3: Building a high capacity wireless network for the future

Wireless support for ad-hoc events

Page 4: Building a high capacity wireless network for the future

There isn’t a one size fits all solution!

Page 5: Building a high capacity wireless network for the future

10 Years = Replacement of wireless 5 times

Page 6: Building a high capacity wireless network for the future

Manufacturers are required to deliver a product that adheres to a standard.

Page 7: Building a high capacity wireless network for the future

Coverage Based DesignEnough signal so that folks can connect

Page 8: Building a high capacity wireless network for the future

Capacity Based Design = 40 users max per access point per band

Page 9: Building a high capacity wireless network for the future
Page 10: Building a high capacity wireless network for the future

Build reallybig data

pipes!

Page 11: Building a high capacity wireless network for the future

Implementation Strategy• Bring in experienced personnel• Use big teams for big jobs• Active stake holder is essential• Capacity based design

Page 12: Building a high capacity wireless network for the future

Large venue customers think risk…

Page 13: Building a high capacity wireless network for the future

…while equipment providers pitch features

Page 14: Building a high capacity wireless network for the future

Risk is mitigated by methodologynot features

Page 15: Building a high capacity wireless network for the future

Quality is conformance to functional requirements. Functional requirements are set by teams not individuals.

Non-technical elements usually more challenging than technical issues.

Optimal project sequencing requires synthesis of tech and non-tech issues.

Page 16: Building a high capacity wireless network for the future

Optimal Project Sequencing1. Ratification of requirements by all stakeholders2. Project phasing ratified by all stakeholders3. Critical Design Review4. Pre-deployment audit to verify RF design 5. Deployment6. Post-deployment audit- application layer test7. Final RF node adjustments8. Automated maintenance & management

Page 17: Building a high capacity wireless network for the future

Key Elements- Tactical Sequencing

• Project Sequencing• Design Principles• Critical Design Review• Smart Design- Know the Algorithms• Smart Site Surveys• Communications Plan is Critical

Page 18: Building a high capacity wireless network for the future

Hire Really Smart Folks!

Page 19: Building a high capacity wireless network for the future

Embed your staff into the deployment team

Page 20: Building a high capacity wireless network for the future

The Wild Wild West of Wi-Fi

Page 21: Building a high capacity wireless network for the future

Policies with teeth

Page 22: Building a high capacity wireless network for the future

The MCCA owns and operates 802.11 compliant Wi-Fi systems… The MCCA provides these systems to its customers… free of charge as an exclusive service. The MCCA may suspend service to any customer if it determines that such customer’s devices are not 802.11 compliant or their devices are causing interference to MCCA’s systems.

Page 23: Building a high capacity wireless network for the future

The MCCA is the sole provider of Wi-Fi Internet services within its facilities. Customers may not use their own wireless access points, wireless routers, MiFi devices, or any other device to provide shared Wi-Fi Internet access. Customers are not authorized or permitted to install and operate their own Wi-Fi systems without the specific prior written approval of the MCCA.

Page 24: Building a high capacity wireless network for the future

Monitor, Manage & Maintain

Page 25: Building a high capacity wireless network for the future

Real-time analytics

Page 26: Building a high capacity wireless network for the future

Real-time allocation of bandwidth

Page 27: Building a high capacity wireless network for the future

More to think about:• Training• Documentation Review• Spares• Maintenance and

Escalation• Automated maintenance

& management

Page 28: Building a high capacity wireless network for the future

• Cellular Coverage is another necessity• Distributed Antenna System (DAS)– PAX show 60,000+ data connections per hour and

13,000 voice connections per hour

Page 29: Building a high capacity wireless network for the future