BPC Modeling Results: Projected Impact of Changing ...For those plants that burn HCl-compliant coal,...
Transcript of BPC Modeling Results: Projected Impact of Changing ...For those plants that burn HCl-compliant coal,...
July 2012
BPC Modeling Results:
Projected Impact of
Changing Conditions
on the Power Sector From the Staff of the Bipartisan Policy Center
BPC Modeling Results: Projected Impact of Changing Conditions on the Power Sector | 2
AUTHORS Jennifer Macedonia, Senior Advisor Colleen Kelly, Policy Analyst DISCLAIMER This report was prepared by the staff of the Bipartisan Policy Center
to promote a better understanding of the possible impacts of U.S.
Environmental Protection Agency regulation of the electric power
sector. The views expressed here do not necessarily reflect those of
the Bipartisan Policy Center’s Energy Project. ACKNOWLEDGEMENTS The Bipartisan Policy Center would like to express its thanks for the
strong support of its funders. In addition, we would like to thank
Chris MacCracken and the team at ICF International for their
modeling support and guidance on this project.
BPC Modeling Results: Projected Impact of Changing Conditions on the Power Sector | 3
Electric Power Sector Current Landscape
The electric power sector in the United States is facing a changing market environment—
one that features low natural gas prices, rising coal prices, flattening electric demand, new
environmental regulations, expanding renewable power, uncertainty about future carbon
risk, and an aging coal fleet. This combination of factors continues to influence the relative
competitive positions of all forms of electricity generation, as evidenced by recent shifts in
dispatch resulting in a declining share of electricity generation from coal-fired generators, as
well as infrastructure decisions including announced coal plant retirements, planned gas-
fired and renewable capacity additions, and proposed retrofits.
To help understand the impacts of these changes, the Bipartisan Policy Center (BPC) has
continued its ongoing effort begun several years ago to model and to analyze the power
sector with ICF International’s Integrated Planning Model (IPM). This document is a follow-
up to the power-sector analysis presented in the June 2011 BPC staff paper, Environmental
Regulation and Electric System Reliability, specifically to the modeling results presented in
that report’s “Appendix B: BPC Modeling Using ICF’s Integrated Planning Model.” This paper
details the assumptions—including important updates on fuel price trends, electric demand
projections, and final air regulations—and results from BPC’s recent analysis.
BPC Modeling Results: Projected Impact of Changing Conditions on the Power Sector | 4
Background on IPM Modeling
IPM is a multi-region model that endogenously determines capacity- and transmission-
expansion plans; unit dispatch and compliance decisions; and power, coal, and allowance
price forecasts—all based on power-market fundamentals. To use the model, it is necessary
to make a number of assumptions concerning key market parameters, including electricity
demand growth, fuel prices, cost and performance of new generating capacity, and cost and
performance of pollution controls and other options for complying with environmental
regulations. This document details the assumptions and regulatory compliance scenarios
included in the BPC analysis. With complex and differing financial, regulatory, and local
considerations influencing the investment decisions for specific generators, IPM is not
intended to accurately predict each unit level decision, but rather is designed to reflect
national trends and to incorporate the key drivers of investment and dispatch decisions.
Assumption for Analysis BPC based many of the assumptions for this analysis on information from the Energy
Information Administration’s Annual Energy Outlook (EIA AEO 2012 Early Release). In some
cases, BPC selected alternative assumptions to reflect recent market conditions.
Assumptions for electricity demand growth, cost and performance of new capacity, and
costs of regulatory compliance options were held constant across the scenarios analyzed.
Natural gas and coal prices varied by scenario based on the relative fuel demand from
scenario to scenario. The model is designed to include the relevant pollutant emission rates
for different fuel and unit types and to choose compliance options to meet the defined
emission limits assumed for each scenario based on the assumed cost and performance of
available pollutant-control technology options and/or fuel switching, as appropriate. Table 1
below summarizes the sources of key assumptions in the analysis. Table 2 summarizes our
detailed assumptions for select parameters.
BPC Modeling Results: Projected Impact of Changing Conditions on the Power Sector | 5
Table 1: Sources of Key Input Assumptions
INPUT
PARAMETER
SOURCE OF
ASSUMPTION NOTES
Electric Demand Growth
EIA AEO 2012 Early Release (regional net energy for load)
BPC did not simulate demand response or additional electric demand sensitivities to represent further energy efficiency investment, appliance standards, etc.
Peak Demand Growth
EIA AEO 2012 Early Release and the same premium in peak overload assumption that EPA makes in the December 2011 MATS analysis
EPA’s peak growth rates are derived from AEO’s load growth and the assumed hourly load profiles in each region.
Natural Gas Prices
EIA AEO 2012 Early Release and ICF-derived curves
BPC used ICF-derived curves, which were created from plotting gas prices and consumption points from AEO 2011 scenarios and calibrating with AEO 2012 Early Release; AEO 2011 data were used for the curve shape and slope, because AEO 2012 Early Release didn’t include scenarios to represent the curve.
Coal Price & Production
ICF-derived coal supply curves
For HCl-compliant coal in the Powder River Basin, BPC adopted EPA’s coal supply curves to limit the production of these coal types as a response to policy drivers.
Air Pollution Control Costs
EPA (FGD, scrubber upgrades, LSD, DSI, SNCR, Fabric Filter, ACI); BPC (SCR)
For those plants that burn HCl-compliant coal, the capital costs of backup DSI were imposed without the operating costs.
Nuclear Power Licensing / Operation
BPC Nuclear units are assumed to receive one 20-year license extension and then retire (at age 60).
Production Tax Credit (PTC) Outlook
BPC
The full value of the PTC is assumed to retire this year, but half of the PTC value is assumed through 2015, before it completely disappears. The half value is intended to reflect some probability that the PTC will be renewed.
Abbreviations used:
MATS: Mercury and Air Toxics Standards HCl: Hydrogen Chloride; air pollutant FGD: Flue Gas Desulfurization; pollution control technology known as a scrubber
LSD: Lime Spray Dryer; pollution control technology known as a dry scrubber DSI: Dry Sorbent Injection, pollution control technology SNCR: Selective Non-Catalytic Reduction; pollution control technology
ACI: Activated Carbon Injection; pollution control technology SCR: Selective Catalytic Reduction; pollution control technology
BPC Modeling Results: Projected Impact of Changing Conditions on the Power Sector | 6
Table 2: BPC Assumptions for the Cost and Performance of Air-
Pollution Controls
CAPACITY
(MW) WET FGD LSD DSI SCR SNCR
Capital Costs (2010$/kW)
300 596 510 57 450 20
500 516 441 40 400 15
700 469 419 31 350 N/A
Variable O&M (2010$/kW) 1.91 2.45 Bit. 8.46 Sub. & Lig. 3.83
1.29 1.02
Energy Penalty % 2.10% 1.33% 0.02% 0.50% 0.05%
Removal SO2 – 95% SO2 – 92% SO2 – 70% NOX – 85% NOX – 30%
First Year Allowed 2014 2014 2014 2014 2013
Source EPA EPA EPA BPC EPA
CAPACITY
(MW)
FABRIC
FILTER ACI
FGD
UPGRADE ESP UPGRADE
Capital Costs (2010$/kW)
300 168 Bit. – H 3.65; Bit. – L 2.72; Lig. 25.11; Sub. 3.86
101 55-100 500 152
700 142
Variable O&M (2010$/kW) 0.15
Bit. – H 0.41; Bit. – L 0.27; Lig. 0.50; Sub. 0.35
0 0
Energy Penalty % 0% 0% 0% 0%
Removal Hg – 90% Hg – 90% SO2 – 90% Hg – 99%
PM Compliance
First Year Allowed 2014 2013 2014 2014
Source EPA EPA EPA EPA
Abbreviations used (see also: list under Table 1):
MW: Megawatt kW: Kilowatt
O&M: operation and maintenance Bit: bituminous coal Sub: sub-bituminous coal
Lig: lignite coal SO2: sulfur dioxide
NOX: nitrogen oxides Hg: mercury
BPC Modeling Results: Projected Impact of Changing Conditions on the Power Sector | 7
Description of Scenarios For this analysis, BPC defined two scenarios—a Base Case and a Policy Case—to examine
the impacts of the Environmental Protection Agency’s (EPA) proposed regulations on the
U.S. power sector. BPC had ICF analyze these cases using IPM based on the assumptions
described above. The cases are described below in more detail. BPC conducted similar
modeling analysis in spring 2011; two of the cases for the 2011 scenarios are also detailed
briefly below as they are included for comparison in some of the results figures.
Table 3: Overview of Modeling Scenarios
MODELING SCENARIO DESCRIPTION
Base Case All existing regulations as of summer 2011 without CSAPR and MATS
Policy Case All existing regulations as of summer 2011 with CSAPR and MATS
Former BAU Case All existing regulations as of winter 2011 with CAIR and without MATS and CSAPR
Former Policy Case All existing regulations as of winter 2011 with proposed rules—MATS, Transport Rule, cooling water intake rule, and
coal ash regulation
BPC BASE CASE
The BPC Base Case represents a business-as-usual (BAU) projection in the absence of two
recently finalized EPA air regulations: the Mercury and Air Toxics Standards (MATS) for
power plants and the Cross-State Air Pollution Rule (CSAPR). This Base Case incorporates
other existing finalized federal and state regulations as of summer 2011, including state
mercury, SO2, and NOX requirements, as well as state renewable portfolio standards. It
assumes regional cap-and-trade programs for SO2 and NOX in the eastern United States, as
stated under Phases I and II of the Clean Air Interstate Rule (CAIR). Pollution control and
retirement decisions reflected in completed New Source Review consent decrees, settlement
agreements, and “firm”1 public retirement announcements as of fall 2011 are also included
in the BPC Base Case.
BPC POLICY CASE
This case builds on the BPC Base Case and adds the recently finalized EPA air rules MATS
and CSAPR. This BPC Policy Case does not include proposed regulations for cooling water
and coal ash, the proposed New Source Performance Standard for greenhouse gases, or
more stringent requirements for SO2 and NOX beyond CSAPR that might be required in the
future to meet National Ambient Air Quality Standards and/or future Regional Haze
BPC Modeling Results: Projected Impact of Changing Conditions on the Power Sector | 8
requirements. BPC incorporated the following assumptions regarding the final air
regulations:
Mercury and Air Toxics Standards (MATS): IPM models emissions from various fuels and
unit types and allows the model to choose the most economic compliance strategy based
on the cost and performance assumptions of pollution retrofits and fuel changes
available for specific unit types to comply with emission limits under the MATS rule. As
mentioned above, this case primarily relies on EPA assumptions from the MATS final
rulemaking for control-equipment costs and performance. For compliance timing, this
Policy Case assumes that when chosen as a viable and economic compliance option,
installations of ACI, DSI, as well as ESP upgrades will be completed by January 2015. To
simulate use of the one-year MATS compliance-deadline waiver authorized by permitting
authorities, BPC assumed that all wet and dry scrubber and baghouse/fabric filter
installations required for compliance would be completed by January 2016. In addition,
units that were economically projected to retire rather than incur compliance costs were
assumed to get a one-year compliance waiver that would allow operation without MATS
compliance through the end of 2015 for units that retire by January 2016. To simulate
potential reliability constraints, retirements were limited to 15 gigawatts (GW) in 2014
and then determined on an economic basis thereafter. This BPC Policy Case assumes a
limited supply of sub-bituminous coal with low chlorine content that allows compliance
with the MATS HCl limit without any additional pollution controls. For units burning this
“HCl-compliant coal,” we assigned a capital cost for the installation of “backup” DSI, but
did not include an operating/sorbent cost for DSI.
Cross-State Air Pollution Rule (CSAPR): This BPC Policy Case, developed without
knowledge of the court’s final decision, assumes that the court’s stay on the regulation
delays Phase I CSAPR compliance until 2013 and that Phase II and the assurance
provisions begin in 2014. In this exercise, interstate trading is limited to regional
markets (i.e., Group 1 vs. Group 2 SO2; annual vs. ozone season NOX). Before 2013, the
Policy Case includes the same CAIR assumptions as the Base Case.
BPC FORMER BAU AND POLICY CASES
The BPC Former BAU Case was presented in the June 2011 BPC staff paper Environmental
Regulation and Electric System Reliability and represents our business-as-usual (BAU)
projection as of spring 2011. This case includes existing federal and state regulations as of
January 2011, including state mercury, SO2, and NOX requirements, as well as renewable
portfolio standards. The case assumes regional cap-and-trade programs for SO2 and NOX in
the eastern United States, as stated under CAIR Phases I and II. The case does not include
any federal mercury-reduction or carbon dioxide requirements for the power sector.
The BPC Former Policy Case was also presented in the June 2011 staff paper and includes
BPC assumptions as of spring 2011 for the requirements under EPA’s then-proposed suite of
new regulations, including the proposed MATS, proposed transport rule (which was
BPC Modeling Results: Projected Impact of Changing Conditions on the Power Sector | 9
subsequently finalized as CSAPR), the proposed cooling water intake rule §316 (b), and an
assumed non-hazardous coal ash regulation.
Select Results of BPC Analysis The following charts present select results for the BPC cases described in the previous
section and, in some cases, also include the 2011 BPC scenarios for comparison. Unless
otherwise specified, the results are presented for the continental United States and do not
include Hawaii and Alaska.
Figure 1: Projected Fate of Current Fleet by 20162
Figure 1 reflects the projected status of the current fleet of U.S. electric-generating units as
of the year 2016 under BPC’s Policy Case with MATS and CSAPR. (New capacity additions
are not included in Figure 1.) A total of 56 GW of coal-fired generating capacity is expected
to retire by 2016, with 40 GW retiring under BAU market conditions and an additional 16
GW retiring as a result of MATS and CSAPR compliance requirements. For the Base Case,
the key drivers of coal plant retirements include flattening electric demand, low natural gas
prices, and higher coal prices. These model inputs have experienced significant changes
since the last round of BPC analysis in 2011.
Remaining Coal (264 GW)
Natural Gas/Oil Retired in Base Case (30 GW)
Remaining Natural Gas/Oil
(427 GW)
Nuclear (105 GW)
Other (168 GW)
Remaining Coal
Natural Gas/Oil Retired in Base Case
Remaining Natural Gas/Oil
Nuclear
Other (Renewables, Hydro)
Coal Retired in Base Case (40 GW)
Coal Retired by Air Rules (16 GW)
Retiring coal (56 GW = 5% of total fleet)
BPC Modeling Results: Projected Impact of Changing Conditions on the Power Sector | 10
Figure 2: Electric Demand Annual Forecasts 2009 – 20353
A key input that has changed since BPC’s 2011 analysis is the forecast for electric demand.
As seen in Figure 2, electric demand projections from EIA AEO 2012 reflect a flattening of
demand growth. The AEO 2012 demand forecast is lower than in recent years, which has a
significant impact on power-sector projections. Even though there are some regions of the
country expecting growth in electricity demand, the national trend reflects a slowing of the
historical growth rate for electricity demand due to a slow economic recovery in the short
term, as well as deployment of energy efficiency measures throughout the economy. The
absence of growing demand for electricity, combined with the excess capacity in the existing
fleet, is expected to depress the need for new generating capacity, even as significant
amounts of existing generation retire.
Figure 3: Projected Natural Gas Prices at Henry Hub4,5
3500
4000
4500
5000
5500
6000
Bil
lio
n k
Wh
AEO 2012 AEO 2011 AEO 2010 AEO 2009 AEO 2008 AEO 2007
4.00
4.50
5.00
5.50
6.00
6.50
7.00
7.50
8.00
8.50
9.00
$ /
MM
BT
U
Base Case Policy Case Former BAU Former Policy Case
BPC Modeling Results: Projected Impact of Changing Conditions on the Power Sector | 11
Another key assumption that was updated since the 2011 analysis is the reference case of
natural gas prices, which we based on recently derived gas supply curves that were
calibrated with natural gas price projections in AEO 2012 Early Release. Figure 3 shows
projected natural gas prices at Henry Hub—used for the current analysis—compared with
results from the previous 2011 BPC analysis. In the current BPC Base Case, the natural gas
price is assumed to be near $4/mmBtu in 2013 and to climb over time to around
$6.25/mmBtu in 2030. As a result of the model simulating the impacts of increased demand
for natural gas under the BPC Policy Case, natural gas prices rise above the Base Case
prices from 2013 and beyond, but nonetheless remain below the Former BAU case natural
gas price. In 2030, the Policy Case natural gas price is projected to be around
$6.25/mmBtu, compared with around $8.00/mmBtu projected in the 2011 BPC analysis.
Figure 4: National Minemouth Coal Prices
While natural gas price projections have decreased recently, the coal price projections have
increased over the last few years. This BPC analysis incorporates updated coal price
projections (blue line in Figure 4). Figure 4 compares current coal price projections with the
assumptions from last year’s BPC analysis (in dashed lines). Throughout the entire period,
the BPC Base and Policy Case coal prices were higher than the former BPC BAU and Policy
Cases. The spike in the 2016 national average coal price in the BPC Policy Case is due to the
projected premium for low-chlorine-content sub-bituminous western coal (HCl-compliant
coal); this premium is projected based on the assumption, consistent with EPA’s analysis
supporting the MATS Final Rule, that such HCl-compliant coal allows compliance with the
MATS HCl limit without additional pollution controls.
1.50
1.60
1.70
1.80
1.90
2.00
2.10
$ /
MM
BT
U
Base Case Policy Case Former BAU Case Former Policy Case
BPC Modeling Results: Projected Impact of Changing Conditions on the Power Sector | 12
Figure 5: Cumulative Coal Retirements
In comparison with the 2011 BPC modeling scenarios, the Base Case coal retirements have
more than doubled (from 14 GW in the previous analysis to 40 GW today), while the
incremental retirements from the EPA rules is roughly the same (15–18 GW in the previous
case and 16 GW today). (See Figure 5.)
Figure 6: Cumulative Projected Capacity Additions6
Figure 6 shows cumulative U.S. capacity additions by type in both the BPC Base and Policy
Cases. In both cases, the build mix is dominated by renewable capacity (i.e., wind, biomass,
and other renewables) in the short term, as states work to meet Renewable Portfolio
Standards. Natural gas–fired plants are not built in substantial numbers until 2025, largely
0.00
10.00
20.00
30.00
40.00
50.00
60.00
Gig
aw
att
s
Base Case Policy Case Former BAU Case Former Policy Case
Current projection: 16 GW retires due to air rules
Last year's BPC projection: policy retires 15-18 GW
0
20
40
60
80
100
120
140
Base Case
Policy Case
Base Case
Policy Case
Base Case
Policy Case
Base Case
Policy Case
2016 2020 2025 2030
Gig
aw
att
s
Other NG/Oil Nuclear Biomass
BPC Modeling Results: Projected Impact of Changing Conditions on the Power Sector | 13
because of the surplus of gas-fired capacity that was built out in the 1990s. Visibly absent is
new coal capacity; through 2030, no new coal generation is projected to be built in either
case except for the units that began construction prior to this analysis, which are not
included in this chart. Although the Policy Case does not include the EPA’s proposed New
Source Performance Standard for greenhouse gases—which would essentially require any
new coal capacity to include carbon capture and sequestration—these results would not be
impacted by such a requirement, because of the lack of new coal builds.
Figure 7: Generation Mix for Base and Policy Cases 2012 – 2035
Coal generation has seen a decline in recent years that is expected to continue. However,
even with the movement toward natural gas and renewables and a projected retirement of
56 GW of coal capacity in the coming years, coal is projected to remain the largest
generation source in both the Base Case and Policy Case through 2035 (as shown in Figure
7). In fact, the differences in generation fuel mix between the two cases are somewhat
modest. Generation from coal in the Policy Case is 3 percent lower in 2020 and 6 percent
lower in 2030 relative to the Base Case, as compliance costs further impact the competitive
position of coal generators. Increased gas-fired generation makes up for the majority of that
decline. In the BPC Policy Case, generation from gas is 5 percent higher in 2020 and 9
percent higher in 2030, compared with the BPC Base Case. Potential future environmental
requirements that are not included in this Policy Case, such as stricter NOX and/or
particulate limits, GHG limits for existing sources, coal ash handling, and cooling water
requirements have the potential to further influence the future generation mix.
0
1000
2000
3000
4000
5000
6000
Th
ou
san
d G
Wh
Base Case
Coal Natural Gas/Oil Nuclear Hydro Renewables Other
0
1000
2000
3000
4000
5000
6000
Th
ou
san
d G
Wh
Policy Case
BPC Modeling Results: Projected Impact of Changing Conditions on the Power Sector | 14
Figure 8: Coal Capacity and Percent Difference in Coal Generation
Figure 9: 2012 Generation from Retiring and Non-Retiring Coal-
fired Units
Figure 8 highlights the changes in coal-fired generating capacity (i.e., nameplate capacity of
all remaining coal-fired electric generating units), as well as the amount of electricity
projected to be generated from coal-fired facilities. As coal-fired generators retire, coal-
generating capacity falls through 2016 and then remains constant. In response to the
competitive advantage of gas-fired generation in the short term, the percent change in coal
generation follows a similar downward trajectory through 2016. However, by 2020, the
amount of electricity generated from coal-fired facilities is projected to increase above
current levels and continue to grow well beyond today’s historically low level to reach 2007
– 2008 levels around 2025.
-10%
-5%
0%
5%
10%
15%
20%
0
50
100
150
200
250
300
350
% D
iffe
ren
ce
(B
ase Y
ear =
20
12
)
Co
al C
ap
acit
y (
GW
)
Coal Capacity Coal Generation % Diff
-
500,000
1,000,000
1,500,000
2,000,000
Base Case Policy Case
20
12
Gen
erati
on
(G
Wh
)
Operate Post-2016 Retire by 2016
BPC Modeling Results: Projected Impact of Changing Conditions on the Power Sector | 15
Figure 9 offers an explanation for these trends, which on the surface may seem to be
contradictory. The coal plants that are retiring contribute only a small percentage (see the
red portion in Figure 9) to the total amount of electricity produced from coal-fired
generators in 2012. As shown in Figure 10, the units projected to retire tend to be older,
smaller, and less efficient on average than the rest of the fleet and tend to operate much
less frequently than baseload coal capacity: 74 percent of the projected retiring coal is at
least 40 years old, 50 percent are 200-megawatt capacity or less, and 55 percent have heat
rates of at least 11,000 mmBtu. (Higher heat rates indicate lower efficiency.) More details
about the age, size, and heat rate of units in the fleet can be found in the appendix.
Figure 10: Demographics of Coal Units Projected to Retire by
20167
Figure 11: Nationwide Emissions of Various Pollutants in 2016
15%
13%
17% 34%
16%
5% Size of Retiring Coal
500+
300-500
200-300
100-200
50-100
Less than 50
3% 5%
11%
36%
32%
13%
Heat Rate of Retiring Coal
14,000+
13,000-14,000
12,000-13,000
11,000-12,000
10,000-11,000
Less than 10,000
8%
40%
26%
16%
10%
Age of Retiring Coal
60+
50-60
40-50
30-40
Less than 30
Retiring plants tend to be older, smaller, and less
efficient:
74% are at least 40 years old
50% are 200 MW capacity or less
55% are at least 11,000 mmBtu heat rate
0
1
2
3
4
Base Case
Policy Case
Mil
lio
n T
on
s
Sulfur Dioxide
0
5
10
15
20
25
30
Base Case
Policy Case
To
ns
Mercury
0
500
1000
1500
2000
2500
Base Case
Policy Case
Mil
lio
n M
etr
ic T
on
s
Carbon Dioxide
0.0
0.5
1.0
1.5
2.0
Base Case
Policy Case
Mil
lio
n T
on
s
Nitrogen Oxides
BPC Modeling Results: Projected Impact of Changing Conditions on the Power Sector | 16
Table 4: 1995 vs. 2016 Emissions by Pollutant8,9
POLLUTANT UNITS 1995 LEVELS 2016 BASE
CASE LEVELS
2016 POLICY
CASE LEVELS
SO2 Million Tons 12.1 3.8 1.8
NOx Million Tons 6.4 1.5 1.4
CO2 Million Metric Tons 1960 2009 1938
Mercury Tons 59.010 27.0 6.1
In addition to impacting the generation fuel mix, the impact of the Policy Case is seen in the
estimates of nationwide emission levels in Figure 11. The largest differences from CSAPR
and MATS are seen in the levels of SO2 and mercury; the Base Case levels are more than
two times the Policy Case levels for SO2 in 2016 and more than four times for mercury.
Looking at Table 4, substantial progress has also been made in reducing NOX from earlier
levels. Moving forward, there is potential for further reductions both within and outside the
power sector.
Figure 12: Compliance with SO2 and HCl Requirements (CSAPR
and MATS)11 for Non-Retiring Units
Of the pollution controls expected for compliance with the various limits in CSAPR and
MATS, a wet scrubber (flue gas desulfurization) is the most expensive technology. Contrary
to the final EPA regulations and available control-technology options, some previous
analyses have assumed that all plants will require wet scrubbers to comply with these
regulations, which has inflated the projected costs and resulting coal plant retirements in
their assessments.12 Instead, BPC analysis allows the model to choose the most economic
compliance strategy from the cost and performance data specified in the final rulemakings,
which include additional lower-cost technologies and fuel-switching options.
Existing Scrubbers Add wet scrubber
Add dry scrubber
Add DSI
Compliant coal
BPC Modeling Results: Projected Impact of Changing Conditions on the Power Sector | 17
Figure 12 shows that almost 70 percent of the coal capacity projected to remain in
operation through 2016 already has scrubbers in place, although some require upgrades. To
comply with the SO2 requirements of CSAPR and the HCl limit in MATS, 13 percent of the
coal capacity forecasted to remain in operation is projected to add control technology (6
percent to add DSI, 4 percent to add a dry scrubber, and 3 percent to add a wet scrubber).
In addition, almost 20 percent (49 GW) of the remaining coal-fired fleet is projected to
comply by burning compliant coal13 (primarily Powder River Basin/western sub-bituminous
coal with low enough chlorine and sulfur contents to meet the HCl and SO2 emission
requirements without add-on controls). The units projected to burn such compliant coal are
units that have previously burned sub-bituminous coal, either in total or as part of a blend
(see Figure 18 in the Appendix). Because these units are not projected to install a scrubber
or operate DSI, their compliance costs are substantially less than most analyses assume
and many are projected to avoid retirement and remain competitive.
Figure 13: Regional Pollution Control Status by 2016
Figure 13 shows the projected status and pollution control complement of the remaining
coal fleet in 2016, broken out by areas of the country. The local conditions, environmental
requirements, and extent of pollution controls vary by state and region. Most of the units in
the West and Northwest are well controlled for SO2/acid gases with a scrubber or DSI but
lack post-combustion NOX controls. The amount of post-combustion NOX control (i.e., SCR
and SNCR) increases as you move east across the country, reflecting the fact that many of
these eastern areas have a regional ozone problem that has led to control requirements.
The central region has the largest percentage of capacity without advanced post-combustion
controls and is where much of the lower-emitting (for SO2 and HCl) compliant western coal
is burned.
BPC Modeling Results: Projected Impact of Changing Conditions on the Power Sector | 18
Appendix: Additional Figures
Figure 14: Coal Retirements by Age and Size
Figure 15: Coal Retirements by Age and Heat Rate
-
200
400
600
800
1,000
1,200
1,400
- 10 20 30 40 50 60 70 80
Size
(MW
)
Age in 2016 (Years)
Coal Retirements by Age and Size
Operates Post-2016
Retires in Policy Case
Retires in Reference Case
6,000
7,000
8,000
9,000
10,000
11,000
12,000
13,000
14,000
15,000
16,000
- 10 20 30 40 50 60 70 80
Hea
t Rat
e (B
tu/K
Wh)
Age in 2016 (Years)
Coal Retirements by Age and Heat Rate
Operates Post-2016
Retires in Policy Case
Retires in Reference Case
BPC Modeling Results: Projected Impact of Changing Conditions on the Power Sector | 19
Figure 16: Status of SO2 and NOX Pollution Controls after
Implementation of CSAPR and MATS14
Figure 17: Regional Breakout of Projected Coal Plant Retirements
(GW)
56%
0%
44%
SO2 Controls in 2012
Wet Scrubbers
Dry Scrubbers
No add-on SO2 Controls 70%
4%
6%
20%
SO2 Controls by 2016: Policy Case
Wet Scrubbers
Dry Scrubbers
DSI
No add-on SO2 Controls
17%
4%
78%
NOx Controls in 2012
SCR
SNCR
No post-combustion NOx Controls
19%
4%
77%
NOx Controls by 2016: Policy Case
SCR
SNCR
No post-combustion NOx Controls
BPC Modeling Results: Projected Impact of Changing Conditions on the Power Sector | 20
Figure 18: Impact of Policy on Coal Switching: Coal Consumption
by GW
-
50
100
150
200
250
300
350
2012 2017
Gig
aw
att
s
Lignite
Blended
HCl Compliant Sub-Bit
Sub-Bit
Bituminous
BPC Modeling Results: Projected Impact of Changing Conditions on the Power Sector | 21
Endnotes
1 For this analysis, “firm” planned retirements are defined as units that were (1) subject to agreement with EPA,
(2) tied to construction of new capacity that is underway, and (3) already in the process of closing as of fall 2011. Firm coal retirements using that criterion totaled roughly 14 GW over the period 2011 to 2020. The firm units did not include more recent announcements made specifically in response to MATS, low natural gas prices, and electric demand—which may coincide with IPM projected economic retirements.
2 New capacity additions not included.
3 Energy Information Administration. Annual Energy Outlook. Available at: http://www.eia.gov/forecasts/aeo/.
4 The 2011 BAU and Policy Cases are in 2006 dollars, while the 2012 BAU and Policy Cases are in 2010 dollars.
5 IPM does not model every year that is illustrated in the figures; the model includes 2012 – 2017, 2020, 2025,
2030, and 2035. Data for the other years in the charts throughout the paper was extrapolated.
6 This chart does not include firm builds. Firm builds are units that are currently under construction or units that are sufficiently far along in the permitting and financing processes.
7 The percentages are computed as percent of megawatts.
8 Energy Information Administration. U.S. Carbon Dioxide Emissions from Electric Power Sector Energy
Consumption, 1990-2009.
9 Environmental Protection Agency. National Emissions Inventory Air Pollutant Emissions Trends Data.
10 1990 levels listed in lieu of 1995 figure. Environmental Protection Agency. Mercury and Air Toxics Standards (MATS): Cleaner Power Plants. Available at: http://www.epa.gov/mats/powerplants.html#limits.
11 Analysis based on BPC Spring 2012 Policy Case; Particulate control upgrades/retrofits may also be required.
12 For example, in their May 2012 analyses, the Electric Power Research Institute assumed scrubber installations in
its “Reference (Environmental Controls) Scenario,” and North American Electric Reliability Corporation assumed wet scrubbers for all units in its analyses.
13 This is projected to result in a premium for such compliant coal, which is reflected as a spike in the national
mine-mouth coal price in Figure 4.
14 SO2 controls charts include just coal plants; NOx controls charts include both coal and natural gas plants. The
percentages are computed as percent of megawatts.