Buffalo Wild Wings - Cornerstone Construction...

372
P R O J E C T M A N U A L FOR Buffalo Wild Wings at West Broadway Blvd. & Oak Grove Lane Sedalia, MO 65031 Stadia Endcap - Version V1.16.3 Including Change Memos thru [16-1] Issue Date: 12-5-16 Issued for Bids: [Date] Project No.: 10-0186

Transcript of Buffalo Wild Wings - Cornerstone Construction...

  • P R O J E C T M A N U A L

    FOR

    Buffalo Wild Wings

    at

    West Broadway Blvd. & Oak Grove Lane Sedalia, MO 65031

    Stadia Endcap - Version V1.16.3

    Including Change Memos thru [16-1]

    Issue Date: 12-5-16 Issued for Bids: [Date]

    Project No.: 10-0186

  • V1.16.1 PROJECT TITLE PAGE Last Revised: 04-13-16 00 0101 -1

    SECTION 00 0101 - PROJECT TITLE PAGE

    PROJECT TITLE: BUFFALO WILD WINGS West Broadway Blvd. & Oak Grove Lane Sedalia, MO 65031

    ISSUE DATE: 12/5/2016

    END OF PROJECT TITLE PAGE

  • V1.16.1 TABLE OF CONTENTS Last Revised: 04-13-16 00 0110 - 1

    SECTION 00 0110 - TABLE OF CONTENTS

    NOTE: This specification section updated per coordination with Buffalo Wild Wings design team.

    DIVISION 00 - PROCUREMENT AND CONTRACT REQUIREMENTS

    00 0100 - PROJECT COVER PAGE

    00 0101 - PROJECT TITLE PAGE

    00 0110 - TABLE OF CONTENTS

    00 0125 - MATERIAL IDENTIFICATION LIST

    00 1116 - SAMPLE INVITATION TO BID

    00 1117 - BID INFORMATION

    00 2113 - INSTRUCTIONS TO BIDDERS

    00 3110 - VENDOR CONTACT INFORMATION

    00 3132 - SUBSURFACE INVESTIGATION

    00 3133 - SITE SPECIFIC SUBSURFACE INVESTIGATION REPORT

    00 4100 - BID FORM

    00 5000 - CONTRACT AND GENERAL CONDITIONS

    DIVISION 01 - GENERAL REQUIREMENTS

    01 1100 - SUMMARY OF WORK

    01 2000 - PRICE AND PAYMENT PROCEDURES

    01 3000 - ADMINISTRATIVE REQUIREMENTS

    01 3330 - SCHEDULE OF SUBMITTALS

    01 4200 - REFERENCES

    01 4300 - QUALITY REQUIREMENTS

    01 5000 - TEMPORARY FACILITIES AND CONTROLS

    01 6000 - PRODUCT REQUIREMENTS

    01 7000 - EXECUTION AND CLOSEOUT REQUIREMENTS

    DIVISION 02 - EXISTING CONDITIONS

    02 4110 - MINOR DEMOLITION FOR REMODELING (OPTIONAL)

    DIVISION 03 - CONCRETE

    03 3000 - CAST-IN-PLACE CONCRETE

    03 3500 SPECIALTY CONCRETE FINISHING

    03 3910 - CONCRETE INTEGRAL HARDENER AND SEALER

  • V1.16.1 TABLE OF CONTENTS Last Revised: 04-13-16 00 0110 - 2

    DIVISION 04 - MASONRY

    04 0510 - MORTAR AND MASONRY GROUT

    04 2000 - UNIT MASONRY

    DIVISION 05 - METALS

    05 1200 - STRUCTURAL STEEL

    05 2100 - STEEL JOISTS

    05 3100 - STEEL DECK

    05 4000 - COLD FORMED METAL FRAMING

    05 5000 - METAL FABRICATIONS

    DIVISION 06 - WOOD PLASTICS AND COMPOSITES

    06 1000 - ROUGH CARPENTRY

    06 2000 - FINISH CARPENTRY

    06 4100 - CUSTOM CABINETS

    06 4120 - COUNTERTOPS

    06 6400 - FIBERGLASS REINFORCED PLASTIC PANELS

    DIVISION 07 - THERMAL AND MOISTURE PROTECTION

    07 1113 - BITUMINOUS DAMPPROOFING

    07 1326 - SHEET MEMBRANE WATERPROOFING (OPTIONAL)

    07 2100 - BUILDING INSULATION

    07 2400 - EXTERIOR INSULATION AND FINISH SYSTEM

    07 2610 - AIR AND VAPOR BARRIERS

    07 4213 - METAL WALL PANELS (OPTIONAL)

    07 4646 - FIBER CEMENT PANELS

    07 5423 - MECHANICALLY ATTACHED MEMBRANE ROOFING

    07 6200 - SHEET METAL FLASHING AND TRIM

    07 7200 - ROOF ACCESSORIES

    07 9200 - JOINT SEALANTS

    DIVISION 08 - OPENINGS

    08 1113 - HOLLOW METAL DOORS AND FRAMES

    08 1416 - FLUSH WOOD DOORS

    08 3100 - ACCESS PANELS

    08 3800 - TRAFFIC DOORS

  • V1.16.1 TABLE OF CONTENTS Last Revised: 04-13-16 00 0110 - 3

    08 4113 - ALUMINUM FRAMED ENTRANCES AND STOREFRONT

    08 7100 - DOOR HARDWARE

    08 8000 GLAZING

    DIVISION 09 - FINISHES

    09 2116 - GYPSUM BOARD ASSEMBLIES

    09 3000 - TILE

    09 5100 - ACOUSTICAL CEILINGS

    09 6513 - RESILIENT BASE

    09 6516 - RESILIENT SHEET FLOORING

    09 6726 - RESINOUS QUARTZ FLOORING (OPTIONAL)

    09 6800 - CARPETING

    09 7200 - WALL COVERING

    09 9100 - PAINTING

    DIVISION 10 - SPECIALTIES

    10 0010 - MISCELLANEOUS SPECIALTIES

    10 1400 - INTERIOR SIGNAGE

    10 2613 - CORNER GUARDS

    10 2813 - TOILET ACCESSORIES

    10 4400 - FIRE PROTECTION SPECIALTIES

    10 5113 - METAL LOCKERS

    10 8213 - ROOF TOP EQUIPMENT SCREENS

    10 8240 - PATIO SCREEN ENCLOSURE (OPTIONAL)

    DIVISION 11 - EQUIPMENT

    Not Used

    DIVISION 12 - FURNISHINGS

    12 2413 - WINDOW SHADES

    DIVISION 13 - SPECIAL CONSTRUCTION

    Not Used

    DIVISION 14 - CONVEYING EQUIPMENT

    Not Used

  • V1.16.1 TABLE OF CONTENTS Last Revised: 04-13-16 00 0110 - 4

    DIVISION 20 - GENERAL MECHANICAL

    20 0010 - MECHANICAL GENERAL CONDITIONS

    20 0050 - BASIC MATERIALS AND METHODS

    DIVISION 21 - FIRE SUPPRESSION

    21 1300 - FIRE SPRINKLER SYSTEM (PERFORMANCE BASED)

    DIVISION 22 - PLUMBING

    22 1000 - PIPING MATERIALS AND METHODS

    22 1119 - PLUMBING SPECIALTIES

    22 4200 - PLUMBING FIXTURES

    22 5300 - PATIO MISTING SYSTEM (OPTIONAL)

    DIVISION 23 - HEATING, VENTILATING, AND AIR-CONDITIONING (HVAC)

    23 0593 - TESTING AND BALANCING

    23 0700 - INSULATION

    23 0900 - AUTOMATIC CONTROL SEQUENCES

    23 3000 - HEATING, VENTILATING AND AIR CONDITIONING

    23 3100 - DUCTWORK MATERIALS AND METHODS

    DIVISION 26 - ELECTRICAL

    26 0010 - ELECTRICAL GENERAL CONDITIONS

    26 0030 - CUTTING AND PATCHING

    26 0050 - BASIC MATERIALS AND METHODS

    26 0503 - ELECTRICAL CONNECTIONS

    26 0519 - WIRE AND CABLE (600 VOLTS AND BELOW)

    26 0520 - CONDUITS AND FITTINGS

    26 0526 - GROUNDING SYSTEM

    26 0533 - OUTLET BOXES

    26 0534 - PULL AND JUNCTION BOXES

    26 2416 - PANELBOARDS

    26 2726 - WIRING DEVICES

    26 2813 - FUSES

    26 2819 - SAFETY SWITCHES

    26 5000 LIGHTING

  • V1.16.1 TABLE OF CONTENTS Last Revised: 04-13-16 00 0110 - 5

    DIVISION 31 - EARTHWORK

    31 3116 TERMITE CONTROL

    END OF TABLE OF CONTENTS

  • Material Identification Codes for use on Drawings and within Specifications

    Stadia Endcap V1.16.3 Updated 05-19-17

    NOTE: This specification section updated per coordination with Buffalo Wild Wings design

    team. Overview

    The Material Identification Codes List is intended to be a tool to improve the coordination and naming conventions between Drawings and Specifications. The Material Identification Codes List is organized by CSI MasterFormat Specification Section numbers. These Material Identification Codes are indicated with the material and product choices currently available in the Buffalo Wild Wings Master Specification.

  • V1.16.1 MATERIAL ID LIST Last Revised: 04-13-16 00 0125 - 2

    DIVISION 2 EXISTING CONDITIONS

    SECTION 02 4110 - MINOR DEMOLITION FOR REMODELING (Optional) As applicable for specific project

    (Remove): Indicate on Drawings items to be removed and discarded. (Remove/Reinstall): Provide list of existing building items to be removed by Contractor

    and reinstalled. (Remove/Salvage): Provide list of existing building items to be removed by Contractor

    and retained, (salvaged), by Owner.

    DIVISION 3 - CONCRETE

    SECTION 03 3000 - CAST-IN-PLACE CONCRETE Indicated on Drawings as:

    (CONC-1): Concrete Patio Wall, Smooth Formed Finish. (CONC-2): Interior Concrete Slabs, Steel trowel (smooth). (CONC-3): Exterior Horizontal Concrete Surfaces, Float finish, Light Broom. (CONC-4): Exterior Horizontal Colored Concrete Surfaces, Float finish. Color: Scofield BWW Stone. (CONC-5): Interior Concrete Slabs, Smooth power trowel. Honed, sealed with (SCF), and burnished. (Curing and Sealing Compound for Colored Concrete): Scofield; Cureseal-S Gloss.

    SECTION 03 3500 SPECIALTY CONCRETE FINISHING Indicated on Drawings as: (SCF) Specialty Polished Concrete

    (SCF): Specialty concrete finish with water-based penetrating densifier and sealer.

    SECTION 03 3910 - CONCRETE INTEGRAL HARDENER AND SEALER Indicated on Drawings as: (SC) Sealed Concrete

    (SC): Water based, concrete hardener / sealer. Exterior horizontal concrete surfaces,

    except colored concrete.

    DIVISION 4 - MASONRY

    SECTION 04 0510 - MORTAR AND MASONRY GROUT Indicated on Drawings as:

    (Mortar): Portland cement lime mortar, masonry cement not allowed. 1. Natural colored mortar for all locations. (Grout): 3000 psi grout.

    SECTION 04 2000 - UNIT MASONRY Indicated on Drawings as: Concrete Masonry Units

    (CMU-1): Normal weight hollow concrete masonry units. Block Coursing: Running Bond, 3/8 concave joints.

    Accessories for Section 04 2000

  • V1.16.1 MATERIAL ID LIST Last Revised: 04-13-16 00 0125 - 3

    (Joint Reinforcement): Single wythe, truss type, hot dip galvanized. (Wall Ties): Corrugated formed sheet metal, 7/8 inch wide, hot dip galvanized. (Masonry Weeps): 3/8" dia. cotton rope wicks or 1/4" dia. plastic tubes.

    DIVISION 5 - METALS

    SECTION 05 4000 - COLD FORMED METAL FRAMING Indicated on Drawings as: Indicate stud and joist sizes and maximum spacing on Drawings.

    (Stl Studs): Structural Steel Studs. (Stl Joists): Structural Steel Joists. (Sill Sealer): 1/4 thick, close cell polyethylene. Exterior Wall Sheathing: Refer to Section 06 1000 - Rough Carpentry for wall sheathing.

    SECTION 05 5000 - METAL FABRICATIONS Miscellaneous steel shapes, plates and other metal fabrications:

    (Stl Angles) (Stl Channels) (Loose Lintel) (Stl Plate) (Stl Tube) (Stl Ladder): Steel ladders for roof access. (Stl Bollards): Exterior bollards. (Perforated Metal Panel): Perforated Metal, Round Hole, Plain Steel Cold Rolled, 20

    Gauge, Mill Finish, 1/4" Holes on 3/8" Centers, Staggered Pattern, 40% Open Area. McNichols Company.

    Item Number: 1614382041. DIVISION 6 - WOODS AND PLASTICS SECTION 06 1000 - ROUGH CARPENTRY

    Indicated on Drawings as: Dimensional Framing Lumber and Wood Blocking

    (WD FRAMING): Wood framing lumber. (WD BLKG): Exposed or concealed wood blocking.

    Construction Plywood and Sheathing (SHTG-1): Wall Sheathing:

    1. Plywood Wall Sheathing: DOC PS 1, C-D, exposure 1, structural 1. 1/2" nominal thickness. - Or -

    2. Oriented Strand Board Wall Sheathing: DOC PS 2, exposure 1, structural 1. 1/2" nominal thickness.

    (SHTG-2): Not Used. (SHTG-3): Concealed Plywood: DOC PS 1, C-D, exposure 1. Thickness as indicated on

    drawings. (SHTG-4): Not Used. (SHTG-5): Electrical Panel Boards: APA rated sheathing, fire retardant treated. 3/4

    nominal thickness. Treated Wood Material

    (PT): Preservative treated wood materials. (FRT): Fire retardant treated wood materials. (Building Paper): Roofing Felt: Type 30, asphalt saturated felt, non-perforated, conforming

    to ASTM D226.

  • V1.16.1 MATERIAL ID LIST Last Revised: 04-13-16 00 0125 - 4

    SECTION 06 2000 - FINISH CARPENTRY Indicated on Drawings as: Items furnished by Owners Millwork Vendor:

    (WD-1): Yellow Poplar. Used for painted wood trim. (WD-2): White Maple. Used for clear finished wood trim.

    Items furnished by Owner:

    (Ceiling Clouds): EPS Specialties; DGS Retail, Inc.; Ceiling Cloud System. Factory Finished (Painted) Millwork: Paint System PS-31/C-8 Factory Finished (Clear) Millwork: Paint System PS-30 Accessories for Section 06200

    (Adjustable Shelf Brackets): Brackets and standards, white finish.

    SECTION 06 4100 - CUSTOM CABINETS Items furnished by Owners Millwork Vendor:

    (WD-1): Yellow Poplar, painted finish.

    Factory Finished Millwork: Paint System PS-31/C-8 Plastic Laminate

    (PLAM-1): Wilsonart # 1573-60, Frosty White, Matte. (PLAM-2): Wilsonart # 1595-60, Black, Matte

    Accessories for Section 06410

    (Grommet): Power cord grommet, 3 diameter.

    SECTION 06 4120 - COUNTERTOPS Indicated on Drawings as: Plastic Laminate

    (PLAM-1): Wilsonart # 1573-60, Frosty White, Matte.

    Solid Surface (SS-1): Corian, Concrete.

    SECTION 06 6400 - FIBERGLASS REINFORCED PLASTIC PANELS Indicated on Drawings as:

    Fiberglass Reinforced Plastic Panels (FRP): 0.090 inch thick, USDA approved, textured surface wall panels with Class III/Class C fire rating. (FRP-1): White. (FRP-2): Black. Fiberglass Reinforced Plastic Panels (FRP): 0.090 inch thick, USDA approved, glossy surface wall panels with horizontal and vertical grooves with Class III/Class C fire rating. (FRP-3): Black. Grids spaced at 3 O.C. Vertically and 6 O.C. Horizontally. (FRP-4): Yellow. Grids spaced at 3 O.C. Vertically and 6 O.C. Horizontally.

  • V1.16.1 MATERIAL ID LIST Last Revised: 04-13-16 00 0125 - 5

    FRP Adhesive Franklin International; Titebond Solvent-Based FRP Adhesive.

    DIVISION 7 - THERMAL AND MOISTURE PROTECTION SECTION 07 1113 - BITUMINOUS DAMPPROOFING

    Indicated on Drawings as:

    (Dampproofing): Emulsified Bituminous Dampproofing, non-fibered, water-based, non-sag asphaltic coating designed for spray application.

    (Protection Board): 1/4 thick, fan folded extruded-polystyrene board.

    SECTION 07 1326 - SHEET MEMBRANE WATERPROOFING (Optional) Indicated on Drawings as:

    (Waterproofing): 60 mil. thick, self-adhering, sheet membrane waterproofing.

    (i.e. Bituthene 3000) or comparable. (Protection Board): 1/4 thick, fan folded extruded-polystyrene board.

    SECTION 07 2100 - BUILDING INSULATION Indicated on Drawings as: (INSUL-#)

    (INSUL-1): Unfaced fiberglass batt insulation. (INSUL-2): Under Slab and Foundation Insulation, Extruded Polystyrene Board (INSUL-3): Roof Insulation, Polyisocyanurate board with organic/inorganic facers. (INSUL-4): 1 thick, semi-rigid board, ASI Echo Eliminator. (Needed when no clouds in

    design). (INSUL-5): Spray Foam Insulation: Single-component, closed cell, spray polyurethane foam

    sealant. Use for voids and crevices.

    SECTION 07 2400 - EXTERIOR INSULATION AND FINISH SYSTEM Indicated on Drawings as: (EIFS-#)

    (EIFS-1): EIFS color to Match Sherwin Williams Color SW #7019, Gauntlet Gray, (C-6), Finish: Sandpebble.

    (EIFS-2): EIFS color to Match Sherwin Williams Color SW #6906, Citrus, (C-1), Finish: Sandpebble Fine.

    (EIFS-3): Exterior, un-insulated Custom Gray; Water Resistive Barrier, Reinforcing, and Basecoat over exterior gypsum sheathing (GYBSH-1). Finish: Smooth Finish and Sealer. Color: Dryvit; National Account Color # BUWW151094, Lymestone Custom Color Gray. Sto; Color No. NA14-0010.

    (EIFS-4): Interior, un-insulated Custom Gray; Reinforcing, and Basecoat over gypsum board (GYB-2). Finish: Smooth Finish and Sealer. Color: Dryvit; National Account Color # BUWW151094, Lymestone Custom Color Gray. Sto; Color No. NA14-0010.

    (EIFS-5): Color: Dryvit Color #715, Licorice Finish: Sandpebble Fine.

    SECTION 07 2610 - AIR AND VAPOR BARRIERS Indicated on Drawings as:

    (Air Barrier): DuPont Tyvek, CommercialWrap. (Vapor Barrier): 6 mil poly; (Northern Climates Only) (Underslab Vapor Barrier): Stego Wrap.

  • V1.16.1 MATERIAL ID LIST Last Revised: 04-13-16 00 0125 - 6

    SECTION 07 4213 - METAL WALL PANELS (Optional) Indicated on Drawings as:

    (MWP-1): 12 Reveal Panel, horizontal, prefinished galvanized steel, kynar finish. Color: to match Sherwin Williams paint color SW #6906, (C-1), Matte sheen.

    (MWP-2): 18 Snap-on Batten Panel, vertical, prefinished galvanized steel, kynar finish. Color: Matte Black.

    (MWP-3): 12 Flush Panel, vertical, prefinished galvanized steel, kynar finish. Color: Matte Black.

    SECTION 07 4646 FIBER CEMENT PANELS Indicated on Drawings as:

    (FCP-1): Nichiha, Vintage Brick, color Alexandria Buff. (FCP-2): Nichiha, Vintage Brick, color Whitewash.

    SECTION 07 5423 - MECHANICALLY ATTACHED MEMBRANE ROOFING Indicated on Drawings as:

    (Membrane Roofing System): Mechanically attached thermoplastic sheet, .040 inch

    Duro-Last Roofing.

    SECTION 07 6200 - SHEET METAL FLASHING AND TRIM Indicated on Drawings as: (SHT MET-#)

    (SHT MET-1): Prefinished galvanized steel, kynar finish. (SHT MET-2): Standard steel galvanized flashing, field painted. (Reglets): Manufactured reglets, surface mounted and recessed.

    SECTION 07 7200 - ROOF ACCESSORIES Indicated on Drawings as:

    (Roof Hatch): Roof hatch for vertical ladder locations (2'-6" by 3'-0"), Bilco Type S Roof

    Hatch. Safety Post and Railing.

    SECTION 07 9200 - JOINT SEALANTS Indicated on Drawings as: (SLNT-#)

    (SLNT-1): General Purpose Exterior Sealant, 1 part, polyurethane. (SLNT-2): General Purpose Interior Sealant, acrylic. (SLNT-3): Sanitary/Tile Sealant, 1 part , mildew resistant silicone. (SLNT-4): Concrete Paving Joint Sealant, 2 part, self-leveling polyurethane for traffic. (SLNT-5): Butyl Sealant. (SLNT-6): Low modulus Silicone Sealant, 1 part, general purpose silicone. (SLNT-7): Ultra-Low Modulus Silicone Sealant,1 part, silicone.

    Sealant Schedule - Sealant types will be scheduled within the project manual as follows:

    (SLNT-1): General Purpose Exterior Sealant, use for:

    a. Control, expansion, and soft joints in masonry. b. Joints between concrete and other materials. c. Joints between metal frames and other materials. d. Other exterior joints for which no other sealant is indicated.

    (SLNT-2): General Purpose Interior Sealant, use for: a. Interior wall and ceiling control joints. b. Joints between door and window frames and wall surfaces. c. Other interior joints for which no other type of sealant is indicated.

  • V1.16.1 MATERIAL ID LIST Last Revised: 04-13-16 00 0125 - 7

    (SLNT-3): Sanitary/Tile Sealant, use for:

    a. Joints between plumbing fixtures and floor and wall surfaces. b. Joints between casework, kitchen and restroom countertops and wall

    surfaces. c. Control joints in tile installations in toilet rooms and kitchen.

    (SLNT-4): Concrete Paving Joint Sealant use for:

    a. Joints in concrete sidewalks and vehicular paving.

    (SLNT-5): Butyl Sealant, use for: a. Seam sealant for masonry flashing. b. Bedding sealant for thresholds and sills.

    (SLNT-6): Low modulus Silicone Sealant, use for:

    a. Air barrier perimeter. b. Exterior sheet metal joints.

    (SLNT-7): Ultra-Low Modulus Silicone Sealant, use for:

    a. Perimeter and internal joints in EIFS System.

    DIVISION 8 - DOORS AND WINDOWS SECTION 08 1113 - HOLLOW METAL DOORS AND FRAMES

    Indicated on Drawings as: (HM Frames): 14 gauge galvanized for Exterior Frames. 14 gauge for Traffic Door

    Frames. 16 gauge for Interior Frames. (HM Doors): 16 gauge galvanized with polystyrene core for Exterior Doors. 16 gauge

    with honeycomb core for Interior Doors.

    SECTION 08 1416 FLUSH WOOD DOORS Indicated on Drawings as:

    (Wood Doors): Restroom Stall Doors; Solid core, natural birch veneer doors. Doors to be

    factory painted (PS-22/C-4), by TCH. Door faces to be covered with diamond plate plastic laminate, (PLAM-5), factory applied by TCH. Manufacturer: Advanced Technology, Inc., Greensboro, NC; Tel: 800-849-1320; www.advtechnology.com Color and Pattern: NuMetal Design Collection; # 256 GEK, Diamond Plate Stainless Steel.

    SECTION 08 3100 - ACCESS PANELS

    Indicated on Drawings as: (AP) Access Panel: Access panels for drywall locations.

    SECTION 08 3800 - TRAFFIC DOORS Indicated on Drawings as:

    (TD): Chase Model # SC-3018, Plastic laminate both sides, 18 s.s. impact plate and 9 x 14 acrylic vision panel.

    Plastic Laminate Colors:

    Black: Formica Black 909-58, Dining/Public side of door. White: Formica White 949-58, Kitchen side of door.

    http://www.advtechnology.com/

  • V1.16.1 MATERIAL ID LIST Last Revised: 04-13-16 00 0125 - 8

    SECTION 08 4113 ALUMINUM ENTRANCES AND STOREFRONT

    Indicated on Drawings as: (STF-1): Aluminum Storefront & Window Framing; 2 x 4-1/2, thermally broken, center

    glazed to accept 1/4" and 1 insulated glass. Kynar Finish, Matte Black. (Aluminum Doors): 2 thick, medium stile aluminum doors.

    SECTION 08 7100 - DOOR HARDWARE Indicated within the Hardware Groups and on the Door Schedule Manufacturers

    Hinges: PBB. Lock and Latch Sets; Schlage; AL Series. Cylinders: Schlage. Exit Devices: Von Duprin 99 Series Exit Alarm Locks: Von Duprin; Guard X. Panic Exit Devices: Detex; Value Series. Push/Pull Sets; Kick Plates/Armor Plates: Hiawatha. Closers: LCN. Flush Bolts; Coat Hooks; Hinge Pin Stops; Door Viewers: Ives. Wall Stops: Don-Jo Manufacturing. Weatherstripping; Door Sweep; Thresholds; Rain Drips: Reese.

    Hardware Supplier Twin City Hardware: Brent Chuhel; 651-731-7126; [email protected]

    HARDWARE GROUPS Hardware Furnished by Section 08 4113 Aluminum Framed Entrances and Storefronts

    GROUP 1: Exterior Entry Dbl. Doors Door No. 100 GROUP 2: Interior Entry Vestibule Dbl. Doors (Queuing) Door No. 101 GROUP 3: Exterior Patio Door Door Nos. 105A and 105B GROUP 4: Exterior Take-Out Entry Door Door No. 125 GROUP 5: Interior Take-Out Entry Door Door No. 102 Note: TCH to provide Cylinders for Groups 1 & 3; Cylinders and Floor Stop for Group 4;

    Wall Stop for Group 5.

    Hardware Furnished by TCH GROUP 6: Sprinkler Room Door Door No. 124 GROUP 7: Exterior Service Door - Door No. 116 GROUP 8: Office Door Door No. 113 GROUP 9: Electrical Room Door Door No. 114 GROUP 10: Restroom Doors Door Nos. 111A and 112A GROUP 10B: Family Restroom GROUP 11: Restroom Stall Doors Door Nos. 111B, 111C, 111D, and 112B GROUP 12: Traffic Doors Door Nos. 115A and 115B GROUP 13: Patio Gates Door Nos. 108A and 108B GROUP 14: Coat Hooks Bar Stool Area GROUP 16: Trash Enclosure Man Gate Door No. 126

    Hardware Furnished by Owner

    mailto:[email protected]

  • V1.16.1 MATERIAL ID LIST Last Revised: 04-13-16 00 0125 - 9

    GROUP 15: Padlocks Keg Storage, Trash & Chemical Enclosure & Roof Hatch

    Cores and Keys: Insta-Key interchangeable cores.

    SECTION 08 8000 - GLAZING Indicated on Drawings as: Monolithic Glass

    (GL-1): Clear tempered glass, 1/4". (GL-5): Clear tempered glass, 3/8". (Entry Graphic Wall)

    Insulated Glass (GL-2): Clear insulated unit, tempered, 1/4"/1/2"/1/4". Low E coating on No. 2 surface.

    INSULATED SPANDREL GLASS: ADD OPTIONAL INSULATED SPANDREL GLASS UNITS FOR FALSE WINDOWS IF REQUIRED FOR SPECIFIC PROJECT DESIGN. VERIFY PRIOR USE.

    (GL-6): Clear insulated unit, heat strengthened, 1/4" (clear/frit)/1/2"/1/4" (clear). Ceramic frit

    on No. 2 surface. Frit color: Black.

    Mirror Glass (GL-4): One-way mirror glass, 1/4. Provided by Section 08 1113.

    TINTED WINDOW FILM: USE TINTED WINDOW FILM FOR EXISTING WINDOWS AND STOREFRONT ON REMODELS WHEN REQUIRED FOR SUN SHADING. DELETE FOR NEW CONSTRUCTION UNLESS REQUIRED BY BWW PROJECT MANAGER. VERIFY USE.

    Tinted Window Film (TF-1): 3M Sun Control Window Film, Prestige Series, PR 70.

    ALTERNATE TINTED WINDOW FILM: USE TF2 WINDOW FILM BELOW INSTEAD OF TF1 ABOVE FOR SPECIFIC PROJECT CONDITIONS WHERE PROTECTION FROM INTENSE SUNLIGHT AND GLARE IS REQUIRED. VERIFY PRIOR TO USE WITH BUFFALO WILD WINGS DESIGN TEAM.

    (TF-2): 3M Sun Control Window Films, Night Vision Series, NV 35.

    DIVISION 9 - FINISHES SECTION 09 2116 - GYPSUM BOARD ASSEMBLIES

    Indicated on Drawings as: (GYB-#) (GYB-1): Not Used. (GYB-2): 5/8" Mold and Moisture-Resistant Gypsum Board.

    Cement Backer Board (CBD-1): 5/8" Portland Cement Panels, USG Corporation: Durock.

    Exterior Gypsum Sheathing (GYBSH-1): 5/8 Glass Mat Faced Gypsum Sheathing: Dens Glass.

    Metal Framing Systems (interior non-load bearing)

  • V1.16.1 MATERIAL ID LIST Last Revised: 04-13-16 00 0125 - 10

    (Metal Studs): Non-Loadbearing framing. (Ceiling Channels): 2-1/2, 20 gauge ceiling channels. (Furring Channels): 7/8 Hat-shaped furring channels.

    Gypsum Board Accessories and Trim Pieces (Sheet Metal Backing) (Corner Bead) (CJ): Control Joint. (EJ): Expansion Joint.

    Gypsum Board Finish Level Schedule Level 1: Above finished ceilings concealed from view. Level 2: Utility areas and areas behind cabinetry. Level 4: Walls and ceilings scheduled to receive paint finish.

    SECTION 09 3000 - TILE Ceramic Tile Indicated on Drawings as: Ceramic Floor and Wall Tile:

    (CT-1): 6 x 36 Dining Area Floor Tile, Evolution, RBC # BW11. 1/3 stagger pattern. (CT-2): 12 x 12 Restroom Floor Tile, RBC # BW1060, Black. (CT-3): 3 x 6 Restroom Wall Tile, RBC # BW759, Black. (CT-4): 3 x 6 Restroom Wall Tile, RBC # BW744, Yellow.

    Ceramic Tile Base: (CT-5): 6 x 12 Dining Area Cove Base Tile, RBC # BW3200-COVE12, Smooth Round

    Top, Super Black. (CT-5a): 1 x 6 Dining Area Cove Base Outcorner, RBC # BW3200-COVE12OC Smooth

    Round Top, Super Black. (CT-6): 6 x 12 Restroom Cove Base Tile, RBC # BW3210-COVE12, Smooth Flat Top,

    Super Black. (CT-6a): 1 x 6 Cove Base Outcorner, RBC # BW3210-COVE12OC, Smooth Flat Top,

    Super Black.

    Quarry Tile: Indicated on Drawings as: Floor Tile:

    (QT-1): 6 x 6 Kitchen Quarry Tile with abrasive surface, RBC # QT10A-66, Red. (QT-3): 6 x 6 Bar/POS/Take-Out Quarry Tile with abrasive surface, RBC # QT44A, Gray.

    Base: (QT-2): 6 x 6 Kitchen Quarry Tile Cove Base, RBC # 10-Q3565, Red. (QT-2a): 6 x 6 Kitchen Quarry Tile Cove Right Corner, RBC # 10-QCR3565, Red. (QT-2b): 6 x 6 Kitchen Quarry Tile Cove Left Corner, RBC # 10-QCL3565, Red. (QT-4): 6 x 6 Bar/POS/Take-Out Quarry Tile Cove Base, RBC # 44-Q3565, Gray. (QT-4a): 6 x 6 Bar/POS/Take-Out Quarry Tile Cove Right Corner, RBC # 44-QCR3565,

    Gray. (QT-4b): 6 x 6 Bar/POS/Take-Out Quarry Tile Cove Left Corner, RBC # 44-QCL3565,

    Gray.

    Floor Transitions and Tile Trim (T-#) (T-1): Tile Trim: Wall Corner Protection; use with tile in restrooms. Schluter Systems,

    Rondec RO 80 EB, brushed stainless finish. (T-2): Floor Transition: Floor Tile to Carpet. Schluter Systems, Schiene, AE, satin anodized

    aluminum finish. (T-3): Floor Transition: Floor Tile to Floor Tile. Schluter Systems, Deco, AE, satin anodized

    aluminum.

  • V1.16.1 MATERIAL ID LIST Last Revised: 04-13-16 00 0125 - 11

    (T-4): Floor Transition: Floor Tile to Concrete. Schluter Systems, Reno-Ramp, AE, satin anodized aluminum finish.

    FLOOR TRANSITION: ADD THE FOLLOWING FLOOR TRANSITION WHERE CERAMIC TILE MEETS RESINOUS QUARTZ FLOORING IF USED (REFER TO SECTION 09 6726). VERIFY PRIOR TO USE.

    (T-5): Floor Transition: Floor Tile to Quartz Resinous Flooring. Schluter Systems, Deco, AE, satin anodized aluminum.

    Grout

    Standard Grout: All other areas. Bostik-Hydroment Ceramic Tile Grout, Sanded, with acrylic latex admixture.

    Color: (GT-1); Taupe, H151S-25. Use for (CT-1) floor tile areas. Color: (GT-2); Delorean Gray, H160S-25. Use for (CT-2) floor areas. Color: (GT-5); Char Black, H139S-25. Use for (CT-5) and (CT-6) base areas.

    Bostik-Hydroment Dry Tile Grout, unsanded, with acrylic latex admixture.

    Color: (GT-3); Char Black, H139U. Use for (CT-3) wall areas. Color: (GT-4); Buff, H188U. Use for (CT-4) wall areas.

    Epoxy Grout: Use for all Quarry Tile locations. Hydroment Ezpoxy Grout.

    Color: (GT-6); Delorean Gray, H160.

    Accessories: (SSTB) Stainless Steel Cove Corner Base: Century Corners; 5 profile. Manufacturer:

    Decimet Sales, Inc. DSI; Rogers, MN 763-428-4321.

    SECTION 09 5100 - ACOUSTICAL CEILINGS

    Indicated on Drawings as: (ACT-1): 24 x 48, Vinyl faced gypsum board, White. USG ClimaPlus Vinyl, Stipple 3270. (GRID-1): 15/16" Light Duty, aluminum grid system. USG; Donn AX Suspension System.

    Color: White. (Egg Crate Ceiling Panel): 1/2 x 1/2" x 3/8 thick, styrene plastic egg crate panel. 24 x 48

    panel, Color White. To be field painted (PS-28/C-2) to match ceiling finish.

    SECTION 09 6513 - RESILIENT BASE Indicated on Drawings as: (RB-#) Resilient Base

    (RB-1): 6 inch base, Coved, Color Black.

    SECTION 09 6516 - RESILIENT SHEET FLOORING Indicated on Drawings as:

    (RSF): Protect-All, 1/4 thick, vinyl flooring with chemical welded seams and coved base.

    Color: Light Gray, Matte. (Cove Base Cap): Aluminum Z cove base cap.

    SECTION 09 6726 - RESINOUS QUARTZ FLOORING (Optional) Indicated on Drawings as: (RQF-#) Note: Replaces Quarry Tile in Kitchen and/or Resilient Sheet Flooring in Coolers/Freezers

  • V1.16.1 MATERIAL ID LIST Last Revised: 04-13-16 00 0125 - 12

    (RQF-1): Kitchen Area: Degaclad CQ R61SL floor topping system: 1/8" thick R61SL with appropriate Primer and Topcoats. Final floor thickness approximately 3/16.

    (RQF-2): Coolers and Freezers: Degaclad CQ R61SL floor topping system: 1/8" thick R61SL with appropriate Primer and Topcoats. Final floor thickness approximately 3/16.

    Color Blend: SRS # 1027641, Smoke.

    SECTION 09 6800 - CARPETING Indicated on Drawings as: (CPT-#)

    (CPT-1): Custom Mohawk, Broadloom, BWW 50545-37907. (CPT-2): Mohawk Commercial Products; Lees; Step Up II Tile, #GT311; Color: # 955, Cobalt; Size: 24 x 24; Install Pattern: Quarter Turn.

    SECTION 09 7200 - WALL COVERINGS

    Indicated on Drawings as: (WC-#) (WC-1): Forbo Marmoleum, Linoleum Wall Covering, Pattern: Real, Color: #2939, Black. (WC-2): Forbo Marmoleum, Linoleum Wall Covering, Pattern: Real, Color: #2629, Eiger. (WC-3): Forbo Marmoleum, Linoleum Wall Covering, Pattern: Real, Color: #3251, Lemon

    Zest. (Metal Trim): Aluminum T Trim; Outwater Plastics Industries, Inc; Part # ALU1028-S

    SECTION 09 9100 - PAINTING Indicated on Drawings as:

    (PS-#) = Paint System: Prime and Topcoat on Substrate (C-#) = Color Number: Color and Sheen Example: (PS-1/C-2) = Paint System and Color

    COLOR INDICATORS All products from Sherwin-Williams Co., (SW) (C-1): SW 6906, Citrus.

    Note: (EIFS-2) to match color, refer to Section 07 2400. (C-2): SW 7044, Amazing Gray. (C-3): SW 7069, Iron Ore. (C-4): SW 6991, Black Magic. (C-5): SW 7006, Extra White. (C-6): SW 7019, Gauntlet Gray.

    Note: (EIFS-1) to match color, refer to Section 07 2400. (C-7): NOT USED (C-8): SW BW 3S Gray, H66XXA24764-4347 (C-9): SW 4084 Safety Yellow. (C-10): SW TM226 White Traffic Marking Paint. (C-11): SW7018, Dovetail

    EXTERIOR SUBSTRATES PS-1 Concrete and Concrete Block

    Urethane Satin PS-2 Steel / Galvanized Steel HM Doors and Frames (at Exterior of Kitchen Door).

    Urethane Satin PS-3 Exposed Steel Structure (Patio steel structure, deck, Channel, etc).

  • V1.16.1 MATERIAL ID LIST Last Revised: 04-13-16 00 0125 - 13

    Acrylic EggShell PS-4 Steel / Galvanized Steel HM Doors and Frames (within EIFS Finish).

    Acrylic EggShell PS-5 Steel Gates / Misc. Metal / Flashing / Gas Piping on Walls

    Acrylic EggShell PS-6 Bollards / Gas Piping on Roof

    Acrylic Gloss

    PAINTED METAL PANELS: USE FOR STORES THAT REQUIRE YELLOW (CITRUS) COLORED METAL PANELS TO BE FIELD PAINTED INSTEAD OF FACTORY FINISHED, NOT PROTOTYPE.

    PS-7 Exterior Metal Panels (C-1). Acrylic EggShell

    STUCCO: ADD FOR STORES THAT REQUIRE PAINTED STUCCO, NOT PROTOTYPE. DELETE IF NOT REQUIRED.

    PS-8 Exterior Stucco Acrylic Semi-Gloss Finish

    PS-9 NOT USED PS-10 Concrete and Asphalt Pavement Marking

    Acrylic Flat Finish

    Exterior Paint System Notes:

    Gas Piping: Paint exterior gas piping that runs on face of walls or exposed to view, the color of the surrounding substrate, (PS-5). Paint gas piping on roof, (C-9) Safety Yellow, Sher-Cryl HPA Acylic Gloss, B66-300, unless local code requires another color.

    INTERIOR PAINT SYSTEMS

    PS-20 Gypsum Board (All Gypsum Board in Public Areas) Latex Egg-Shell PS-21 Gypsum Board (All Gypsum Board in Kitchen, (not covered with Glass Bd.) Elec

    Room/ Sprinkler Room. Latex Semi-Gloss PS-22 Wood Stall Doors Latex Semi-Gloss, (Painted by TCH) PS-23 HM Doors and Frames

    Pro Industrial Pre-Catalyzed Waterbased Epoxy Semi-Gloss, (Restrooms, Traffic Door Frames)

    PS-24 Steel Deck, Bar Joists & Ductwork, Dry Fall Acrylic Flat

    PS-25 Steel Columns and Beams and Misc. Steel Latex Semi-Gloss

    PS-26 Steel Roof Ladder & Roof Hatch Latex Semi-Gloss

    PS-27 Video Supports / Misc. Steel Support Structures Latex Flat

    PS-28 Wood, Paint Latex Egg Shell PS-29 Wood, Paint (Juke Box Frame, underside of bar top, etc.)

    Latex Flat PS-30 Wood, Transparent (Clear) Finish

    Finish: 1 coat, Pre-finished by Millwork Vendor using Catalyzed Polyurethane system, satin sheen. Finish: 1 coat, clear final finish, polyurethane, satin sheen.

    PS-31 Wood, Varnish (Low Wall trim, window sill)

  • V1.16.1 MATERIAL ID LIST Last Revised: 04-13-16 00 0125 - 14

    Finish: 2 coats, Pre-finished by Millwork Vendor using Pigmented Conversion Varnish, satin sheen.

    DIVISION 10 - SPECIALTIES SECTION 10 0010 - MISCELLANEOUS SPECIALTIES

    Indicated on Drawings as: (Knox Box): Knox Company, 3200 Series, Option for Recessed or Surface Mount.

    Color: Black. (Precast Concrete Splash Blocks): Install at downspout locations. Anti-Graffiti Film for all Restroom Mirrors: Clear, 4 mil. thick, polyester film with acrylic

    abrasion resistant coating to be applied to exterior surface of glass.

    SECTION 10 1400 - INTERIOR SIGNAGE Indicated on Drawings as:

    (SIGN-1): 6 x 9, Handicap Wall Sign, black sign with engraved white letters and symbols and Braille coding. Product # SG 2521B, Women.

    (SIGN-2): 6 x 9, Handicap Wall Sign, black sign with engraved white letters and symbols and Braille coding. Product # SG 2511B, Men.

    SECTION 10 2613 - CORNER GUARDS

    Indicated on Drawings as: Corner and End Wall Guards supplied by RBC Tile & Stone

    (WCG-1): Corner Guard: 2 x 2 x length as indicated, stainless steel wall corner guards. (WCG-2): Corner Guard: 1-1/2 x 1-1/2 x length as indicated, PVC wall corner guards,

    Black. Provided by Millwork Vendor. (WCG-3): Wall End Guard; stainless steel, 2 leg x wall thickness x length as indicated,

    stainless steel wall end guards.

    SECTION 10 2813 - TOILET ACCESSORIES Indicated on Drawings as: The following Toilet Accessories are supplied through Twin City Hardware Framed Mirrors

    (MIR-1): Framed tempered mirror, 24 x 36. (MIR-2): Framed tempered mirror, 24 x 60. For Womens Restroom.

    Sanitary Napkin Disposal (SND): Surface mounted, sanitary disposal, Bobrick Model B270.

    Grab Bars (GB) 1-1/2" Grab Bar - Concealed mounting. (GB-1): 18 long. (GB-2): 36 long. (GB-3): 42 long.

    Waste Receptacle: (WR) Recessed mounted, with keyed removable waste receptacle and optional vinyl liner.

    12 gallon capacity. Diaper Changing Station

    (DCS): Koala, Model KD-200, wall mounted, horizontal. Color (01), Grey. The following Toilet Accessories are Owner Furnished Soap Dispensers

    (SDISP): Ecolab, Digitizer Handsoap Dispenser.

  • V1.16.1 MATERIAL ID LIST Last Revised: 04-13-16 00 0125 - 15

    Paper Towel Dispenser - Semi-Recessed

    (PTD): Tork, Intuition Hand Towel Roll Dispenser, H1 Elevation Intuition System, #5511281, Black. Tork Elevation Intuition Trim Ring & Mounting Bracket Kit, # 3106440. Stainless steel trim ring with a galvanized steel mounting bracket and hardware.

    Toilet Paper Dispenser

    (TPD): Tork, Bath Tissue Jumbo Roll Twin Dispenser.

    SECTION 10 4400 - FIRE PROTECTION SPECIALTIES Indicated on Drawings as: (FE-#)

    (FE-1): Multi-Purpose Dry Chemical, cabinet & bracket mounted. (FE-2): Class K Wet Chemical, bracket mounted. (FE-1 CAB): Cabinet Mounted Portable Fire Extinguishers: Type (FE-1) extinguisher. Cabinet Finish: Pre-finished, Black powder coat.

    SECTION 10 5113 - METAL LOCKERS Indicated on Drawings as: (Lockers) 12 x 12 x 18 deep wall mounted lockers. Configuration: Double tier. 2 units high, 4 units

    wide, 45 coat rod mounted under lockers. Color: Gray. ASI Storage Solutions, Inc.

    SECTION 10 8213 ROOF TOP EQUIPMENT SCREENS Indicated on Drawings as: (Roof Top Equipment Screens): Pre-formed, sliding thermoplastic panel system for enclosing roof

    top mechanical equipment.

    Manufactuers: CityScapes Incorporated; Envisor Screening System. North American Enclosures, Inc.; Spinnaker Screening System.

    SECTION 10 8240 - PATIO SCREEN ENCLOSURE (Optional) Indicated on Drawings as:

    DIVISION 11 - EQUIPMENT NOT USED

    DIVISION 12 - FURNISHINGS SECTION 12 2413 - WINDOW SHADES

    Indicated on Drawings as: (Window Shades): Owner Furnished, MechoShade 5 manual roller shades. Fabric Color: EuroTwill Shade Cloth; No. 6012, Charcoal. Fascia Finish: Baked Enamel, Black.

    DIVISION 13 - SPECIAL CONSTRUCTION NOT USED

  • V1.16.1 MATERIAL ID LIST Last Revised: 04-13-16 00 0125 - 16

    DIVISION 14 - CONVEYING SYSTEMS NOT USED

    DIVISION 31 EARTHWORK SECTION 31 3116 TERMITE CONTROL

    Indicated on Drawings as: (Termite Control): Spray applied, Non-repellant termiticide with 5 year warranty. BASF Corporation, Agricultural Products; Termidor. Bayer Environmental Science; Premise Pre-construction.

    -End of Materials Identification Codes List-

  • (Enter Date) To Whom It May Concern: You are invited to submit a bid for general construction for the Buffalo Wild Wings Restaurant located at:

    Xxx Street Name Suite # City, State Zip Code

    Plans will be available through Plan Command. Please refer to the Instructions to Bidders for the instructions of using Plan Command and any project specific information. All bids are to be sent via email in the format as specified (pdf and excel). Faxed copied will not be accepted. Bids should be addressed to Kari Roepke at the address listed below. Any bids sent via email with the Construction Manager ccd will automatically be disqualified.

    Kari Roepke Construction Development Coordinator Email: [email protected]

    Bids are due on Day, Month Year at 3:00PM CST. During the Bidding Period, questions will be taken until 3:00 P.M. two days prior to bids being due. Questions must be submitted on the Contractors letterhead and emailed to: (insert Construction Manager email). Responses will be distributed to all bidders in written form via email. A Pre-bid Meeting shall be held: Access to the facility/site can be made in advance by contacting the construction manager. Yours truly, (Construction Manager Name) Construction Manager Consultant Buffalo Wild Wings

    mailto:[email protected]

  • V1.16.1 BID INFORMATION Last Revised: 04-13-16 00 1117 -1

    SECTION 00 1117 - BID INFORMATION

    1.01 Bid Invitation and Submission for the above referenced project shall be by e-mail to the location as indicated in the Invitation to Bid.

    1.02 Bids are to be received no later than 3:00 PM Central Standard Time on the date defined by the Owner. LATE BIDS WILL NOT BE ACCEPTED FOR CONSIDERATION.

    1.03 Bidders agree in submitting a proposal that the bid will remain firm for a period not less than ninety (90) days from the bid due date stipulated. Bids to receive consideration must be complete and cover the full scope of work described in the bid documents and must include unit pricing (see attached). Substitutions for material and equipment listed in the bid documents is not permitted. Clarifications and acknowledgement of Addenda shall be noted in the bid proposal.

    1.04 By submitting a bid each bidder represents and acknowledges the following:

    A. They have read and understand the bid documents and their bid is made in accordance therewith. Bid shall acknowledge and record the bid documents issuance dated and index of drawings;

    B. Basis of payment is a LUMP SUM;

    C. Bidder has visited the site (General Contractor and/or Subcontractor) and has familiarized themselves with local conditions under which the work is to be performed. Discrepancies between existing conditions and bid documents shall be identified, written, and submitted to Owner for clarification prior to bid submission. Compensation for unidentified discrepancies shall be at the Owner's discretion for payment.

    D. Their bid is based upon the materials, systems and equipment described in the bid documents without exceptions (No substitutions will be accepted on material and equipment as listed in the bid documents).

    E. Their bid is based on a site specific schedule, from permit to Certificate of Occupancy, as stated in the Instructions to Bidders Document. No extension of the project's schedule is anticipated and no extension of the contract is allowed without the specific written instructions of the Owner. The proposed construction time is firm and critical.

    F. Submit a construction schedule and subcontractor list to the Owner with Bids. Owner retains the right to reject any subcontractor bids as deemed necessary.

    G. Upon the start of construction, Contractor shall maintain daily progress reports, and submit weekly progress reports with photos (hard or digital photos), due on Thursday evenings.

    1.05 Refer to Drawing Sheet G001 for Project Responsibility Matrix.

    1.06 Bid proposals must be in accordance with the Owners provided Bid Template.

    END OF SECTION

  • V1.16.1 INSTRUCTIONS TO BIDDERS Last Revised: 04-13-16 00 2113 -1

    SECTION 00 2113 - INSTRUCTIONS TO BIDDERS

    INSTRUCTIONS TO BIDDERS Sedalia, Missouri

    PART 1 - PRE-BID REQUIREMENTS 1.01 INTENT

    A. The Owner/Architect has made every effort to set forth in the Bid Documents the complete scope of the Work. Nevertheless, minor omissions and discrepancies shall not excuse the Bidder from providing a price to totally complete the project in accordance with the intent of these documents. Bring any conflicts, omissions, or discrepancies to the attention of the Owner prior to submission of an executed bid form. These issues shall be communicated via fax or email only. No verbal direction is allowed. After execution of the Contract, no extra charges will be allowed for items of work where such are concluded to conform to normal construction practices and methods.

    1.02 CONFIRMATION

    A. Inquiries: Notify the Owner if the meaning of the documents is in doubt, or if discrepancies or omissions are noted. This notification shall be by written correspondence only. An Addendum clarifying the issue in question will be sent to all Bidders.

    B. Site Inspection: Visit the location where the Work is to be performed, become thoroughly familiar with all conditions affecting the work, and compare conditions with the Bid Documents. No consideration will be granted for any misunderstanding of existing conditions resulting from failure to visit the site.

    1.03 CONTRACT FORMS

    A. Read carefully and become familiar with the forms identified in the List of Contract Forms. Should the Owner elect to enter into an agreement to execute the Work, the listed forms prepared by Buffalo Wild Wings, Inc. shall be used. A copy of the Contract accompanies these Instructions to Bidders for review.

  • V1.16.1 INSTRUCTIONS TO BIDDERS Last Revised: 04-13-16 00 2113 -2

    1.04 LAWS AND REGULATIONS

    A. All applicable federal, state, and local laws and ordinances, as well as the rules and regulations of the jurisdiction where the work is to be executed, shall apply to the Contract throughout. These will be deemed to be included in the Contract to the same extent as though herein written, including, but not limited to the following: Rules and regulations issued by the City of Sedalia. Rules and regulations issued by the State of Missouri. Rules and regulations issued by the Pettis County Department of Health. Rules and regulations issued as part of a developers agreement.

    1.05 COMPLETION TIME

    A. Evaluation of each Bid will include serious consideration of the time of completion. The Bidder shall be prepared to execute the Contract to accommodate the Owner's commitments and shall govern himself accordingly in completing the Bid Form.

    B. The Bidder is hereby advised that the Owner has made commitments to Sedalia, MO based upon the following construction schedule: (Enter Date) - Start Construction. (Enter Date) - Complete Construction. (Enter Date) - Turnover to Operations

    PART 2 - BID PROCEDURES 2.01 BID DOCUMENTS

    A. You may view and order bid documents by going to the Buffalo Wild Wings Online Plan Room at: http://ipd.moliordata.com/clients/MoliorData/bww/

    B. If it is your first time, please register and retain your login information for future access to the Buffalo Wild Wings Online Plan Room.

    C. After you have registered. Please use your email address and the password you created to log into the Plan Room. Please enter the project password [PROJECT CITY] (This is case sensitive) Once you have selected the project, review the Bid Details for information on ordering documents.

    D. To receive Bid Notices, Bid Addendums, Construction Bulletins, Shipped Order Confirmations, and Electronic Downloads for this project from Buffalo Wild Wings, you must place the following email address in your list of Outlook Contacts: [email protected] Notifications are sent from this email address and not from Buffalo Wild Wings. If you do not do this, your email server may block the receipt of these notifications. There is a ?Help button that you can select for assistance using the Online Plan Room.

    E. If you still have problems, please contact Franz Reprographics by phone @ 763-503-3401.

    2.02 PREPARATION OF BIDS

    A. The Bid shall be prepared using the Bid Form template forwarded electronically by Buffalo Wild Wings, Inc.; no other forms will be considered. a) Bids shall be submitted electronically to the following email address: [email protected]

    http://ipd.moliordata.com/clients/MoliorData/bww/mailto:[email protected]:[email protected]

  • V1.16.1 INSTRUCTIONS TO BIDDERS Last Revised: 04-13-16 00 2113 -3

    b) Bids shall include the Bidder's legal name, fully written. c) Oral, telegraphic, or other modifications will not be considered. d) Bids shall include a preliminary construction schedule. e) Bids shall include a list of qualifications and or exclusions. f) Bid period is approximately three (3) weeks.

    B. Bid Forms shall be sent for delivery prior to the date and time indicated in the Invitation to Bid Letter.

    C. Late bids will not be accepted without prior communication and approval from the Construction Manager via email; Development Coordinator should be ccd on the email.

    D. Any bids submitted with the Construction Manager included will be automatically disqualified.

    2.03 OWNERS RESPONSE TO BIDS

    A. Submitted Bid Forms will be opened and read privately on the date indicated in the Invitation to Bid Letter. Notice of award will be made by the Owner after consideration of Bids received.

    B. The Owner reserves the right to respond to the Bids as follows: Reject any or all Bids without explanation. Waive technicalities. Advertise for new bids. Proceed to do the work otherwise.

    C. The following Bids may be rejected as being informal: Bids that fail to meet the requirements of these instructions. Bids that are incomplete, conditional, or obscure. Bids that contain additions not called for, erasures, alterations, or other irregularities. Bids that contain abnormally high or abnormally low prices for any class or item of work.

    PART 3 - CONTRACT EXECUTION 3.01 POST-BID SUBMITTALS

    A. After notification of selection for the award of a Contract, but prior to issuance of a Construction Agreement, the Bidder shall submit the following to the Owner in writing. A designation of the work to be performed with the Bidder's own forces. Names of the manufacturers, products and the suppliers of principal items or systems of materials and equipment proposed for the Work. Names of persons or entities proposed for the execution of principal portions of the Work.

    B. The Owner will notify the Bidder in writing if the Owner has reasonable objection to a Subcontractor proposed by the Bidder. If the Owner has reasonable objection to a proposed Subcontractor, the Bidder may, at the Bidder's option: Withdraw the bid. Submit an acceptable substitute subcontractor with an adjustment in the Bid to cover the difference in cost.

  • V1.16.1 INSTRUCTIONS TO BIDDERS Last Revised: 04-13-16 00 2113 -4

    C. The Owner may accept the adjusted Bid Price or disqualify the Bidder. Persons and entities accepted by the Owner must be used on the work for which they were proposed and shall not be changed except with the written consent of the Owner.

    3.02 INSURANCE AND BONDS

    A. Insurance: Upon receipt of a written Notice to Proceed, the Bidder shall furnish to the Owner a certificate of insurance in compliance with the requirements of the following: General Conditions of the Contract. Special Conditions of the Contract.

    B. Performance and Payment Bonds (if required by Owner): Upon receipt of a Construction Contract, the Bidder shall furnish to the Owner a Performance Bond and Labor & Materials Payment Bond, both for the full amount of the Contract. The bonds shall be provided by a properly qualified surety company. The cost of the Performance and Payment Bonds shall be indicated on the Bid Form and shall be included in the total proposed Contract Amount.

    3.03 LABOR FORCE

    A. Cooperation: The Bidder is advised that the Work may be performed within a building currently occupied by the public. The Bidder shall assure the Owner that he will provide labor that can work without unduly disturbing the public and ongoing operations within the building.

    B. Non-Discrimination: The Bidder is advised that the Owner will not tolerate any discrimination on the basis of age, gender, race, national origin, or sexual orientation by the Bidder or Subcontractors.

    C. The Contractor shall provide a full time, on-site Superintendent for the Project. The Superintendent shall be onsite from the Mobilization Phase until after the Grand Opening Day.

    END OF BID INSTRUCTIONS

  • V1.16.1.1 VENDOR CONTACT INFORMATION Last Revised: 07-08-16 00 3110 -1

    SECTION 00 3110 VENDOR CONTACT INFORMATION

    PART 1 - GENERAL

    1.01 SUMMARY

    A. The following is a list of approved Vendors for the construction of Buffalo Wild Wings Restaurants. These vendors have, within the Drawings and Specifications, products that are approved for use for these projects and have either a National Account with the Owner or are specified as a sole provider for their particular material, component or system. These items are required in the construction of all Corporate Facilities.

    B. Please note that the vendors with the asterisk * notation before the company name means the vendor is a required vendor with a closed specification that must be used for all Buffalo Wild Wings corporate & franchise projects. All other vendors are recommended for Buffalo Wild Wings projects.

    APPROVED VENDORS LIST

    Company Name Contact Phone/Fax E-Mail Address Sign Vendors

    * Lawrence Sign

    Robb Walker Tom Jones

    (651)488-6711 (o) (651)488-6715 (f)

    [email protected] [email protected]

    * Philadelphia Sign

    Bret Matthews Adrian Corda

    (847)707-769 (o)

    [email protected] [email protected]

    * Federal Heath Sign

    Randy Cearlock Tom DeFillipo

    (317)581-7790 x23(o) (317)697-4442 (c)

    [email protected] [email protected]

    Hardware Vendors

    Twin City Hardware

    Brent Chuhel

    (651)731-7126(o) 651-735-1800 (f)

    [email protected]

    Insta Key Frank Newton

    (800)316-5397 x110 (303)761- 6359

    [email protected]

    Millwork/Furniture/Marmoleum Vendors

    * Wisconsin Built (millwork)

    Bill Taylor

    (608)764-8661 x303 (608)764-8664 (f)

    [email protected]

    * Dras Cases (millwork)

    Amy Peterson

    (507)402-6030 (c) (641)592-3333 x123

    [email protected]

    * Blair Companies (millwork)

    Kevin Baumgardner

    (814) 283-2080 (o)

    [email protected]

    * Plymold (furniture)

    Brian Rothmeyer Judy Ryan

    (952)358-2609 (o) (952)943-8289 (f)

    [email protected] [email protected]

    * Seating Concepts (furniture)

    Bill Overton Ken Hibben

    (815)730-7980 x2222 (815)730-7969 (f)

    [email protected] [email protected]

    mailto:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]

  • V1.16.1.1 VENDOR CONTACT INFORMATION Last Revised: 07-08-16 00 3110 -2

    Company Name Contact Phone/Fax E-Mail Address Kitchen Equipment / Smallwares Vendors

    * C & T Design Equipment

    Dominic Esposito- 1st Bob Boesenberg 2nd

    (513)682-1133(o) (513)771-9528 (f)

    [email protected] [email protected]

    * Bargreen Ellingson

    Ryan Kuehne - 1st Ken Hirsch - 2nd

    (817)932-6009 (o) (888)775-6210 (f)

    [email protected] [email protected]

    * Hockenbergs Jimmy Tran - 1st

    Jeff Witt - 2nd

    (612)455-6760 (o) (612)362-8470 (f)

    [email protected] [email protected]

    Edward Don (smallwares)

    Jennifer Maloney Careen Berones

    (770)239-5056 (o) (708)692-3700 (o)

    [email protected] [email protected]

    HVAC/Hoods, Air Balance Vendors

    * Trane (RTU)

    Justin Strain

    (651)468-2769 (o)

    [email protected]

    * Lennox Industries (RTU)

    Michael Johnston David Ebner

    (800)367-6285 (651)233-1582

    [email protected] [email protected]

    * Accurex (Proximity Hood)

    Chris Anderson

    (715)355-2313

    [email protected]

    Captive Aire (Canopy Hood-Only)

    Steve Luddy Jr

    (407)682-3100 (o) (407)682-2820 (f)

    [email protected]

    Air Solutions & Balancing, LLC (Air Balance)

    Colleen Grenon Gould

    (603)262-9292 x700 (603)262-9292 (f)

    [email protected]

    Light Fixtures & Intergrated Electrical Panel Vendors * On Site Lighting

    Mike Gleeson

    (763)682-7122 (o) (612)801-3422 (c) [email protected]

    * Villa Lighting Kevin Pytlinski (314)633-0428 (o) [email protected]

    Hill Phoenix

    Mike Ceciliani Scott Higginbotham

    (770)285-3216 (o)

    [email protected] [email protected] [email protected]

    Flooring Vendors

    * Mohawk Carpet Erica Wells (800)622-6228 x24747 [email protected]

    * RBC Tile Margie Yurek (763)559-5531 (o) (763)559-6579 (f) [email protected]

    Miscellaneous Vendors

    Network Design Brian Finnvik (763)475-7440 (o) (763)475-7441 (f)

    [email protected]

    * Pepsi Beverages Company (Soft Drink Vendor)

    Kathy Fast

    (949)420-2037 (o) (909)229-5668 (c) [email protected]

    Tyco Security Marc Singer Christina Wengartner (402)614-3071 (o) (402)510-0532 (c)

    [email protected] [email protected]

    * Tegan Marketing (window shades) Paul Tegan

    (763)475-1340 (o) (612)817-5498 (c) [email protected]

    * HME Wireless Jolene Smith (678)280-2727 (o) (800)925-8091 x1727 [email protected]

    mailto:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]

  • V1.16.1.1 VENDOR CONTACT INFORMATION Last Revised: 07-08-16 00 3110 -3

    Company Name Contact Phone/Fax E-Mail Address Miscellaneous Vendors continued

    * NCR Corporation Ernie DiBenedetto (770)576-7057 (o) (404)78804129 (c) (770)619-4705

    [email protected]

    * Nichiha USA Inc. (Brick Panels)

    Matt Stephenson Tim Seims

    (770)789-8228 (425)495-1840

    [email protected] [email protected]

    * Petersen Aluminum Corp. (Metal Panels) David Landis

    (800)272-4482 (o) (404)797-2143 (c) [email protected]

    * EPS Specialties (Ceiling Clouds)

    Lee Wilkinson Art Wilkinson (800)422-3556

    [email protected] [email protected]

    Schwank (Patio Heaters) Pam Davis

    (877)446-3727 (o) (706)526-3011 (c) [email protected]

    Mendota Valley VendingTouchtunes Molly Lethert

    (651)451-0420 (o) (612)849-4994 (f) [email protected]

    Buzztime Entertainment Gina (Oie) Palmer

    (866)686-4299 (760)438-7400 x1129 [email protected]

    * DirecTV Garrick Whipple (512)712-5320 (303)513-4371 (c) [email protected]

    Amphion Scott Denton Jason Velez (800)520-2677 x201 (800)520-2677 x133

    [email protected] [email protected]

    Burroughs Payment Systems Laura Borgeson (612)750-0104 (c) [email protected]

    Corporate Safe Specialist Jack Costello

    (800)342-3033 x129 (708) 371-3326 [email protected]

    NUCO2 (CO2 & Nitrous) John - Paul Venanzi

    (513)774-0500 (772)781-3515

    [email protected]

    Northcoast Productions Terry Getner (419)624-1155 [email protected]

    Rooftop Solutions-Grease Guard LLC. (Grease Guard)

    Jim Selle Amanda Rigert

    (800)284-8273 x8153 (224)629-1631 (c) (800)913-7034 (847)428-7270 (f)

    [email protected] [email protected]

    Ecolab (Chemicals) Jody DePonty

    (651)795-6730 (o) (651)306-4186 (f) [email protected]

    Selecto Scientific (Water Filteration) Jessica Nieves (800)635-4017 x3 [email protected]

    Culligan Janet La Plume (847)430-1383 (o) (847)430-2770 (f) [email protected]

    Cisco-Eagle (Keg Storage Enclosure)

    Keegan Moore (888)877-3861 [email protected]

    Labor Ready Worldwide Patrick McAllister

    (314)567-6560 (314)480-7095

    [email protected]

    Filtercorp George Montecino (770)296-4119 [email protected]

    Partstown Mark Marron (800)438-8896 [email protected]

    mailto:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]

  • V1.16.1.1 VENDOR CONTACT INFORMATION Last Revised: 07-08-16 00 3110 -4

    Company Name Contact Phone/Fax E-Mail Address Miscellaneous Vendors continued

    Smart Safe / Brinks Rick Lopresti (614)761-1205 (o) (614)787-6869 (c)

    [email protected]

    * Haines, Jones & Cadbury (Toto restroom Fixtures)

    Systra Hernandez David Lightfoot

    (800)459-7099 (o) (484)708-9732 (f) (479)366-0642 (c)

    [email protected] [email protected]

    SCA Tissue North America, LLC Cameron Rutherford

    (866)722-6659x1043 (o) (513)382-8095 (c)

    [email protected]

    Dcor Vendors/Installers National Fixture Installation (Dcor Installer)

    Felix Vigeant (763)278-7320 (o) (763)232-7378 (c) [email protected]

    Matthew Madler (Dcor Installer) Matthew Madler

    (770)271-0914 (o) (678)361-6294 (c) [email protected]

    Installation Solutions (Dcor Installer) Luke Vossen

    (612)276-6887 (o) (612)839-9860 (c)

    [email protected]

    * Eclipse Corp. (Dcor Vendor-Vinyl Graphics)

    Paul Hartong (614)626-8596 (o) (614)580-1181 (c) [email protected]

    Collection Connection Frame Shop (Dcor Vendor)

    Kevin Stewart (503)594-1789 (o) (503)515-8335 (c) [email protected]

    Frame Time (Dcor Vendor) Marty Hoeft

    763-553-2995 (o) 612-508-1696 (c) [email protected]

    Frameworth Sports Marketing, Inc. (Canada Only)

    Brian Ehrenworth (416)781-1115 x 221 (o) (416)727-0887 (c)

    [email protected]

    Trash Compactors-OPTIONAL

    Harmony Enterprises Nicholas Roberts (952)221-8627 (o) (952)487-2509 (f) [email protected]

    Grease Transfer Systems-System is required for all locations & vendor listed is recommended.

    Mahoney Environmental

    Patrick Darin Sonny Nuccio Bill Mega

    (800)892-9392 (o) (815)791-1005 (c) (815)791-0996 (c)

    [email protected] [email protected] [email protected]

    PART 2- PRODUCTS

    Not Used

    PART 3 - EXECUTION

    Not Used

    END OF SECTION

    mailto:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]

  • V1.16.1 SUBSURFACE INVESTIGATION Last Revised: 04-13-16 00 3132 -1

    SECTION 00 3132 - SUBSURFACE INVESTIGATION

    PART 1 - GENERAL

    1.01 GENERAL

    A. Geotechnical Investigation (Subsurface Soils Tests) for the project site has been performed and a report of that investigation has been completed. A copy of the investigation report is contained within Section 00 3133.

    1.02 SUBSURFACE INFORMATION

    A. Log of borings indicates materials penetrated at specific locations. Owner and/or Architect assume no responsibility for any conclusions or interpretations made by Contractor related to information included in the Report. Should Contractor require additional information concerning sub-surface conditions, he may without cost to Owner, make additional investigations. Should additional investigations produce information different from that in Soil Report, notify Owner in writing.

    1.03 REQUIREMENT

    A. Contractor read and otherwise become completely familiar with contents of Soil Report, including but not limited to its recommendations for preparation of subsoil, bases, sub-bases and fill and construction of building foundations, parking and paving. Provide building foundations in compliance with recommendations in Report. Should discrepancy be found between the requirements of Soil Report and the drawings and/or specifications, notify Owner in writing prior to beginning Work.

    PART 2 - PRODUCTS

    Not Used

    PART 3 - EXECUTION

    Not Used

    END OF SECTION

  • V1.16.1 BID FORM Last Revised: 04-13-16 00 4100 -1

    SECTION 00 4100 - BID FORM

    For

    Buffalo Wild Wings

    PROPOSAL OF:

    ______________________________________________________________________

    (Name of Bidder)

    SUBMITTED NO LATER THAN:

    3:00 PM CST on

    Date: as per Invitation to Bid

    AT THE OFFICE OF:

    As specified on the Invitation to Bid

    The Undersigned hereby proposes to furnish all supervision, labor, materials, equipment, tools and necessary accessories for the construction of Buffalo Wild Wings in (Location Name), as set forth for the Project in the Drawings & Project Manual as shown on design documents, and Addenda as prepared by the Architect.

    The Undersigned hereby proposes to furnish all of the above for the Lump Sum Bid Amount of:

    _________________________________________________________________________________________________________________________________________________.00)

    (Note: Amounts shall be shown in both words and figures. In case of discrepancies, the amount in words will govern.)

    Execute duplicate Proposal from in original for each Bid submitted.

    Do not alter the wording of this Form.

    Bidders may attach typewritten sheet(s) providing any additional information, substitutions, or voluntary alternates for the Owners consideration.

  • V1.16.1 BID FORM Last Revised: 04-13-16 00 4100 -2

    1.01 BID A. The Lump Sum Bid includes all sales taxes, excise taxes, and any other taxes for

    materials, appliances, and/or services subject to and upon which taxes are levied.

    1.02 ACKNOWLEDGEMENTS A. Addenda: The Undersigned hereby acknowledges receipt of the following Addenda

    to the Drawings & Specifications, all of the provisions and requirements of which Addenda have been taken into consideration in the preparation of this Proposal:

    Addendum No. 1, dated ____________ Addendum No. 4, dated ___________ Addendum No. 2, dated ____________ Addendum No. 5, dated ___________ Addendum No. 3, dated ____________ Addendum No. 6, dated ___________

    B. The length of time required for completion of the Work of this Project will be a determining factor in the award of the Contract to the Bidder.

    The Undersigned hereby declares that he has visited the site, has had sufficient time to make all investigations, has carefully examined the Contract Documents, and has become familiar with all conditions, to arrive at an intelligent estimate of the cost of performing the Work, and that he agrees to do the Work for the Sums set forth in this Proposal.

    Respectfully submitted, __________________________________________________________ Legal Name of Bidding Firm __________________________________________________________ Type of Legal Entity __________________________________________________________ State of Incorporation (if a Corporation) __________________________________________________________ Name of President __________________________________________________________ Name(s) of Owner(s) (if not a Corporation) __________________________________________________________ Street Address __________________________________________________________ City, State, & ZIP Code ______________________ _____________________________ Telephone Number Fax Number __________________________________________________________ Authorized Signature __________________________________________________________ Title ________________________ Date (If a CorporationAffix Seal Here)

    END OF BID FORM

  • CONTRACT BETWEEN OWNER AND CONTRACTOR (LUMP SUM CONTRACT)

    THIS CONTRACT is made effective the day of , 201_ BETWEEN:

    OWNER: BLAZIN WINGS, INC.

    5500 Wayzata Boulevard Suite 1600 Minneapolis, MN 55416 Telephone Number: 952-593-9943 Fax Number: 952-593-9787 Owners Representative:

    Rev 4/19/12

    and CONTRACTOR:

    Contractors Representative: for the PROJECT:

    ARCHITECT:

    RECITALS

    A. Owner has entered into a lease agreement (the Lease) with

    (Landlord) for the property at in the City of , (the Property).

    B. Owner and Contractor have agreed that Contractor shall perform improvements to

    the Property as an independent contractor as provided in this Contract.

    AGREEMENT

    NOW, THEREFORE, in consideration of the mutual covenants contained herein, Owner and Contractor agree as follows:

    1. Contractor, as an independent contractor, shall furnish all of the materials,

    supplies, tools, equipment, labor, supervision, administration, and other services (collectively the Work) necessary for the construction and completion of the work described in the drawings, specifications and instructions to bidders listed on Exhibit B (collectively, the Drawings and Specifications) and the General Conditions attached as Exhibit C. Contractor shall achieve Substantial Completion (as defined in the General Conditions) of the Work by (the Substantial Completion Date).

    2. For and in consideration of Contractors performance of the Work and

    compliance with all terms of this Agreement, Owner shall pay to Contractor the lump sum of

  • $ (Contract Sum), and reimburse Contractor for the cost of the building permit, all in the manner and at such times as set forth in the General Conditions.

    3. The following documents are incorporated into this Agreement as though fully set

    forth herein: Exhibit A (Guaranty); Exhibit B (Drawings and Specifications); Exhibit C (General Conditions); Exhibit D (Sworn Construction Statement); Exhibit E (GC Partial Lien Waiver); Exhibit F (General Release and Final Waiver of Lien); Exhibit G (Subcontractor Partial Unconditional Lien Waiver); and Exhibit H (Insurance Rider). Contractor hereby acknowledges that Contractor has reviewed and fully understands the foregoing documents.

    This Agreement is acknowledged and executed effective as of the date set forth above.

    Owner BLAZIN WINGS, INC. CONTRACTOR:

    By: By:

    Print: Print:

    Title: Title:

    2

  • A-1

    EXHIBIT A

    PERSONAL GUARANTY OF CONSTRUCTION CONTRACT

    To induce Blazin Wings, Inc. (Owner) to execute and deliver the Construction Contract

    between Owner and Contractor (Contract) to which this Guaranty is attached, said Contract being between Owner and (Contractor), and relating to the improvements of property at in the City of , , the undersigned (Guarantor, whether one or more), a principal of Contractor or other person who will benefit directly from the existence of the Contract, for himself or herself, his or her heirs, successors and assigns, unconditionally, absolutely and irrevocably: (i) guarantees the full and punctual payment and performance of each of the terms, covenants, conditions and indemnifications to be kept or performed by Contractor under the terms of the Contract, including any modifications thereof (including, without limitation, such modifications thereof made after a purported revocation of this Guaranty); and (ii) agrees as follows:

    1. This Guaranty is an absolute, primary, and continuing, guaranty of payment and

    performance and is independent of Contractors obligations under the Contract.

    2. Guarantor waives any right to require Owner to: (a) join Contractor with Guarantor in any suit arising under this Guaranty; or (b) pursue or exhaust any other remedy in Owners power. Until all of Contractors obligations to Owner have been discharged in full, Guarantor shall have no right of subrogation against Contractor.

    3. Guarantor hereby waives all presentments, demands for performance, notices of

    nonperformance, protests, notices of protest, dishonor and notices of acceptance of this Guaranty, and waives all notices of existence, creation or incurring of new or additional obligations from Contractor to Owner.

    4. Guarantor further waives all defenses afforded guarantors or based on suretyship or

    impairment of collateral under applicable Laws, other than payment and performance in full of Contractors obligations under the Contract.

    5. The liability of Guarantor under this Guaranty will not be affected by (a) the release or

    discharge of Contractor from, or impairment, limitation or modification of, Contractors obligations under the Contract, including without limitation, arising out of any bankruptcy, receivership, or other debtor relief proceeding, whether state or federal and whether voluntary or involuntary; (b) the rejection or disaffirmance of the Contract in any such proceeding; or (c) the cessation from any cause whatsoever of the liability of Contractor under the Contract.

    6. This Guaranty shall be binding upon the heirs, legal representatives, successors and

    assigns of Guarantor and shall inure to the benefit of Owners successors and assigns. If this Guaranty is signed by more than one person the obligations of each signatory hereto shall be

  • A-2

    joint and several. The Guarantor shall pay all expenses (including court costs and reasonable attorneys fees) paid or incurred by Owner in endeavoring to enforce this Guaranty.

    day of

    IN WITNESS WHEREOF, the Guarantor has executed this instrument as of the _, 2012.

    STATE OF )

    ) ss. COUNTY OF )

    The foregoing instrument was acknowledged before me this day of

    , 20 , by .

    Notary Public

  • EXHIBIT B

    DRAWINGS AND SPECIFICATIONS

    B-1

  • Owner Contractor

    C-1

    EXHIBIT C (General Conditions for Blazin Wings, Inc. Projects)

    ARTICLE 1 CONTRACT DOCUMENTS

    1.1 The Contract Documents consist of the Contract, these General Conditions,

    Lease, Drawings and Specifications, all Exhibits to the foregoing, all addenda issued prior to execution of this Contract, and all modifications issued by Owner subsequent thereto (hereinafter the Contract Documents). The intent of the Contract Documents is to include all items necessary for the proper execution and completion of the Work. The Contract Documents are complementary and what is required by any one shall be as binding as if required by all. Work not covered in the Contract Documents will be required if it is consistent with the Contract Documents and is reasonably inferable therefrom as being necessary to produce the intended results. In case of a conflict in terms, subject to the provisions of this Section 1.1, the terms of the Contract shall prevail over the terms of any other Contract Document, and the Plans and Specifications shall prevail over these General Conditions.

    1.2 Contractor acknowledges that all Contract Documents have been made available

    to or provided to Contractor for its review. The completeness and correctness of the Contract Documents shall be verified by Contractor before the execution of the Contract by Contractor. The Contractor shall not proceed with the Work if any error, ambiguity or disagreement appears to exist on any portion of the Contract Documents, but shall immediately notify Owner and submit a written request for an explanation or decision to Owner. Should Contractor proceed without a written response by the Owner, Contractor shall be so doing so at its own risk and expense, and shall not be entitled to any relief in the form of additional time or money.

    ARTICLE 2

    SUBMITTALS

    2.1 By submitting its bid, Contractor represents that it has carefully reviewed the Contract Documents, and is familiar with the Project conditions and details applicable to all Work required under this Contract.

    2.2 Contractor shall review, approve and submit directly to Architect, with reasonable

    promptness and in such sequence as to cause no delay in the Work, all shop drawings, product data and samples required by the Contract Documents. By approving and submitting shop drawings, product data and samples, Contractor represents that it has determined and verified all materials, field measurements and field construction criteria related thereto, and that it has checked and coordinated all information contained therein, including but not limited to layouts and existing utility locations. If Contractor at any time believes that Architects failure to respond to submittals is in any way impeding or delaying the Work, Contractor shall immediately notify the Owners Representative.

  • Owner Contractor

    C-2

    2.3 Architect and/or Owners approval of submittals tendered hereunder is for general design only and shall not relieve Contractor of its obligation to perform the Work in strict accordance with Contract Documents and applicable codes, laws, ordinances, rules, regulations and lawful orders of public authorities (collectively, Laws).

    ARTICLE 3

    TIME OF COMMENCEMENT AND COMPLETION

    3.1 Contractor shall commence the Work upon a notice to proceed from Owner.

    3.2 Substantial Completion shall mean that the Work is completed to allow Owner to obtain, and Owner does obtain, its Certificate of Occupancy, subject only to Contractor completing the Punch List Work as provided in Article 15.

    3.3 Contractor shall achieve substantial completion of the Work, unless modified by

    change order as set out herein, by the Substantial Completion Date set forth in the Contract. Prior to or in conjunction with the pre-construction meeting scheduled by Owner (Pre- construction Meeting), Contractor will furnish to Owner, for Owners comment and approval, a Construction Project Schedule (Construction Project Schedule), scheduling the progress of the Work that shall meet the Substantial Completion Date, and Contractor shall at all times schedule the Work such that the components of the Work shall be completed on the applicable dates set out in the Construction Project Schedule. Contractor shall incorporate Owners requirements for installation of fixtures, furnishings and equipment into its Construction Project Schedule.

    3.4 Upon approval by Owner, the Construction Project Schedule shall become a

    Contract Document and may be revised only with the written consent of Owner.

    3.5 TIME IS OF THE ESSENCE OF THIS AGREEMENT. Contractor acknowledges that Owner will suffer great financial loss, for which Contractor shall be liable, if the Work is not completed by the Substantial Completion Date. Contractor shall maintain the progress of the Work in accordance with the Construction Project Schedule or any agreed upon revision thereof. Contractor shall begin its Work at the time specified by Owner and perform its Work with diligence and sufficient manpower to maintain the progress of the Work. In the event that Owner reasonably believes that the Project is in jeopardy of not meeting the Substantial Completion Date, Owner shall have the option upon written notice to Contractor to require Contractor to immediately take measures to accelerate the Work in order to meet the Substantial Completion Date. The cost of such acceleration shall be borne by Contractor.

    3.6 Execution of this Contract is a certification by Contractor that the required

    materials and labor are available to perform the Work in accordance with the Construction Project Schedule.

    3.7 Contractor shall have a representative on call (the Store Opening

    Representative) from the Substantial Completion Date through the closing of the stores first date of business to respond to Punch List, startup and/or warranty issues. The Store Opening

  • Owner Contractor

    C-3

    Representative shall be Contractors project manager, site superintendent, or other person subject to Owners approval.

    ARTICLE 4

    PERMITS, FEES, AND COMPLIANCE WITH LAWS

    4.1 The Contractor shall secure and pay for the building permit. The amount paid to the issuing authority for the building permit shall be reimbursed by the Owner without payment of Contractors overhead or profit upon receipt of a copy of the building permit and proof of payment of the cost of the permit. Contractor shall pay for all other permits, governmental fees, licenses and inspections necessary for proper execution and completion of the Work and the cost thereof shall be included in the Contract Sum. Contractor shall promptly send to the Owner a photocopy of all permits or licenses required in connection with the construction of the Project.

    4.2 The Contractor shall comply with and give notices required by Laws applicable to

    performance of the Work. The Contractor shall promptly notify the Architect and Owner if the Drawings and Specifications are observed by the Contractor to be at variance therewith. If the Contractor performs Work knowing it to be contrary to Laws, without such notice to the Architect and Owner, the Contractor shall assume responsibility for such Work and shall bear the costs attributable to correction. It is the Contractors responsibility to make sure that the Work, as constructed, complies with all applicable government requirements and codes, including local codes and ordinances, which bears on performing the Work, whether or not reflected in the Contract Documents.

    ARTICLE 5

    CONTRACT SUM

    5.1 Owner shall pay Contractor for the performance of the Work, subject to additions and deductions by written change order as set out below, the Contract Sum set forth in the Contract. The Contract Sum includes all applicable federal, state and local taxes, and the cost of all permits required to construct the Work, other than the building permit, the cost of which Owner shall reimburse pursuant to Section 4.1. This is a lump sum contract and, except as expressly provided herein, the Contract Sum can be decreased or increased only by a written change order signed by Owner.

    5.2 Contractor shall provide the State tax sales/use ID number for the jurisdiction in

    which the Work is to occur. Further, Contractor will identify in its Sworn Construction Statement the amount of sales tax included in the Contract Sum and identify the specific items that are subject to sales tax.

    5.3 For agreed-upon Changes in the Work performed by Contractors own forces, in

    accordance with Article 7, the Contract Sum shall be adjusted by mutual agreement, or alternatively, by the Actual Cost (as defined in Section 7.2.1.1) of the Change in Work plus a five percent (5%) mark-up for profit and Overhead (as defined in Section 7.2.1.2).

  • Owner Contractor

    C-4

    5.4 For Changes in the Work performed by subcontractors, the Contract Sum shall be adjusted by mutual agreement, or alternatively, the Actual Cost (as defined in Section 7.2.1.1) of the Change in Work, plus ten percent (10%) mark-up for the subcontractor plus a five percent (5%) mark-up for Contractors profit and overhead.

    ARTICLE 6

    PROGRESS AND FINAL PAYMENTS

    6.1 On the first day of each month, Contractor shall submit an application for payment (Application for Payment) to Owners Representative covering the Work accomplished through the last day of the previous calendar month, along with such documents as required by Owner for materials suitably stored on-site pursuant to the direction and approval of Owner. Payment shall be made on 90% of the approved Application for Payment within 30 days from the date of Owners receipt of a valid and complete Application for Payment (or, if the 30th day falls on a weekend or holiday, on the first working day thereafter); provided, however, that Owner may refuse to pay any amounts it believes are in excess of the percentage of Work actually completed. In addition, Owner may withhold payment as provided in Article 17 below.

    6.2 Each Application for Payment shall be supported on forms to be supplied by

    Owner and other documents as may be required by Owner and/or Landlord. Contractor shall provide original lien waivers as follows (i) from Contractor in the form attached as Exhibit E effective through the last date covered for the Application for Payment; and (ii) from all subcontractors and Major Suppliers, defined as any supplier providing materials in excess of $2,000, in the form attached as Exhibit G effective through the last date covered by the previous Application for Payment. PDF, facsimile or other copies will not be accepted.

    6.3 Completion of the Work shall mean: (1) full performance of all Contract

    terms; (2) acceptance of the Work by Owner; (3) resolution of all outstanding Change Orders; and (4) completion of all punch-list items. Final Payment, constituting the entire unpaid balance of the Contract Sum, plus retainage, shall be paid by Owner to Contractor upon Contractors Completion of the Work, and upon receipt of the following documents:

    6.3.1 Final Releases of Liens from both the General Contractor, all

    subcontractors and Major Suppliers in the form attached as Exhibit F;

    6.3.2 Delivery of all written warranties and operation manuals for equipment and systems provided by or through Contractor;

    6.3.3 A CD of as built drawings;

    6.3.4 Delivery of all original permits, licenses, and approvals for the Work

    and/or Project, including the final Certificate of Occupancy; and

    6.3.5 Signed punchlist by store manager.

  • Owner Contractor

    C-5

    6.4 Contractor shall pay each subcontractor the amount listed on the pay application for such subcontractor within seven days of Contractors receipt of payment from Owner. All payments received from Owner shall be held in trust by Contractor and used solely for the Project (including without limitation, payment to subcontractors and suppliers to the Project) and not be diverted to other projects or uses.

    ARTICLE 7

    CHANGES IN WORK

    7.1 Lump Sum Change Order.

    7.1.1 Owner may, at any time, by a written order, make changes to the Drawings and Specifications (Change in Work). Contractor shall notify Owner of any changed conditions or Owner directives which Contractor believes entitles Contractor to an adjustment in the Contract Sum or Substantial Completion Date within forty-eight (48) hours of becoming aware of said potential increase and prior to performing any Change in Work.

    7.1.2 When a condition is identified which requires a Change in Work or a

    revision to the scope of Contractors Work, Owner shall submit to Contractor a Proposal Request which will stipulate details and terms of the required Proposal. Owner and Contractor