BUILDING A BANKABLE SOLAR + ENERGY STORAGE PROJECT...BUILDING A BANKABLE SOLAR + ENERGY STORAGE...
Transcript of BUILDING A BANKABLE SOLAR + ENERGY STORAGE PROJECT...BUILDING A BANKABLE SOLAR + ENERGY STORAGE...
BUILDING A BANKABLE
SOLAR + ENERGY STORAGE PROJECTVikas Bansal
Head, Business Development, International Solar
RANKED WORLD’S #1SOLAR EPC COMPANY
Outside China by IHS Markit
Source: BNEF, 2017
WORLD’S INSTALLED POWER MIX: OPPORTUNITY
EU
Non EU Europe
Africa
MENAAsia
Total Installed Power Globally ~ 5700 GWInstalled Solar Capacity < 500 GW
SWOT ANALYSIS
OPPORTUNITIES
• Capability to replacing coal/oil based power plant to serve base load
• Reduction in Cost on Solar PV + ESS, lowering LCOE every Year
• Favorable Government policy & incentives promoting clean energy
• Awareness to Decarbonizing the world & embrace clean energy
THREATS
• Unclear USE cases for ESS, together with finite life cycles of battery
• Relatively uncertain revenue stream makes project financing difficult
• Li-Ion ESS comes with poor OEM warranties with too many caveats
• Combined Cycle Gas plant, Bloom Cell & Hydrogen Cell technology
STRENGTHS
• Huge Development and Financing Experience on Solar PV, which can be
extended to Solar PV + ESS
WEAKNESS
• Limited Technical Expertise on ESS
• Limited Track Record of Project Financing for Solar + ESS
BANKABLE PV+ESS PROJECT
TECHNOLOGY RISK REVENUE STREAM UNCERTAINTY
Hedge the Risk
Insurance company underwrite
Technology Risk, thus protect
both the developer as well as
the lender
Pass On the Risk
Full wrapped EPC Agreement
deliver single point of
responsibility, thus make the
project bankable.
Avoid the Risk
EPCs Engineer the plant &
ensure performance as
envisaged in the business
model for financing
Realize through Energy Payment
Fuel cost + O&M costs + Variable Operational Payment
Measured through quantum of electricity delivered.
Realize through Capacity Payment
Compensation for fixed costs of Plant installation + ROI.
Predetermined amount, adjusted for plant availability.
Realize through Renewable Credits
Incentives to produce renewable energy.
To increase production of renewable energy.
REVENUE STREAMS
Ancillary Services
Reserve & Regulation market, with frequency/voltage Regulation,
, Reactive Power Control, Transient Smoothing service
Policy Incentives
30% ITC in USA
RECs in S. Korea
Capacity PPA
Entire capacity sold in exchange for fixed monthly capacity fee
+ reimbursement of other recurring expenses.
Time-of-Day (TOD) PPA
TOD factor in PPA, means electricity produced during peak times
is more valuable than electricity produced during off-peak time
Energy PPA Model Market Participation Model
Energy Arbitrage
Real Time & Day Ahead market options. And even leftover is
sufficient for making business model viable with Real Time market
3.49
4.31
4.95
5.455.78
3.49
5.14
6.44
7.47
8.17
3.49
5.98
7.97
9.54
10.66
0.00
2.00
4.00
6.00
8.00
10.00
12.00
0 Hr 1 Hr 2 Hr 3 Hr 4 Hr
LCO
E in
USD
Cen
ts
LCOE trend: Year 2019
25% BESS 50% BESS 75% BESS
Cost of PV @ 65 USD cents per Wp
Cost of interest @ 6% PA, Loan term = 12 Yr, Project Life = 25 Yr
Cost of BESS (USD per kWh) is as below
Cost of PV @ 60 USD cents per Wp
Cost of interest @ 6% PA, Loan term = 12 Yr, Project Life = 25 Yr
Cost of BESS (USD per kWh) is as below
2.53
3.23
3.78
4.214.50
2.53
3.95
5.07
5.95
6.55
2.53
4.67
6.38
7.74
8.69
0.00
1.00
2.00
3.00
4.00
5.00
6.00
7.00
8.00
9.00
10.00
0 Hr 1 Hr 2 Hr 3 Hr 4 Hr
LCO
E in
USD
Cen
ts
LCOE Trends: Year 2021
25% BESS 50% BESS 75% BESS
1 Hr back-up 2 Hr back-up 3 Hr back-up 4 Hr back-up
USD 298 USD 263 USD 233 USD 203
1 Hr back-up 2 Hr back-up 3 Hr back-up 4 Hr back-up
USD 345 USD 305 USD 270 USD 235
LCOE: PV + ESS PROJECT