BTW 2012 Network Changes – 3 month rolling plan

11
1 The information contained in this Presentation is confidential information as per your terms and conditions with British Telecommunications plc (BT). Please treat it accordingly and do not forward, republish or permit unauthorized access. BT reserves the right to make changes to the information in this Presentation at any time without further notice . BTW Planned Engineering Works 90 day overview November 2013 to January 2014 These dates are indicative dates only and not to be used for any forecasting purposes as they are all subject to change. Please ensure that you wait for formal notifications from IRAMS.

description

BTW Planned Engineering Works 90 day overview November 2013 to January 2014 These dates are indicative dates only and not to be used for any forecasting purposes as they are all subject to change. Please ensure that you wait for formal notifications from IRAMS. - PowerPoint PPT Presentation

Transcript of BTW 2012 Network Changes – 3 month rolling plan

Page 1: BTW 2012 Network Changes – 3 month rolling plan

1

The information contained in this Presentation is confidential information as per your terms and conditions with British Telecommunications plc (BT).

Please treat it accordingly and do not forward, republish or permit unauthorized access.

BT reserves the right to make changes to the information in this Presentation at any time without further notice.

BTW Planned Engineering Works 90 day overview November 2013 to January 2014

These dates are indicative dates only and not to be used for any forecasting purposes as they are all subject to change. Please ensure that you wait for formal notifications from IRAMS.

Page 2: BTW 2012 Network Changes – 3 month rolling plan

2

BTW 2012 Network Changes – 3 month rolling plan

• Whilst BTW has continually worked to enhance its network, we are currently undergoing an exceptional level of change driven by four main drivers:-

– Stability – to improve the reliability of the network, BTW is targeting certain network elements with hardware and software improvements.

– Capacity – the need for additional capacity is driven by an increase in the number of broadband users on the 21C network (through migration from 20C and growth) and also by the ever-increasing bandwidth demands of those users.

– Resilience –to improve the resilience of the network , BTW is actively removing single points of failure from the network

– New Functionality – to meet the needs of the market BTW needs to enhance its network to deliver the services its customers require.

• This presentation outlines the key upgrade programmes, their drivers, customer impact and the number of upgrades per programme per week.

• BTW is keen to deliver all the required improvements as quickly as possible whilst actively managing the risk to customers. For this reason a range of run-rates against each programme has been outlined. The actual run-rates achieved will be determined by this ongoing live analysis of risk.

• Customer outage times for the PEWs start between 00:01 and 02:00 with the aim of completing customer impacting work by 06:00. This allows 2 hours for roll-back should the PEW be unsuccessful.

• Business as usual capacity upgrades and upgrades to resilient structures have not been listed here.

Page 3: BTW 2012 Network Changes – 3 month rolling plan

21C UpgradesProg No:

Upgrade Key Drivers Upgrades Complete / Total

EUs per upgrade

Upgrades per PEW

Affected Products

Av. End user outage (Mins)

Upgrades per week

Progress Planne

d EndN

ovD

ecJan

Feb

SVLAN moves

Capacity,Stability

Ongoing Av 800Min 0

Max 1000

9 WBC 35 Up to 75 Ongoing

2nd Vendor MSPE Software Upgrades

Functionality(LAG Support)

65/67 Non Service Impacting

0 None 0 4

Nov 13

7750 R10 Upgrade

Features (Ipv6), Vendor Support

78/2500 Av 3000 1 HE, WBC, WBMC

10 80

Aug 14

High ThroughputBEA-VS

Capacity 15/20 Av 300K 1 WBC / WCC

45 mins 1 Apr-14

BEA-VS Software Upgrade

Stability 0/20 Av 300K 1 WBC / WBMC /

WCC

Sub-second 1 Apr-14

6

SVLAN moves - these moves offload SVLAN’s (bundles of Broadband traffic) from one BRAS to another. This is carried out to alleviate capacity issues mplet

38Supports LAG functionality and also improved resilience performance.

45 Required to support IPv6 and due to current software going end of support

22Broadband capacity requirement

50Resolves software defect.

Microsoft Excel Worksheet

Page 4: BTW 2012 Network Changes – 3 month rolling plan

4

Ongoing 20C Upgrades Cont’d

Prog No:

Upgrade Key Drivers Upgrades Complete / Total

EUs per upgrade

Upgrades per PEW

Affected Products

Av. End user outage (Mins)

Upgrades per week

Progress Planne

d EndN

ovD

ecJan

Feb

ERX BRAS12.3

EoL 67/225 Av 11000Min 3000

Max 18000

2 IPSC 20 8Apr 14

DSLAM SDH Bypass (MSIP Closure)

MSIP Platform Closure

401/4620 700 15 IPSC 10 60Sep 14

44

46

Microsoft Excel Worksheet

Page 5: BTW 2012 Network Changes – 3 month rolling plan

5

Completed 20C Upgrades

1

14

2

10k BRAS SB11 Stability 122/122 Av 11000Min 3000

Max 18000

6 IPSC Up to 18 Apr 1336

Page 6: BTW 2012 Network Changes – 3 month rolling plan

6

Completed 21C Upgrades

Progr No:

Upgrade Key Drivers

Upgrades Complete / Total

BB EUs and/or Ethernet Circuits per upgrade

Upgrades per PEW

Affected Products

Av. End user outage (Mins)

Upgrades per week

Date Ende

d

High ThroughputBEA-VS

Capacity 5/5 Av 120K 1 WBC / WCC

45 mins 1 Jun 12

BRAS software Upgrade

Stability 193/193 Av 17000Max 32000

1 WBC / WBMC/

WCC

45 mins Up to 50 Jul 12

Copper MSANSoftware Upgrade

Stability / Capacity

5844/5844 Average 700

120 WBC /WBMC

30 mins 480 May 12

2nd vendor MSAN Upgrade

Stability 702/702 Average 700

40-50 WBC / WBMC/WCC

40 mins 200 - 250 Jul 12

2nd Vendor MSPE

Stability 51/51 Av 20k 1 WBC / WCC /

Ethernet

30 secs – 2 mins

2 Jan 13

22

26

27

30

23

Page 7: BTW 2012 Network Changes – 3 month rolling plan

7

Completed 21C Upgrades

Progr No:

Upgrade Key Drivers

Upgrades Complete / Total

BB EUs and/or Ethernet Circuits per upgrade

Upgrades per PEW

Affected Products

Av. End user outage (Mins)

Upgrades per week

Date Ende

d

BRAS 11.1.2.5 P8 Upgrade

Functionality (IPv6), stability.

243/243 BB EU’s per BRAS

Av 35000Max 45000

6 WBC / WBMC

45 Up to 24

BRAS software Upgrade

Stability 193/193 Av 17000Max 32000

1 WBC / WBMC/

WCC

45 mins Up to 50 Jul 12

Copper MSANSoftware Upgrade

Stability / Capacity

5844/5844 Average 700

120 WBC /WBMC

30 mins 480 May 12

2nd vendor MSAN Upgrade

Stability 702/702 Average 700

40-50 WBC / WBMC/WCC

40 mins 200 - 250 Jul 12

2nd Vendor MSPE

Stability 51/51 Av 20k 1 WBC / WCC /

Ethernet

30 secs – 2 mins

2 Jan 13

26

27

30

23

37

Page 8: BTW 2012 Network Changes – 3 month rolling plan

Broadband Services on 21CN

12

46

9

11

14

20 22

23

2628

29

31

3227

3834

40 3435

36

3739

44

45

45

45

45

46

47 48

1151

4946

39

3950

Page 9: BTW 2012 Network Changes – 3 month rolling plan

9

Ethernet Service on 21CN

Page 10: BTW 2012 Network Changes – 3 month rolling plan

10

Descriptions

Page 11: BTW 2012 Network Changes – 3 month rolling plan

11

Management of risk