Building a High-Capacity Wireless Network for the Future
![Page 2: Building a high capacity wireless network for the future](https://reader036.fdocuments.in/reader036/viewer/2022062820/58a18bc91a28abca5a8b6b4b/html5/thumbnails/2.jpg)
50,000 Gamers = 800+ Mbps
![Page 3: Building a high capacity wireless network for the future](https://reader036.fdocuments.in/reader036/viewer/2022062820/58a18bc91a28abca5a8b6b4b/html5/thumbnails/3.jpg)
Wireless support for ad-hoc events
![Page 4: Building a high capacity wireless network for the future](https://reader036.fdocuments.in/reader036/viewer/2022062820/58a18bc91a28abca5a8b6b4b/html5/thumbnails/4.jpg)
There isn’t a one size fits all solution!
![Page 5: Building a high capacity wireless network for the future](https://reader036.fdocuments.in/reader036/viewer/2022062820/58a18bc91a28abca5a8b6b4b/html5/thumbnails/5.jpg)
10 Years = Replacement of wireless 5 times
![Page 6: Building a high capacity wireless network for the future](https://reader036.fdocuments.in/reader036/viewer/2022062820/58a18bc91a28abca5a8b6b4b/html5/thumbnails/6.jpg)
Manufacturers are required to deliver a product that adheres to a standard.
![Page 7: Building a high capacity wireless network for the future](https://reader036.fdocuments.in/reader036/viewer/2022062820/58a18bc91a28abca5a8b6b4b/html5/thumbnails/7.jpg)
Coverage Based DesignEnough signal so that folks can connect
![Page 8: Building a high capacity wireless network for the future](https://reader036.fdocuments.in/reader036/viewer/2022062820/58a18bc91a28abca5a8b6b4b/html5/thumbnails/8.jpg)
Capacity Based Design = 40 users max per access point per band
![Page 9: Building a high capacity wireless network for the future](https://reader036.fdocuments.in/reader036/viewer/2022062820/58a18bc91a28abca5a8b6b4b/html5/thumbnails/9.jpg)
![Page 10: Building a high capacity wireless network for the future](https://reader036.fdocuments.in/reader036/viewer/2022062820/58a18bc91a28abca5a8b6b4b/html5/thumbnails/10.jpg)
Build reallybig data
pipes!
![Page 11: Building a high capacity wireless network for the future](https://reader036.fdocuments.in/reader036/viewer/2022062820/58a18bc91a28abca5a8b6b4b/html5/thumbnails/11.jpg)
Implementation Strategy• Bring in experienced personnel• Use big teams for big jobs• Active stake holder is essential• Capacity based design
![Page 12: Building a high capacity wireless network for the future](https://reader036.fdocuments.in/reader036/viewer/2022062820/58a18bc91a28abca5a8b6b4b/html5/thumbnails/12.jpg)
Large venue customers think risk…
![Page 13: Building a high capacity wireless network for the future](https://reader036.fdocuments.in/reader036/viewer/2022062820/58a18bc91a28abca5a8b6b4b/html5/thumbnails/13.jpg)
…while equipment providers pitch features
![Page 14: Building a high capacity wireless network for the future](https://reader036.fdocuments.in/reader036/viewer/2022062820/58a18bc91a28abca5a8b6b4b/html5/thumbnails/14.jpg)
Risk is mitigated by methodologynot features
![Page 15: Building a high capacity wireless network for the future](https://reader036.fdocuments.in/reader036/viewer/2022062820/58a18bc91a28abca5a8b6b4b/html5/thumbnails/15.jpg)
Quality is conformance to functional requirements. Functional requirements are set by teams not individuals.
Non-technical elements usually more challenging than technical issues.
Optimal project sequencing requires synthesis of tech and non-tech issues.
![Page 16: Building a high capacity wireless network for the future](https://reader036.fdocuments.in/reader036/viewer/2022062820/58a18bc91a28abca5a8b6b4b/html5/thumbnails/16.jpg)
Optimal Project Sequencing1. Ratification of requirements by all stakeholders2. Project phasing ratified by all stakeholders3. Critical Design Review4. Pre-deployment audit to verify RF design 5. Deployment6. Post-deployment audit- application layer test7. Final RF node adjustments8. Automated maintenance & management
![Page 17: Building a high capacity wireless network for the future](https://reader036.fdocuments.in/reader036/viewer/2022062820/58a18bc91a28abca5a8b6b4b/html5/thumbnails/17.jpg)
Key Elements- Tactical Sequencing
• Project Sequencing• Design Principles• Critical Design Review• Smart Design- Know the Algorithms• Smart Site Surveys• Communications Plan is Critical
![Page 18: Building a high capacity wireless network for the future](https://reader036.fdocuments.in/reader036/viewer/2022062820/58a18bc91a28abca5a8b6b4b/html5/thumbnails/18.jpg)
Hire Really Smart Folks!
![Page 19: Building a high capacity wireless network for the future](https://reader036.fdocuments.in/reader036/viewer/2022062820/58a18bc91a28abca5a8b6b4b/html5/thumbnails/19.jpg)
Embed your staff into the deployment team
![Page 20: Building a high capacity wireless network for the future](https://reader036.fdocuments.in/reader036/viewer/2022062820/58a18bc91a28abca5a8b6b4b/html5/thumbnails/20.jpg)
The Wild Wild West of Wi-Fi
![Page 21: Building a high capacity wireless network for the future](https://reader036.fdocuments.in/reader036/viewer/2022062820/58a18bc91a28abca5a8b6b4b/html5/thumbnails/21.jpg)
Policies with teeth
![Page 22: Building a high capacity wireless network for the future](https://reader036.fdocuments.in/reader036/viewer/2022062820/58a18bc91a28abca5a8b6b4b/html5/thumbnails/22.jpg)
The MCCA owns and operates 802.11 compliant Wi-Fi systems… The MCCA provides these systems to its customers… free of charge as an exclusive service. The MCCA may suspend service to any customer if it determines that such customer’s devices are not 802.11 compliant or their devices are causing interference to MCCA’s systems.
![Page 23: Building a high capacity wireless network for the future](https://reader036.fdocuments.in/reader036/viewer/2022062820/58a18bc91a28abca5a8b6b4b/html5/thumbnails/23.jpg)
The MCCA is the sole provider of Wi-Fi Internet services within its facilities. Customers may not use their own wireless access points, wireless routers, MiFi devices, or any other device to provide shared Wi-Fi Internet access. Customers are not authorized or permitted to install and operate their own Wi-Fi systems without the specific prior written approval of the MCCA.
![Page 24: Building a high capacity wireless network for the future](https://reader036.fdocuments.in/reader036/viewer/2022062820/58a18bc91a28abca5a8b6b4b/html5/thumbnails/24.jpg)
Monitor, Manage & Maintain
![Page 25: Building a high capacity wireless network for the future](https://reader036.fdocuments.in/reader036/viewer/2022062820/58a18bc91a28abca5a8b6b4b/html5/thumbnails/25.jpg)
Real-time analytics
![Page 26: Building a high capacity wireless network for the future](https://reader036.fdocuments.in/reader036/viewer/2022062820/58a18bc91a28abca5a8b6b4b/html5/thumbnails/26.jpg)
Real-time allocation of bandwidth
![Page 27: Building a high capacity wireless network for the future](https://reader036.fdocuments.in/reader036/viewer/2022062820/58a18bc91a28abca5a8b6b4b/html5/thumbnails/27.jpg)
More to think about:• Training• Documentation Review• Spares• Maintenance and
Escalation• Automated maintenance
& management
![Page 28: Building a high capacity wireless network for the future](https://reader036.fdocuments.in/reader036/viewer/2022062820/58a18bc91a28abca5a8b6b4b/html5/thumbnails/28.jpg)
• Cellular Coverage is another necessity• Distributed Antenna System (DAS)– PAX show 60,000+ data connections per hour and
13,000 voice connections per hour