braun_ma3_sm_04.doccvbcvb
description
Transcript of braun_ma3_sm_04.doccvbcvb
Chapter 4
Managerial Accounting 3e Solutions ManualChapter 4 Activity-Based Costing, Lean Operations, and the Costs of Quality
Chapter 4
Activity-Based Costing, Lean Operations, and the Costs of Quality
Quick Check
Answers:
QC4-1. dQC4-3. cQC4-5. cQC4-7. c QC4-9. a
QC4-2. dQC4-4. cQC4-6. dQC4-8. cQC4-10. c
Short Exercises
(5 min) S 4-1
a.
Product-level costs
b.
Activity-based costingc.
Internal failure costs
d.
Unit-level costs
e.
External failure costs
f.
Facility-level costs
g.
Kaizen
h.
Appraisal costs
i.
Takt time
j.
POUS
k.
TQM
l.Manufacturing cycle time
m.
Lean thinking
n.
Batch-level costs
o. Prevention costs
p. Activity-based management
q.
DOWNTIME (5 min) S 4-2
Req. 1
JOB 484Cutting DepartmentFinishing Department
Departmental overhead rate$12 per machine
hour$15 per direct
labor hour
Direct labor hours incurred in the Finishing Department 5 direct labor hours
Machine hours incurred in the Cutting Department 9 machine
hours
Allocation of manufacturing overhead$108$75
The total manufacturing overhead allocated to Job 484 is $183.
(continued) S 4-2
Req. 2
The manufacturing cost of Job 484 is determined by summing the three manufacturing costs assigned to the job.
Direct Materials$2,550
Direct Labor ($26 per hour 9 hours)234
Manufacturing overhead 183
Total Job Cost$2,967
(5-10 min) S 4-3
Req. 1
Manufacturing OverheadMachine HoursPlantwide Overhead Rate
$3,762,00017,100=$220 per machine hour
Req. 2
Production DepartmentsDepartmental Manufacturing OverheadMachine HoursDepartmental Overhead Rates
Potato Chips$2,147,000 11,300=$190 per machine hour
Corn Chips$959,000 2,600=$368.85 (rounded) per machine hour
Cheese Puffs$ 656,000 3,200=$205 per machine hour
TOTAL$3,762,00017,100
Req. 3
Potato ChipOvercosted
Corn ChipUndercosted
Cheese PuffsOvercosted
(5 min.) S 4-4
ActivityManufacturing OverheadCost DriverActivity Cost Allocation Rate
Preparation$610,000 10,000 preparation hours=$61 per preparation hour
Cooking and Draining$972,000 36,000 cooking and draining hours=$27 per cooking and draining hour
Packaging$320,000 4,000,000 packages =$0.08 per package
(5-10 min.) S 4-5
Req. 1 and 2
The total amount of manufacturing overhead allocated to the order (and the amount of manufacturing overhead per bag) is computed as follows:
Activity Cost Allocation RateUse of Cost DriverAllocated Manufacturing Overhead
$61 per preparation hour22 preparation hours$ 1,342
$27 per cooking and draining hour32 cooking anddraining hours864
$0.05 per package15,000 bags 750
TOTAL$2,956
Number of bags 12,000
Manufacturing overhead per bag $ 0.20 (rounded)
(continued) S 4-5Manufacturing overhead allocated=$2,956=$0.20
Number of units15,000per unit
Req. 3
In addition to the costs above, Uncle Joe needs to consider the direct materials and direct labor.
(5-10 min.) S 4-6
Req. 1
ActivityEstimated Total Manufacturing Overhead Costs
(A)Estimated Total Usage of Cost Driver
(B)Activity Cost Allocation Rate
(A B)
Machine setup$ 150,4502,950 set-ups$ 51 per setup
Machining$ 999,9005,050 machine hours$198 per machine hour
Quality control$ 339,7004,300 tests run$ 79 per QC test
Req. 2
Job Cost Record
JOB #557Manufacturing Costs
Direct Materials$1,350
Direct Labor:
Evan Berg: 9 $25 = $225
Stephanie Berg: 7 $32 = $224449
Manufacturing Overhead:
2 setups $51 / setup = $102
5 machine hours $198 /
machine hour = $990
2 tests $79 / test = $158 1,250
TOTAL JOB COST$3,049
(15-20 min.) S 4-7
Req. 1
Alloy Technology
Activity Cost Allocation
ActivityCost Allocated to Each Board
Start station
6$ 0.70=$ 4.20
Dip insertion
20$ 0.40=8.00
Manual insertion
9$ 0.60=5.40
Wave solder
6$ 6.40=38.40
Backload
7$ 0.60=4.20
Test
0.14$70.00=9.80
Defect analysis
0.17$60.00= 10.20
Total
$80.20
(continued) S 4-7
Direct materials cost.$56.00
Direct labor cost.$49.00
Activity costs allocated 80.20
Manufacturing product cost$185.20
Req. 2
Managers might favor this multiple-rate, activity-based costing system because it better pinpoints activities for planning and control and it provides more accurate data for product costing.
(15-20 min.) S 4-8
a.
Unit-level
b.
Facility-level
c.
Unit-level
d.
Product-level
e.
Product-level
f.
Facility-level
g.
Facility-level
h.
Batch-level
i.
Unit-level or Batch-level
j.
Product-level
k.Unit-level or Batch-level
l.
Unit-level
(15-20 min.) S 4-9
1.
Unit-level
2.
Product-level
3.
Unit-level
4.
Facility-level
5.
Facility-level
6.
Product-level
7.
Batch-level
8.
Product-level
9.
Facility-level
10.
Facility-level
(5 min) S 4-10
1. The company has very few indirect costs less likely
2.The company operates in a very competitive industry more likely
3.The company has re-engineered its production process but has not changed its accounting system more likely
4. In bidding for jobs, managers lose bids they expected to win and win bids they expected to lose more likely
5.The company produces few products, and the products consume resources in a similar manner less likely
6.The company produces high volumes of some of its products and low volumes of other products more likely
(10 min.) S 4-11
Req. 1
Indirect cost=Estimated total indirect costs
allocation rateEstimated direct labor hours
=$710,500
4,900 hours
=$145 / hour
Req. 2
WilsonNanry
Direct labor (95 hours $335 / hour)$31,825$31,825
Indirect costs (95 hours $145 / hour) 13,630 13,630
Total costs$45,455$45,455
Req. 3
WilsonNanry
Service revenue (160% $31,825)$50,920$50,920
Direct labor (from Req. 2) 31,825 31,825
Indirect costs (from Req. 2) 13,630 13,630
Total costs 45,455 45,455
Operating income$ 5,465$ 5,465
(5-10 min.) S 4-12
There are several warning signs that Sunflowers cost system may be broken:
1.One client is complaining that the firm's fees are too high, while another client is happy with the fees.
2.On a job where Schnell feels efficient, the client is complaining about the high fees.
3.On a complex job where Schnell feels less efficient, the client is happy with the fees.
4.Sunflowers competitor is able to undercut her fees.
5.Sunflowers cost system has not changed since the firm was founded.
6.Sunflower allocates indirect costs using a single allocation basedirect labor hours.
These signals suggest it is time for Schnell to reevaluate her cost system.
(5 min.) S 4-13
Mission, Inc.
ABC Cost Allocation Rates
Documentation PreparationInformation
Technology SupportTraining
Estimated indirect costs of
activity$144,500$119,000$447,000
Divide by estimated quantity
of cost allocation base 2,890 pages 700 applications 4,470 DL hrs.
Cost allocation rate for
activity$ 50 / page $ 170 / application$ 100 / DL hour
(10-15 min.) S 4-14
Req. 1
WilsonNanry
Direct labor (95 hours $335)$31,825$31,825
Documentation preparation:
(50 pages $50)2,500
(300 pages $50)15,000
Information technology support:
(1 application $170)170
(95 applications $100)13,260
Training (95 hours $100) 9,500 9,500
Total costs$43,995$69,585
Req. 2
WebbGreg
Service revenue (160% $31,825)$50,920$ 50,920
Direct labor 31,825 31,825
Indirect costs:
Documentation preparation2,50015,000
Information technology support17013,260
Training 9,500 9,500
Total costs$43,995$ 69,585
Operating income (loss)$ 6,925$(18,665)
(10-15 min.) S 4-15
a.
Value added
b.
Value added
c.
Non-value added
d.
Non-value added
e.
Non-value added
f.
Non-value added
g.
Non-value added
h.
Non-value added
(10-15 min.) S 4-16
1.
Value added
2.
Non-value added
3.
Value added
4.
Non-value added
5.
Value added
6.
Non-value added
7.
Non-value added
8.
Value added
9. Value added
10. Non-value added
(5-10 min.) S 4-17
a.
Lean
b.
Lean
c. Traditional
d.
Lean
e.
Lean
f.
Traditional
g.
Traditional
h.
Lean
i.
Lean
j.
Lean
k.
Traditional
l.
Traditional
m.
Lean
(5 min.) S 4-18
a. Not utilizing people to their full potential
b. Excess processing
c. Movement
d. Waiting
e. Defects
f. Overproduction
g. Transportation
h. Inventory
(10-15 min.) S 4-19
1. Repairing defective units found during inspection internal failure
2.Legal fees from customer lawsuits externalfailure
3.Inspecting products that are half the way through the production process appraisal
4. Redesigning the production process prevention5. Cost incurred producing and disposing of defective units internal failure6. Incremental cost of using a higher grade raw material prevention 7.Training employees prevention
8.Lost productivity due to machine breakdown internal failure9. Inspecting incoming raw materials appraisal
10. Warranty repairs external failure (10-15 min.) S 4-20
Req. 1
Cost (Benefit)
AnalysisCosts (Savings)
Prevention costs:
Negotiating with and training suppliers to obtain higher quality materials and on-time delivery$ 510,000
Redesigning the speakers to make them easier to manufacture1,409,000
Appraisal costs:
Additional 20 minutes of testing for each speaker600,000
Avoid inspection of raw materials(409,000)
Internal failure costs:
Rework avoided because of fewer defective units(652,000)
Avoid lost profits from lost production due to rework(307,000)
External failure costs:
Reduced warranty repair costs(202,000)
Avoid lost profits from lost sales due to disappointed customers (855,000)
Net cost (benefit) from implementing quality program$ 94,000
Req. 2
Boatsburg should not implement the new quality program. The company would lose $94,000 by implementing the new program.
(5-10 min.) S 4-21
1.
External failure cost
2.
External failure cost
3.
External failure cost
4.
Internal failure cost
5.
Appraisal cost
6.
Prevention cost
Exercises (Group A)
(15-20 min.) E 4-22A
Req. 1
Plantwide
overhead rate==Estimated total manufacturing costs
Estimated cost allocation base
==$1,150,000
25,000* direct labor hours
=$46 per direct labor hour
*When calculating plantwide overhead rates, all direct labor
hours incurred in the plant are used.
(continued) E 4-22A
Req. 2
Departmental overhead rate=Total department overhead
Cost allocation base (estimated)
Machining Dept. overhead rate=$825,000
13,750 machine hours
=$60 per machine hour
Finishing Dept. overhead rate=$325,000
13,000** direct labor hours
=$25 per direct labor hour
**When calculating the finishing departmental rate, only the direct labor hours incurred in the finishing department are used.
Req. 3
Overhead allocation based on single, plantwide rate:
Job 450Job 455
Cost allocation base (actual)5 DL hours5 DL hours
Plantwide cost allocation
rate $46/ DL hour $46 / DL hour
Overhead allocation$ 230$ 230
Req. 4
Overhead allocation based on departmental rates:
Job 450Job 455
Machining Department:
Departmental allocation rate$60/ MH$60/ MH
Machine hours used by Job 3 MH 6 MH
Overhead allocation$180$360
Finishing Department:
Departmental allocation rate$25/ DL hr$25/ DL hr
DL hours used by Job 4 DL hrs 3 DL hrs
Overhead allocation$100$75
Total overhead allocation (from
both departments$ 280$ 435
Req. 5
The single plantwide rate undercosts Job 450 and undercosts Job 455. Since Donovan sets the sales price at 125% of cost, and the job cost is affected by the allocation system used, the sales price will be affected by the allocation system used.
(15-20 min.) E 4-23A
Req. 1
West Horizon
Computation of Cost Allocation Rates
ActivityTotal Activity Overhead (est.)Cost Allocation Base (est.)Activity
Overhead Rate
Materials handling$13,2003,300 parts=$ 4 per part
Machine setup$ 5,20020 setups=$260 per setup
Insertion$49,5003,300 parts=$ 15 per part
Finishing $86,1002,100 hours=$ 41 per hour
Req. 2
The amount of manufacturing overhead to be assigned to Job 420 is computed as follows:
ActivityMOH Cost
Materials handling$ 400
Machine setup780
Insertion of parts1,500
Finishing 5,740
Total$8,420
Req. 3
The amount of manufacturing overhead to be assigned to Job 510 is computed as follows:
ActivityMOH Cost
Materials handling$ 1,700
Machine setup1,560
Insertion of parts6,375
Finishing 14,350
Total$23,985
(15-20 min.) E 4-24A
Req. 1
Total overhead $ 790,000
Total machine hours 10,000
Predetermined MOH rate$ 79
Cost of Job #356
Machine hours used100
POHR 79
Total MOH$ 7,900
Job #356traditional POHR
Direct material300 lbs. @ $50/lb.$ 15,000
Direct labor55 hrs. @ $20/hr.1,100
MOH 7,900
Total cost of job$ 24,000
(continued) E 4-24A
Req. 2
Job #356ABC
Direct material300 lbs. @ $50/lb.$ 15,000
Direct labor55 hrs. @ $20/hr.1,100
Machine hours100 2,500
No. of engineering changes6360
Pounds of hazardous waste generated50 15,000
Total cost of job$ 33,960
Req. 3
The estimate based on the activity-based costing (ABC) method provides more useful information. Activity-based costing (ABC) focuses on activities, rather than departments, as the fundamental cost objects. ABC recognizes that activities are costly to perform, and each product manufactured may require different types and amounts of activities. Thus, activities become the building blocks for compiling the indirect costs of products, services, and customers. Managers use ABC to more accurately estimate the cost of resources required to produce different products, to render different services, and to serve different customers.
(15-20 min) E 4-25A
Req. 1
Operating
overheadTotal professional hoursCurrent operating overhead allocation rate
$233,50010,000=$23.35 per
professional hour
Req. 2
Billing Calculations for the Lillian Yu Kitchen Remodeling Job
Based on current allocation system
Professional time (27 hours $63 per hour)$1,701.00
Operating overhead (27 hours $23.35 per hour) + 630.45
Total cost of job$2,331.45
Markup on cost 120%
Bill to client$2,797.74
Req. 3
ActivityCostTotal activity allocation baseActivity allocation rate
Transportation to clients$ 10,50015,000a=$0.70 / mile
Blueprint copying$ 37,0001,000b=$35 / copy
Office support$186,0005,000c=$38 / secretarial hour
To calculate the activity cost allocation rates, you must use the total activity for the year:
a 4,500 + 10,500 = 15,000
b 400 + 600 = 1,000
c 2,100 + 2,900 = 5,000
Req. 4
Total cost of jobxMarkup percentage=Amount billed to client
$2751.40x120%=$3,301.68
(continued) E 4-25A
Req. 5
The ABC billing system should be more fair to clients because they are charged according to the resources they used. For example, copying blueprints is very expensive. Under the fairer ABC system, clients are charged according to the number of blueprint copies their job required. The fairer system better recognized the extent to which operating costs are incurred by each unique client job.
(20-25 min.) E 4-26A
Req. 1
Total pharmacy rate (using number of prescriptions):
$190,000 / 25,000 = $7.60
Req. 2
Cost assigned using traditional overhead allocation
Used:Used by this order
Customer order #1247 (standard prescriptions)3$7.60
Req. 3
Cost assigned using traditional overhead allocation
Used:Used by this order
Customer order #1248 (complicated formulation)1$7.60
Req. 4
Cost PoolsEstimated CostCost DriversEstimated Cost Driver ActivityCost Pool Rate
Pharmacy Occupancy Costs$60,000Technician Hours75,000$0.80
Packaging Supplies$30,000Number of Prescriptions25,000$1.20
Req. 5
Customer order #1247 (standard prescriptions)
Used:Used by this orderABC assigned cost
Technician hrs. for order0.5$0.80$ 0.40
Number of prescriptions3$1.20$ 3.60
Pharmacist hours1$4.00$ 4.00
Total ABC Cost$ 8.00
Req. 6
Customer order #1248 (standard prescriptions)
Used:Used by this orderABC assigned cost
Technician hrs. for order0.5$0.80$ 0.40
Number of prescriptions1$1.20$ 1.20
Pharmacist hours2.5$4.00$ 10.00
Total ABC Cost$ 11.60
(continued) E 4-26A
Req. 7
The estimate based on the activity-based costing (ABC) method provides more useful information. Activity-based costing (ABC) focuses on activities, rather than departments, as the fundamental cost objects. ABC recognizes that activities are costly to perform, and each product manufactured may require different types and amounts of activities. Thus, activities become the building blocks for compiling the indirect costs of products, services, and customers. Managers use ABC to more accurately estimate the cost of resources required to produce different products, to render different services, and to serve different customers.
(20-25 min.) E 4-27A
Req. 1
First, compute the current plantwide manufacturing overhead rate:
Total manufacturing overheadTotal direct labor hoursPlantwide overhead rate
$820,00020,500=$40 per
direct labor hour
Then, apply it to the two products:
Manufacturing CostMedium
(42-inch)Large
(63-inch)
Direct materials$ 660,000$1,227,000
Direct labor 225,000 388,000
Manufacturing overhead:
(7,875 DL hours $40) = 315,000
(12,625 DL hours $40) = 505,000
Total manufacturing cost$1,200,000$2,120,000
Number of units produced 3,200 4,000
Cost per unit$ 375$ 530
Req. 2
First, compute the activity cost allocation rates:
ActivityActivity costTotal activity allocation baseActivity allocation rate
Materials handling$120,000600a=$200 / mat. order handled
Machine processing$600,00040,000b=$15 / machine hour
Packaging $100,00010,000c=$10 / packaginghour
You must use the TOTAL activity for the year as follows. Since Owens only manufactures two products, you add the activity of each of the individual products to find the total activity:
a 350 + 250 = 600
b 25,000 + 15,000 = 40,000
c 3,000 + 7,000 = 10,000
(continued) E 4-27A
Req. 2 (continued)
Then, apply them to the two products:
Manufacturing CostMedium
(42-inch)Large
(63-inch)
Direct materials$ 660,000$1,227,000
Direct labor 225,000 388,000
Manufacturing overhead:
Medium:
(350 material orders $200
= $70,000)
(25,000 machine hours
$15 = $375,000)
(3,000 packaging hours
$10 = $30,000)
Total allocation of overhead 475,000
Large:
(250 material orders $200
= $50,000)
(15,000 machine hours
$15 = $225,000)
(7,000 packaging hours
$10 = $70,000)
Total allocation of overhead 345,000
Total manufacturing cost$1,360,000$2,018,000
Number of units produced 3,200 4,000
Cost per unit$ 425.00$ 490.00
Req. 3
Medium Large
Cost per unit using current
system$ 375$ 530
Cost per unit using ABC 425 490
Overcosting / (Undercosting) ($ 50)$ 40
Number of units 3,200 4,000
Total cost distortion($160,000)$118,000
The Medium units had been undercosted and the Large units had been overcosted. Since Joness sets its sales price at 300% of manufacturing cost, the resulting sales price should have been about $150 higher for the Medium units and about $120 lower for the Large units. This helps to explain why Jones is the low cost leader for Medium plasma TVs, but faces competitive pressure on the Large plasma TVs.
(20-30 min.) E 4-28A
Req. 1
King
Total Budgeted Indirect Manufacturing Costs
ActivityBudgeted Quantity of Cost Allocation BaseActivity Cost Allocation RateTotal Budgeted Indirect Cost
Materials handling12,000a$ 3.75$ 45,000
Machine setups 30b$314.20 9,426
Insertion of parts12,000a $ 32.00384,000
Finishing 3,900c$ 54.00 210,600
Total budgeted indirect cost$649,026
__________
a (5 1,000) + (7 1,000)
b 15 + 15
c (1.1 1,000) + (3.1 1,000)
Req. 2
King
ABC Indirect Manufacturing Cost per Unit
ActivityCostAllocationRateQuantity of Cost Allocation Base
Used By:Allocated Activity Cost Per Wheel
StandardDeluxeStandardDeluxe
Materials handling$ 3.7557 $ 18.75$ 26.25
Machine setups$314.200.015*0.015* 4.71 4.71
Insertion of parts$ 32.0057160.00 224.00
Finishing$ 54.001.12.8 59.40 151.20
Total ABC allocated indirect cost$242.86$406.16
__________
*15 setups 1,000 wheels = 0.015 per wheel
Req. 3
Total budgeted manufacturing overhead=$649,026 (Req. 1)
Total budgeted direct labor hours=(1,000 2) + (1,000 3)
=2,000 + 3,000
=5,100
Plantwide overhead rate=$461,500
5,000
=$127.26 / DL hour
Manufacturing overhead cost per wheel:
Standard:
2.00 $127.26 = $254.52Deluxe:3.10 $127.26 = $394.51
(continues E 4-28A) (15-20 min.) E 4-29A
Req. 1
King
Total cost per unit using ABC Data
StandardDeluxe
Direct materials $ 32.00 $ 46.25
Direct labor45.0050.00
Manufacturing overhead 242.86 406.16
Total manufacturing cost$ 320.36$ 502.41
The gross profit (using ABC data) for the two models are:
King
Gross profit per unit using ABC Data
StandardDeluxe
Sales price $ 496.00 $ 670.00
Total manufacturing cost$ 320.36$ 502.41
Gross profit $ 175.64 $ 167.59
Req. 2
King
Total cost per unit using plantwide overhead rate
StandardDeluxe
Direct materials $ 32.50 $ 46.25
Direct labor45.0050.00
Manufacturing overhead 254.52 394.51
Total manufacturing cost$332.02$490.76
King
Gross profit per unit using plantwide overhead rate
StandardDeluxe
Sale price$496.00$670.00
Total manufacturing costs 332.02 490.76
Gross profit$163.98$179.24
Req. 3
The standard model is more profitable than the deluxe model. Activity-based costing data generally are more accurate than cost data generated by a plantwide overhead allocation rate. ABC systems have more cost categories (activities), each with its own allocation base. ABC cost assignments more accurately represent the cost of resources consumed to manufacture (and support) products.
Req. 4
The ABC system is likely to pass the cost-benefit test because King manufactures two different products that use different amounts of resources.
The old cost system appears broken because profits have been declining even though the company shifted its product mix toward the product that had appeared most profitable under the old system.
(15-20 min.) E 4-30A
Req. 1
Either the materials handling cost or the grinding cost is inaccurate. Both costs were assigned based on the number of parts. Thus, the ratio of Job 409 materials handling cost to Job 622 materials handling cost should be the same as the ratio of Job 409 grinding cost to Job 622 grinding cost. The materials handling cost ratio is 1:3, but the grinding cost ratio is 1:5. Job 622 cannot have three times as many parts as Job 409 and five times as many parts simultaneously.
Req. 2
The first step is to determine the allocation rate for each of the four activities:
Franklin Fabricators
ABC Allocation Rates
ActivityJob 622
Activity CostDivide by Quantity
of the Cost
Allocation BaseActivity Cost
Allocation Rate
Lathe work$20,000 62,500 turns $0.32 / lathe turn
Milling$25,000 1,000 hours $25 / machine hour
Grinding$ 1,800 2,500 parts $0.72 / part
Testing $ 3,000 375 units $8 / unit
The second step is to use the cost allocation rate for each activity to determine the quantity of the allocation base Job 409 used.
Franklin Fabricators
Quantity of the Allocation Base Used by Job 409
ActivityJob 409
Activity CostDivide by Activity Cost Allocation RateQuantity of the Allocation Base Used by Job 409
Lathe work$5,200 $0.32 / turn16,250 turns
Milling$3,700 $25 / hour148 hours
Grinding$ 360 $0.72 / part500 parts
Testing$ 120 $8 / unit15 units
Req. 3
Based on the ABC information, Franklin should not accept the company's offer to test units for $15 each. Franklins cost of performing this activity is only $8 per unit.
(15-20 min) E 4-31A
1. Inventory levels Lean production systems strive to maintain low inventory levels. Lean producers try to purchase raw materials just in time to meet the production schedule, and have the finished inventory ready just in time to meet customer demand. Traditional production systems maintain greater quantities of raw materials, work in process, and finished goods inventory.
2. Batch sizes Lean production systems produce units in much smaller batches than traditional production systems. These batches are demand-pulled through production, rather than pushed through production (like a traditional system), allowing the company to only produce what customers have ordered.
3. Set-up times Lean production systems stress short set-up times so that they can produce and deliver the product to the end customer in a very short amount of time. By keeping set-up times short, lean producers dont have to worry about keeping extra inventory on hand just to be able to quickly meet demand.
(continued) E 4-31A
4.Workplace organization Lean companies use a workplace organization system called 5s (sort, set in order, shine, standardize, sustain) to keep their work cells clean and organized. The goal of workplace organization is, a place for everything and everything in its place. By having a clean, well organized, ergonomic workplace, every employee within the work cell knows where to find the tools and supplies they need to do each job in the cell as efficiently as possible. A clean workplace also leads to fewer defects (due to contaminants), a safer work place, and fewer unscheduled machine repairs.
5. Roles of plant employees At lean producers, plant employees tend to have broader roles. They are cross-trained to perform about every role that is needed in each production cell. They set-up, operate, and repair the machines in the cell. They also perform the quality inspections. As a result, employees tend to have higher morale. Additionally, this decreases bottlenecks caused by having to wait for the right person to come do the job.
6. Manufacturing cycle times Lean producers put great emphasis on shortening their manufacturing cycle times. Lean producers need to have short cycle times since they have very little, if any, safety stock ready to sell to customers. By having short cycle times, they are able to fill customer orders quickly, keeping customers satisfied.
7. Quality Lean producers stress high quality in every aspect of production. Since lean producers do not carry much, if any stock, they need to be able to produce the product right, the first time. Lean producers tend to build-in quality, rather than inspect-in quality as traditional firms do.
(5-10 min.) E 4-32A
a. Movement
b. Excess processing
c. Not utilizing people to their full potential
d. Waiting
e. Defects
f. Transportation
g. Inventory
h. Overproduction
i. Waiting
j. Defects
k. Not utilizing people to their full potential
l. Transportation
m. Inventory
n. Movement
o. Overproduction
p. Excess processing
(15-20 min) E 4-33A
Req. 1
Cost of Quality Report for Healthy Snacks CorpTotal Costs of QualityPercentage of total costs of quality (rounded)
Prevention Costs:
Personnel training$ 28,000
Preventative maintenance 7,000
Total prevention costs$ 35,0004%
Appraisal Costs:
Inspecting products at half-way point$ 52,000
Inspection of raw materials 3,000
Total appraisal costs$ 55,0007%
Internal Failure Costs:
Production loss due to machine breakdowns$ 24,000
Cost of defective products93,000
Cost of disposing of rejected products 13,000
Total internal failure costs$130,00016%
External Failure Costs:
Recall of Batch #59374$171,000
Warranty claims 436,000
Total external failure costs$607,00073%
Total Costs of Quality$827,000100%
Req. 2
Because the company has warranty returns and has had a product recall, the company may suffer a reputation for poor quality products. If so, they are probably losing profits from losing sales. Unsatisfied customers will be reluctant to buy from the company again. This report does not include an estimate of the lost profits arising from a reputation for poor-quality products.
Req. 3
The Cost of Quality report shows that very little is being spent on prevention and appraisal, which is probably why the internal and external failure costs are so high. It appears that the company is only inspecting the product halfway through the production process, and not again at the end of the process. Perhaps that is the reason their external failure costs are so high. The CEO should use this information to develop quality initiatives in the areas of prevention and appraisal. Such initiatives should reduce future internal and external failure costs.
(15-20 min.) E 4-34A
Req. 1
Prevention costs:
Training employees in TQM
Training suppliers in TQM
Identifying preferred suppliers who commit to on-time delivery of perfect quality materials
Appraisal costs:
Strength-testing one item from each batch of panels
Avoid inspection of raw materials
Internal failure costs:
Avoid rework and spoilage
External failure costs:
Avoid lost profits from lost sales due to disappointed customers
Avoid warranty costs
Req. 2
Cost / AnalysisCost/
Prevention costs:
Training employees in TQM$ 29,000
Training suppliers in TQM... 33,000
Identifying preferred suppliers who commit to on-
time delivery of perfect quality materials.. 59,000
Appraisal costs:
Strength-testing one item from each batch of
panels... 64,000
Savings on Inspection of raw materials $
Internal failure costs:
Savings on Rework and spoilage..
External failure costs:
Savings on Lost profits from lost sales due to
disappointed customers.
Savings on Warranty costs.. < 16,000>
Net ... $
Clarke should adopt the new quality program. The program would save the company $39000
Exercises (Group B)
(15-20 min.) E 4-35B
Req. 1
Plantwide
overhead rate==Total manufacturing overhead
Cost allocation base (estimated)
==$1,350,000
50,000
=$ 27
Req. 2
Department overhead rate=Total department overhead
Cost allocation base (estimated)
Machining Dept. overhead rate=$900,000
20,000 machine hours
=$45 per machine hour*
Finishing Dept. overhead rate=$450,000
25,000** direct labor hours
=$18 per direct labor hour*
*Rounded to the nearest dollar.
**When calculating the finishing departmental rate, only the direct labor hours incurred in the finishing department are used.
Req. 3
Overhead allocation based on single, plantwide rate:
Job 450Job 455
Total direct labor hours5 DL hours5 DL hours
Plantwide allocation rate $27/ DL hour $27/ DL hour
Overhead allocation$135$135
(continued) E 4-35B
Req. 4
Overhead allocation based on departmental rates:
Job 450Job 455
Machining Department:
Departmental allocation rate$45/ MH$45/ MH
Machine hours used by Job 3 MH 6 MH
Overhead allocation$135$270
Finishing Department:
Departmental allocation rate$18/ DL hr$18/ DL hr
DL hours used by Job 4 DL hrs 3 DL hrs
Overhead allocation$ 72$ 54
Total overhead allocation (from
both departments$207$324
Req. 5
The single plantwide rate undercosts Job 450 by $72 and undercosts Job 455 by $189. Since Bergeron sets his sales price at 125% of cost, and the job cost is affected by the allocation system he uses, its sales price will also be affected by the allocation system it uses.
(15-20 min.) E 4-36B
Req. 1
Fortunado Company
Computation of Indirect Cost Allocation Rates
ActivityTotal Estimated
CostEstimated Quantity of Cost Allocation Base Activity
Cost Allocation Rate
Materials handling$ 6,4003,200 parts=$ 2 per part
Machine setups$ 9,00025 setups=$360 per setup
Insertion of parts$54,4003,200 parts=$ 17 per part
Finishing $89,7002,300 hours=$ 39 per hour
(continued) E 4-36B
Req. 2
The amount of manufacturing overhead to be assigned to Job 420 is computed as follows
Central Plain - Job 420
Manufacturing overhead allocation
ActivityActual Quantity of Cost Allocation Base Used Cost Allocation RateMOH assigned
Materials handling 250 parts $2 / part=$ 500
Machine setups 3 setups$360 / setup= 1,080
Insertion of parts 250 parts $17 / part= 4,250
Finishing 130 hours$ 39 / hr.= 5,070
Total$ 10,900
Req. 3
The amount of manufacturing overhead to be assigned to Job 510 is computed as follows
Central Plain - Job 510
Manufacturing overhead allocation
ActivityActual Quantity of Cost Allocation Base Used Cost Allocation RateMOH assigned
Materials handling 425 parts $2 / part= $ 850
Machine setups 6 setups$370 / setup= 2,160
Insertion of parts 425 parts $17 / part= 7,225
Finishing 320 hours$ 39 / hr= 12,480
Total $22,715
(15-20 min.) E 4-37B
Req. 1
Total overhead $1,310,000
Total machine hours 10,000
Predetermined MOH rate$ 131
Req. 2
Cost of Job #356
Machine hours used100
POHR $131
Total MOH$ 13,100
Job #356traditional POHR
Direct material (400 lbs. @$50/lb.)$ 20,000
Direct labor (75 hrs. @$20/hr.)$1,500
MOH$13,100
Total cost of job$ 34,600
(continued) E 4-37B
Job #356ABC
Direct material (400 lbs. @$50/lb.)$ 20,000
Direct labor (75 hrs. @$20/hr.)$1,500
Machine hours 100$3,500
No. of engineering changes 8$960
Lbs. of hazardous waste
generated 60$13,100
Total cost of job$ 61,960
Req. 3
The estimate based on the activity-based costing (ABC) method provides more useful information. Activity-based costing (ABC) focuses on activities, rather than departments, as the fundamental cost objects. ABC recognizes that activities are costly to perform, and each product manufactured may require different types and amounts of activities. Thus, activities become the building blocks for compiling the indirect costs of products, services, and customers. Managers use ABC to more accurately estimate the cost of resources required to produce different products, to render different services, and to serve different customers.
(15-20 min) E 4-38B
Req. 1
Operating
overheadTotal professional hoursCurrent operating overhead allocation rate
$236,50010,000=$23.65 per
professional hour
Req. 2
Total cost of jobxMarkup percentage=Amount billed
$1,992.95x140%=$2,790.13
Req. 3
ActivityCostTotal activity allocation baseActivity allocation rate
Transportation to clients$ 7,50015,000a
miles driven=$0.50 per mile
Blueprint copying 38,0001,000b
copies=$38 per copy
Office
support191,0005,000c
secretarial hours=$38.20 per secretarial hour
To calculate the activity cost allocation rates, you must use the total activity for the year:
a 3,000 + 12,000 = 15,000
b 300 + 700 = 1,000
c 2,700 + 2,300 = 5,000
(continued) E 4-38B
Req. 4
Total cost of jobxMarkup percentage=Amount billed
$2,159.60x140%=$3,023.44
Req. 5
The ABC billing system should be more fair to clients because they are charged according to the resources they used. For example, copying blueprints is very expensive. Under the fairer system, clients are charged according to the number of blueprint copies that their job required. The fairer system better recognized the extent to which operating costs are incurred by each unique client job.
(15-20 min.) E 4-39B
Req. 1
Cost poolsTotal annual
estimated cost
Pharmacy occupancy costs (utilities, rent, and other costs)$80,000
Packaging supplies (bottles, bags, and other packaging)$30,000
Professional training and insurance costs $100,000
Total pharmacy overhead$210,000
Divide by number of prescriptions20,000
Total pharmacy rate (using # of prescriptions)$ 10.50
Req. 2
Cost assigned using traditional overhead allocation
Customer order #1102
(standard prescriptions)2 @ $10.50$21.00
Req. 3
Cost assigned using traditional overhead allocation
Customer order #1103
(standard prescriptions)1 @ $10.50$10.50
Req. 4
Cost PoolsEstimated CostCost DriversEstimated Cost Driver ActivityCost Pool Rate
Pharmacy Occupancy Costs$80,000Technician Hours80,000$1.00
Packaging Supplies$30,000Number of Prescriptions20,000$1.50
Training and Insurance Costs$100,000Pharmacist Hours23,810$4.20
Req. 5
Customer order #1102 (standard prescriptions)
Used:Used by this orderABC assigned cost
Technician hours for order1 @ $1$1.00
Number of prescriptions2 @ $1.50$3.00
Pharmacist hours2 @ $4.20 $8.40
Total ABC Cost$12.40
(continued) E 4-39B
Req. 6
Customer order #1103 (complicated formulation)
Used:Used by this orderABC assigned cost
Technician hours for order0.5 @ $1$0.50
Number of prescriptions1 @ $1.50$1.50
Pharmacist hours4 @ $4.20$16.80
Total ABC Cost$18.80
Req. 7
The estimate based on the activity-based costing (ABC) method provides more useful information. Activity-based costing (ABC) focuses on activities, rather than departments, as the fundamental cost objects. ABC recognizes that activities are costly to perform, and each product manufactured may require different types and amounts of activities. Thus, activities become the building blocks for compiling the indirect costs of products, services, and customers. Managers use ABC to more accurately estimate the cost of resources required to produce different products, to render different services, and to serve different customers.
(20-25 min.) E 4-40B
Req. 1
Total manufacturing overheadTotal direct labor hours=Plantwide overhead rate
$1,020,00020,400=$50.00
Manufacturing costMedium
(42-inch)Large
(63-inch)
Direct materials$ 954,750$1,520,250
Direct labor280,000525,000
Manufacturing overhead 350,250 669,750
Total manufacturing cost1,585,0002,715,000
Number of units produced 4,000 5,000
Cost per unit396.25543.00
Req. 2
Activity costTotal activity allocation base=Activity allocation rate
Materials handling$145,000500=$290 / mat. orders handing
Machine processing$750,00075,000=$10 / machine hr.
Packaging$125,00025,000=$5 / packaging hr.
Manufacturing costMedium
(42-inch)Large
(63-inch)
Direct materials$ 954,750$1,520,250
Direct labor280,000525,000
Manufacturing overhead 565,250 454,750
Total manufacturing cost1,800,0002,500,000
Number of units produced 4,000 5,000
Cost per unit$ 450$ 500
(continued) E 4-40B
Req. 3
Medium
(42-inch)Large
(63-inch)
Cost/unit using current system$ 396.25$543.00
Cost/unit using ABC 450.00 500.00
Overcosting/(Undercosting) $(53.75)43.00
Number of units produced 4,000 5,000
Cost per unit$(215,000.00)$215,000.00
The Medium units had been undercosted and the Large units had been overcosted. Since Joness sets its sales price at 300% of manufacturing cost, the resulting sales price should have been about $161.25 higher for the Medium units and about $129.00 lower for the Large units.
(20-30 min.) E 4-41B
Req. 1
Rickett Corp.
Total Budgeted Indirect Manufacturing Costs
ActivityBudgeted Quantity of Cost Allocation BaseActivity Cost Allocation RateTotal Budgeted Indirect Cost
Materials handling10,000a$ 3.75$ 37,500
Machine setups 40b$340.00 13,600
Insertion of parts10,000a $ 27.00270,000
Finishing 4,700$ 55.00 249,100
Total budgeted indirect cost$570,200
__________
a (4 1,000) + (6 1,000)
b 20 + 20
c (1.5 1,000) + (3.2 1,000)
Req. 2
Rickett Corp.
ABC Indirect Manufacturing Cost per Unit
ActivityCostAllocationRateQuantity of Cost Allocation Base
Used By:Allocated Activity Cost Per Wheel
StandardDeluxeStandardDeluxe
Materials handling$ 3.7546 $ 15.00$ 22.50
Machine setups$340.000.020*0.020* 6.80 6.80
Insertion of parts$ 27.0046108.00 162.00
Finishing$ 53.001.53.2 79.50 169.60
Total ABC allocated indirect cost$209.30$360.90
__________
*20 setups 1,000 wheels = 0.020 per wheel
(continued) E 4-41B
Req. 3
Total budgeted manufacturing
overhead cost=$570,200 (Req. 1)
Total budgeted direct labor hours=(1,000 2.0) + (1,000 3.0)
=2,000 + 3,000
=5,000
Plantwide overhead rate=$570,200
5,000
=$114.04 per direct labor hour
Manufacturing overhead cost per wheel:
Direct labor hoursxPlantwide
overhead rate=Manufacturing overhead
Standard2.00x114.04=$228.08
Deluxe3.00x114.04=$342.12
(continues E 4-31B) (15-20 min.) E 4-42B
Req. 1
Begin by computing the total costs.
Rickett Corp
Total cost per unit using ABC Data
StandardDeluxe
Direct materials $ 32.00 $ 46.25
Direct labor45.6054.00
Manufacturing overhead 209.30360.90
Total manufacturing cost$ 286.90$ 461.15
Now compute the gross profit.
Rickett Corp
Gross profit per unit using ABC Data
StandardDeluxe
Sales price$470.00$610.00
Total manufacturing costs 286.90461.15
Gross profit$ 183.10$ 148.85
Req. 2
Rickett Corp.
Gross profit per unit using plantwide overhead rate
StandardDeluxe
Sale price$470.00$610.00
Total manufacturing costs 305.68 442.37
Gross profit$ 164.32$ 167.63
(continued) E 4-42B
Req. 3
The standard model is more profitable than the deluxe model. Activity-based costing data generally are more accurate than cost data generated by a plantwide overhead allocation rate. ABC systems have more cost categories (activities), each with its own allocation base. ABC cost assignments more accurately represent the cost of resources consumed to manufacture (and support) products.
Req. 4
The ABC system is likely to pass the cost-benefit test because the company manufactures two different products that use different amounts of resources.
The old cost system appears broken because profits have been declining even though the company shifted its product mix toward the product that had appeared most profitable under the old system.
(15-20 min.) E 4-43B
Req. 1
Either the materials handling cost or the grinding cost is inaccurate. Both costs were assigned based on the number of parts. Thus, the ratio of Job 409 materials handling cost to Job 622 materials handling cost should be the same as the ratio of Job 409 grinding cost to Job 622 grinding cost. The materials handling cost ratio is 1:3 ($600 to $1,800), but the grinding cost ratio is 1:5 ($312 to $1,560). Job 622 cannot have three times as many parts as Job 409 and five times as many parts simultaneously.
Req. 2
The first step is to determine the allocation rate for each of the four activities:
Williamson Fabricators
ABC Allocation Rates
ActivityJob 622
Activity CostDivide by Quantity
of the Cost
Allocation BaseActivity Cost
Allocation Rate
Lathe work$14,500 58,000 turns = $0.25 / turn
Milling$29,000 1,000 hours = $29.00 / mach. hr.
Grinding$ 1,560 3,250 parts = $0.48 / part
Testing $ 2,700 300 units = $9.00 / unit
The second step is to use the cost allocation rate for each activity to determine the quantity of the allocation base Job 409 used.
Williamson Fabricators
Quantity of the Allocation Base Used by Job 409
ActivityJob 409
Activity CostDivide by Activity Cost Allocation RateQuantity of the Allocation Base Used by Job 409
Lathe work$4,500 $0.25 / turn18,000 turns
Milling$4,350 $29 / hour150 hours
Grinding$ 312 $0.48 / part650 parts
Testing$ 126 $9.00 / unit14 units
(15-20 min.) E 4-43B
Req. 3
Based on the ABC information, Williamson should not accept the company's offer to test units for $12 each. Williamsons cost of performing this activity is $9 per unit ($2,700 300 units tested for Job 622).
(15-20 min) E 4-44B
1. Business strategy of manufacturing without waste Lean production
2. Just in time inventory philosophy Lean production
3. Large finished goods inventories Traditional manufacturing
4. Highly specialized machine operators Traditional manufacturing
5. Long production lead times Traditional manufacturing
6. Pull product demand Lean production
7. Work in process inventories Traditional manufacturing
8. Production areas are organized by function Traditional manufacturing
9. Safety stock Traditional manufacturing
10. Reduced machine setup or changeover times Lean production
11. Cross-trained production employees Lean production
12. Partnerships with suppliers Lean production
(15-20 min) E 4-45B
a. Waiting
b. Overproduction
c. Excess processing
d. Not utilizing people to their full potential
e. Transportation
f. Defects
g. Overproduction
h. Inventory
i. Excess processing
j. Waiting
k. Defects
l. Not utilizing people to their full potential
m. Transportation
n. Movement
o. Inventory
p. Movement
(15-20 min) E 4-46B
Req. 1
Cost of Quality Report for
Skinny Treats Corp.Total Costs of QualityPercentage of total costs of quality (rounded)
Prevention Costs:
Personnel training$ 32,000
Preventative maintenance 8,000
Total prevention costs$ 40,0005%
Appraisal Costs:
Inspecting products at half-way point$ 51,000
Inspection of raw materials 4,000
Total appraisal costs$ 55,0007%
Internal Failure Costs:
Production loss due to machine breakdowns$ 17,000
Cost of defective products88,000
Cost of disposing of rejected products 11,000
Total internal failure costs$116,00014%
External Failure Costs:
Recall of Batch #59374$175,000
Warranty claims 423,000
Total external failure costs$598,00074%
Total Costs of Quality$809,000100%
Req. 2
Because the company has warranty returns and has had a product recall, the company may suffer a reputation for poor quality products. If so, they are probably losing profits from losing sales. Unsatisfied customers will be reluctant to buy from the company again. This report does not include an estimate of the lost profits arising from a reputation for poor-quality products.
Req. 3
The Cost of Quality report shows that very little is being spent on prevention and appraisal, which is probably why the internal and external failure costs are so high. It appears that the company is only inspecting the product half-way through the production process, and not again at the end of the process. Perhaps that is the reason their external failure costs are so high.
The CEO should use this information to develop quality initiatives in the areas of prevention and appraisal. Such initiatives should reduce future internal and external failure costs.
(15-20 min.) E 4-47B
Req. 1
Prevention costs:
Training employees in TQM
Training suppliers in TQM
Identifying preferred suppliers who commit to on-time delivery of perfect quality materials
Appraisal costs:
Strength-testing one item from each batch of panels
Avoid inspection of raw materials
Internal failure costs:
Avoid rework and spoilage
External failure costs:
Avoid lost profits from lost sales due to disappointed customers
Avoid warranty costs
Req. 2
The company should implement the new quality program. The program should save the company $48,000.
Problems (Group A)
(40 min.) P 4-48A
Req. 1
Plantwide
overhead rate=Total manufacturing overhead
Total direct labor hours
=$1,070,000
17,000* direct labor hours
=$63 per direct labor hour
*When calculating plantwide overhead rates, all direct labor
hours incurred in the plant are used.
(continued) P 4-48A
Req. 2
Departmental cost allocation rate=Department overhead cost
Department allocation base
Machining=$630,000
10,000 machine hours
=$63 per machine hour
Assembly=$440,000
14,000** direct labor hours
=$31 per direct labor hour
**When calculating the assembly departmental rate, only the direct labor
hours incurred in the assembly department are used.Req. 3
Job #501 uses more of the companys resources. Job 501 uses twice as many machine hours as the other job. The accounting system should show that one job actually costs the company more resources than the other.
Req. 4
Overhead allocation based on single, plantwide rate:
Job 500Job 501
Total direct labor hours17 DL hours17 DL hours
Plantwide allocation rate $63 / DL hour $63 / DL hour
Overhead allocation$1,071$1,071
Req. 5
Overhead allocation based on departmental rates:
Job 500Job 501
Machining Department:
Departmental allocation rate$63/ MH$63/ MH
Machine hours used by Job 9 MH 18 MH
Overhead allocation$567$1,134
Assembly Department:
Departmental allocation rate$31/ DL hr$31/ DL hr
DL hours used by Job 14 DL hrs 14 DL hrs
Overhead allocation$434$434
Total overhead allocation $1,001$1,568
(from both departments)
Req. 6
The single plantwide overhead rate assigned the same amount of overhead to both jobs. The departmental rates assign more overhead cost to Job 501 than Job 500 due to the extra machine hours used. This seems fairer.
(continued) P 4-48A
Req. 7
Manufacturing cost and sales price using current costing system:
Job 500Job 501
Direct Materials$1,800$1,800
Direct Labor (14 DL hours $25) 510510
Manufacturing overhead 1,071 1,071
Total manufacturing cost $3,381 $3,381
Markup for pricing 110% 110%
Sales price$3,719$3,719
Req. 8
Gross profit using current costing system:
Job 500Job 501
Sales Price (from Req. 1)$3,719$3,719
Less: Total manufacturing cost 3,381 3,381
Gross profit / (loss)
$ 338$ 338
Gross profit using departmental rate costing system:
Job 500Job 501
Sales price (from Req. 7)$3,719$2,717
Less: Total manufacturing cost:
Direct Materials$1,800$1,800
Direct Labor (17 DL hours $30) 510510
Manufacturing overhead 1,001 1,568
Total manufacturing cost $3,311 $3,878
Gross profit (loss)
$ 408$ (159)
Req. 9
When utilizing a single rate allocation method, the company believes that both jobs are equally profitable.
When utilizing a refined costing method, the company realizes that Job 500 is profitable but Job 501 shows a loss.
(20-30 min.) P 4-49A
Req. 1
McKnight Corp.
Per-Unit Manufacturing Costs
Standard
DeskUnpainted
Desk
Direct materials$ 93,000$21,000
Materials handling
(120,500 and 30,500) $0.6072,30018,300
Assembling (5,900 and 700) $1588,50010,500
Painting (5,000 $5.10) 25,500 0
Total manufacturing costs$279,300$49,800
Number of units 5,000 2,500
Manufacturing product cost per unit$ 56 $ 20
(continued) P 4-49A Req. 2
Hone
Full Product Costs
Standard
Desk Unpainted
Desk
Premanufacturing activities$ 5.00$ 4.00
Manufacturing product costs56.0020.00
Postmanufacturing activities 22.00 21.00
Full product cost per unit$83.00$45.00
Req. 3
Manufacturing product costs are reported in the financial statements.
Managers use full product costs for decisions, such as pricing and product emphasis.
Full product costs are reported in the costs of premanufacturing activities and postmanufacturing activities that are expensed as incurred for external reporting. However, these costs often are assigned to products for internal decisions.
Req. 4
Full product cost... $ 83.00
Desired profit.. 42.00
Sale price per unit standard desk $125.00
(30-40 min.) P 4-50A
Req. 1
Corbertt Company
ABC Cost Allocation Rates
Applications
DevelopmentContent
ProductionTesting
Estimated indirect activity cost$1,800,000$2,800,000$248,000
Estimated cost allocation base 6 applications 14,000,000 lines 1,600 testing hours
Activity overhead rate$300,000/application $0.20 / line $155 / hour
Req. 2
Corbertt Company
Activity Costs per Unit
X-PageX-Secure
Applications development
(1 and 1) $300,000$300,000$ 300,000
Content production
(680,000 and 10,200,000) $0.20136,000 2,040,000
Testing (90 and 540) $155
13,950 83,700
Total costs
$449,950$2,423,700
Number of units
20,000 8
Per unit cost$ 22.50$302,962.50
(continued) P 4-50A
Req. 3
First, compute the total indirect costs under the original single-allocation-based system.
ProductEstimated qty. of the allocation basexCost allocation rate=Indirect cost allocated
X-Page$113x8,000=$904,000
X-Secure$113x12,000=$1,356,000
Now compute the indirect cost per unit for each product under the original single-allocation-base system.
Corbertt Company
Costs per Unit Under Original Direct-Labor Based System
X-PageX-Secure
Total indirect costs allocated$ 904,000$1,356,000
Number of units
20,000 8
Per unit cost
$ 45.20$169,500.00
Req. 4
The original system overcosted X-Page and undercosted X-Secure.
The original system allocated more overhead to X-Secure than to X-Page. But X-Secure required 15 times as many lines of code and 6 times as much testing as X-Page. The ABC system recognizes this difference and allocates more of the content production and testing costs to X-Secure.
Req. 5
Corbertt Companys different software applications use different amounts of resources.
Corbertt Company has high indirect costs.
Corbertt Company produces high volumes of some software applications and low volumes of other software applications.
Corbertt Company is in a competitive environment and needs accurate product costs.
Corbertt Company has accounting and information system expertise to implement the system.
(30-40 min.) P 4-51A
Req. 1
Jacobsen Pharmaceuticals
ABC Cost Allocation Rates
Materials HandlingPackagingQuality Assurance
Estimated indirect
activity costs$160,000$430,000$113,000
Estimated cost
allocation base 16,000 kilos 2,300 hours 2,000 samples
Activity overhead rate$ 10 / kilo$ 187 / hour$ 57 / sample
(continued) P 4-51A
Req. 2
Jacobsen Pharmaceuticals
Activity Costs Per Unit
Commercial ContainerTravel Pack
Materials handling (8,300 and 6,500) $10
$ 83,000$ 65,000
Packaging (900 and 300) $187
168,30056,100
Quality assurance (240 and 340) $57
13,680 19,380
Total indirect costs
$264,980 $140,480
Number of units
2,800 20,000
Indirect activity cost per unit
$ 94.64 $ 7.02
Req. 3
ProductCost allocation ratexActual quantity of allocation base=Indirect cost allocated
Commercial $400x900=$360,000
Travel$400x300=$120,000
Jacobsen Pharmaceuticals
Costs per Unit Under Original Machine-Hour Based System
Commercial ContainerTravel Pack
Total indirect costs allocated$360,000$120,000
Number of units
2,800 20,000
Indirect cost per unit
$ 128.57 $ 6.00
Req. 4
The original system overcosted the commercial containers and undercosted the travel packs.
The original system allocated 3 times as much indirect cost to the commercial containers as to the travel packs. However, commercial containers did not use 3 times as much of the material handling and quality assurance resources. The ABC system recognizes that commercial containers do not require 3 times as much material handling and quality assurance as travel packs. So, relative to the original system, ABC allocates less of the material handling and quality assurance costs to commercial containers.
(20-30 min.) P 4-52A
Req. 1
Real Toys
Predicted Quality Cost Savings
ActivityPredicted Reduction In Activity UnitsActivity Cost Allocation Rate=Predicted
Reduction
In Activity
Costs
Inspection of incoming materials385$25$ 9,625
Inspection of finished goods385$3413,090
Number of defective units discovered in-house3,400$1551,000
Number of defective units discovered by customers975$4240,950
Lost sales to dissatisfied customers270$5815,660
Total predicted quality cost savings$130,325
(continued) P 4-52A
Req. 2
Creative Construction Toys Corp.
Net Benefit of Design Engineering Effort
Total predicted qualitycost savings $130,325
Less: Cost of design engineering (75,000)
Net benefit of design engineering$ 55,325
Req. 3
Measuring the cost of quality-related activities is difficult. As an alternative, they could monitor nonfinancial measures of quality and attempt to improve them.
Problems (Group B)
(40 min.) P 4-53B
Req. 1
Plantwide
overhead rate=Total manufacturing overhead
Total direct labor hours
=$1,040,000
14,500* direct labor hours
=$72 per direct labor hour
*When calculating plantwide overhead rates, all direct labor
hours incurred in the plant are used.
Req. 2
Department allocation rate=Department overhead cost
Department allocation base
Machining=$600,000
4,000 machine hours
=$150 per machine hour
Assembly=$440,000
12,000** direct labor hours
=$37 per direct labor hour
**When calculating the assembly departmental rate, only the direct labor
hours incurred in the assembly department are used.
(continued) P 4-53B
Req. 3
Job 501 uses more of the companys resources.
Job 501 uses more machine hours than the other job. The accounting system should show that one job actually costs the company more resources than the other.
Req. 4
Overhead allocation based on single, plantwide rate:
Job 500Job 501
Total direct labor hours18 DL hours18 DL hours
Plantwide allocation rate $72 / DL hour $72 / DL hour
Overhead allocation$1,296$1,296
Req. 5
Overhead allocation based on departmental rates:
Job 500Job 501
Machining Department:
Departmental allocation rate$150/ MH$150/ MH
Machine hours used by Job 10 MH 20 MH
Overhead allocation$1,500$3,000
Assembly Department:
Departmental allocation rate$37/ DL hr$37/ DL hr
DL hours used by Job 12 DL hrs 12 DL hrs
Overhead allocation$444$444
Total overhead allocation $1,944$3,444
Req. 6
The single plantwide overhead rate assigned the same amount of overhead to both jobs. The departmental rates assign more overhead cost to Job 501 than Job 500 due to the extra machine hours used. This seems fairer.
Req. 7
Manufacturing cost and sales price using current costing system:
Job 500Job 501
Direct Materials$2,000$2,000
Direct Labor (18 DL hours $25) 450450
Manufacturing overhead 1,2961,296
Total manufacturing cost $3,746 $3,746
Markup for pricing (%) 130% 130%
Sales price$4,870$4,870
Req. 8
Gross profit using current costing system:
Job 500Job 501
Sales Price (from Req. 7)$4,870$4,870
Less: Total manufacturing cost 3,746 3,746
Gross profit / (loss)
$1,124$1,124
(continued) P 4-53B
Gross profit using departmental rate costing system:
Job 500Job 501
Sales price (from Req. 7)$ 4,870$ 4,870
Less: Total mfg. cost
Direct Materials$ 2,000$ 2,000
Direct Labor 450450
Manufacturing overhead 1,9444,3943,4445,894
Gross profit (loss)
$ 476$(1,0224)
Req. 9
When utilizing a single rate allocation method, the company believes that both jobs are equally profitable.
When utilizing a refined costing method, the company realizes that Job 500 is profitable but Job 501 shows a loss.
(20-30 min.) P 4-54B
Req. 1
McMillan Furniture
Per-Unit Manufacturing Costs
Standard
DeskUnpainted
Desk
Direct materials$ 95,000$22,000
Materials handling
(119,000 and 29,000) $0.7083,30020,300
Assembling (5,700 and 1,000) $1691,20016,000
Painting (7,500 $5.30) 39,750 0
Total manufacturing costs$309,250$58,300
Number of units 7,500 2,500
Manufacturing cost per unit$ 41 $ 23
Req. 2
McMillan Furniture
Full Product Costs
Standard
Desk Unpainted
Desk
Premanufacturing activities$ 7$ 2
Manufacturing product costs4123
Postmanufacturing activities2321
Full product cost per unit$71$46
(continued) P 4-54B
Req. 3
Manufacturing product costs are reported in the financial statements. Managers use full product costs for
decisions such as pricing and product emphasis.
Full product costs include the costs of premanufacturing activities and postmanufacturing activities that are expensed as incurred for external financial reporting. However, these costs often are assigned to products for internal decisions.
Req. 4
Full product cost. $ 71
Desired profit 42
Sale price per unit std. desk... $113
(30-40 min.) P 4-55B
Req. 1
Willitte Co.
ABC Cost Allocation Rates
Applications
DevelopmentContent
ProductionTesting
Estimated indirect activity cost$2,400,000$3,000,000$350,000
Cost allocation base (estimated) 8 applications 10,000,000 lines 2,000 testing hours
Activity overhead rate$300,000/application $0.30 / line $175 / hour
Req. 2
Willitte Co.
Activity Costs per Unit
X-PageX-Secure
Applications development
(1 and 1) $300,000$300,000$ 300,000
Content production
(580,000 and 8,700,000) $0.30174,000 2,610,000
Testing (130 and 780) $175
22,750 136,500
Total costs
$496,750$3,046,500
Number of units
35,000 13
Indirect activity cost per unit
$ 14.19*$ 234,346.15*
*Rounded to nearest cent
Req. 3
ProductEstimated qty. of the allocation basexCost allocation rate=Indirect cost allocated
X-Page$134x10,000=$1,340,000
X-Secure$134x15,000=$2,010,000
(continued) P 4-55B
Willitte Co.
Costs per Unit Under Original Direct-Labor Based System
X-PageX-Secure
Total indirect costs allocated
(10,000 and 15,000) $134
$1,340,000$ 2,010,000
Number of units
35,000 13
Per unit cost $ 38.29$ 154,615.38*
__________
*Rounded to nearest cent
Req. 4
The original system overcosted X-Page and undercosted X-Secure.
The original system allocated more overhead to X-Secure than to X-Page. But X-Secure required 15 times as many lines of code and 6 times as much testing as X-Page. The ABC system recognizes this difference and allocates more of the content production and testing costs to X-Secure.
Req. 5
Willitte Companys different software applications use different amounts of resources.
Willitte Company has high indirect costs.
Willitte Company produces high volumes of some software applications and low volumes of other software applications.
Willitte Company is in a highly competitive environment and needs accurate product costs.
Willitte Company has accounting and information system expertise to implement the system.
(30-40 min.) P 4-56B
Req. 1
McNeil Pharmaceuticals
ABC Cost Allocation Rates
Materials HandlingPackagingQuality Assurance
Estimated indirect
activity cost$180,000$420,000$118,000
Cost allocation base
(estimated) 18,000 2,200 1,700
Overhead rate$ 10 / kilo$ 191 / hour$ 69 / sample
(continued) P 4-56B
Req. 2
McNeil Pharmaceuticals
Activity Costs Per Unit
Commercial ContainerTravel Pack
Materials handling (8,000 and 6,300) $10
$ 80,000$ 63,000
Packaging (1,500 and 500) $191
286,50095,500
Quality assurance (270 and 370) $69
18,630 25,530
Total indirect costs
$385,130 $184,030
Number of units
2,600 60,000
Indirect activity cost per unit*
$ 148.13 $ 3.07
*Rounded
Req. 3
ProductCost allocation ratexActual qty. of allocation base=Indirect cost allocated
Commercial$300x1,500=$450,000
Travel$300x500=$150,000
Now compute the indirect cost per unit for each product under the original single-allocation-base system.
McNeil Pharmaceuticals
Costs per Unit Under Original Machine-Hour Based System
Commercial ContainerTravel Pack
Total indirect costs allocated$450,000$150,000
Number of units
2,600 60,000
Indirect cost per unit*$ 173.08 $ 2.50
*Rounded
Req. 4
The original system overcosted the commercial containers and undercosted the travel packs.
The original system allocated 3 times as much indirect cost to the commercial containers as to the travel packs. However, commercial containers did not use 3 times as much of the material handling and quality assurance resources. The ABC system recognizes that commercial containers do not require 3 times as much material handling and quality assurance as travel packs. So, relative to the original system, ABC allocates less of the material handling and quality assurance costs to commercial containers.
(20-30 min.) P 4-57B
Req. 1
Tiny Toys
Predicted Quality Cost Savings
ActivityPredicted Reduction In Activity UnitsActivity Cost Allocation Rate=Predicted
Reduction
In Activity
Costs
Inspection of incoming materials370$22$ 8,140
Inspection of finished goods370$2910,730
Defective units discovered in-house3,200$1341,600
Defective units discovered by
customers875$36$31,500
Lost sales to dissatisfied customers330$62 20,460
Total predicted quality cost savings$112,430
(continued) P 4-57B
Req. 2
Tiny Toys
Net Benefit of Design Engineering Effort
Total predicted quality cost savings $112,430
Cost of design engineering (70,000)
Net benefit of design engineering$ 42,430
Req. 3
Measuring the cost of quality-related activities is difficult. An alternative approach to measure quality improvement is to monitor nonfinancial measures of quality and attempt to improve them.
Discussion & Analysis
A4 58 Discussion & Analysis Questions
1. Explain why departmental overhead rates might be used instead of a single plantwide overhead rate.
A single plantwide overhead rate doesnt always do a good job of matching the cost of overhead resources with the products that consume those resources. By using department overhead rates, companies can more equitably assign overhead to their jobs, products, or services. As a result, less cost distortion occurs and managers have more accurate information for making business decisions.
2. Using activity-based costing, why are indirect costs allocated while direct costs are not allocated?
Since direct costs can be traced to products, they are not allocated. Indirect costs, such as overhead, cannot be traced as easily as direct costs, so must be allocated to products and services.
Discuss the difference between allocate and assign.
In terms of overhead, allocation can be described as a distribution of the cost to products or services via some predetermined cost base such as machine hours. To assign overhead costs rather than allocate, a company will develop a model that refines the costs of overhead into departments or various activity pools and cost drivers. Then the overhead is traced to the products/services as they are used.
3. How can using a single predetermined manufacturing overhead rate based on a unit-level cost driver cause a high-volume product to be overcosted?
When a company uses a plantwide allocation system that is based on a volume-related driver, such as direct labor hours, the high-volume products will be allocated more cost than the low volume products simply because there are more of them produced, not necessarily because they use more overhead. This can result in the higher volume product being overcosted.
4. Assume a company uses a plantwide predetermined manufacturing overhead rate that is calculated using direct labor hours as the cost driver. The use of this plantwide predetermined manufacturing overhead rate has resulted in cost distortion. The companys high-volume products are overcosted and its low-volume products are undercosted. What effects of this cost distortion will the company most likely be experiencing?
A company that overcosts its high-volume products may be experiencing low sales while the undercosted low-volume products are experiencing high sales.
Why might the cost distortion be harmful to the companys competitive position in the market?
The cost distortion can be harmful to a companys competitive position in the market because it could be losing sales of its high-volume products due to the overcosting and therefore over-pricing. It could also be harmed by losing money on the undercosted low-volume products due to under-pricing.
5. A hospital can use activity-based costing (ABC) for costing its services. In a hospital, what activities might be considered to be value-added activities?
Operating on a patient
Dispensing medication to a patient
Evaluating test results
What activities at that hospital might be considered to be non-value-added?
Waiting for a procedure
Fixing equipment
Inspecting prescriptions
6. A company makes shatterproof, waterproof cases for iPhones. The company makes only one model and has been very successful in marketing its case; no other company in the market has a similar product. The only customization available to the customer is the color of the case. There is no manufacturing cost difference between the different colors of the cases. Since this company has a high-volume product, its controller thinks that the company should adopt activity-based costing. Why might activity-based costing not be as beneficial for this company as for other companies?
Activity-based costing is beneficial to companies who are
in highly competitive markets
produce many different products that require different types and amounts of resources
produce high volume of some products and low volume of others.
Since this company does not fit into these categories, it might not be beneficial for them to incur the cost of developing and using ABC.
7. Compare a traditional production system with a lean production system. Discuss the similarities and the differences.
Some of the differences between a traditional production system and a lean production system are
like machines grouped together vs. production cells
longer vs. shorter setup times
larger vs. smaller batches
higher vs. lower inventories
many suppliers vs. fewer, well-coordinated suppliers
single tasked labor vs. wider range of labor tasks
longer vs. shorter manufacturing cycles
Similarities include
machinery needed
labor needed
inspection of products
8. Think of a product with which you are familiar. Explain how activity-based costing could help the company that makes this product in its efforts to be green.
Student answers may vary.
9. It has been said that external failure costs can be catastrophic and much higher than the other categories. What are some examples of external failure costs?
Lost sales
Sales returns
Warranty repairs/replacements
Why is it often difficult to arrive at the cost of external failures?
Often the largest external failure cost - lost sales/profits - is hard to measure because of its nature. There are no records kept of lost sales. They must be estimated using subjective experiences and judgments. Defect rates, the number of customer complaints, and warranty repairs/replacements can help in the estimation.
10. What are the four categories of quality-related costs? Name a cost in each of the four categories for each of the following types of organizations:
a. Restaurant
b. Hospital
c. Law firm
d. Bank
e. Tire manufacturer
f. University
The four categories of quality-related costs are prevention, appraisal, internal failure costs, and external failure costs.
PreventionAppraisalInternal Failure CostsExternal Failure Costs
a. RestaurantTraining for cooks/serversWait staff inspects orders before servingMeals not as ordered Mold/insect found on meal by customer
b. HospitalTraining for ER employeesEvaluating an ER patientReissuing medication due to inaccurate recordingRe-casting improperly set broken arm
c. Law firmTraining for paralegalsAttorney review of paralegals workUnderestimated case timeLosing a case due to carelessness
d. BankTraining for tellersManager approval for certain transactionsCashed an NSF checkCustomer reporting bank error on statement
e. Tire manufacturerTraining for factory employeesTires inspected before shippingTires returned to factory for rework or scrapedWarranty repairs
f. UniversityTraining for admissions staffDean approval for depart-mental budgetsCanceled classesLosing alumni support
11. What are the similarities between sustainability and lean thinking? What are the differences between sustainability and lean thinking?
Sustainability and lean thinking have many similarities: both practices seek to reduce waste. However, lean operations focus on eliminating waste and empowering employees in an effort to increase economic profits. On the other hand, sustainability focuses on eliminating waste and empowering employees not only to increase economic profits, but also to preserve the planet and improve the lives of all people touched by the company.
12. Why might a company want to take lean thinking a step further by including operations and methods associated with sustainability?
While lean practices tend to center on internal operational waste, green practices also consider the external waste that may occur as a result of the product. To become greener, a lean company should be particularly cognizant of all waste that could harm the planet: packaging waste, water waste, energy waste, and emissions waste that would occur from both manufacturing the product and from consumers using and eventually disposing of the product.
Application & Analysis
A4 59 ABC in Real Companies
Basic Discussion Questions
1. Describe the company selected, including its products or services.
A bookstore provides books and other products to its customers. In addition, it could offer events such as book signings or book clubs for its customers.
2. List eight key activities performed at this company. Choose at least one activity in the areas of production, sales, human resources, and accounting.
1. Process customer purchases
2. Process customer special orders
3. Handle customer inquiries
4. Hiring and training new employees
5. Stock shelves
6. Advertise events
7. Close out cash registers daily
8. Record daily transactions
3. For each of the key activities, list a potential cost driver for that activity and describe why this cost driver would be appropriate for the associated activity.
1. customer sales
2. special orders
3. customer inquiries
4. training sessions held
5. packages delivered
6. events scheduled
7. cash registers used
8. bookkeepers hours
Student responses will vary.
A4 60 ABC in Real Companies
Go to a fast food restaurant (or think of the last time you were at a fast food restaurant). Observe the steps involved in providing a meal to a customer. You will be watching for value-added steps and non-value-added steps. Answer the following questions.
Basic Discussion Questions
1. Describe the steps involved with delivering the meal to the customer that you can observe.
2. Describe the behind-the-scenes processes that are likely in the restaurant, such as cleaning, stocking, and cooking activities.
3. With your answers for 1 and 2 above, list all of the possible activities, materials, and information that you think might be included on a value stream map for the restaurant. Include all steps you can think of (not necessarily of those you can observe).
4. Make a list of the eight wastes as denoted by the acronym DOWNTIME (defects, overproduction, waiting, not utilizing people to their full potential, transportation, inventory, movement, and excess processing). Next to each waste category, list at least one possible non-value-added activity that might or might not be in the processes in that restaurant.
5. Go back to the list of items for the potential value stream map. Circle potential areas for improvement and explain what wastes might be involved in those areas.
Student answers will vary.
Decision Cases
(20-40 min.) A 4-61
Req. 1
Axis Systems
Product Costs per Unit (Original Cost System)
Job AJob B
Direct materials
$210,000$30,000
Direct labor
160,00012,000
Allocated overhead (8,000 and 600) $22 176,000 13,200
Total cost
$546,000$55,200
Divide by number of units
100 10
Product cost per unit
$ 5,460$ 5,520
Req. 2
Axis Systems
Product Costs Per Unit (ABC System)
Job AJob B
Direct materials
$ 210,000$30,000
Direct labor
160,00012,000
Allocated overhead:
Materials handlinga
12,7501,700
Machine setupb
3,0002,000
Assemblingc
120,00016,000
Shippingd
1,500 1,500
Total cost
$ 507,250$63,200
Divide by number of units
100 10
Product cost per unit
$5,072.50$ 6,320
__________
a (15,000and2,000)$0.85
b (6and 4)$500
c (1,500and 200)$80
d (1and 1)$1,500
The change in costs of Job A does not exactly offset the change in costs of Job B between the original system and ABC, because Axis has more than these two jobs. If Axis had only these two jobs, then the change in one jobs costs would exactly offset the change in the other jobs costs.
(continued) A 4-61
Req. 3
The activity-based costing system is more accurate than the single-rate system in assigning the costs of the resources each job consumes. The single rate allocates all overhead cost based on direct labor hours. Job A units require 80 direct labor hours each (8,000 100), and Job B units require 60 direct labor hours each (600 10). Consequently, the single rate system assigns to each unit of Job A 133% (80 60) of the overhead cost assigned to each unit of Job B.
But a unit of Job A does not consume 133% as much of each activity as does a unit of Job B. The data given in the problem reveal the following resource consumption patterns:
Job AJob B
Parts per unit
150200
Setups per unit
0.06 0.4
Assembling hours per unit
15 20
Shipments per unit
0.01 0.1
These data show that a unit of Job B actually consumes more of every overhead resource than a unit of Job A. The ABC system recognizes the actual resource consumption. The single rate undercosts Job B and overcosts Job A.
Students responses will probably not be this complete. The response above is intended to provide a basis for class discussion.
Req. 4
a.If Axis Systems managers base their decision on original system costs, they will outsource both jobs. The original cost system indicates that Axis can produce the A and B jobs for $5,460 and $5,520 per unit, respectively, which is more than the $5,400 outsourcing cost.
b.If the managers base their decision on ABC system costs, they will only outsource Job B. The ABC system shows that Axis Systems will incur $327.50 ($5,400 $5,072.50) less in costs to make the Job A units than to buy them. Because the ABC costs are more accurate, Axis managers should outsource Job B and produce Job A to maximize income.
(15 min.) A 4-62
Axis Systems
Original and Revised Product Costs per Unit (ABC System)
Job B Original Job B Revised
Direct Materials:
Original
Revised ($3,000 0.90%)$3,000$2,700
Direct Labor1,2001,200
Allocated overhead:
Materials handling170170
Machine setup200200
Assembling1,600980*
Shipping 150 150
Total unit cost$6,320$5,400
__________
(continued) A 4-62
*The new assembly process must result in a revised assembling
cost per unit of no more than $980:
$980 = $5,400 ($2,700 + $1,200 + $170 + $200 + $150)
Therefore, the value engineering needs a minimum cost saving in assembling of $620 per unit ($1,600 $980).
$16,000 / 10 units = $1,600 assembly cost per unit from
Decision Case 4-69. Ethical Issue
(15-20 min.) A 4-63
The IMA Statement of Ethical Professional Practice includes overarching ethical principles that express values (honesty, fairness, objectivity and responsibility) and four standards that guide conduct (competence, confidentiality, integrity and credibility). Three of the four specific standards are relevant to Rachel Gambol.
Competence: Gambol has the responsibility to maintain her professional competence (as evidenced by attending the ABC conference), and also to apply that competence to benefit her employer. Gambol can apply her knowledge of ABC by identifying the Order Department as a likely candidate for ABC.
Integrity: Gambol is responsible for communicating unfavorable as well as favorable information and judgments. The unfavorable outcome that some employees may lose their jobs does not excuse Gambol from pursuing the ABC opportunity in the Order Department.
Credibility: Gambol is responsible for communicating all relevant information about the ABC proposal fairly and objectively. She should recognize the benefits and the costs, including how cost savings will require the termination of some employees.
Termination of long-term employees can hurt the morale of remaining employees and possibly even subject the firm to age-discrimination lawsuits. Therefore, Gambol should carefully consider all the relevant implications, not just those for which "hard" numbers are available. Gambol should consider alternatives to terminations, such as transferring "extra" employees to other departments, or offering early retirement packages.
Student responses will probably be less complete.
CMA Question
(5 - 10 min.) A 4-64
Answer: C
144 Copyright 2013 Pearson Education, Inc. publishing as Prentice Hall
145Copyright 2013 Pearson Education, Inc. publishing as Prentice Hall