Breaching the Mahar Regional School Dam Presentation to Ralph C. Mahar Regional School Committee GZA...

download Breaching the Mahar Regional School Dam Presentation to Ralph C. Mahar Regional School Committee GZA GeoEnvironmental, Inc. February 9, 2011.

If you can't read please download the document

Transcript of Breaching the Mahar Regional School Dam Presentation to Ralph C. Mahar Regional School Committee GZA...

  • Slide 1
  • Breaching the Mahar Regional School Dam Presentation to Ralph C. Mahar Regional School Committee GZA GeoEnvironmental, Inc. February 9, 2011
  • Slide 2
  • Presentation Outline Introductions Derek Schipper, P.E. and Greg Hunt GZA GeoEnvironmental, Inc., Norwood, MA Existing Site Information Project Background Summary of Dam Breach Feasibility Study Proposed Dam Breach Design Permitting & Construction Preliminary Cost Estimate Timeline Example Project Questions
  • Slide 3
  • Existing Site
  • Slide 4
  • Existing Dam Pond / Impoundment Dam Spillway & Low- level Outlet with Culvert through Dam Concrete Core Wall Around Spillway
  • Slide 5
  • Dam Information Mahar Regional School Dam: Dam Size: Small Hazard Rating: Significant Condition: Poor Main Deficiencies: Growth of trees throughout dam Erosion on top of dam and near waterline Embankment seepage
  • Slide 6
  • Project Background 1950s: Dam constructed 1960: Dam repaired following spillway damage 2005: New MA Dam Safety Regulations go into effect 2008: DCR Office of Dam Safety (DCR/ODS) ordered that dam be inspected by professional engineer July 2009: GZA performed Phase I Inspection/ Evaluation of Dam; found dam to be in Poor condition Sept. 2009: School District ordered by DCR/ODS to repair, breach, or remove dam by March 11, 2011and continue to have dam inspected every 6 months.
  • Slide 7
  • Project Background (Cont.) 2009 present: GZA has performed three 6-month inspections, dam found to be in similar condition 2010: School Committee approves plan to address condition of dam through dam removal/breach 2010: GZA prepares Dam Breach Feasibility Study to evaluate potential dam breach
  • Slide 8
  • Dam Breach Feasibility Study GZA Scope of Work: Extension request from DCR/ODS (11/30/2012 New Date) Field Work Site Survey, Wetland Resource Evaluation, Sediment Analysis Technical Analysis Hydrologic & Hydraulic Modeling, Conceptual Breach Design Permitting Investigation Estimate of project impacts and required local, state, and federal permits Cost Estimate & Funding Sources Cost estimate to perform dam breach & potential grants
  • Slide 9
  • Existing Site
  • Slide 10
  • Proposed Conditions Conceptual Design Restored Wetland & Upland Vegetation Remove Existing spillway/culvert. Excavated Breach Channel. Partial Removal of Core Wall Restored Gulf Brook Stream Channel
  • Slide 11
  • Proposed Conditions Conceptual Design Restored Gulf Brook Stream Channel Excavated Section of Dam for Breach Channel Concrete Core Wall to Remain Below Ground Stone Erosion Protection Grassed Slopes
  • Slide 12
  • Permitting & Construction Environmental Permitting: Numerous Local, State, and Federal permits required to work in wetland resource areas Permit process will likely lasts 9 months 1 year Final Design and Specifications: Prepare final design plans and specifications suitable for contractor bidding and construction Construction: Once Final Design is complete and permits are in place, work awarded to Contractor to perform breach work Construction to take about 4 weeks
  • Slide 13
  • Preliminary Cost Estimate Permitting & Final Design Engineering $ 85,000 Construction Work$ 170,000 Construction Contingency (25%)$ 43,000 Construction Engineering (5 weeks)$ 35,000 Total Estimated Cost$ 333,000
  • Slide 14
  • Preliminary Timeline Spring 2011: Submit Environmental Permitting Summer 2011: Final Engineering Design & Specifications Spring 2012: Award Construction Contract Summer 2012: Perform Dam Breach Work Fall 2012 - 2013: Revegetation Monitoring & Maintenance by Contractor Note: Under current timeline, dam breach work must be completed by November 30, 2012, and Six-Month Follow-Up Inspections of Dam must continue until work is completed.
  • Slide 15
  • Questions?
  • Slide 16
  • Before Dam Breach One Year After Dam Breach Example Project: Champlin Pond Dam Breach
  • Slide 17
  • Champlin Upper Pond Dam Removal Construction
  • Slide 18
  • From Left Abutment April, 2005
  • Slide 19
  • From Left Abutment September, 2005
  • Slide 20
  • From Left Abutment November, 2005
  • Slide 21
  • From Left Abutment August, 2006
  • Slide 22
  • Mouth of Channel November, 2005
  • Slide 23
  • Slide 24
  • Mouth of Channel June, 2006
  • Slide 25
  • From Right Abutment September, 2006
  • Slide 26
  • Discussion/ Questions.