Brookline Reconstruction Project
Transcript of Brookline Reconstruction Project
Brookline Reconstruction ProjectPioneer Avenue to Starcamp Street
Project Sponsors
City of PittsburghPennsylvania Department of Transportation
Federal Highway Administration
Consultant TeamMichael Baker Jr., Inc. John J. Clark & Associates
Santangelo &Lindsay, Inc.
Brookline Boulevard Reconstruction Project:Here Tonight to:
Bureau of Transportation and Engineering / Department of Public Works / City of Pittsburgh
• Present Final Designs• Present Schedule for Construction
• Room Set Up:TablesBoards
Brookline Boulevard Reconstruction Project:Project Limits
Bureau of Transportation and Engineering / Department of Public Works / City of Pittsburgh
Pioneer
Starcamp
Brookline Boulevard Reconstruction Project:Project Development Process:
• Design Charrette• Development of Alternatives• Public Meeting #1 (December 2006)• Identify Preferred Alternative• Public Meeting #2 (May 2009)• Final Design• Public Meeting #3 (March 2012)• Construction
Bureau of Transportation and Engineering / Department of Public Works / City of Pittsburgh
Brookline Boulevard Reconstruction Project:Project Elements
• New Sidewalks/Crosswalks• Traffic Signals/Pavement Markings• Curb Extensions• ADA Ramps/Audible signals• Street Lighting• Street Trees / Landscaping• Roadway Mill/Pave/Markings
Bureau of Transportation and Engineering / Department of Public Works / City of Pittsburgh
Brookline Boulevard Reconstruction Project:Typical Roadway Pan
Bureau of Transportation and Engineering / Department of Public Works / City of Pittsburgh
Bureau of Transportation and Engineering / Department of Public Works / City of Pittsburgh
Brookline Boulevard Reconstruction Project:Typical Landscaping Plan
Bureau of Transportation and Engineering / Department of Public Works / City of Pittsburgh
Brookline Boulevard Reconstruction Project:Sidewalk Treatments
Brookline Boulevard Reconstruction Project:Lights and Furniture
Bureau of Transportation and Engineering / Department of Public Works / City of Pittsburgh
Bureau of Transportation and Engineering / Department of Public Works / City of Pittsburgh
Brookline Boulevard Reconstruction Project:Landscaping Palette
Bureau of Transportation and Engineering / Department of Public Works / City of Pittsburgh
Brookline Boulevard Reconstruction Project:Typical Landscaping Plan
Complete Designs June 2012Advertise Construction Aug. 2012Award Contract Sept. 2012Notice To Proceed Dec. 2012Start Construction March 2013
Phase 1A/1EPhase 1B/1DPhase 1C/1FPhase 2A/1CPhase 2B/2DPhase 2EPhase 3
FINISH CONSTRUCTION: November 2013
Brookline Boulevard Reconstruction Project:Project Schedule
Bureau of Transportation and Engineering / Department of Public Works / City of Pittsburgh
Brookline Boulevard Reconstruction Project:Construction Phasing
Bureau of Transportation and Engineering / Department of Public Works / City of Pittsburgh
Brookline Boulevard Reconstruction Project:Maintaining Traffic/Access
Bureau of Transportation and Engineering / Department of Public Works / City of Pittsburgh
Brookline Boulevard Reconstruction Project:
Bureau of Transportation and Engineering / Department of Public Works / City of Pittsburgh
QUESTIONS/COMMENTS
Brookline Reconstruction ProjectPioneer Avenue to Starcamp Street
Project Sponsors
City of PittsburghPennsylvania Department of Transportation
Federal Highway Administration
Consultant TeamMichael Baker Jr., Inc. John J. Clark & Associates
Santangelo &Lindsay, Inc.
Brookline Boulevard Reconstruction Project:Project Schedule
Bureau of Transportation and Engineering / Department of Public Works / City of Pittsburgh