Brookland/Turkey Thicket Community Meeting (Sept. 24th, 2013)
Brookland Middle School · 2014-07-18 · BROOKLAND COMMUNITY MEETING –MARCH 23, 2013...
Transcript of Brookland Middle School · 2014-07-18 · BROOKLAND COMMUNITY MEETING –MARCH 23, 2013...
BROOKLAND COMMUNITY MEETING – MARCH 23, 2013
Brookland Middle School
Neighbor Group Meeting
July 16, 2014
BROOKLAND COMMUNITY MEETING – MARCH 23, 2013
AGENDA / GOALS
• Introductions / Rules
• Construction Updates
• Design Update
• Mascot
• Public Art Selection
• Local Business Utilization
• DCPS Update / Expanding the SIT
• Next Steps / Q&A
BROOKLAND COMMUNITY MEETING – MARCH 23, 2013
BROOKLAND MIDDLE SCHOOL
SITE PLAN
BROOKLAND COMMUNITY MEETING – MARCH 23, 2013
BROOKLAND MIDDLE SCHOOL
CONSTRUCTION UPDATES
• ONGOING & UPCOMING WORK
• Building Envelope
• Exterior Brick and Masonry
• Glass Installation
• Interior Drywall and Ceiling Grids
• Water and Sewer Connections at Shepherd Street
• Upcoming: Interior Finishes
BROOKLAND COMMUNITY MEETING – MARCH 23, 2013
BROOKLAND MIDDLE SCHOOL
CONSTRUCTION UPDATE
BROOKLAND COMMUNITY MEETING – MARCH 23, 2013
BROOKLAND MIDDLE SCHOOL
CONSTRUCTION UPDATES
BROOKLAND COMMUNITY MEETING – MARCH 23, 2013
BROOKLAND MIDDLE SCHOOL
CONSTRUCTION UPDATES
BROOKLAND COMMUNITY MEETING – MARCH 23, 2013
CONSTRUCTION UPDATE
PARK USAGE
WORK ACTIVITY TIMEFRAME
Ongoing DPR modernization of Turkey Thicket park COMPLETE
Baseball field and track closed during geothermal well drilling and
field restoration
COMPLETE
Basketball courts closed during expansion of Turkey Thicket
parking lot and basketball court relocation (*pending permits)
October –
December 2014
Two (2) Tennis courts closest to school not in use during school
structure and façade work
Present –
October 2014
All eight (8) tennis courts closed during court re-surfacing October 2014
BROOKLAND COMMUNITY MEETING – MARCH 23, 2013
CONSTRUCTION UPDATE
CONSTRUCTION ACTIVITY
INTERIORS
May 2013 – January 2015
Tennis courts get resurfaced
in October 2014
Parking lot expanded and basketball
courts relocated during Oct & Nov 2014
BROOKLAND COMMUNITY MEETING – MARCH 23, 2013
BROOKLAND MIDDLE SCHOOL
DESIGN UPDATE - INTERIORS
BROOKLAND COMMUNITY MEETING – MARCH 23, 2013
BROOKLAND MIDDLE SCHOOL
DESIGN UPDATE - INTERIORS
BROOKLAND COMMUNITY MEETING – MARCH 23, 2013
BROOKLAND MIDDLE SCHOOL
DESIGN UPDATE - GYM
BROOKLAND COMMUNITY MEETING – MARCH 23, 2013
BROOKLAND MIDDLE SCHOOL
DESIGN UPDATE – PERFORMANCE HALL
BROOKLAND COMMUNITY MEETING – MARCH 23, 2013
BROOKLAND MIDDLE SCHOOL
DESIGN UPDATE – OUTDOOR CLASSROOM
BROOKLAND COMMUNITY MEETING – MARCH 23, 2013
BROOKLAND MIDDLE SCHOOL
DESIGN UPDATE – MASCOT SELECTION
• Presented Mascot options to 4th
, 5th
, 6th
grade
students at: Brookland Educational Campus,
Burroughs, Langdon, Noyes at lunchtime
meetings .
• Students voted to rank the options in order of
preference
BROOKLAND COMMUNITY MEETING – MARCH 23, 2013
BROOKLAND MIDDLE SCHOOL
PUBLIC ART
• 97 Entries from 52 artists. 21 selected as semi-finalists
• Semi finalists announced for each area
• Entry Plaza (Community) - 8 semi finalists
• Atrium – likely hanging (Diversity) – 4 semi-finalists
• Outdoor Classroom (Sustainability) – 6 semi finalists
• Michigan Ave (Brookland) – 4 semi finalists
• Main Lobby (Performing Arts) – 6 semi finalists
• Semi-finalists toured the school in early May and proposals have
been submitted.
BROOKLAND COMMUNITY MEETING – MARCH 23, 2013
BROOKLAND MIDDLE SCHOOL
PUBLIC ART - ATRIUM SEMI-FINALISTS (SAMPLES)
BROOKLAND COMMUNITY MEETING – MARCH 23, 2013
BROOKLAND MIDDLE SCHOOL
PUBLIC ART – MICHIGAN AVE SEMI-FINALISTS (SAMPLES)
BROOKLAND COMMUNITY MEETING – MARCH 23, 2013
BROOKLAND MIDDLE SCHOOL
PUBLIC ART – ENTRY PLAZA SEMI-FINALISTS (SAMPLES)
BROOKLAND COMMUNITY MEETING – MARCH 23, 2013
BROOKLAND MIDDLE SCHOOL
PUBLIC ART – MAIN LOBBY SEMI-FINALISTS (SAMPLES)
BROOKLAND COMMUNITY MEETING – MARCH 23, 2013
BROOKLAND MIDDLE SCHOOL
PUBLIC ART – OUTDOOR RM SEMI-FINALISTS (SAMPLES)
BROOKLAND COMMUNITY MEETING – MARCH 23, 2013
BROOKLAND MIDDLE SCHOOL
CBE AND WORKFORCE
• Local Business Participation (CBE)
• $22.4 out of $37.5M (60% ) of construction subcontracts have
been awarded to District CBE firms
• 16 CBE firms currently working on project
• 7 of those firms are located in Ward 5
• Local Workforce Utilization
• Approximately 40% of all workers to date DC residents
• 10 workers hired from jobsite walk-ups!!
BROOKLAND COMMUNITY MEETING – MARCH 23, 2013
BROOKLAND MIDDLE SCHOOL
DCPS UPDATE
• Academic Planning Team and Office of Teaching and
Learning ramping up educational planning.
• Outreach to students and families to begin Fall 2014.
• School Improvement Team (SIT) to be expanded to
include staff and parents from four feeder schools
• Brookland @ Bunker Hill EC
• Burroughs EC
• Langdon EC
• Noyes EC
BROOKLAND COMMUNITY MEETING – MARCH 23, 2013
BROOKLAND MIDDLE SCHOOL
NEXT STEPS
• The next “Community Meeting” will be held in September
with a focus on Academics. Place and time TBD.
• The “Envelope Group” will meet again in September.
• Jobsite tours for SIT, envelope group, and community.
BROOKLAND COMMUNITY MEETING – MARCH 23, 2013
Questions & Answers