BTS Installation Guideline for INWI Project-V1 8

download BTS Installation Guideline for INWI Project-V1 8

of 74

Transcript of BTS Installation Guideline for INWI Project-V1 8

  • 8/10/2019 BTS Installation Guideline for INWI Project-V1 8

    1/74

    BTS Installation Guideline for INWI Project

    2014-11-8 Huawei Confidential Page1, Total 74 ,

    BTS Installation Guideline

    for

    INWI Project

    Huawei Technologies Co., Ltd.

  • 8/10/2019 BTS Installation Guideline for INWI Project-V1 8

    2/74

    BTS Installation Guideline for INWI Project

    2014-11-8 Huawei Confidential Page2, Total 74 ,

    Document History

    Date Version Changes Author Email

    2009-10-18 V1.0 First draft issued Ge Ping [email protected]

    2009-10-23 V1.1 1. Add CPRI cable and jumper connection of DRFU

    and GRFU

    2. Add antenna system installation

    Ge Ping [email protected]

    2009-11-25 V1.2 1. Add guideline for battery cabinet installation

    2. Add guideline for E1 cable connection for

    cascade site

    3. Add guideline for alarm cable distribution

    Ge Ping [email protected]

    2010-1-11 V1.3 1. Add guideline for CDMA&GSM dual-band

    antenna installation

    Ge Ping [email protected]

    2010-1-13 V1.4 1. Add guideline for faulty antenna swap Ge Ping [email protected]

    2010-1-13 V1.5 1. Add guideline for DBS installation Ge Ping [email protected]

    2010-3-10 V1.5 1. Update guideline for DBS installation

    2. Change WANA to INWI

    Ge Ping [email protected]

    2010-4-22 V1.6 1. Add installation guideline for IBBS200T V302 Ge Ping [email protected]

    2010-5-13 V1.7 1. Add installation guideline for IBBS200T V303 Ge Ping [email protected]

    2010-5-14 V1.8 1. Add installation guideline for DC power cable

    connector making for TEC FAN in IBBS200T

    V303

    Ge Ping [email protected]

  • 8/10/2019 BTS Installation Guideline for INWI Project-V1 8

    3/74

    BTS Installation Guideline for INWI Project

    2014-11-8 Huawei Confidential Page3, Total 74 ,

    Content

    1.

    Key Principles ........................................................................................................................ 6

    2.

    Indoor BTS Installation .......................................................................................................... 7

    2.1.

    Overview of Huawei indoor BTS3900...........................................................................7

    2.2.

    CPRI cable layout (Singal cable between BBU and GRFU/DRFU) .............................7

    2.3.

    Cable routing of indoor BTS3900 .................................................................................9

    2.4.

    Fix the redundancy cable on top of the cabinet ......................................................... 10

    2.5.

    All cables should be layout straightly between cable ladder and cabinet ................. 11

    2.6.

    All power cables and signal cables should be covered by different cable ducts ....... 11

    2.7.

    DDF installation in the existing transmission cabinet ................................................ 12

    2.8.

    E1 transmission cable connection for normal sites ................................................... 12

    2.9.

    E1 transmission cable connection for cascade sites ................................................. 12

    2.10.

    E1 cable color sequence ........................................................................................... 13

    2.11.

    Alarm cable connection (From INWI alarm system to BTS) ...................................... 14

    2.12.

    The antistatic wrist strap should be installed in the BTS cabinet .............................. 15

    2.13.

    No any document and labels in the back of the cabinet door ................................... 15

    2.14.

    No any materials in the bottom of BTS ...................................................................... 15

    2.15.

    Label for power cable ................................................................................................ 16

    2.16.

    Label for CPRI cable (Singal cable between BBU and GRFU/DRFU) ...................... 17

    2.17.

    BTS Power on ............................................................................................................ 19

    2.18.

    Deal with the rubbish and clean up the shlelter ......................................................... 20

    3.

    Outdoor BTS Installation ..................................................................................................... 21

    3.1.

    Overview of Huawei outdoor BTS3900A ................................................................... 21

    3.2.

    CPRI cable layout (Singal cable between BBU and GRFU/DRFU) .......................... 22

    3.3.

    Cable routing of outdoor BTS3900A.......................................................................... 22

    3.4.

    PGND cable connection for outdoor BTS3900A ....................................................... 25

    3.5.

    All power cable and signal cable should be protected with metal pipe ..................... 26

    3.6.

    DDF installation in the existing transmission cabinet ................................................ 27

    3.7.

    E1 transmission cable connection for normal sites ................................................... 27

    3.8.

    E1 transmission cable connection for cascade sites ................................................. 27

    3.9.

    E1 cable color sequence ........................................................................................... 28

    3.10.

    Alarm cable connection (From INWI alarm system to BTS) ...................................... 30

    3.11.

    The antistatic wrist strap should be installed in the BTS cabinet .............................. 31

    3.12.

    No any materials in the bottom of APM30 ................................................................. 31

  • 8/10/2019 BTS Installation Guideline for INWI Project-V1 8

    4/74

    BTS Installation Guideline for INWI Project

    2014-11-8 Huawei Confidential Page4, Total 74 ,

    3.13.

    Make waterprof of the outdoor cabinets .................................................................... 32

    3.14.

    Label for power cable ................................................................................................ 33

    3.15.

    Label for CPRI cable (Singal cable between BBU and GRFU/DRFU) ...................... 33

    3.16.

    BTS Power on ............................................................................................................ 33

    3.17.

    Deal with the rubbish and clean up the sites ............................................................. 35

    3.18.

    IBBS200 (Big Battery Cabinet) installation ................................................................ 36

    3.19.

    IBBS200T (Small Battery Cabinet) installation .......................................................... 43

    3.20.

    IBBS200T V302 (Small Battery Cabinet) installation ................................................ 45

    3.21.

    IBBS200T V303 (Small Battery Cabinet) installation ................................................ 48

    4. DBS Installation ................................................................................................................... 54

    4.1.

    Overview of Huawei DBS3900 .................................................................................. 54

    4.2.

    BBU installation (for scenario 1&2, BBU in APM30) ................................................. 56

    4.3.

    DC power cable conection (for scenario 1&2, BBU in APM30) ................................. 56

    4.4.

    BBU installation (for scenario 3, BBU in transmission cabinet) ................................. 57

    4.5.

    DC power cable conection (for scenario 3, BBU in transmission cabinet) ................ 57

    4.6.

    DC power cable and CPRI cable in RRU .................................................................. 58

    4.7.

    Outside cables of RRU .............................................................................................. 59

    4.8.

    Keep necessary operation space between RRUs ..................................................... 59

    4.9.

    Battery installation for DBS3900 ................................................................................ 60

    4.10.

    Alarm cable connection (From INWI alarm system to BTS) ...................................... 61

    5. Antenna System Installation ............................................................................................... 62

    5.1.

    Install the antenna according to the IO parameters .................................................. 62

    5.2.

    Keep at least 1 meter distance between GSM and CDMA antennas ....................... 63

    5.3.

    Install the grounding cables for antennas .................................................................. 63

    5.4.

    Install the feeder clamps 1 pcs/ meter ....................................................................... 64

    5.5.

    Install the grounding cables for feeders .................................................................... 64

    5.6.

    Make waterproof to all outside conenctors ................................................................ 65

    5.7.

    Make labels for jumpers and feeders ........................................................................ 66

    5.8.

    Reserve spare space in cable tray for 3G in future ................................................... 67

    5.9.

    Reserve spare space in feeder window for 3G in future ........................................... 67

    5.10.

    Install CDMA&GSM dual-band (Bi-technology) antenna........................................... 68

    5.11.

    GSM antenna swap for faulty antenna with high VSWR ........................................... 69

    6. BTS Integration ................................................................................................................... 70

    6.1.

    Hardware Ready for Integration ................................................................................ 70

  • 8/10/2019 BTS Installation Guideline for INWI Project-V1 8

    5/74

    BTS Installation Guideline for INWI Project

    2014-11-8 Huawei Confidential Page5, Total 74 ,

    6.2.

    Transmission Ready for Integration........................................................................... 70

    6.3.

    Hardware and Transmission Ready for Integration ................................................... 71

    6.4.

    BTS Integration .......................................................................................................... 71

    6.5.

    Tools and Materials for Site Engineer for BTS Integration ........................................ 72

    6.6.

    BSC Engineer for BTS Integration............................................................................. 72

    6.7.

    Possible Problem for BTS Integration and Solution .................................................. 72

    6.8.

    BTS Integration Status Check ................................................................................... 74

  • 8/10/2019 BTS Installation Guideline for INWI Project-V1 8

    6/74

    BTS Installation Guideline for INWI Project

    2014-11-8 Huawei Confidential Page6, Total 74 ,

    1. Key Principles

    1. Before you enter the site, please call INWI NOC(529000800/529000604);

    2. Before you leave the site, please call INWI NOC(529000800/529000604);

    3. Before leaving the indoor site, please check the air conditioner is

    working normal and the light already power off;

    4. If there is any action which will cause the site down, please inform and

    discuss with Huawei and INWI. The dangerous action should get

    approval from Huawei and INWI before implementation;

  • 8/10/2019 BTS Installation Guideline for INWI Project-V1 8

    7/74

    BTS Installation Guideline for INWI Project

    2014-11-8 Huawei Confidential Page7, Total 74 ,

    2. Indoor BTS Installation

    2.1. Overview of Huawei indoor BTS3900

    900M S111 900M S222~S555 900M&1800M

    2.2. CPRI cable layout (Singal cable between BBU and GRFU/DRFU)

    900M 900M &1800M

    Notes: Only connect CPRI cable to down CPRI port (Not up CPRI port)!

  • 8/10/2019 BTS Installation Guideline for INWI Project-V1 8

    8/74

  • 8/10/2019 BTS Installation Guideline for INWI Project-V1 8

    9/74

    BTS Installation Guideline for INWI Project

    2014-11-8 Huawei Confidential Page9, Total 74 ,

    2.3. Cable routing of indoor BTS3900

  • 8/10/2019 BTS Installation Guideline for INWI Project-V1 8

    10/74

    BTS Installation Guideline for INWI Project

    2014-11-8 Huawei Confidential Page10, Total 74 ,

    2.4. Fix the redundancy cable on top of the cabinet

    Power CableAlarm Cable

    E1 Cable

  • 8/10/2019 BTS Installation Guideline for INWI Project-V1 8

    11/74

    BTS Installation Guideline for INWI Project

    2014-11-8 Huawei Confidential Page11, Total 74 ,

    2.5. All cables should be layout straightly between cable ladder and cabinetwithout any loop or angle

    2.6. All power cables and signal cables should be covered by differentcable ducts

    Cable duct for

    DC power cable

    Cable duct for

    E1 cable and

    alarm cable

  • 8/10/2019 BTS Installation Guideline for INWI Project-V1 8

    12/74

    BTS Installation Guideline for INWI Project

    2014-11-8 Huawei Confidential Page12, Total 74 ,

    2.7. DDF installation in the existing transmission cabinet

    2.8. E1 transmission cable connection for normal sites

    2.9. E1 transmission cable connection for cascade sites

    Huawei

    E1 DDF

    INWI IDU to up hop

    HuaweiRes onsible

    HuaweiRes onsible

    INWIRes onsible

    Huawei

    BBU INWI IDU to next hop

    INWI

    DDF

    HuaweiE1 DDF

    INWIDDF

    INWIIDU

    HuaweiRes onsible

    HuaweiRes onsible

    INWIRes onsible

    HuaweiBBU

    Huawei

    E1 DDF

    Huawei alarm

    DDF

    3 holes

    3 holes

  • 8/10/2019 BTS Installation Guideline for INWI Project-V1 8

    13/74

    BTS Installation Guideline for INWI Project

    2014-11-8 Huawei Confidential Page13, Total 74 ,

    2.10. E1 cable color sequence

    E1 PIN Wire Color Remarks Huawei E1 DDF port

    No.1 E1

    X.19 gray TX+ 1

    X.20 white TX- 2

    X.1 blue RX+ 3

    X.2 white RX- 4

    No.2 E1

    X.21 blue TX+ 5

    X.22 red TX- 6

    X.3 orange RX+ 7

    X.4 white RX- 8

    No.3 E1

    X.23 orange TX+ 9

    X.24 red TX- 10

    X.5 green RX+ 11

    X.6 white RX- 12

    No.4 E1

    X.25 green TX+ 13

    X.26 red TX- 14

    X.7 brown RX+ 15

    X.8 white RX- 16

  • 8/10/2019 BTS Installation Guideline for INWI Project-V1 8

    14/74

    BTS Installation Guideline for INWI Project

    2014-11-8 Huawei Confidential Page14, Total 74 ,

    2.11. Alarm cable connection (From INWI alarm system to BTS)

    Alarm cable distribution in UPEU The alarm label should be printed

    and sticked on the DDF

    Label for Alarm

    DDF.xls

    Huawei

    Alarm DDF

    INWI

    Alarm System

    HuaweiRes onsible

    INWIRes onsible

    Huawei

    BBU

    Huawei alarm DDF

    Huawei

    E1 DDF

    FANDCDUAlarm DDF

  • 8/10/2019 BTS Installation Guideline for INWI Project-V1 8

    15/74

    BTS Installation Guideline for INWI Project

    2014-11-8 Huawei Confidential Page15, Total 74 ,

    2.12. The antistatic wrist strap should be installed in the BTS cabinet

    2.13. No any document and labels in the back of the cabinet door

    2.14. No any materials in the bottom of BTS

  • 8/10/2019 BTS Installation Guideline for INWI Project-V1 8

    16/74

    BTS Installation Guideline for INWI Project

    2014-11-8 Huawei Confidential Page16, Total 74 ,

    2.15. Label for power cable

    Label in the bottom of BTS Label in the top of the BTS

    Label in INWI power cabinet

  • 8/10/2019 BTS Installation Guideline for INWI Project-V1 8

    17/74

    BTS Installation Guideline for INWI Project

    2014-11-8 Huawei Confidential Page17, Total 74 ,

    2.16. Label for CPRI cable (Singal cable between BBU and GRFU/DRFU)

    CPRI lable in BBU side:

    CPRI lable in GRFU/DRFU side:

  • 8/10/2019 BTS Installation Guideline for INWI Project-V1 8

    18/74

  • 8/10/2019 BTS Installation Guideline for INWI Project-V1 8

    19/74

    BTS Installation Guideline for INWI Project

    2014-11-8 Huawei Confidential Page19, Total 74 ,

    2.17. BTS Power on

    1. When should we power on BTS?

    1.1. For new sites, the BTS should be power on after hardware installation;

    1.2. For the sites which already installed, please power on the BTS when you enter

    the sites for clean up/ pre-acceptance/ acceptance with INWI.

    2. Measure input voltage before power on BTS and record the voltage value.

    The input voltage of the indoor BTS should be between -44V DC~-57V DC;

    The input voltage of the outdoor BTS should be between 180V AC~260V AC;

    3. If the voltage is out of the range, please record the problem and inform your

    PM to ask INWI to solve the rectifier problem.

    4. Indoor BTS power on sequence:

    1) Switch on the switch for 2G BTS in INWI power cabinet;

    2) Switch on FAN;

    3) Switch on BBU;

    4) Switch on UPEU (in BBU);

    5) Switch on GRFU/DRFU;

    DCDU01 in BTS3900 cabinet:

    5. Indoor BTS power off sequence:

    1) Switch off GRFU/DRFU;

    2) Switch off UPEU (in BBU);

    3) Switch off BBU;

    4) Switch off FAN;

    5) Switch off the switch for 2G BTS in INWI power cabinet;

  • 8/10/2019 BTS Installation Guideline for INWI Project-V1 8

    20/74

    BTS Installation Guideline for INWI Project

    2014-11-8 Huawei Confidential Page20, Total 74 ,

    2.18. Deal with the rubbish and clean up the shlelter

  • 8/10/2019 BTS Installation Guideline for INWI Project-V1 8

    21/74

    BTS Installation Guideline for INWI Project

    2014-11-8 Huawei Confidential Page21, Total 74 ,

    3. Outdoor BTS Installation

    3.1. Overview of Huawei outdoor BTS3900A

    900M S111 900M S222~S555 900M&1800M

  • 8/10/2019 BTS Installation Guideline for INWI Project-V1 8

    22/74

    BTS Installation Guideline for INWI Project

    2014-11-8 Huawei Confidential Page22, Total 74 ,

    3.2. CPRI cable layout (Singal cable between BBU and GRFU/DRFU)

    900M 900M &1800M

    Notes: Only connect CPRI cable to down CPRI port (Not up CPRI port)!

    3.3. Cable routing of outdoor BTS3900A

    Cable holes at the bottom of the BTS cabinet (RFC):

  • 8/10/2019 BTS Installation Guideline for INWI Project-V1 8

    23/74

    BTS Installation Guideline for INWI Project

    2014-11-8 Huawei Confidential Page23, Total 74 ,

    No. Item Description

    1 Left cable trough AC power cables, PGND cables and AC power cables from battery cabinet to APM30

    2 Right cable trough Battery power cable, E1 cables, alarm cable from battery cabinet to APM30

    3 Cable hole for Jumpers 1/2Jumpers

    4 Reserved cable hole CPRI cables and monitoring signal cable between two BTS.

    Cable holes at the bottom of the power cabinet (APM30):

    No. Description

    1 AC power cables and PGND cables

    2 CPRI cables between BTS cabinet and APM30 cabinet

    3 DC power cable from PDU to DCDU (Already connected before

    delivery)

    4 Battery power cable,E1 cables, alarm cable from battery cabinet to

    APM30

    The jumper holes can only used for jumpers:

  • 8/10/2019 BTS Installation Guideline for INWI Project-V1 8

    24/74

    BTS Installation Guideline for INWI Project

    2014-11-8 Huawei Confidential Page24, Total 74 ,

    Wrong connection of AC cable/PGND cable/battery cables.

  • 8/10/2019 BTS Installation Guideline for INWI Project-V1 8

    25/74

    BTS Installation Guideline for INWI Project

    2014-11-8 Huawei Confidential Page25, Total 74 ,

    3.4. PGND cable connection for outdoor BTS3900A

    The PGND cable from battery cabinet should be connected to thegrounding bar in APM30 cabinet.

  • 8/10/2019 BTS Installation Guideline for INWI Project-V1 8

    26/74

    BTS Installation Guideline for INWI Project

    2014-11-8 Huawei Confidential Page26, Total 74 ,

    3.5. All power cable and signal cable should be protected with metal pipe

    Metal pipe for

    E1 and alarm cable

    Metal pipe for

    AC power cable

  • 8/10/2019 BTS Installation Guideline for INWI Project-V1 8

    27/74

    BTS Installation Guideline for INWI Project

    2014-11-8 Huawei Confidential Page27, Total 74 ,

    3.6. DDF installation in the existing transmission cabinet

    3.7. E1 transmission cable connection for normal sites

    3.8. E1 transmission cable connection for cascade sites

    Huawei

    E1 DDF

    INWI

    DDF

    INWI IDU to up hop

    HuaweiRes onsible

    HuaweiRes onsible

    INWIRes onsible

    Huawei

    BBU INWI IDU to next hop

    HuaweiE1 DDF

    INWIDDF INWIIDU

    HuaweiRes onsible

    HuaweiRes onsible

    INWIRes onsible

    HuaweiBBU

    3 holes

    Huawei DDF Rack

  • 8/10/2019 BTS Installation Guideline for INWI Project-V1 8

    28/74

    BTS Installation Guideline for INWI Project

    2014-11-8 Huawei Confidential Page28, Total 74 ,

    3.9. E1 cable color sequence

    E1 PIN Wire Color Remarks Huawei E1 DDF port

    No.1 E1

    X.19 gray TX+ 1

    X.20 white TX- 2

    X.1 blue RX+ 3

    X.2 white RX- 4

    No.2 E1

    X.21 blue TX+ 5

    X.22 red TX- 6

    X.3 orange RX+ 7

    X.4 white RX- 8

    No.3 E1

    X.23 orange TX+ 9

    X.24 red TX- 10

    X.5 green RX+ 11

    X.6 white RX- 12

    No.4 E1

    X.25 green TX+ 13

    X.26 red TX- 14

    X.7 brown RX+ 15

    X.8 white RX- 16

  • 8/10/2019 BTS Installation Guideline for INWI Project-V1 8

    29/74

    BTS Installation Guideline for INWI Project

    2014-11-8 Huawei Confidential Page29, Total 74 ,

    The E1 cable should be grounded in the APM30 cabinet:

    E1 lighting-protection

    E1 grounding clip

    E1 cable from IDU

    From MW IDU

    To GTMU

    Metal shieldin la er 25 mm

    E1 grounding

    clip

  • 8/10/2019 BTS Installation Guideline for INWI Project-V1 8

    30/74

    BTS Installation Guideline for INWI Project

    2014-11-8 Huawei Confidential Page30, Total 74 ,

    3.10. Alarm cable connection (From INWI alarm system to BTS)

    Alarm cable distribution in UPEU The alarm label should be printed

    and sticked on the DDF

    Label for Alarm

    DDF.xls

    HuaweiAlarm DDF

    INWIAlarm System

    HuaweiRes onsible

    INWIRes onsible

    HuaweiBBU

    Huawei alarm DDF

    Huawei

    E1 DDF

    FMUA in BTS cabinet

    HPMI in APM30Alarm DDF

  • 8/10/2019 BTS Installation Guideline for INWI Project-V1 8

    31/74

    BTS Installation Guideline for INWI Project

    2014-11-8 Huawei Confidential Page31, Total 74 ,

    3.11. The antistatic wrist strap should be installed in the BTS cabinet

    3.12. No any materials in the bottom of APM30

  • 8/10/2019 BTS Installation Guideline for INWI Project-V1 8

    32/74

    BTS Installation Guideline for INWI Project

    2014-11-8 Huawei Confidential Page32, Total 74 ,

    3.13. Make waterprof of the outdoor cabinets

    Make waterproof of the 2

    cable holes of each cabinet

    Make waterproof of the 2

    cable holes of each cabinet

  • 8/10/2019 BTS Installation Guideline for INWI Project-V1 8

    33/74

    BTS Installation Guideline for INWI Project

    2014-11-8 Huawei Confidential Page33, Total 74 ,

    3.14. Label for power cable

    Label in INWI power cabinet

    3.15. Label for CPRI cable (Singal cable between BBU and GRFU/DRFU)

    Same standard with the indoor BTS

    3.16. BTS Power on

    1. When should we power on BTS?

    1.1. For new sites, the BTS should be power on after hardware installation;

    1.2. For the sites which already installed, please power on the BTS when you enter

    the sites for clean up/ pre-acceptance/ acceptance with INWI.

    2. Measure input voltage before power on BTS and record the voltage value.

    The input voltage of the outdoor BTS should be between 180V AC~260V AC;

    3. If the voltage is out of the range, please record the problem and inform your

    PM to ask INWI to solve the rectifier problem.

    4. Outdoor BTS power on sequence:

    1) Switch on the switch for 2G BTS in INWI power cabinet;

    2) Switch on AC Main in APM30;

    3) Switch on SW9 (DCDU0), SW8 (DCDU1), SW5 (BBU), SW4 (HEUA);

    4) Switch on UPEU (in BBU);

    5) Switch on FMUA (in BTS cabinet);

    6) Switch on GRFU/DRFU (in BTS cabinet);

    7) Switch on Battery after battery installation;

  • 8/10/2019 BTS Installation Guideline for INWI Project-V1 8

    34/74

    BTS Installation Guideline for INWI Project

    2014-11-8 Huawei Confidential Page34, Total 74 ,

    DC power switch 0~9 in APM30:

    Switch Switch Name Operation

    SW9 DCDU0 (30A) Need to switch on

    SW8 DCDU1 (30A) Need to switch on

    SW7 SPARE5 (30A)

    SW6 SPARE4 (30A)

    SW5 BBU (12A) Need to switch on

    SW4 HEUA (12A) Need to switch on

    SW3 SPARE3 (4A)

    SW2 SPARE2 (4A)

    SW1 SPARE1 (4A)

    SW0 SPARE0 (4A)

    5. Outdoor BTS power off sequence:

    1) Switch off Battery;

    2) Switch off GRFU/DRFU (in BTS cabinet);

    3) Switch off FMUA (in BTS cabinet);

    4) Switch off UPEU (in BBU);

    5) Switch off SW9 (DCDU0), SW8 (DCDU1), SW5 (BBU), SW4 (HEUA);

    6) Switch off AC Main in APM30;

    7) Switch off the switch for 2G BTS in INWI power cabinet;

    AC Main

    Battery Switch

    Switch 0~9

  • 8/10/2019 BTS Installation Guideline for INWI Project-V1 8

    35/74

    BTS Installation Guideline for INWI Project

    2014-11-8 Huawei Confidential Page35, Total 74 ,

    3.17. Deal with the rubbish and clean up the sites

  • 8/10/2019 BTS Installation Guideline for INWI Project-V1 8

    36/74

    BTS Installation Guideline for INWI Project

    2014-11-8 Huawei Confidential Page36, Total 74 ,

    3.18. IBBS200 (Big Battery Cabinet) installation

    Scenario 1: Have extra space for Huawei battery space

    Install Huawei battery cabinet in extra place.

    Battery layout in the battery cabinet:

    Huawei Battery Group 2

    Huawei Battery Group 1

    Power cable connection of scenario 1:

    Huawei Battery Group 1

    Huawei Battery Group 2

  • 8/10/2019 BTS Installation Guideline for INWI Project-V1 8

    37/74

    BTS Installation Guideline for INWI Project

    2014-11-8 Huawei Confidential Page37, Total 74 ,

    Scenario 2: No extra space for Huawei battery space

    Dismantle ZTE battery cabinet and install Huawei battery cabinet in original place.

    The ZTE battery and power cable will be reused.

    The ZTE battery cabinet can be removed as rubbish.

    Battery layout in the battery cabinet:

    Huawei Battery Group 2

    Huawei Battery Group 1

    ZTE Battery Group 2

    ZTE Battery Group 1

  • 8/10/2019 BTS Installation Guideline for INWI Project-V1 8

    38/74

    BTS Installation Guideline for INWI Project

    2014-11-8 Huawei Confidential Page38, Total 74 ,

    Power cable connection of scenario 2:

    Huawei battery cabinet installation after swap ZTE battery cabinet:

    Huawei Battery Group 1

    Huawei Battery Group 2

    ZTE Battery Group 1

    ZTE Battery Group 2

  • 8/10/2019 BTS Installation Guideline for INWI Project-V1 8

    39/74

    BTS Installation Guideline for INWI Project

    2014-11-8 Huawei Confidential Page39, Total 74 ,

    ZTE battery cabinet dismantling and Huawei battery installation steps:

    1) Check the AC power and battery is working normally for ZTE BTS;

    2) Switch off ZTE battery from ZTE BTS cabinet;

    3) Dismantle ZTE battery and battery cabinet;

    4) Install Huawei battery cabinet;

    5) Remove the battery switch from layer1 to layer3 in Huawei battery cabinet;

    6) Disconnect the RTN (+) power cable (red color) between two copper wiring bars

    (between layer2 and layer3);

    7) Disconnect the NEG (-48V) power cable (black color) between two copper wiring

    bars (between layer2 and layer3);

    8) Install ZTE battery and connect power cable to ZTE BTS;

    9) Install Huawei battery and connect power cable to Huawei BTS;

    Notes: There is no battery switch in ZTE battery cabinet. The switch for battery is in

    ZTE BTS cabinet.

  • 8/10/2019 BTS Installation Guideline for INWI Project-V1 8

    40/74

    BTS Installation Guideline for INWI Project

    2014-11-8 Huawei Confidential Page40, Total 74 ,

    Battery installation check

    1) Measure the battery voltage and make sure the value is -48V to -54V;

    2) Switch on battery in battery cabinet and APM30;

    3) Swith off the AC power to check if the battery is working normally or not;

    4) After the check, switch on the AC power finally.

    Do the same test for ZTE battery installation to check the ZTE battery is working

    normally.

    Battery Switch in APM30

    Battery Switch in battery cabinet

  • 8/10/2019 BTS Installation Guideline for INWI Project-V1 8

    41/74

    BTS Installation Guideline for INWI Project

    2014-11-8 Huawei Confidential Page41, Total 74 ,

    Temperature sensor connection in battery cabinet

    Connect battery temperature sensor to RTN+ connector in Huawei battery group 1.

    Alarm cable connection from battery cabinet to APM30

    Temperature alarm cable connection (orange white);

    Door alarm cable connection (green white);

    Temperature alarm and door alarm cable connection in battery cabinetion:

    To sensor

    To APM30

    To sensor

    To APM30

    White WhiteGreenOrange

    White Orange Green

    White

  • 8/10/2019 BTS Installation Guideline for INWI Project-V1 8

    42/74

    BTS Installation Guideline for INWI Project

    2014-11-8 Huawei Confidential Page42, Total 74 ,

    Temperature alarm and door alarm cable connection in APM30 cabinet:

    After the alarm cable installation, please contact BSC engineer to confirm thedoor open alarm of battery cabinet.

    Name ID PositionMobile-Phone No.

    EmailINWI IAM

    BTS Integration Hotline 0000001 BTS Integration Hotline 0646117035

    If the BTS integration hotline is busy, you can also contact with the following BSC engineers:

    EN NAQI Abdelilah WX22053 BSC Engineer for Integration 0646117029 0662120789 [email protected]

    Temperature alarm cable

    Door alarm cable

    mailto:[email protected]:[email protected]
  • 8/10/2019 BTS Installation Guideline for INWI Project-V1 8

    43/74

    BTS Installation Guideline for INWI Project

    2014-11-8 Huawei Confidential Page43, Total 74 ,

    3.19. IBBS200T (Small Battery Cabinet) installation

    There are 2 hardware versions of BTS3900A and IBBS200T: V302 and V303.

    1) IBBS200T(V302) using 25mm battery power cable with OT terminal;

    2) IBBS200T(V303) using16mm battery power cable with special connector;

    BTS3900A (V302) and IBBS200T (V302)

  • 8/10/2019 BTS Installation Guideline for INWI Project-V1 8

    44/74

    BTS Installation Guideline for INWI Project

    2014-11-8 Huawei Confidential Page44, Total 74 ,

    BTS3900A (V303) and IBBS200T (V303)

  • 8/10/2019 BTS Installation Guideline for INWI Project-V1 8

    45/74

    BTS Installation Guideline for INWI Project

    2014-11-8 Huawei Confidential Page45, Total 74 ,

    3.20. IBBS200T V302 (Small Battery Cabinet) installation

    IBBS200T V302

    BTS3900A V302

  • 8/10/2019 BTS Installation Guideline for INWI Project-V1 8

    46/74

    BTS Installation Guideline for INWI Project

    2014-11-8 Huawei Confidential Page46, Total 74 ,

    Battery power cable connection:

    Not used for INWI project

    Not used for INWI project

  • 8/10/2019 BTS Installation Guideline for INWI Project-V1 8

    47/74

    BTS Installation Guideline for INWI Project

    2014-11-8 Huawei Confidential Page47, Total 74 ,

    Alarm cable connection:

    After the alarm cable installation, please contact BTS integration hotline to

    confirm the door open alarm of battery cabinet.

  • 8/10/2019 BTS Installation Guideline for INWI Project-V1 8

    48/74

    BTS Installation Guideline for INWI Project

    2014-11-8 Huawei Confidential Page48, Total 74 ,

    3.21. IBBS200T V303 (Small Battery Cabinet) installation

    BTS3900A V303

    IBBS200T V303

  • 8/10/2019 BTS Installation Guideline for INWI Project-V1 8

    49/74

    BTS Installation Guideline for INWI Project

    2014-11-8 Huawei Confidential Page49, Total 74 ,

    Battery power cable connection:

    Battery cable connector in APM30H cabinet: Battery cable connector in IBBS200T cabinet:

  • 8/10/2019 BTS Installation Guideline for INWI Project-V1 8

    50/74

    BTS Installation Guideline for INWI Project

    2014-11-8 Huawei Confidential Page50, Total 74 ,

    TEC FAN power cable connection:

    Connection point for TEC FAN

    power cable in IBBS200T

    Connection point for battery

    power cable in IBBS200T

  • 8/10/2019 BTS Installation Guideline for INWI Project-V1 8

    51/74

    BTS Installation Guideline for INWI Project

    2014-11-8 Huawei Confidential Page51, Total 74 ,

    Make TEC FAN power cable connector:

    The DC power cable for TEC FAN should be made in site.

    Load 3 for TEC FAN

  • 8/10/2019 BTS Installation Guideline for INWI Project-V1 8

    52/74

    BTS Installation Guideline for INWI Project

    2014-11-8 Huawei Confidential Page52, Total 74 ,

  • 8/10/2019 BTS Installation Guideline for INWI Project-V1 8

    53/74

    BTS Installation Guideline for INWI Project

    2014-11-8 Huawei Confidential Page53, Total 74 ,

    Alarm cable connection:

    Alarm cable in IBBS200T cabinet (Ethernet cable, RJ45 connector):

    After the alarm cable installation, please

    contact BTS integration hotline to confirm

    the door open alarm of battery cabinet.

  • 8/10/2019 BTS Installation Guideline for INWI Project-V1 8

    54/74

    BTS Installation Guideline for INWI Project

    2014-11-8 Huawei Confidential Page54, Total 74 ,

    4. DBS Installation

    4.1. Overview of Huawei DBS3900

    For all DBS sites, the site survey should be performed with INWI maintenance

    engineers before equipment delivery and installation.

    During the site survey, the installation strategy (install BBU in APM30 or

    transmission cabinet)/space requirement/power requirement and cable connection

    should be confirmed and agreed with INWI maintenance engineers.

    TSSR for DBS3900

    Instalaltion

    Scenario 1: BBU in APM30 (on the ground), RRU in tower or Pole (3 Poles)

    APM30H V303

    RRU1RRU2

    RRU3

  • 8/10/2019 BTS Installation Guideline for INWI Project-V1 8

    55/74

    BTS Installation Guideline for INWI Project

    2014-11-8 Huawei Confidential Page55, Total 74 ,

    Scenario 2: BBU in APM30 (on the tower), RRU in tower or Pole (1 Pole)

    Scenario 3: BBU in transmission cabinet, RRU in tower or pole

    APM30 Cabinet

    BBU in transmission cabinet

  • 8/10/2019 BTS Installation Guideline for INWI Project-V1 8

    56/74

    BTS Installation Guideline for INWI Project

    2014-11-8 Huawei Confidential Page56, Total 74 ,

    4.2. BBU installation (for scenario 1&2, BBU in APM30)

    4.3. DC power cable conection (for scenario 1&2, BBU in APM30)

    DC power cable for HPMI

    DC power cable for BBU

    DC power cable for RRU1

    DC power cable for RRU2

    DC power cable for RRU3

  • 8/10/2019 BTS Installation Guideline for INWI Project-V1 8

    57/74

    BTS Installation Guideline for INWI Project

    2014-11-8 Huawei Confidential Page57, Total 74 ,

    4.4. BBU installation (for scenario 3, BBU in transmission cabinet)

    4.5. DC power cable conection (for scenario 3, BBU in transmissioncabinet)

    If the BBU was installed in the transmission cabinet (no APM30), the DC power

    switch for BBU and RRU should be provided by INWI in the transmission cabinet or

    DC power cabinet.

    DC Switch for BBU (5A~10A) 1 DC switch for BBU

    DC Switch for RRU (10A~20A) 1 DC switch for 1 RRU (3 switchs for 3 RRUs)

  • 8/10/2019 BTS Installation Guideline for INWI Project-V1 8

    58/74

    BTS Installation Guideline for INWI Project

    2014-11-8 Huawei Confidential Page58, Total 74 ,

    4.6. DC power cable and CPRI cable in RRU

    CPRI_W

    CPRI Cable to BBU

    DC Power Cable

  • 8/10/2019 BTS Installation Guideline for INWI Project-V1 8

    59/74

    BTS Installation Guideline for INWI Project

    2014-11-8 Huawei Confidential Page59, Total 74 ,

    4.7. Outside cables of RRU

    4.8. Keep necessary operation space between RRUs

    Jumpers

    Grounding

    Cable

    CPRI Cable

    RRU DC

    Power Cable

  • 8/10/2019 BTS Installation Guideline for INWI Project-V1 8

    60/74

    BTS Installation Guideline for INWI Project

    2014-11-8 Huawei Confidential Page60, Total 74 ,

    4.9. Battery installation for DBS3900

    Please refer to 3.22 IBBS200T V303 (Small Battery Cabinet) ins tallat ion

    Remark: IBBS200T can be installed with APM30H stackable:

  • 8/10/2019 BTS Installation Guideline for INWI Project-V1 8

    61/74

    BTS Installation Guideline for INWI Project

    2014-11-8 Huawei Confidential Page61, Total 74 ,

    4.10. Alarm cable connection (From INWI alarm system to BTS)

    Alarm cable distribution in UPEU The alarm label should be printed

    and sticked on the DDF

    Label for Alarm

    DDF.xls

    HuaweiAlarm DDF

    INWIAlarm System

    HuaweiRes onsible

    INWIRes onsible

    HuaweiBBU

    Huawei alarm DDF

    Huawei

    E1 DDF

    HPMI in APM30

    (if there is APM30)Alarm DDF

  • 8/10/2019 BTS Installation Guideline for INWI Project-V1 8

    62/74

    BTS Installation Guideline for INWI Project

    2014-11-8 Huawei Confidential Page62, Total 74 ,

    5. Antenna System Installation

    5.1. Install the antenna according to the IO parameters

    Design Sector 3

    AZ(Azimuth)

    HMA TER(Antennato roof)

    HMA SOL(Antenna

    to ground)Antenna 3

    ElectricalTilt

    MechanicalTilt

    H.BuildingPylne

    (m)

    Mast(m)

    230 8.8 31.3Agisson DXX-824-9601710-2170-6565-17.5i18i-MM

    4 4 22.5 9

    1. Mechanical Tilt

    2. Electrical Tilt

  • 8/10/2019 BTS Installation Guideline for INWI Project-V1 8

    63/74

    BTS Installation Guideline for INWI Project

    2014-11-8 Huawei Confidential Page63, Total 74 ,

    5.2. Keep at least 1 meter distance between GSM and CDMA antennas

    5.3. Install the grounding cables for antennas

    1

    meter

    About 2.5m between antenna and ground bar

  • 8/10/2019 BTS Installation Guideline for INWI Project-V1 8

    64/74

    BTS Installation Guideline for INWI Project

    2014-11-8 Huawei Confidential Page64, Total 74 ,

    5.4. Install the feeder clamps 1 pcs/ meter

    5.5. Install the grounding cables for feeders

    If the feeder is between 10m~40m, 3 points of cable grounding:

    Top of the tower/Tri-pole/ Guyed mast;

    Bottom of the tower/Tri-pole/ Guyed mast;

    Outside of feeder window;

    If the feeder is more than 40m, 4 points of cable grounding:

    Top of the tower/Tri-pole/ Guyed mast;

    Middle of the tower/Tri-pole/ Guyed mast;

    Bottom of the tower/Tri-pole/ Guyed mast;

    Outside of feeder window;

    Top of the tower/Tri-pole/ Guyed mast Middle of the tower/Tri-pole/ Guyed mast

    1m

    1m

    1m

    1m

  • 8/10/2019 BTS Installation Guideline for INWI Project-V1 8

    65/74

    BTS Installation Guideline for INWI Project

    2014-11-8 Huawei Confidential Page65, Total 74 ,

    Bottom of the tower/Tri-pole/ Guyed mast Outside of feeder window

    5.6. Make waterproof to all outside conenctors

  • 8/10/2019 BTS Installation Guideline for INWI Project-V1 8

    66/74

    BTS Installation Guideline for INWI Project

    2014-11-8 Huawei Confidential Page66, Total 74 ,

    5.7. Make labels for jumpers and feeders

    Antenna Jumper to feeder side

    Feeder close to antenna

    Feeder outside of feeder window

    Feeder inside of feeder window

    BTS Jumper to BTS side

    BTS Jumper to feeder side

    Feeder outside of feeder window

    Feeder close to antenna

    Feeder window

    Antenna Jumper to antenna side

  • 8/10/2019 BTS Installation Guideline for INWI Project-V1 8

    67/74

    BTS Installation Guideline for INWI Project

    2014-11-8 Huawei Confidential Page67, Total 74 ,

    5.8. Reserve spare space in cable tray for 3G in future

    5.9. Reserve spare space in feeder window for 3G in future

    2G3G

    2G 3G

  • 8/10/2019 BTS Installation Guideline for INWI Project-V1 8

    68/74

    BTS Installation Guideline for INWI Project

    2014-11-8 Huawei Confidential Page68, Total 74 ,

    5.10. Install CDMA&GSM dual-band (Bi-technology) antenna

    Connectors in CDMA&GSM antenna (View from Back face of the antenna)

    Connector in antenna bottom 45 45 45 45

    Jumer from BTS CDMA TX CDMA RX GSM TX GSM RX

    Stand Operation Procedure:

    On-tower Activity In-site Activity OMC ActivityStartTime

    EndTime

    Before enter the site, contact with INWI NOCBe informed siteenter

    9:30 9:30

    Install new feeder for GSMBTS

    Install GSM filter and connect to GSM BTS (ifGSM filter is needed for this site)Install CDMA filter

    9:30 13:00

    Connect GSM feeder to GSM filter (if GSM filter isneeded for this site)

    12:30 13:00

    Contact with INWI NOC before power off CDMABTS

    Be informed CDMABTS will be power off

    14:00 14:05

    Power off CDMA BTS 14:05 14:10

    VSWR test for existing CDMA sectors 14:10 14:30

    Dismantle and deliveryCDMA antenna from tower

    to site (sector by sector)

    Connect CDMA feeder to CDMA filter 14:30 15:30

    Delivery and install newCDMA&GSM dual-bandantennas from site totower (sector by sector)

    15:30 17:30

    Check Mechanical tilt andelectrical tilt

    VSWR test for new CDMA sectors (0.1) 17:30 17:45

    VSWR test for new GSM sectors (1.4) 17:45 18:00

    Troubleshooting if there is any VSWR problem

    Make waterproof for newantenna/jumper

    connectors

    18:00 18:30

    Power on CDMA BTS 18:30 18:35

    Power on GSM BTS 18:30 18:35

    Contact with INWI NOC after power on CDMABTS

    Alarm monitor forCDMA BTS

    18:35 18:40

    Contact with Huawei BTS integration hotline afterpower on GSM BTS

    Alarm monitor forGSM BTS

    18:40 18:45

    Troubleshooting if there is any BTS alarm

    Packing CDMA antennas with existing GSMpacking materials

    18:45 19:45

    Site cleaning 19:45 20:00

  • 8/10/2019 BTS Installation Guideline for INWI Project-V1 8

    69/74

    BTS Installation Guideline for INWI Project

    2014-11-8 Huawei Confidential Page69, Total 74 ,

    Contact with INWI NOC before leaving the site Leaving approval 20:00 20:00

    Delivery CDMA antenna to subcontractor'swarehouse

    20:00

    Notes:

    INWI NOC: 529000800/529000604

    Huawei BTS integration hotline: 0646117035

    5.11. GSM antenna swap for faulty antenna with high VSWR

    Stand Operation Procedure:

    On-tower Activity In-site ActivityOMC

    ActivityStartTime

    EndTime

    Enter the site 9:30 9:30

    Unpack the materials 9:30 10:00

    Record the Bar Code of new antenna(sector by sector)

    9:30 10:00

    Power off GRFU/DRFU 10:00 10:00

    Dismantle and delivery old GSMantenna from tower to site (sector bysector)

    10:00 11:00

    Delivery and install new GSM

    antennas from site to tower (sectorby sector) 11:00 12:30

    Check distance between GSM andCDMA antenna (1m) VSWR test for new GSM sectors (

    1.4)

    12:30 12:40

    Check antenna Azimuth and Height 12:40 12:50

    Check Mechanical tilt and Electricaltilt

    Troubleshooting if there is any VSWRproblem

    12:50 13:00

    Make waterproof for newantenna/jumper connectors

    13:00 13:15

    Power on GRFU/DRFU 13:15 13:15

    After 10 minutes, contact with INWI

    NOC/Huawei BTS integration hotlineto check the alarm

    Alarm

    monitor forGSM BTS

    13:15 13:25

    Troubleshooting if there is any BTSalarm

    Site cleaning 13:25 13:30

    Delivery swapped GSM antenna tosubcontractor's warehouse

    Notes:

    INWI NOC: 529000800/529000604

    Huawei BTS integration hotline: 0646117035

  • 8/10/2019 BTS Installation Guideline for INWI Project-V1 8

    70/74

    BTS Installation Guideline for INWI Project

    2014-11-8 Huawei Confidential Page70, Total 74 ,

    6. BTS Integration

    6.1. Hardware Ready for Integration

    BTS was installed (with GRFU/DRFU);

    E1 cable was connected from BTS to INWI DDF;

    BTS was power on;

    6.2. Transmission Ready for Integration

    BSC engineer perform the loop test with INWI the check the E1 link from Microwave

    IDU to BSC

    Huawei

    BTS

    INWI

    DDFHuawei

    Responsible

    Huawei

    Responsible

    INWI

    Responsible

    Huawei

    BSC

    BTS Site BSC POP

    Huawei

    E1 DDF

    INWI

    ADM

    INWI

    ODF

    INWI

    IDU

    Soft-loop from INWI IDU

    to Huawei BSC

  • 8/10/2019 BTS Installation Guideline for INWI Project-V1 8

    71/74

    BTS Installation Guideline for INWI Project

    2014-11-8 Huawei Confidential Page71, Total 74 ,

    6.3. Hardware and Transmission Ready for Integration

    1. BTS was installed (with GRFU/DRFU);

    2. E1 cable was connected from BTS to INWI DDF;

    3. BTS was power on;

    4. E1 loop test was done by INWI&Huawei and the E1 link from IDU to BSC is OK;

    6.4. BTS Integration

    If the BTS is power on and E1 connection is done without problem, the BTS can be

    integrated automatically.

    If the BTS cant be integrated, site engineer should visit the sites for troubleshooting.

    For example, the following sites need to be visited for integration:

    No. BSC Site ID Hardware

    Installation

    Filter

    Installation

    and Power

    on

    TR Actived

    by INWI

    TR Loop Test by

    INWI&Huawei

    TR Ready

    for

    Integration

    Hardware

    and TR

    Ready for

    Integration

    Integration

    3 CAS_BSC1 CAS-1099 2009-9-5 2009-9-30 2009-9-3 2009-9-24 2009-10-3 2009-10-3 Need visit

    5 CAS_BSC1 CAS-1080 2009-9-7 2009-10-1 2009-9-3 2009-10-6 2009-10-6 2009-10-6 Need visit

    12 CAS_BSC1 CAS-1083 2009-9-6 2009-9-30 2009-9-3 2009-9-25 2009-9-25 2009-9-25 Need visit

    15 CAS_BSC1 CAS-1120 2009-8-5 2009-9-20 2009-9-25 2009-10-8 2009-10-8 2009-10-3 Need visit

    26 CAS_BSC1 CAS-1167 2009-7-22 2009-9-26 2009-9-3 2009-10-6 2009-10-6 2009-10-6 Need visit

    27 CAS_BSC1 CAS-1102 2009-9-5 2009-9-30 2009-9-3 2009-9-25 2009-9-25 2009-9-25 Need visit

    28 CAS_BSC1 CAS-1037 2009-9-15 2009-9-30 2009-9-3 2009-9-24 2009-10-3 2009-10-3 Need visit

    30 CAS_BSC1 CAS-1047 2009-9-5 2009-9-30 2009-9-3 2009-10-3 2009-10-3 2009-10-3 Need visit

    31 CAS_BSC1 CAS-1039 2009-9-5 2009-9-24 2009-9-3 2009-9-26 2009-10-3 2009-10-3 Need visit

  • 8/10/2019 BTS Installation Guideline for INWI Project-V1 8

    72/74

    BTS Installation Guideline for INWI Project

    2014-11-8 Huawei Confidential Page72, Total 74 ,

    6.5. Tools and Materials for Site Engineer for BTS Integration

    When you go to the sites, please take necessary tools and materials and try to close

    the installation problem in sites. Do not just record and report the problem.

    1) Master Key for sites;

    2) Multimeter;

    3) Krone E1 connection tool;

    4) E1 cable (20 meters);

    5) E1 loop cable;

    6) Key for Indoor BTS3900;

    7) Key for outdoor BTS3900A;

    8) Key for the outdoor transmission cabinet;

    9) DC power cable and connectors (10 meters);

    10) AC power cable and connectors (10 meters);

    6.6. BSC Engineer for BTS Integration

    When you enter the sites for BTS integration, please call BTS Integration Hotlineto

    check the BTS integration status with BSC engineer:

    Name ID PositionMobile-Phone No.

    EmailINWI IAM

    BTS Integration Hotline 0000001 BTS Integration Hotline 0646117035

    If the BTS integration hotline is busy, you can also contact with the following BSC engineers:EN NAQI Abdelilah WX22053 BSC Engineer for Integration 0646117029 0662120789 [email protected]

    6.7. Possible Problem for BTS Integration and Solution

    No Problem Solution

    1 Access problem (Owner refuse) Contact with INWI deployment engineer

    2 Access problem (No suitable key) Contact with INWI deployment engineer

    3 Access problem (Lock was broken) Use screw driver for help

    mailto:[email protected]:[email protected]
  • 8/10/2019 BTS Installation Guideline for INWI Project-V1 8

    73/74

    BTS Installation Guideline for INWI Project

    2014-11-8 Huawei Confidential Page73, Total 74 ,

    No Problem Solution

    4 BTS didnt power on Power on BTS

    5 E1 cable didnt be connected from BTS

    to INWI DDF

    Connect E1 cable

    6 E1 cable connection mistake; Reconnect E1 cable

    7 GRFU/DRFU board didnt be installed Record the problem and inform RPM

    8 Transmission problem Physic loop from Huawei DDF to BSC to

    check INWI transmission from IDU to BSC;

    (BSC engineer will check status)

    Physic loop from Huawei DDF to BTS to

    check the E1 cable connection;

    (If the LIU0 LED light is off, the E1 cable

    connection is OK)

    9 INWI didnt connect E1 cable from IDU

    to INWI DDF

    Contact INWI deployment engineer for

    help and connect the E1 cable by ourself

    10 INWI didnt remark TX/RX in INWI DDF Contact INWI deployment engineer forhelp and connect the E1 cable by ourself

    11 [Outdoor] INWI didnt connect AC

    power cable from TGBT to the fuse (for

    2G BTS)

    Record the problem and inform INWI

    deployment engineer and Huawei RPM

    12 [Outdoor] INWI didnt provide AC power

    cable from fuse (for 2G BTS) to BTS

    Connect the AC power cable by ourself

    13 [Outdoor] INWI outdoor power doesntwork

    Record the problem and inform INWIdeployment engineer and Huawei RPM

    14 [Outdoor] No key for INWI outdoor

    transmission cabinet

    Contact with INWI deployment engineer

  • 8/10/2019 BTS Installation Guideline for INWI Project-V1 8

    74/74

    BTS Installation Guideline for INWI Project

    6.8. BTS Integration Status Check

    1. If the LIU0 LED light is off, that means the transmission to BTS is OK,

    2. Also please check with BSC engineer that if he can see the BTS in BSC.

    If the BTS can be monitored in BSC, the BTS is integrated successfully!

    3. Check if there is any alarm of the BTS in site. All the LED lights should be off or

    green. No any redlight.

    LIU0 light should be off