SCOPECEA Project Logistics Myanmar was contracted for the transportation and installation of two 18 Tonne vertical storage tanks at a Yangon brewery. The project would prove complex due to two cranes being required to operate in a very narrow location outside the facility.
BREWERY TA
NKS IN
STALLATIO
NLocations Yangon, My.
Duration 1 Day
Cargo Storage tanks x 2 18 Tonne Dimensions (m) W2.5xH15
Equipment Used Mobile crane 100 Tonne Tailing crane 30 Tonne Services Used Project Engineer Project Manager Special Projects Team
CASE STUDY CS024Brewery Tanks Installation 1/2
BREWERY TANKS INSTALLATION
PROJECT TEAMS PREPARE THE INSTALLATION SITE
CEA PROJECT LOGISTICS
G-18 PEARL CONDO
KABAR AYE PAGODA ROAD
BAHAN TOWNSHIP
YANGON
MYANMAR
+959 421 031 286
www.ceaprojects.com
BREW
ERY
TAN
KS IN
STA
LLAT
ION
Before the arrival of the tanks, CEA teams prepared the installation area and affixed anchor bolts to each concrete tank base. After the first tank had arrived both the 100 Tonne mobile crane and 30 Tonne tailing crane positioned themselves either side of the trailer in the narrow alley. All required slings were attached to both ends of the tank and the cranes began the lift.
Due to working in such a confined space each tank had to be lifted above and clear of the adjacent buildings, the crane then turned and lowered each tank onto its concrete base allowing for final alignment and the anchor bolts to be fixed.
CASE STUDY CS024Brewery Tanks Installation 2/2
ON-SITE SAFETY TOOLBOX TALK
CONCRETE BASE LOCATION FOR THE TANKS
FINAL ALIGNMENT
TAILING CRANE BEGINS LIFT
100 TONNE MOBILE CRANE MOVES THE FIRST TANK INTO POSITION
In advance of this operation, CEA Engineering submitted highly detailed lift plans for approval by the client.