Bray/ VAASO-Ported Series Knife Gate Valve

770/780 SeriesOperation and Maintenance Manual

Table of Contents

Definition of Terms 1

Safety Instructions 1

Introduction 2

Unpacking 2

Storage 2

Installation 2

Commissioning 3

Cylinder-Operated Valves 3

Manual Valves 3

Maintenance 4

Lubrication 4

Packing Replacement 5

Seat Replacement 5

Actuator Maintenance 6

Spare Parts 6

Packing Details 7

Troubleshooting 8

For information on this product and other Bray products please visit us at our web page - www.bray.com.

O-Ported SeriesOperations and Maintenance Manual

1

O-Ported SeriesOperation and Maintenance Manual

Definition of Terms - Safety Instructions

READ AND FOLLOW THESE INSTRUCTIONSSAVE THESE INSTRUCTIONS

DEFINITION OF TERMS

Indicates a potentially hazardous situation which, if not avoided, could result in death or serious injury

Indicates a potentially hazardous situation which, if not avoided, may result in minor or moderate injury

NOTICE Used without the safety alert symbol indicates a potential situation which, if not avoided, may result in an undesirable result or state, including property damage

HAZARD-FREE USEThis device left the factory in proper condition to be safely installed and operated in a hazard-free manner The notes and warnings in this document must be observed by the user if this safe condition is to be maintained and hazard-free opera-tion of the device assured

Take all necessary precautions to prevent damage to the valve due to rough handling, impact, or improper storage Do not use abrasive compounds to clean the valve, or scrape metal surfaces with any objects

The control systems in which the valve is installed must have proper safeguards to prevent injury to personnel, or damage to equipment, should failure of system components occur

QUALIFIED PERSONNEL• A qualified person in terms of this document is one who is familiar with the installation, commissioning, and operation

of the device and who has appropriate qualifications, such as:

• Is trained in the operation and maintenance of electrical equipment and systems in accordance with established safety practices

• Is trained or authorized to energize, de-energize, ground, tag, and lock electrical circuits and equipment in accordance with established safety practices

• Is trained in the proper use and care of personal protective equipment (PPE) in accordance with established safety practices

• Is trained in first aid

• In cases where the device is installed in a potentially explosive (hazardous) location – is trained in the commissioning, operation, and maintenance of equipment in hazardous locations

2

O-Ported SeriesOperation and Maintenance Manual

The valve must only be installed, commissioned, operated, and repaired by qualified personnel.

The device generates a large mechanical force during normal operation.

All installation, commissioning, operation, and maintenance must be performed under strict observation of all applicable codes, standards, and safety regulations.

Observe all applicable safety regulations for valves installed in potentially explosive (hazardous) locations.

INTRODUCTIONThe Bray/ VAAS Series 770/ 780 provides repeatable bidirectional shutoff in a rugged, double-piece cast body

Additional information about Series 770/ 780 valves – including application data, engineering specifications, and actuator selection is available from your Bray/ VAAS distributor or sales representative

UNPACKINGEnsure the box is not damaged externally Remove the valve from the packaging and check for any damage to the valve and its components during transit

Valve size and brief material specification of body (markings such as “SS” or “DI”) are marked on the valve body Stainless steel nameplate (below) fixed on to the yoke of valve contains most of the relevant information on the valve including Bray/VAAS work order number and unique serial number of the valve These details should be quoted for all requirements of service and spares

SERIAL NUMBER

SIZE MODEL FLG. DRILL BODY GATE

SEAT PACKING CWP MAX TEMP

STORAGEWrap the valve with a polyethylene cover Cover the ports for pneumatic actuator/accessories with plastic caps Store these valves in the same packing indoors and without direct exposure to the environment

INSTALLATION

• Valves can be mounted with flow in both directions

• Install the valve between flanges using fasteners & gaskets

• Bolt holes are always blind tapped and care should be taken not to bottom the bolts while tightening Refer to GA Drawing/ Technical Bulletin for quantity and size of blind tapped holes on valve chest area If the correct size bolts are not available, use studs and nuts for chest area bolts to avoid damage of body

3

O-Ported SeriesOperation and Maintenance Manual

Support should be used for valves size 8” and over when installed in vertical pipe Failure to do so can result in improper valve operation and/or valve failure

COMMISSIONING GUIDELINES

• Gland packing is tightened to hold the specified pressure and tested for no leakage before dispatch However, this may require some adjustment at site due to loosening in transit etc

• Check for gland leakage after the valve is subjected to pressure and if any leak is observed, tighten the gland uniformly in a cris-cross pattern until the leakage stops

Wrong electrical supply to accessories will damage the equipment Do not over tighten the gland nuts as this may cause excessive friction and premature damage to packing

Cylinder Operated Valves1 Connect instrument quality air, preferably through an air filter/regulator of adequate size The recommended air pres-

sure is 80-120 psi (5-8 bar) Refer to the appropriate bulletin/drawing for port and cylinder size details 2 Ensure the supply air is free from moisture, dirt, and other foreign particles Drain the filter regulator before operating

the actuator so that pipe rust and dirt if any in the air line will be removed before actuation 3 If valves are supplied with electrical accessories like limit switch and solenoid valve, ensure wiring is done as per local

electrical safety codes and regulations Ensure correct electrical supply is given to electrical accessories for proper func-tioning and safety of the equipment

4 Open the valve by energizing the solenoid valve/giving air supply to cylinder and operate the valve 2-3 times

Manual valvesOpen/Close the valve manually and observe valve operation

4

O-Ported SeriesOperation and Maintenance Manual

MAINTENANCE

NOTICE

Any modification or use of unauthorized parts voids any and all warranty considerations

LubricationThe manual valve stem should be lubricated at regular intervals for smooth operation of the valve A lubrication nipple is provided on the collar Cylinder operated valves do not require routine lubrication

NOTICE

If the cylinder actuator is disassembled for repair, the cylinder wall and seals need to be lubricated with a lithium-based grease prior to reassembly

Manual Valve Stem Cylinder Actuator

5

O-Ported SeriesOperation and Maintenance Manual

Packing Replacement

Relieve line pressure before loosening gland nuts to avoid injury and/or equipment damage

1 Relieve the line pressure

2 Fully close the valve

3 Ensure the line is empty, and flush if necessary

Manual Valves1 Ensure the valve is fully closed

2 Disconnect the stem from the gate by removing the clevis bolts & nuts (6)

3 Rotate the handwheel (1) counter-clockwise by holding the stem from rotation, so that the stem retracts fully from the gate

4 If valves are supplied with bellows, ensure stem is not rotating, as rotation will damage the bellows

5 Remove the gland nuts (2) and the gland (3)

6 Remove the old packing (4) from the packing chamber, one layer at a time, using a long thin tool to pry it out

7 Insert the new packing one at a time according to the illustration below Stagger the cut end of the packing so that they meet together and do not line up

8 Install the packing gland (3) and gland nuts (2)

9 Ensure the gap between the gland and the gate is uniform all around

10 Tighten the gland nuts finger tight plus one turn

11 For Series780, remove the gate cover at the bottom side and repeat the procedure as mentioned above for bottom packing replacements

12 Lower the stem by rotating the handwheel clockwise while holding the stem and fasten the stem to the gate with nuts & bolts

NOTICEIf leakage is observed from the packing area after installing the valve in the pipeline and the valve is pressurized or charged with media, tighten the gland nuts evenly side to side just enough to stop leakage Do not over-tighten the gland nuts

Seat Replacement1 Relieve the line pressure and close the valve Flush the line if necessary

2 Remove the valve from the line by loosening the flange mounting bolts, studs, and nuts

3 Clamp the valve in the vertical position to a fixture Do not block the valve port when clamping the valve An overhead

Quad Seal2” - 16”

“C” Packing PTFE18” and up

3 Layer Packing

4 Layer Packing

Packing Joint Angle 45°

1

4

2

3

5

6

6

O-Ported SeriesOperation and Maintenance Manual

hoist may be needed for larger size valves

4 Make sure the valve is in the open position

5 Replacing the seats does not require valve or actuator disassembly

6 Remove the seats on either side (which are drop-in fitted) and replace with new seats

7 Ensure alignment of the internal seat bores with same level

8 Seats require lubrication before installing A silicon-based lubricant is recommended (Applicable for Series 770)

ACTUATOR MAINTENANCE

Pneumatic CylinderThe Bray/ VAAS pneumatic cylinder actuator is a low maintenance design and does not require routine maintenance It has an FRP tube which is lubricated for life with a special coating on the inside wall Filtered dry, instrument quality air (non-lubricated) should be used for its operation at the specified air supply pressure

Recommended spare partsFollowing are parts recommended as spares, which may be stocked Following are general recommended spares for valves Provide the valve serial number and work order number from the nameplate for proper parts

• Gland packing

• Spare Seat

• Cylinder repair kit

7

O-Ported SeriesOperation and Maintenance Manual

Packing Details

Series 770

Valve Size (in ) Packing Size (mm) Length (mm) Packing Layers Quad Seal Layer Total Layers

2 Sq 8 235 2 1 3

3 Sq 8 275 2 1 3

4 Sq 8 400 2 1 3

5 Sq 8 425 2 1 3

6 Sq 8 475 2 1 3

8 Sq 8 545 2 1 3

10 Sq 8 650 2 1 3

12 Sq 8 775 3 1 4

14 Sq 10 925 3 1 4

16 Sq 10 1000 3 1 4

18 Sq 10 1100 3 1 4

20 Sq 16 1250 2 1 3

24 Sq 16 1440 2 1 3

Series 780

Valve Size (in ) Packing Size (mm) Length (mm) Total Layers

2 Sq 8 270 6

3 Sq 10 330 6

4 Sq 10 395 6

5 Sq 10 425 6

6 Sq 10 480 6

8 Sq 10 580 6

10 Sq 10 675 6

12 Sq 12 7 800 6

14 Sq 12 7 975 6

16 Sq 16 1150 6

18 Sq 16 1300 8

20 Sq 16 1375 8

24 Sq 16 1575 8

8

O-Ported SeriesOperation and Maintenance Manual

Troubleshooting

Trouble Possible cause Solution

Media oozing out of gland packing Packing deteriorated Replace packing

In fully closed position, valve leaks

Seat is worn out or torn Replace seat

Gate is scratched Replace gate

High torque during valve seating and unseating

Misalignment between gate and stem

a) Remove the clevis fastenersb) Loosen the superstructure fastenersc) Adjust the alignment of the stem and gated) Connect the clevis fastenerse) Retighten superstructure fasteners

Packing is not tighten properly Adjust gland nuts

Valve jerks during open and close

Superstructure fasteners loosen Tighten the super structure fasteners

Insufficient air supplyPneumatic operated valves: Increase supply pressure

Solenoid valve dust accumulation Remove and clean solenoid valve

Piston rod seal damaged Replace seal

All statements, technical information, and recommendations in this bulletin are for general use only Consult Bray/VAAS representatives or factory for the specific requirements and material selection for your intended application The right to change or modify product design or product without prior notice is reserved Patents issued and applied for worldwide

Bray® is a registered trademark ofBray International, Inc © 2015 Bray International, Inc All rights reserved

OM_O-Ported Series_12_20_2016

Bray/VAASDivision of Bray International, Inc 13333 Westland East Blvd Houston, Texas 77041Tel: 281 894 5454 • www bray com