BP-Deepwater horizon-Macondo-Gulf Of Mexico Oil Spill
-
Upload
dhanish-ahsen -
Category
Engineering
-
view
226 -
download
4
Transcript of BP-Deepwater horizon-Macondo-Gulf Of Mexico Oil Spill
oil spill
Presented By
Dhanish Ahsen
What went wrong?
Deepwater HorizonRig operator
Cementing ContractorPrincipal DeveloperMacondo Prospect
Largest accidental marine oil spill
Accused for weaknesses in
cement design and testing, quality
assurance and risk assessment.
Nitrogen based cement used was
blamed
Accused for failure of BOP and incorrect evaluation of negative pressure test results
Accused for Cost Savings, poor safety
operations , well design and
decisions regarding testing procedures
28°44′17.30″N88°21′57.40″W
Mississippi Canyon Block 252
210mnGallons ofCrude Oil
11Killed
17Injured
20 April – 15 July 2010
87Days 5600mDeep Well
1600mDeep Water
The Deepwater Horizon
Semi-submersible, mobile, floating, dynamically positioned drilling rig
9yearOld
3000mDeep Water Operation
ManufacturerOwnerLessee
March ‘08-September ‘13
Upto
57 ft.Tall
400 tonsWeight
Manufacturer Lessee Owner
Blow out preventer
• BOP failed to activate• Didn't test the blowout
preventer's individual safety systems.
• BOP was powered by a battery (Found to be dead one)
8:45 pm CDT- Unexpected burst of pressure from the reservoir (kick)
9:45 pm CDT- High-pressure methane gas from the well expanded into the drilling riser and rose into the drilling rig
9:56 pm CDT- where it ignited and exploded, engulfing the platform
What went wrong?
What went wrong?
• Blind shear rams failed to fully close and seal due to a portion of drill pipe buckling between the shearing blocks.
• Defective cement job
• failure to run a cement bond log test
• BOP had a hydraulic leak and a failed battery, and therefore failed
• Installed just one third centralizers
• Faulty wiring in two places, a dead battery and a bent pipe in the hulking device
Failed safety systems and irresponsible behavior of contractors had led to the explosion, including claims that Halliburton failed to properly use modeling software to analyze safe drilling conditions
“
”
BP blames contractors
• BP opted for a single long run of pipe rather than an alternative approach that would have increased the barriers to gas flow.
• BP failed to conduct a "cement bond log" test to evaluate the integrity of the cement at the bottom of the well, which was what blocked gas and oil from emerging up the production pipe.
• BP installed fewer than one-third of the recommended number of centralizer devices, which Transocean said had the effect of "dramatically increasing the risk of cement channeling and gas flow."
“
”
Contractors blames BP
Word War
BP spokesman Geoff Morrell said all of the evidence "demonstrates that Transocean owned the rig's blowout preventer and was responsible for its maintenance".
Transocean spokesman Brian Kennedy said the CSB report confirms the blowout preventer had been tested properly and had activated during the accident, “but was unable to seal the well because immense pressure buckled the drill pipe and prevented the blind shear ram from functioning as designed.”
“ ”
Conclusion
A complex and interlinked series of mechanical failures, human judgments, engineering design, operational implementation and team interfaces
BP is ultimately responsible for the spill, and that Halliburton and Transocean share some of the blame.
"a rush to completion"Time & Money