    Presented by:

    Mathu Suthana KumaranDubai Cable Company, UAE

    To Maximize the PVCcompound output in PVC

    Compounding machineM/c 3001

  • 7/31/2019 BT - Silver - Ducab

    2/35

    2

    Ducab

    RawMaterials

    CopperRod Plant

    Copper wirerods &

    conductor

    PVCPlant

    Cables

    PowerCables

    High Voltage

    Medium Voltage

    Low Voltage

    SpecialPurpose low

    voltage range

    Ducab FR /Building Wire

    Instrumentation& Pilot

    Control &Auxiliary

    AccessoriesDucab

    Connect

    2.4 3.2 2.4

    2007 2008 2009

    Ducab Sales (AED bn)

    Over 900 employeesMulticultural 20 nationalities

    Dubai 3 Manufacturing Units

    Abu Dhabi

    3 Manufacturing Units

  • 7/31/2019 BT - Silver - Ducab

    3/35

    3

    DEFINE

  • 7/31/2019 BT - Silver - Ducab

    4/35

    4

    Business Case

    This project supports the companys objectives to producequality PVC compound in-house with maximum efficiency.

    The output of PVC compounds as of May 2008 manufacturedin-house is meeting the demands of Ducab-JA & Ducab -Abu

    Dhabi factories. Since Ducab added third manufacturingfacility in June 2008, the demand of the PVC compoundsincreased.

    To meet the PVC demands of all the three factories, thecurrent PVC output needs to be increased

  • 7/31/2019 BT - Silver - Ducab

    5/35

    5

    Opportunity

    The basic opportunity of this project is that if we are able toincrease the PVC production, we can reduce the quantity ofPVC required to be purchased externally.

    Currently( 2nd Jan to 31st May 08 ) the PVC output is in the

    range of 200 to 270 tonnes per week with an average of 255.5tonnes per week. This is sufficient to meet demand of onlytwo factories.

    To meet the demand of third factory, it is required to increasethe average PVC output to 320 tonnes per week. This demand

    will vary depending upon cable product mix. Cost benefit per tonne of PVC manufactured in-house is $174

    which equates to annual cost benefit ofAED 2.0 Million.See appendix -1 for basis of calculation.

  • 7/31/2019 BT - Silver - Ducab

    6/35

    8

    Project Plan

    Time scale

    Milestone July-08 Aug-08 Sep-08 Oct-08 Nov-08 Dec-08

    Form Team

    Finalize Charter

    Gather data

    Analyse data

    Select solution

    Interim report

    Meet management

    Develop plan to

    implement

    Closure &

    Recognition

  • 7/31/2019 BT - Silver - Ducab

    7/359

    Team Selected

    Matt Procter Process Owner / Sponsor

    Mathu Suthana Kumaran Green Belt

    Venkat Vardhan Purchasing OfficerNissam Ashraf Quality technician

    PVC Plant operatorsDay

    shift

    Operator

    PVC Plant operatorsNight

    shift

  • 7/31/2019 BT - Silver - Ducab

    8/3510

    PVC compound manufacturing process - SIPOC

    Suppliers

    Ducab

    RM Stores

    RM Stores

    RM stores

    RM storesRM stores

    RM stores

    Inputs

    PVC Resin

    Filler CalciumCarbonate

    Plasticizers

    Stabilizers

    Additives( Masterbatch,Lubricant etc )

    Pallets, Jumbobags

    Outputs

    PVC

    Compound

    Customers

    SupplyChainDepartment -

    Ducab

    Downloadrecipe from

    Plasmec Software

    Start Boundary

    Receipt of production order from Supply Chain department

    CompoundingProcess

    Loading ofraw materials

    QualityAssurance

    End BoundaryShift the finished PVC compound

    to Warehouse.

    All Inputs

    Check the weightand Pack inJumbo bags

    WIP WIP WIP WIP Book tostock

    WIP

    Process

  • 7/31/2019 BT - Silver - Ducab

    9/3512

    Functional Deployment Process Map for PVCCompounding process

    Production Order StartReceived P.O from

    Supply chain departmentLog in BaaN system Acknowledge P.O

    End

    Planning & materialpreparation

    Release P.O & plan theproduction

    Request raw materialsfrom warehouse

    Receipt of raw materialsin PVC plant & check

    the status

    Load raw materials intoSilo & feeder. Record in

    Plasmec software

    Compoundingprocess

    DownloadRecipe inplasmecsoftware.

    Runthe

    machine

    Visualinspectionof product

    Provide startSample to lab &

    label it withBatch number

    Ramp-upproduction

    Quality AssuranceCollect sample from

    Production runCheck the sample

    As per spec.Release batch

    number in system

    Packing &Book to stock Fill the material

    in Jumbo bagsLabel the bags

    Book to stockIn BaaN software

    Transfer goods towarehouse

    InspectionPass

    Set-upfollowspec

    DecideAccept ?

    Yes

    No

    Yes

    NoQuarantine

  • 7/31/2019 BT - Silver - Ducab

    10/3514

    Quick Win Solutions to increase the PVC compound output

    SOLUTIONS EASY TOIMPLEMENT

    FAST TOIMPLEMENT

    CHEAP TOIMPLEMENT

    WITHINAUTHORITY

    EASILYREVERSIBLE

    QUICKWIN?

    Cycle timeanalysis

    No No Yes Yes Yes No

    Replacement ofmixer blade in hotmixer

    No No No Yes Yes No

    To avoidmanufacturing Pre-coloured product

    No No Yes Yes Yes No

  • 7/31/2019 BT - Silver - Ducab

    11/3515

    Critical to Quality and Critical to Process Chart

    Voice of business Business issues Critical business requirement

    The company cannot continue tolose the output of the machine as

    well as to stop procuring thecompound externally which iscostly.

    To increase the PVC compoundoutput thereby reducing the

    machine downtime due tomaintenance, set-up and colorchange over time.

    Weekly average PVC compoundoutput target is set at 320 Tonnes/

    week

  • 7/31/2019 BT - Silver - Ducab

    12/3516

    MEASURE

  • 7/31/2019 BT - Silver - Ducab

    13/3517

    Input, Process and Output indicators

    InputIndicators

    Inputmeasures

    Raw materials

    Quality

    Stock out

    Customer

    forecast

    Supplier delivery

    People

    Process

    Indicators

    Output

    Performance

    Indicators

    Efficiencymeasures

    Machine utilizationtime

    Colour changerover time

    Set-up time

    Maintenance down

    time

    Machine planneddown time

    Hot mixer cycletime per batch

    CCR

    320tonnes ofPVCcompoundper week

    Effectivenessmeasures

    Weekly average PVCcompound output tonnes / week

  • 7/31/2019 BT - Silver - Ducab

    14/3521

    Measurement Plan

    PerformanceMeasure

    Operational

    Definition

    Data sourceand Location

    Samplesize

    Who willcollect thedata

    When will thedata becollected

    How will thedata becollected

    Other data thatshould becollected at thesame time.

    Weeklyaverage PVCcompoundoutput Tonnes / week

    Machine stopdue to breakdownwith date andtime ( Start )

    Machine startedrunning afterbreakdown withdate and time( End )

    Improvementanalysis data PVCCompoundingPlant

    Minimum 44weeks

    PVC plantoperators /Mathu

    2nd Jan 08 to

    1st Nov 08

    Systematicrecords ofmachinedowntime from2nd Jan 08

    Machine utilizationtime, Color changeover time, set-uptime, Plannedmachinedowntime,Maintenancedowntime & Stockout.

  • 7/31/2019 BT - Silver - Ducab

    15/3522

    Base line

    Data is normal

  • 7/31/2019 BT - Silver - Ducab

    16/3523

    Base line

    Data is not stable, hence Cpk not being computedMean = 259.4 ton

  • 7/31/2019 BT - Silver - Ducab

    17/3527

    Problem Statement

    Currently the average PVC output of 255.5 Tonnes per week meets the demand ofJA factory and M1 Abu dhabi factory. To meet the demand of M2 Abu dhabifactory, needs to maximize the output to 320 tonnes per week as a minimum target .

    Since m/c 3001 is the only compounding machine in Ducab and has to supply PVC

    compounds to across three Ducab sites, productivity improvement would reduce thenecessity to procure compound from external high cost suppliers.

    Since the total maintenance breakdown is reported as 8.47 %, our six sigma team hasdecided to analyze the machine efficiency data over the period Jan to May 2008 highlighteda major opportunity to investigate the downtime incurred due to leakage in cooling pipeline. The cause of the leakage was due to rusting in pipes. Over this period, 4.80% of

    machine time was lost to repair this pipeline leakage. As a consequence of this failure,additional time was also lost in shut down / start-up / set-up time on each occasion thepipe line failure is occurred. The combined lost opportunity was 14 % ( cooling pipe linefailure: 4.8% + other breakdowns: 3.66 % + set-up time : 5.52 %) and to target areduction.

  • 7/31/2019 BT - Silver - Ducab

    18/3528

    Why & Why Analysis

    Low output ofPVC compound

    Maintenancedowntime

    MoreSet-up

    Color change

    over time

    Leakage dueto rustingIn pipes

    Rusting becauseof poor quality

    of Coolant

    Investigate - 1Water / coolantLeakage in

    extruder coolingpipe lines

    Why ?

    Why ?

    Machineidle

    Why ?Why ?

    Why ?

    Why ? Why ?

    Why ?

    Machinebreakdowns

    Late responseto resolve

    the problem

    Why ?Investigate - 2

    P.O withmore

    product mix

    Why ? Stock outof raw

    materials

    Why ?

    Insufficientpersonnel

    Why ?

    Why ?Poor

    planning

    Investigate - 3

  • 7/31/2019 BT - Silver - Ducab

    19/3529

    Mechanical breakdowns duringJan to May 08 before 6 Sigma

    % Before 6 sigma 4.80 2.41 1.15 0.10

    Percent 56.7 28.5 13.6 1.2

    Cum % 56.7 85.2 98.8 100.0

    Breakdown details

    Oth

    er

    Totald

    own

    timedu

    eto

    mecha

    nical

    maintenan

    ce

    Totaldo

    wntim

    edu

    eto

    Ele

    ctric

    almainten

    ance

    Totald

    owntim

    edu

    eto

    leak

    agein

    extrud

    erpip

    es

    9876543210

    100

    80

    60

    40

    200%B

    efore6sigma

    Percent

    Pareto Chart of machine breakdown - before six sigma project

  • 7/31/2019 BT - Silver - Ducab

    20/3536

    IMPROVE

  • 7/31/2019 BT - Silver - Ducab

    21/3537

    SOLUTION EVALUATION CRITERIA

    Sl.

    No.

    Evaluation

    Criteria

    Importance

    Factor

    Remarks

    1 SIGMA IMPACT 10 This criteria describes the main goal of this project

    is PVC compound output Improvement. Thats why

    the Team decided to assign maximum importance to

    it i.e. 10 (in the scale of 1 to 10).

    2 TIME IMPACT 09 Time impact is also of prime importanceconsidering that, earlier the solutions are

    implemented, earlier the tangible benefits (towards

    availability of more machine time for Processing)

    shall be obtained. Thats why the Team decided to

    allocate its importance factor as 09.

    3 COST / BENEFITIMPACT

    05

    For implementation of these solutions, no extraexpenditure is required to be incurred. But once

    solutions are implemented, benefitsboth tangible

    & intangiblewill be obtained. Considering, this

    the team allocated importance factor as 05.

  • 7/31/2019 BT - Silver - Ducab

    22/3539

    SOLUTION SELECTION CRITERIA FOR IMPROVEMENT

    Sigma

    Impact

    Time Impact Cost / Benefit

    Impact

    Evaluation

    Criteria

    10 9 5 Importance

    Root Cause Probable Solutions Co-relation of Solutions to Criteria

    1

    Leakage in

    extruder

    pipe lines of

    extruder

    a) New fittings can be

    replaced for the coolingpipe lines whenever

    leakage is reported. To do

    this, spares to be available

    all the times in the stores.

    6 3 1 92

    b) Entire cooling pipe

    lines can be replaced with

    stainless steel pipes but it

    is not long-lasting

    7 6 1 129

    c) Anti-corrosive additive

    can be added in the coolant

    water tank along with soft

    water to avoid rusting in

    the fittings of the cooling

    pipeline of the extruder.

    9 9 4 191

  • 7/31/2019 BT - Silver - Ducab

    23/3540

    SOLUTION SELECTION CRITERIA FOR IMPROVEMENT

    Sigma

    Impact

    Time Impact Cost /

    BenefitImpact

    Evaluation

    Criteria

    10 9 5 Importance

    Root

    Cause

    Probable Solutions Co-relation of Solutions to Criteria

    2Number

    of

    machine

    set-up is

    high

    a) To reduce the machine downtime by

    doing preventive maintenance. 7 7 2 143

    b) To keep spare parts in stores in case

    of any mechanical or electrical

    breakdowns.

    6 5 1 110

    3

    More

    number

    of color

    change

    a) Production order to be prepared byproper planning to avoid product mix

    8 6 2 144

    b) To keep all the required raw

    materials in stock to avoid raw material

    stock out.

    8 8 3 167

  • 7/31/2019 BT - Silver - Ducab

    24/35

    45

    Implementation

    In order to exercise control over the improvedprocesses, operators are advised touse the pre-mixed anti-corrosive additive

    ( 0.5 % Drewgard 315 with soft water ) as acoolant.

    A can holding 20 litres of pre-mixed coolant is

    kept near the machine and operators will refillthe coolant into the coolant tank to maintainthe minimum level.

  • 7/31/2019 BT - Silver - Ducab

    25/35

    46

    ACTION PLAN - PILOT IMPLEMENTATION

    SL.

    NO.

    DESCRIPTION RESPONSIBILITY START

    DATE

    DUE DATE STATUS AND

    ACTIONS

    01 Initial Data Collection of machine efficiency and idle

    hours due to maintenance, set-up time, color change

    over time etc. Week wise performance

    Plant operators / Mathu 15nd July 08 25th July 08 Completed

    02 Addition of anti-corrosive additive in the coolant tank

    to prevent the leakage in extruder cooling pipe lines.

    Plant operators 1st June 08 2nd June 08 Completed

    03 To reduce the machine downtime by doing preventive

    maintenance

    Maintenance / Mathu 15th July 08 15th oct 08 Completed

    04 To keep all the required raw materials in stock to

    avoid raw material stock out.

    Venkat Vardhan / Mathu 10th July 08 15th Aug 08 Completed

    05 Monitoring and recording of machine downtime

    details to see the performance of new coolantweek

    wise performance

    Plant operators / Mathu 15th July 08 1st Nov 08 Completed

    06 Production order to be raised in a planned manner to

    avoid frequent product mix - week wise performance

    Venkat Vardhan 10st July 08 1st Nov 08 Completed

    07 Testing of PVC compound to check for any variation.

    daily performance review

    Nissam 2nd Jan 08 1st Nov 08 Completed

    08 Data collection of PVC compound outputweek wise

    performacne

    Mathu 2nd Jan 08 1st Nov 08 Completed

    09 Final Data Collection (for finding the entire machine

    idle hours )

    Plant operators / Mathu 2nd Nov 08 10th Nov 08 Completed

    10 Statistical Analysis & Final Conclusion Mathu 15st Nov 08 15th Jan 09 In progress

    ACTION PLAN : Data Period : 2ndJan 2008 to 1stNov 2008

  • 7/31/2019 BT - Silver - Ducab

    26/35

    48

    STATISTICAL EVALUATION OF IMPROVED DATA

  • 7/31/2019 BT - Silver - Ducab

    27/35

    57

    CONTROL

  • 7/31/2019 BT - Silver - Ducab

    28/35

    59

    Revised Functional Deployment Process Map for PVCCompounding process from June 2008 onwards.

    Production Order StartReceived P.O fromSupply chain department

    Log in BaaN system Acknowledge P.O End

    Planning & materialpreparation

    Release P.O & plan theproduction

    Request raw materialsfrom warehouse

    Receipt of raw materialsin PVC plant & checkthe status

    Load raw materials intoSilo & feeder. Record inPlasmec software

    Compoundingprocess

    DownloadRecipe inplasmecsoftware.

    Runthemachine

    Visualinspectionof product

    Provide startSample to lab &label it withBatch number

    Ramp-upproduction

    Quality Assurance Collect sample fromProduction runCheck the sample

    As per spec.Release batchnumber in system

    Packing &Book to stock Fill the material

    in Jumbo bagsLabel the bags

    Book to stockIn BaaN software

    Transfer goods towarehouse

    InspectionPass

    Set-upfollowspec

    DecideAccept ?

    Yes

    No

    Yes

    NoQuarantine

    Added in thechart afterImprovement

    CoolantLevelCheck

    Yes

    NoTop up thecoolant level

    P 1

    P 3

    P 2

  • 7/31/2019 BT - Silver - Ducab

    29/35

    60

    CONTROL MEASURESPROCESS CONTROL SYSTEM :

    Process Description : PVC Compounding process Process Customer : Supply Chain

    department

    Critical Customer Requirement : 320

    tonnes of PVC compound per week

    Activity in Flow-Chart Input-Process-

    Outcome

    Indicators

    Control

    Limits

    Checking Item Frequency Responsibilit

    y

    Contingency

    Action Plan

    Activity

    No.

    Activities Charts & Graph

    Type

    Specs /

    Target

    What to Check When to

    Check

    Who Checks Action Reqd. for

    Exception

    P 1 To check thecoolant level in the

    coolant tank before

    starting the

    machine

    Machine utilizationtime, machine down

    time due to leakage,

    planned down time

    & weely output

    checks

    Up themaximum

    level in the

    coolant tank

    Production lost inhours due to leakage

    in extruder pipelines

    Each andevery shift Plantoperators To inform Materialtechnologist

    P 2 Maintenance

    down time

    Machine downtime

    due mechanical,

    electrical, Leakage

    and weekly output

    checks

    As low as

    possible

    Production lost in

    hours due to

    breakdowns

    Each and

    every shift

    Plant

    operators

    To inform materials

    Technologist

    P 3 Productivity

    Improvement

    Hot mixer cycle

    time per batch,

    machine downtime,

    output checks, raw

    material stock out.

    320 tonnes

    of PVC

    compound

    per week

    To measure the

    production output

    weekwise

    Week wise Mathu To inform Materials

    Manager

    CONTD

  • 7/31/2019 BT - Silver - Ducab

    30/35

    62

    STANDARD TO BE FOLLOWEDSTANDARDS & PROCEDURES STATUS

    FOLLOWING TWO TARGETS HAVE BEEN DECLARED AS STANDARD

    IN PVC COMPOUNDING PLANT.

    A. IN ORDER TO EXERCISE CONTROL OVER THE IMPROVED

    PROCESSES, OPERATORS ARE ADVISED TO USE THE PRE-MIXED

    ANTI-CORROSIVE additive ( 0.5 % Drewgard 315 with soft ware ) AS A

    COOLANT. A CAN HOLDING 20 LITRES OF PRE-MIXED COOLANT ISKEPT NEAR THE MACHINE AND OPERATORS WILL REFILL THE

    COOLANT INTO THE COOLANT TANK TO MAINTAIN THE MINIMUM

    LEVEL OF THE COOLANT TANK.

    B. OPERATORS SHOULD RECORD THE DOWN TIME DETAILS ALONG

    WITH SET-UP TIME, COLOR CHANGE OVER TIME, MACHINE RUNTIME, PLANNED DOWN TIME AND PVC COMPOUND OUTPUT

    DETAILS IN THE FILE LOCATED IN SHARE DRIVE: PVC LOG SHEET

    :KPI -DATA

    INCORPORATED IN

    PROCESS

    SPECIFICATIONDu/PS/3001 ISSUED

    & IMPLEMENTED

    INCORPORATED IN

    PROCESS

    SPECIFICATION

    Du/PS/3001 ISSUED

    & IMPLEMENTED

  • 7/31/2019 BT - Silver - Ducab

    31/35

    63

    TRAINED ASSOCIATES

    SL.

    NO.

    TASKS PARTICIPANTS RESPONSIBILI

    TY

    TRAINING HELD

    ON

    01 SIX SIGMA INTRODUCTION &

    SUCCESS STORY FOR THE PROJECT.

    EMPLOYEES OF PVC

    COMPOUNDING PLANT

    & INTERNAL

    CUSTOMERS

    MATT PROCTER

    / MATHU

    7th JANUARY 09

    (1400 TO 1700

    HRS.)

    02 SIX SIGMA TARGETS OF PVC

    COMPOUND OUTPUT & AWARD

    PROPOSAL DAYS.

    PVC COMPOUNDING

    PLANT EMPLOYEES

    MATT PROCTER 14TH JANUARY 09

    (1500 TO 16:30

    HRS.)

    03 SUBMISSION OF CORRECT

    ESTIMATE IN PROPER FORMAT FOR

    SUCCESS OF SIX SIGMA.

    MATERIALS

    TECHNOLOGIST FROM

    PVC COMPOUNDINGPLANT

    MATHU 14TH JANUARY 09

    TO MATTPROCTER (

    MATERIALS

    MANAGERPVC

    COMPOUNDING

    PLANT

    (1000 TO 1200

    HRS.)

    TRAINING PROGRAM REGARDING SIX SIGMA AWARENESS :

  • 7/31/2019 BT - Silver - Ducab

    32/35

    64

    PROJECT BENEFITTANGIBLE BENEFIT :

    Calculation of Savings Summary

    Weekly average PVC compound output during Jan to May 08before implementation of Six sigma project. = 255.5 Tonnes

    Weekly average PVC compound output during June to Oct 08after implementation of Six sigma project = 316.0Tonnes

    . Increase in average ouput per week in Tonnes = 316 - 255.5

    = 60.5 Tonnes

    Increase in average output per annum in Tonnes = 60.5 x 52 weeks= 3146 Tonnes

    A cost benefit per tonne of compoundafter variable overheads + machine depreciation costs = $ 174

    Assuming a pessimistic cost benefit per tonne at $ 174 = $ 174 X 3146 Tonnes

    after variable overheads equates to an additional costsavings of

    = $ 547404

    = AED 2011709

    Potential savings in a year = AED 2.0 Million

  • 7/31/2019 BT - Silver - Ducab

    33/35

    Project Closure

    The improvement was accepted andappreciated by Ducab management.

    The progress and benefit of the project wereshared and verified with all Stakeholders.

    Team was rewarded with recognition in variousimprovement forums.

    The learning were used in other areas of cable

    manufacturing process especially the use ofcorrosion inhibitor was adopted in manymachines where water is being used as coolingmedium.

  • 7/31/2019 BT - Silver - Ducab

    34/35

    Questions