BrownField Girassol Pazflor Dalia Deep water brown-fields...
Transcript of BrownField Girassol Pazflor Dalia Deep water brown-fields...
Deep water brown-fields: TOTAL’s Approach on the support of the existing assets and their future developments
Girassol
Pazflor Dalia
Clov
Pascal CARRIER, Project Director - Total E&PNicolas HUET, Contract Manager- Total E&P Angola
ProjectosBrownFieldAngola
PBF MAIN STRATEGIES AXES
One single structure to manage all projects:Synergies & global view
Maximise synergiesMinimize shutdown
Project team based in the affiliate, close to the operations
Standardize equipments when possible
Develop Innovative Contracting strategies
Development of local content
Anticipation of future projects
Use of new technologies whenever added value is proven
Human resources
Other Green Field projects
Installation Vessels and Equipments
Accommodation vessel
Know how Experience
PlanningEconomics
Contractual Strategies
5
PBF ENTITY
PBF MAIN INTERFACES
6
HQ• Conceptual
studies• Pre-project
Affiliate
• Logistic• Drilling• Field Operation• GSR• P&D
Concessionaire
Partners
PBF Entities
PBF ORGANIZATION CHART
7
PBF Director
HSE
Service & Control
Field Operation
Engineering & Interfaces
Partner & SNL Relations
Architecture
Project Control
60% of resourcesShared between minimum 2 projects
PBF CHALLENGES
8
Management of Deep water Brown Field Projects with different maturities
and geographic locations
Optimize Local Content fabrication
and develop engineering
Integration of new Technologies in
existing facilities, and modifications
SIMOPS
Contractual strategies and
number of contracts
Cost Optimization and Economics
GIRRI ROSA MPP PROJECT
11
Existing GirassolFPSO
Existing Dalia FPSO
New MPP station P80 Rosa production loop
New MPP station P70 Rosa production loop
Pump Control module + IPC transformer
IPC transformer (Power sharing between FPSOs)
P80 spool repair In synergy with GirRI
M14Re-use of XT from
plugged well
MPP ACTIVATION PRINCIPLES
P > 200 bar
Hydrostatic head approx
70 bars
XT
Sea levelTopside
pressure: 30 bar
Flowing pressure120 bar
Network values fixed
Mid-Life WHFP: approx 130 bars
Pressure valuesfor illustration purpose
1500 m WD
FPSO
End of Life WHFP: approx 50 bars MPP HighBoostΔP between 50 and 120bar
Increased Draw dawnWell / Reservoir
Hydrostatic head approx
90 bars
Flowing pressure100 bar
Gas Lift Injection Impact
Initial WHFP: approx 160 bars
DALIA DEBOTTLENECKING
P21: Produced Water Treatment- Module: Buffers + pumps.- Reject surge drum replacement-
P41: Separation---
DALIA 1A PROJECT
14
• 7 additional oil producers• 2 flowbases to connect 2 oil producers on one manifold slot
• Installation of a 4th MeOH pump and individual flow control valves oneach umbilical at topsides to guarantee the preservation sequencewith 7 additional producers
• Upgrade of ICSS (Integrated control safety system)
• Upgrade the SPS control system
flowbase
ACACIA INFILLS
15
• 3 additional oil producers• 2 water injection wells
• 2 satellite manifolds (one production one injection) to connect 3 wells on one manifold slot• Use of Pazflor contract for XT order and addendum for to contract for satellite manifold
ACA 805 Manifold M41
ACA 809
ACA 814 ( Acacia A East)
ACA 813Satellite Manifold
ACA 817 ( Acacia D East)
Future Development
ZINIA PHASE2 - PROJECT
16
Topside integration work: 423t49 tie-ins (31 cold and 18 hot works)Gas-lift modification on S4 process deckWater injection modifications on S4 mezzanine deck
Subsea network:One 11’’ ID x 10.3 km EHT Pipe in Pipe flowline
Subsea tie-in on P40 production lineThree double Inline tees
One 8.5’’ ID x 13.6 km Water Injection line One 7’’ ID x 10.5 km non-insulated gas lift line
Main technical challenges: EHT qualification and SIMOPS works
PBF THANKS FOR THEIR SUPPORT
• SONANGOL : B17 Concessionnaire
• STATOIL: B17 Partner• EXXON: B17 Partner• BP: B17 Partner
19
DISCLAIMER AND COPYRIGHT RESERVATION
The TOTAL GROUP is defined as TOTAL S.A. and its affiliates and shall include the party making thispresentation.
– Disclaimer• This presentation may include forward-looking statements within the meaning of the
Private Securities Litigation Reform Act of 1995 with respect to the financial condition,results of operations, business, strategy and plans of Total that are subject to riskfactors and uncertainties caused by changes in, without limitation, technologicaldevelopment and innovation, supply sources, legal framework, market conditions,political or economic events.
• The TOTAL GROUP does not assume any obligation to update publicly any forward-looking statement, whether as a result of new information, future events or otherwise.Further information on factors which could affect the company’s financial results isprovided in documents filed by the TOTAL GROUP with the French Autorité desMarchés Financiers and the US Securities and Exchange Commission.
• Accordingly, no reliance may be placed on the accuracy or correctness of any suchstatements.
– Copyright• All rights are reserved and all material in this presentation may not be reproduced
without the express written permission of the TOTAL GROUP.
HYBRID LOOP MANAGEMENT
21
1. Production phase2. Depressurization and Well preservation3. Methanol plug injection (20 m3)4. SLIV and MHV opening5. DO circulation
SLIV MHV
22
LOCATION OF ANGOLAN PARTICIPING INDUSTRIES
Basic &Detailed Engineering Studies
Fabrication of manifolds, suction piles & topside modules
Fabrication of umbilical
Fabrication of manifolds & suction piles
Fabrication of topsides modules and structures
Fabrication of jumpers ,spools and SPS equipt.
LOCAL CONTENT
Overall construction workload: 10 million Man-hoursfrom 2011 to 2017