Boyce Tues 830
-
Upload
leslie-connalley -
Category
Documents
-
view
223 -
download
0
Transcript of Boyce Tues 830
-
7/31/2019 Boyce Tues 830
1/85
Introduction toTrenchless Methods
Presented by
Glenn M. Boyce, PhD, PE
Senior Associates
April 21, 2009
-
7/31/2019 Boyce Tues 830
2/85
Presentation Objectives
Provide a better understandingof trenchless methods used fornew installations
Learn the advantages and
limitations of the methods Discuss contractor
qualifications
-
7/31/2019 Boyce Tues 830
3/85
Types of Infrastructure
Gas Pressure
Water Pressure Sewer Gravity Drainage Gravity Power Non-gravity Communications Non-gravity
-
7/31/2019 Boyce Tues 830
4/85
Trenchless Methods Impact moling Pipe ramming Auger boring Pilot tube Pipe jacking / Microtunneling
Conventional tunneling Horizontal directional drilling Pipe bursting
-
7/31/2019 Boyce Tues 830
5/85
Generic Size and Length Method Size Length
Moling 2 - 12 150
Ramming 8 - 72 300 Auger Bore 8 - 60 250 Pilot Tube 6 - 42 300 Microtunneling 12 - 108 1,500 Pipe Jacking >54 3,000 HDD 2 - 48 6,500 Tunneling >60 Any length
-
7/31/2019 Boyce Tues 830
6/85
What to Do?
Choose the right method Use established Standards Collect information/investigate Plan ahead
Conduct risk assessments Include mechanisms to handle
conflicts
-
7/31/2019 Boyce Tues 830
7/85
-
7/31/2019 Boyce Tues 830
8/85
Auger Boring
Road crossings
Cohesive soils Short distances Above water table Need steel casing Minor steering
-
7/31/2019 Boyce Tues 830
9/85
60-inch Diameter SBU-A
-
7/31/2019 Boyce Tues 830
10/85
Pilot Tube Method
Medium distances
Straight alignments with goodaccuracy Variety of soils Smaller shafts Moderate
equipment costs
-
7/31/2019 Boyce Tues 830
11/85
Step 1
-
7/31/2019 Boyce Tues 830
12/85
-
7/31/2019 Boyce Tues 830
13/85
-
7/31/2019 Boyce Tues 830
14/85
-
7/31/2019 Boyce Tues 830
15/85
Step 2
-
7/31/2019 Boyce Tues 830
16/85
Pilot Tube + Plus
Now used as a guide forother method Auger boring Pipe Ramming
-
7/31/2019 Boyce Tues 830
17/85
Pipe Ramming Wide range of
diameters Soils only Continuously
supported Typically < 300
Above and belowwater table
Need steel casing
No steering control
-
7/31/2019 Boyce Tues 830
18/85
Installation Method Ramming in continuous length or segments
-
7/31/2019 Boyce Tues 830
19/85
Rammingin
Progress
-
7/31/2019 Boyce Tues 830
20/85
Pilot tube
-
7/31/2019 Boyce Tues 830
21/85
Pipe Jacking Large diameters Soils and mixed
ground Face supported Long distances
Above the watertable
Steerable
-
7/31/2019 Boyce Tues 830
22/85
Microtunneling Range of diameters (> 12) All ground types
Continuous face support Long distances Above or below water table
Range of pipe materials Steerable to line and grade
-
7/31/2019 Boyce Tues 830
23/85
Micro vs Utility TunnelingRemotely operatedPrecise guidancePipes jacked from launch pitContinuous support to face
ConventionalRib & Lagging Tunnel
Microtunnel
-
7/31/2019 Boyce Tues 830
24/85
Tunnel Shield Construction
Lining is built within shield. Lining does notmove longitudinally after placement.
-
7/31/2019 Boyce Tues 830
25/85
Required Axial Thrust versus Lengthof Drive for Same Diameter
-
7/31/2019 Boyce Tues 830
26/85
Opposite Approaches
Open Cut
What happenshappens
Trenchless
Understand and plan
-
7/31/2019 Boyce Tues 830
27/85
What to Do? Understand the site history and
potential obstructions
Look at old aerial photos Conduct ageotechnicalprogram
Locate allutilities
-
7/31/2019 Boyce Tues 830
28/85
Potential Obstructions
Cobbles or Boulders
Wood Fill materials Hard zones Mixed faces
-
7/31/2019 Boyce Tues 830
29/85
Typical Machine Sizes Piercing 2 to 3 inches Pilot Tube 6 to 36 inches
HDD 6 to 54 inches Auger Boring 10 to 60 inches
Pipe Jacking/MT 12 to 96 inches Pipe Ramming 12 to 144 inches Shield 60 to 144 inches
-
7/31/2019 Boyce Tues 830
30/85
Typical CMP Culverts
-
7/31/2019 Boyce Tues 830
31/85
Replacement Issues
Need to increase size foraquatic passage
Must keep existing culvertactive during construction
Minimize costs Develop the best cross section Use the right materials
-
7/31/2019 Boyce Tues 830
32/85
Possible Solutions
-
7/31/2019 Boyce Tues 830
33/85
Consume the Culvert
-
7/31/2019 Boyce Tues 830
34/85
Use Liner Plate Tunnel
-
7/31/2019 Boyce Tues 830
35/85
-
7/31/2019 Boyce Tues 830
36/85
Closing Thoughts
Methods still evolving Many hybrid methods emerging Better alignment control
emerging in auger boring
applications Must identify potential
obstructions (or get X-ray vision)
-
7/31/2019 Boyce Tues 830
37/85
HORIZONTAL DIRECTIONALDRILLING (HDD)
Samuel T. Ariaratnam, PhD, PE
Arizona State University
-
7/31/2019 Boyce Tues 830
38/85
BackgroundLengths up to 8,400 feet
Diameters of 2 54
Applications:Utility conduitsPipelinesGravity sewers
Force mainsHorizontal remediation wellsGeotechnical investigations
-
7/31/2019 Boyce Tues 830
39/85
Pilot Bore and Tracking
Pilot Bore
-
7/31/2019 Boyce Tues 830
40/85
-
7/31/2019 Boyce Tues 830
41/85
Drill Bits
-
7/31/2019 Boyce Tues 830
42/85
-
7/31/2019 Boyce Tues 830
43/85
Reaming/Hole Enlargement
Reaming
-
7/31/2019 Boyce Tues 830
44/85
-
7/31/2019 Boyce Tues 830
45/85
CLAY
ANNULAR SPACE REGION
-
7/31/2019 Boyce Tues 830
46/85
SAND
ANNULAR SPACE REGION
-
7/31/2019 Boyce Tues 830
47/85
Pipe Material Distribution
Underground Construction Magazine
9th
Annual Survey, June 2007
-
7/31/2019 Boyce Tues 830
48/85
-
7/31/2019 Boyce Tues 830
49/85
-
7/31/2019 Boyce Tues 830
50/85
-
7/31/2019 Boyce Tues 830
51/85
-
7/31/2019 Boyce Tues 830
52/85
-
7/31/2019 Boyce Tues 830
53/85
-
7/31/2019 Boyce Tues 830
54/85
-
7/31/2019 Boyce Tues 830
55/85
-
7/31/2019 Boyce Tues 830
56/85
-
7/31/2019 Boyce Tues 830
57/85
-
7/31/2019 Boyce Tues 830
58/85
-
7/31/2019 Boyce Tues 830
59/85
Conclusions HDD is a minimally-intrusive trenchlessconstruction method suited for highly
congested urban areas and high traffic zones Horizontal Directional Drilling equipment is
capable of installing a wide range of utilities HDD will never replace traditional open-cut
methods; however, they complement eachother
-
7/31/2019 Boyce Tues 830
60/85
PIPE BURSTING
Samuel T. Ariaratnam, Ph.D., P.E.
Arizona State University
-
7/31/2019 Boyce Tues 830
61/85
Pipe Bursting
Lengths typically 300-600 ft
Diameters up to 42
Applications: replacement of force mains
replacement of gravitysewers
Static Head
Pneumatic Head
-
7/31/2019 Boyce Tues 830
62/85
-
7/31/2019 Boyce Tues 830
63/85
Introduction
Emerging field of pipe replacement
Replacement of the host pipe byfragmenting the existing conduitand installing a completely newpipe of equal diameter or larger inits place.
-
7/31/2019 Boyce Tues 830
64/85
Applications
Total pipe replacementTypical upsize as much as 20 30%Industrial & Municipal - Main Line &LateralsVarious host and product pipe materialsContinuous or Sectional pipe installation
-
7/31/2019 Boyce Tues 830
65/85
Pipe Bursting Feasibility
May achieve lower costs compared
to open trenchLess construction timeMinimal excavationSocial cost savingsReduces ground settlementLow environmental impact
S i M h d (C i )
-
7/31/2019 Boyce Tues 830
66/85
Static Method (Continuous)
-
7/31/2019 Boyce Tues 830
67/85
Static Method (Sectional)
-
7/31/2019 Boyce Tues 830
68/85
Pneumatic Method
Almost all types of pipe can
-
7/31/2019 Boyce Tues 830
69/85
Almost all types of pipe canbe burst
Cast iron Steel Ductile iron High Density Polyethylene Polyvinylchloride
Concrete Reinforced concrete Asbestos cement Clay
-
7/31/2019 Boyce Tues 830
70/85
VariousHostMaterials
STEEL
CAST IRON
VITRIFIED CLAY
-
7/31/2019 Boyce Tues 830
71/85
350mm(14)
750mm
(30)
650mm(26)
-
7/31/2019 Boyce Tues 830
72/85
Conclusions Pipe bursting is the only trenchless
method capable of installing a new pipe ofequal or larger diameter as a replacement
option Almost any type of existing pipe can be
burst and replaced with most pipe
materials Proper planning is critical to project
success!
CONTRACTOR QUALIFICATIONS &
-
7/31/2019 Boyce Tues 830
73/85
CONTRACTOR QUALIFICATIONS &PRE-QUALIFICATION
-
7/31/2019 Boyce Tues 830
74/85
-
7/31/2019 Boyce Tues 830
75/85
-
7/31/2019 Boyce Tues 830
76/85
f l
-
7/31/2019 Boyce Tues 830
77/85
Protection of Existing Utilities
Call in Locates Obtain As-Built Maps (Shared Responsibility) Mark Utilities (Utility Owners)
Confirm Utilities (Pothole) (Excavator) Protect (Excavator)
-
7/31/2019 Boyce Tues 830
78/85
-
7/31/2019 Boyce Tues 830
79/85
As-Builts, Operator Logs, Notes
Contractor is responsible for marking theplans to indicate any and all vertical andhorizontal deviations between the design
and actual installation Operator logs/notes should be maintainedand updated daily by the Contractor andshould include Pipe number, depth, pitch, steering
commands, and notes
-
7/31/2019 Boyce Tues 830
80/85
-
7/31/2019 Boyce Tues 830
81/85
-
7/31/2019 Boyce Tues 830
82/85
Damage Avoidance
-
7/31/2019 Boyce Tues 830
83/85
Trenchless Training Courses
Horizontal Directional Drilling GoodPractices
Pipe Bursting Good Practices New Installation Methods Good Practices Cured-in-Place Pipe (CIPP) Good
Practices Sewer Laterals Rehabilitation &
Replacement(www.nastt.org)
C lt I t T i i g
-
7/31/2019 Boyce Tues 830
84/85
Caltrans Inspector Training
Classroom
Field Exercises
Conclusions
-
7/31/2019 Boyce Tues 830
85/85
Conclusions
Well-written specificationsare important to minimizeclaims
Hiring a competentcontractor can be achievedthrough pre-qualification
There are numerousavailable trenchlesstechnology options