BPE Case study of Pippin Close and Barnlea Close Building ... · BPE Case study of Pippin Close and...
Transcript of BPE Case study of Pippin Close and Barnlea Close Building ... · BPE Case study of Pippin Close and...
BPE Case study of Pippin Close
and Barnlea Close Building Performance Evaluation conference| 14th July 2015 | Woking
Professor Rajat Gupta and Mariam Kapsali Low Carbon Building Group, Oxford Institute for Sustainable Development,
Oxford Brookes University [email protected]
Structure of presentation
• Overview of BPE programme
• Key findings from BPE study elements
• Wider Lessons
BPE competition - TSB programme
Project funded under Technology Strategy
Board’s (now Innovate UK) national ‘Building
Performance Evaluation’ competition
• Performance of buildings in use is highly
variable and does not match predictions
• Case studies investigation of building
performance to understand cause and effects
• Open to domestic new-built, non-domestic
new-built and major refurbishments
• The project included 53 domestic studies: 23
Phase 1 studies and 30 Phase 2 studies
Studies funded under:
• Post completion and early occupation stage
• In-use stage
Design and construction audit
Drawings and SAP calculation review
Interviews and walkthrough with the design team
Review of control interfaces
Fabric testing
Thermographic survey
Air-tightness test
U-value testing
Post construction stage & early occupancy
Commissioning checks of systems and services
MVHR tests
Review of handover process and occupant guidance
BPE methodology for our study
BPE methodology for our study
Energy monitoring and assessment
Smart metering and sub-metering
DomEarm & benchmarking
Monitoring of environmental conditions
Temperature
Relative Humidity
CO2 Levels
Window opening
Occupant studies
Occupant satisfaction survey using BUS
Interviews and walkthroughs with occupants
Activity logging and thermal comfort diaries
Overview
• Location: Feltham, London
• Social housing development
• Scheme comprises of 10 new
houses:
• Eight terraced houses
• Two detached
• Code level 4 development
• Fabric first approach
• Timber frame and masonry
• Construction completed in
March 2012
Barnlea Close
Pippin Close
Pippin Close and Barnlea Close
Similar construction
Similar occupancy pattern
Two case study dwellings
Pippin Close Barnlea Close
Area m² 128 146
Typology Four bed
Mid-terrace
Five bed
Detached
Floors 3 2
Orientation South South West
Occupancy
patterns
Weekdays:
13:00-8:00
Weekend:24h
Weekdays:
13:00-8:00
Weekend:24h
Occupants 2 adults,
3 children
1 adult,
5 children
Barnlea Close
Pippin Close
Two case study dwellings
Case study
Target design rating CSH Level 4
Main construction
elements
(as designed)
U-values W/m2K
Walls: Timber frame and brick, U-value: 0.21
Roof: Slate roofing, U-value: 0.13
Ground floor: Precast concrete with insulation, U-value:
0.25
Windows: Aluminum frame, double glazing, U-value 1.3
Space heating and hot
water system Efficient gas condensing boilers and radiators
Target air tightness
(m3/hm2 @50Pa) 3
Ventilation strategy MVHR system with summer bypass mode and thermal
sensors.
Renewables Photovoltaics 1.65kWp & 1.88kWp
Key findings
Air permeability tests
• Measured air-permeability rate is 2x design target.
• MVHR systems essentially redundant as measured air-permeability rate
is above the threshold (3m3/h.m2) for installing MVHR systems.
• Air-permeability rate slightly increased during the 2 year monitoring period
In-situ U-value tests
Actual wall U-values are better than design U-Values
Location Design
Wall U-value (W/m2K)
Final averaged
U-Value (W/m2K)
Pippin Close 0.21 0.18
Barnlea Close 0.21 0.14
Barnlea Close Pippin Close
Thermal Imaging
• No significant thermal abnormalities evident in
external walls
• Cold bridges from roof beams
• More careful detailing needed in wall/ceiling
joints and junctions.
• Heat loss through thresholds. Air leakage.
• High levels of air ingress evident around some
window frames due to poor fitting.
• All radiator valves set to maximum level (6).
• Heating remains on 24h/day in 16 BC
• Heating thermostat set to 29-30ºC in both houses
• Missing pipe-work insulation in hot water tank cupboard.
• MVHR was found switched off in 2 PC
• In 16 BC, MVHR was on but supply terminals were closed
• MVHR Boost function not working
Commissioning review and MVHR test
MVHR testing
Pippin Close Barnlea Close
Test A Test B Test A Test B
Measured air flow low rate
(l/s)
Total extract
29.7 10.7 27.6 11.5
Total supply
31.1 12.4 0 17.4
• MVHR Tests during commissioning review showed
system imbalances, with supply being higher than
extract and higher than space requirements
• MVHR were re-commissioned and supply and extract
rates were decreased but there was still a discrepancy
between the two with supply being higher.
• Improper commissioning of MVHR system leading to
cold air draughts resulted in mis-use by occupants.
Energy & environmental monitoring & occupant studies
Annual energy use (01/09/13-31/08/14)
Figures for CSH 4, Average UK stock, Part L compliant taken from DomEarm analysis
221
130
83
139
124
26
25
22
29
54
-3
-1
6
6
52
38
3
3
10
8
-50 0 50 100 150 200 250 300
Average UK stock
Part L
CSH 4
Barnlea Close
Pippin Close
Energy use (kWh/m2/annum)
Actual Gas Actual Electricity import Actual PV export
Actual PV use Gas (SAP) Electricity import (SAP)
PV use (SAP)
Annual CO2 emissions (01/09/13-31/08/14)
Figures for CSH 4, Average UK stock, Part L compliant taken from DomEarm analysis
Carbon factors
Gas 0.198
Electricity 0.517
44
26
16
28
25
13
13
11
15
28
10
8
2
1
0 10 20 30 40 50 60 70
Average UK stock
Part L
CSH 4
Barnlea Close
Pippin Close
Carbon emissions (kgCO2/m2/annum)
Actual Gas Actual Electricity import Gas (SAP) Electricity import (SAP)
Living room temperatures
• Monthly mean temperatures close to the
upper level of comfort band.
• Mean temperatures in July and August
around 25oC and maximum temperatures
reach 31oC
• Maximum winter temperatures are also
high as compared to UK average.
• Monthly mean temperatures range from
20oC in May to 25oC in July. Summer
maximum temperatures reach 32oC.
• Winter mean monthly temperatures range
between 20-21oC but maximum
temperatures exceed 26oC.
Internal temperature distribution
• Temperatures in the living room and
bedroom are between 22-24oC for 44-
46% of the time and between 24-26oC
for 24-31% of the time.
• Kitchen temperatures are high,
remaining between 24-26oC for 46% of
the time and above 26oC for almost
37% of the time.
• Temperatures in the living room and
kitchen are between 20-22oC for 31% of
the time, 22-24oC for 15-21% of the time
and above 26oC for 4% of the time.
• Bedroom temperatures are higher,
remaining between 20-22oC for 38% of
the time.
Window opening during winter
• Occupants leave their windows open for long periods leading to temperature variations.
• Pippin Close: Occupants tend to open the living room window and backdoor when indoor
temperatures rise
• Barnlea Close: Occupants leave the living room window open throughout the day.
CO2 levels
• CO2 concentration in the living room
remains between 500-1000ppm for
55% of the time.
• Bedroom CO2 levels remain between
500-1000ppm for 60% of the time and
above 1500ppm for 7% of the time.
• CO2 concentration in the living room
remains between 500-1000ppm for
60% of the time.
• Bedroom CO2 levels remain between
500-1000ppm for 60% of the time and
above 1500ppm for 7% of the time.
Occupant satisfaction survey (BUS)
• Overall positive opinion
towards the houses
• External appearance, layout,
space and storage scored
higher than the benchmark
• Air quality and comfort, most
appreciated elements
• Tenants are not happy with
utility costs.
Better than
benchmark Similar to benchmark
Worse than
benchmark
Response rate of 80%.
Utilities
Heating
Interviews with occupants
• Occupants do not understand the purpose and operation of MVHR. Ventilate
houses by opening windows even when MVHR is on.
• Information passed on during handover about PVs and MVHR not retained
• Occupants do not trust the MVHR system. Noise and draughts coming from the
vents. Several MVHR system breakdowns in Pippin Close
• Heating controls effective and easy to use.
• Windows open throughout the day even when heating is on (Barnlea Close)
• Occupants open windows when spaces get warm but leave heating on.
Thermostat set to 30oC. (Pippin Close)
• High energy use explained by daily heating, cooking and washing patterns and
occupant window opening habits
• It is evident that air-tightness levels <3 m3/h.m2 are not particularly
easy to achieve in mainstream low energy housing, questioning the need
for adding expensive always-on mechanical ventilation systems.
• Ventilation & airtightness strategies should be considered holistically.
• Robust detailing of joints, junctions and thresholds during design and
construction stages. Use rapid diagnostics (thermal imaging, AT tests).
• Accurate ‘as-built’ SAP models (already required under Building
Regulations) should become mandatory and enforced rigorously.
• Arrangements for sub-metering energy use in houses should be
carefully considered as difficult and expensive to retrofit later on.
• Usability of systems, services and controls need to be considered at
the design and specification stages to avoid any potential misuse.
• Maintenance (service) contracts should be set up for unfamiliar low
carbon systems such as heat pumps, MVHR.
• Handover to occupants should involve occupants trying out systems and
controls supplemented by visual home user guides.
• Without the BPE study, the various faults identified with the systems and
services would go unnoticed, and transform into bigger issues at a later
stage requiring expensive and possibly disruptive remedial works.
Wider lessons for the industry
Thank you!