Budget specification EHN1 Extension: Infrastructure (WG2) Mats Wilhelmsson 17 September 2015.
-
Upload
jonah-bradford -
Category
Documents
-
view
212 -
download
0
Transcript of Budget specification EHN1 Extension: Infrastructure (WG2) Mats Wilhelmsson 17 September 2015.
![Page 1: Budget specification EHN1 Extension: Infrastructure (WG2) Mats Wilhelmsson 17 September 2015.](https://reader036.fdocuments.in/reader036/viewer/2022083005/56649f2a5503460f94c44db5/html5/thumbnails/1.jpg)
Budget specification EHN1 Extension:
Infrastructure (WG2)
Mats Wilhelmsson 17 September 2015
![Page 2: Budget specification EHN1 Extension: Infrastructure (WG2) Mats Wilhelmsson 17 September 2015.](https://reader036.fdocuments.in/reader036/viewer/2022083005/56649f2a5503460f94c44db5/html5/thumbnails/2.jpg)
The project is devided in 4 parts:
• EHN1 North Wall dismantling (WG1)• EHN1 extension building infrastructure (WG2)• Extension of the H2 and H4 beam lines (WG3)• Installation of detectors and associated infrastructure (WG4)
![Page 3: Budget specification EHN1 Extension: Infrastructure (WG2) Mats Wilhelmsson 17 September 2015.](https://reader036.fdocuments.in/reader036/viewer/2022083005/56649f2a5503460f94c44db5/html5/thumbnails/3.jpg)
Infrastructure items in WG2 PBS-ID Title Group Budget [CHF]
IN.2.1 Ventilation, heating and air-conditioning
EN-CV 634’500
IN.2.2 Fluids- and water cooling EN-CV 684’316
IN.2.3 Electrical infrastructure and lights
EN-EL 1’033’709
IN.2.4 Counting rooms EN-MEF 96’000
IN.2.5 Gas networks EN-MEF 130’700
ÎN.2.6 Metal structures ΕΝ-MEF or GS (tbc) 193’200
IN.2.7 Doors EN-MEF 20’500
IN.2.8 Alarms- and detection GS-ASE 150’000
IN.2.9 Personnel access GS-ASE 50’000
IN.2.10 IT-networks IT-CO 88’700
IN.2.11 Transport- and handling EN-HE 97’200
Total 3’178’825
Project contingency (10%) 317’883
Total request 3’496’708
![Page 4: Budget specification EHN1 Extension: Infrastructure (WG2) Mats Wilhelmsson 17 September 2015.](https://reader036.fdocuments.in/reader036/viewer/2022083005/56649f2a5503460f94c44db5/html5/thumbnails/4.jpg)
Cooling and Ventilation IN.2.1 - Ventilation, Heating and Air-conditioning EN-CV 634,500
General ventilation system 326,790
Air-conditioning of the counting barracks 140,800
Ventilation of the detector pits (air supply) 116,910 Extraction of Argon from experimental pits is in WG4
Connection to the central heating network 50,000 Estimate by MW (wait for a refined quote from GS)
IN.2.2 - Fluids and water cooling EN-CV 684,316
Raw water 78,243
Compressed air 25,660
Demineralized water 128,317
Chilled water 270,728
Fire fighting water 56,034
Drinking water(domestic) 28,534
Design&Works (by FSU) 96,800
The Argon extraction system for the pits is estimated to 338,173 CHF
!
![Page 5: Budget specification EHN1 Extension: Infrastructure (WG2) Mats Wilhelmsson 17 September 2015.](https://reader036.fdocuments.in/reader036/viewer/2022083005/56649f2a5503460f94c44db5/html5/thumbnails/5.jpg)
Electric infrastructureIN.2.3 - Electric infrastructure and lights EN-EL 1,033,709
DC-Cabling is in WG3
HV switchgear - 18kV Stable + 3.3kV Secure 92,811
Transformers 12,573
Containment for substations only 40,000
Cabling and connections 57,447
Lighting 67,230
Power distribution 84,316
UPS 9,027
Barracks/Counting Room Fit out (Based on 8 times 9x4m) 210,970
Structural Earthing 23,752 Earthing in the concrete slab of extension
Documentations 39,583
Cabletrays 396,000 360 kE
![Page 6: Budget specification EHN1 Extension: Infrastructure (WG2) Mats Wilhelmsson 17 September 2015.](https://reader036.fdocuments.in/reader036/viewer/2022083005/56649f2a5503460f94c44db5/html5/thumbnails/6.jpg)
MEF-ItemsIN.2.4 - Counting rooms EN-MEF 96,000
Barracks 96,000 12kCHF x 8
IN.2.5 - Gas network 130,700
Neutral gas network and panel(s) in extension 130,700
IN.2.6 - Metal structures EN-MEF or GS (tbc) 193,200
Metal structure which are not included in CE-workpackage
Platform, walkways and gridded separations 140,250
Staircases and ladders (crinolines) 52,950
IN.2.7 - Doors EN-MEF 20,500
Personnel and motorized doors 20,500
!
![Page 7: Budget specification EHN1 Extension: Infrastructure (WG2) Mats Wilhelmsson 17 September 2015.](https://reader036.fdocuments.in/reader036/viewer/2022083005/56649f2a5503460f94c44db5/html5/thumbnails/7.jpg)
GS-ASE Items
IN.2.8 - Alarms - and detection GS-ASE 150,000 Estimate by MW (wait for a refined quote from GS)
Fire detection
ODH detection
Evacuation alarm
IN.2.9 - Personnel access GS-ASE 50,000
Access system for machine/detectors is in WG3
SUSI access and video 50,000 6 doors + 5 surveillance cameras
!
![Page 8: Budget specification EHN1 Extension: Infrastructure (WG2) Mats Wilhelmsson 17 September 2015.](https://reader036.fdocuments.in/reader036/viewer/2022083005/56649f2a5503460f94c44db5/html5/thumbnails/8.jpg)
IT networks
IN.2.10 - IT networks IT/CS 88,700
Ethernet 46,000 67 UTP Ethernet sockets
Wi-Fi 18,500
15 UTP Ethernet and Wi-Fi Bases
Connection to fiber-optics network 24,200 22kE - Provided by EN/EL/CF
![Page 9: Budget specification EHN1 Extension: Infrastructure (WG2) Mats Wilhelmsson 17 September 2015.](https://reader036.fdocuments.in/reader036/viewer/2022083005/56649f2a5503460f94c44db5/html5/thumbnails/9.jpg)
Transport & handling
IN.2.11 - Transport and handling ΕΝ-ΗΕ 97,200
Heavy handling and transport for infrastructure work 97,200
two teams of two FTEs for a three months period
![Page 10: Budget specification EHN1 Extension: Infrastructure (WG2) Mats Wilhelmsson 17 September 2015.](https://reader036.fdocuments.in/reader036/viewer/2022083005/56649f2a5503460f94c44db5/html5/thumbnails/10.jpg)
Profile
PBS-ID Title 2015 2016 2017
IN.2.1 Ventilation, heating and air-conditioning 31’725 317’250 285’525
IN.2.2 Fluids- and water cooling 35’216 342’158 306’942IN.2.3 Electrical infrastructure and lights 103’371 465’169 465’169
IN.2.4 Counting rooms 76’800 19’200IN.2.5 Gas networks 39’210 91’490ÎN.2.6 Metal structures 154’560 38’640IN.2.7 Doors 20’500 IN.2.8 Alarms- and detection 75’000 75’000IN.2.9 Personnel access 50’000 IN.2.10 IT-networks 44’350 44’350IN.2.11 Transport- and handling 58’320 38’880 170’312 1’643’317 1’365’196