Boyce Tues 830

download Boyce Tues 830

of 85

Transcript of Boyce Tues 830

  • 7/31/2019 Boyce Tues 830

    1/85

    Introduction toTrenchless Methods

    Presented by

    Glenn M. Boyce, PhD, PE

    Senior Associates

    April 21, 2009

  • 7/31/2019 Boyce Tues 830

    2/85

    Presentation Objectives

    Provide a better understandingof trenchless methods used fornew installations

    Learn the advantages and

    limitations of the methods Discuss contractor

    qualifications

  • 7/31/2019 Boyce Tues 830

    3/85

    Types of Infrastructure

    Gas Pressure

    Water Pressure Sewer Gravity Drainage Gravity Power Non-gravity Communications Non-gravity

  • 7/31/2019 Boyce Tues 830

    4/85

    Trenchless Methods Impact moling Pipe ramming Auger boring Pilot tube Pipe jacking / Microtunneling

    Conventional tunneling Horizontal directional drilling Pipe bursting

  • 7/31/2019 Boyce Tues 830

    5/85

    Generic Size and Length Method Size Length

    Moling 2 - 12 150

    Ramming 8 - 72 300 Auger Bore 8 - 60 250 Pilot Tube 6 - 42 300 Microtunneling 12 - 108 1,500 Pipe Jacking >54 3,000 HDD 2 - 48 6,500 Tunneling >60 Any length

  • 7/31/2019 Boyce Tues 830

    6/85

    What to Do?

    Choose the right method Use established Standards Collect information/investigate Plan ahead

    Conduct risk assessments Include mechanisms to handle

    conflicts

  • 7/31/2019 Boyce Tues 830

    7/85

  • 7/31/2019 Boyce Tues 830

    8/85

    Auger Boring

    Road crossings

    Cohesive soils Short distances Above water table Need steel casing Minor steering

  • 7/31/2019 Boyce Tues 830

    9/85

    60-inch Diameter SBU-A

  • 7/31/2019 Boyce Tues 830

    10/85

    Pilot Tube Method

    Medium distances

    Straight alignments with goodaccuracy Variety of soils Smaller shafts Moderate

    equipment costs

  • 7/31/2019 Boyce Tues 830

    11/85

    Step 1

  • 7/31/2019 Boyce Tues 830

    12/85

  • 7/31/2019 Boyce Tues 830

    13/85

  • 7/31/2019 Boyce Tues 830

    14/85

  • 7/31/2019 Boyce Tues 830

    15/85

    Step 2

  • 7/31/2019 Boyce Tues 830

    16/85

    Pilot Tube + Plus

    Now used as a guide forother method Auger boring Pipe Ramming

  • 7/31/2019 Boyce Tues 830

    17/85

    Pipe Ramming Wide range of

    diameters Soils only Continuously

    supported Typically < 300

    Above and belowwater table

    Need steel casing

    No steering control

  • 7/31/2019 Boyce Tues 830

    18/85

    Installation Method Ramming in continuous length or segments

  • 7/31/2019 Boyce Tues 830

    19/85

    Rammingin

    Progress

  • 7/31/2019 Boyce Tues 830

    20/85

    Pilot tube

  • 7/31/2019 Boyce Tues 830

    21/85

    Pipe Jacking Large diameters Soils and mixed

    ground Face supported Long distances

    Above the watertable

    Steerable

  • 7/31/2019 Boyce Tues 830

    22/85

    Microtunneling Range of diameters (> 12) All ground types

    Continuous face support Long distances Above or below water table

    Range of pipe materials Steerable to line and grade

  • 7/31/2019 Boyce Tues 830

    23/85

    Micro vs Utility TunnelingRemotely operatedPrecise guidancePipes jacked from launch pitContinuous support to face

    ConventionalRib & Lagging Tunnel

    Microtunnel

  • 7/31/2019 Boyce Tues 830

    24/85

    Tunnel Shield Construction

    Lining is built within shield. Lining does notmove longitudinally after placement.

  • 7/31/2019 Boyce Tues 830

    25/85

    Required Axial Thrust versus Lengthof Drive for Same Diameter

  • 7/31/2019 Boyce Tues 830

    26/85

    Opposite Approaches

    Open Cut

    What happenshappens

    Trenchless

    Understand and plan

  • 7/31/2019 Boyce Tues 830

    27/85

    What to Do? Understand the site history and

    potential obstructions

    Look at old aerial photos Conduct ageotechnicalprogram

    Locate allutilities

  • 7/31/2019 Boyce Tues 830

    28/85

    Potential Obstructions

    Cobbles or Boulders

    Wood Fill materials Hard zones Mixed faces

  • 7/31/2019 Boyce Tues 830

    29/85

    Typical Machine Sizes Piercing 2 to 3 inches Pilot Tube 6 to 36 inches

    HDD 6 to 54 inches Auger Boring 10 to 60 inches

    Pipe Jacking/MT 12 to 96 inches Pipe Ramming 12 to 144 inches Shield 60 to 144 inches

  • 7/31/2019 Boyce Tues 830

    30/85

    Typical CMP Culverts

  • 7/31/2019 Boyce Tues 830

    31/85

    Replacement Issues

    Need to increase size foraquatic passage

    Must keep existing culvertactive during construction

    Minimize costs Develop the best cross section Use the right materials

  • 7/31/2019 Boyce Tues 830

    32/85

    Possible Solutions

  • 7/31/2019 Boyce Tues 830

    33/85

    Consume the Culvert

  • 7/31/2019 Boyce Tues 830

    34/85

    Use Liner Plate Tunnel

  • 7/31/2019 Boyce Tues 830

    35/85

  • 7/31/2019 Boyce Tues 830

    36/85

    Closing Thoughts

    Methods still evolving Many hybrid methods emerging Better alignment control

    emerging in auger boring

    applications Must identify potential

    obstructions (or get X-ray vision)

  • 7/31/2019 Boyce Tues 830

    37/85

    HORIZONTAL DIRECTIONALDRILLING (HDD)

    Samuel T. Ariaratnam, PhD, PE

    Arizona State University

  • 7/31/2019 Boyce Tues 830

    38/85

    BackgroundLengths up to 8,400 feet

    Diameters of 2 54

    Applications:Utility conduitsPipelinesGravity sewers

    Force mainsHorizontal remediation wellsGeotechnical investigations

  • 7/31/2019 Boyce Tues 830

    39/85

    Pilot Bore and Tracking

    Pilot Bore

  • 7/31/2019 Boyce Tues 830

    40/85

  • 7/31/2019 Boyce Tues 830

    41/85

    Drill Bits

  • 7/31/2019 Boyce Tues 830

    42/85

  • 7/31/2019 Boyce Tues 830

    43/85

    Reaming/Hole Enlargement

    Reaming

  • 7/31/2019 Boyce Tues 830

    44/85

  • 7/31/2019 Boyce Tues 830

    45/85

    CLAY

    ANNULAR SPACE REGION

  • 7/31/2019 Boyce Tues 830

    46/85

    SAND

    ANNULAR SPACE REGION

  • 7/31/2019 Boyce Tues 830

    47/85

    Pipe Material Distribution

    Underground Construction Magazine

    9th

    Annual Survey, June 2007

  • 7/31/2019 Boyce Tues 830

    48/85

  • 7/31/2019 Boyce Tues 830

    49/85

  • 7/31/2019 Boyce Tues 830

    50/85

  • 7/31/2019 Boyce Tues 830

    51/85

  • 7/31/2019 Boyce Tues 830

    52/85

  • 7/31/2019 Boyce Tues 830

    53/85

  • 7/31/2019 Boyce Tues 830

    54/85

  • 7/31/2019 Boyce Tues 830

    55/85

  • 7/31/2019 Boyce Tues 830

    56/85

  • 7/31/2019 Boyce Tues 830

    57/85

  • 7/31/2019 Boyce Tues 830

    58/85

  • 7/31/2019 Boyce Tues 830

    59/85

    Conclusions HDD is a minimally-intrusive trenchlessconstruction method suited for highly

    congested urban areas and high traffic zones Horizontal Directional Drilling equipment is

    capable of installing a wide range of utilities HDD will never replace traditional open-cut

    methods; however, they complement eachother

  • 7/31/2019 Boyce Tues 830

    60/85

    PIPE BURSTING

    Samuel T. Ariaratnam, Ph.D., P.E.

    Arizona State University

  • 7/31/2019 Boyce Tues 830

    61/85

    Pipe Bursting

    Lengths typically 300-600 ft

    Diameters up to 42

    Applications: replacement of force mains

    replacement of gravitysewers

    Static Head

    Pneumatic Head

  • 7/31/2019 Boyce Tues 830

    62/85

  • 7/31/2019 Boyce Tues 830

    63/85

    Introduction

    Emerging field of pipe replacement

    Replacement of the host pipe byfragmenting the existing conduitand installing a completely newpipe of equal diameter or larger inits place.

  • 7/31/2019 Boyce Tues 830

    64/85

    Applications

    Total pipe replacementTypical upsize as much as 20 30%Industrial & Municipal - Main Line &LateralsVarious host and product pipe materialsContinuous or Sectional pipe installation

  • 7/31/2019 Boyce Tues 830

    65/85

    Pipe Bursting Feasibility

    May achieve lower costs compared

    to open trenchLess construction timeMinimal excavationSocial cost savingsReduces ground settlementLow environmental impact

    S i M h d (C i )

  • 7/31/2019 Boyce Tues 830

    66/85

    Static Method (Continuous)

  • 7/31/2019 Boyce Tues 830

    67/85

    Static Method (Sectional)

  • 7/31/2019 Boyce Tues 830

    68/85

    Pneumatic Method

    Almost all types of pipe can

  • 7/31/2019 Boyce Tues 830

    69/85

    Almost all types of pipe canbe burst

    Cast iron Steel Ductile iron High Density Polyethylene Polyvinylchloride

    Concrete Reinforced concrete Asbestos cement Clay

  • 7/31/2019 Boyce Tues 830

    70/85

    VariousHostMaterials

    STEEL

    CAST IRON

    VITRIFIED CLAY

  • 7/31/2019 Boyce Tues 830

    71/85

    350mm(14)

    750mm

    (30)

    650mm(26)

  • 7/31/2019 Boyce Tues 830

    72/85

    Conclusions Pipe bursting is the only trenchless

    method capable of installing a new pipe ofequal or larger diameter as a replacement

    option Almost any type of existing pipe can be

    burst and replaced with most pipe

    materials Proper planning is critical to project

    success!

    CONTRACTOR QUALIFICATIONS &

  • 7/31/2019 Boyce Tues 830

    73/85

    CONTRACTOR QUALIFICATIONS &PRE-QUALIFICATION

  • 7/31/2019 Boyce Tues 830

    74/85

  • 7/31/2019 Boyce Tues 830

    75/85

  • 7/31/2019 Boyce Tues 830

    76/85

    f l

  • 7/31/2019 Boyce Tues 830

    77/85

    Protection of Existing Utilities

    Call in Locates Obtain As-Built Maps (Shared Responsibility) Mark Utilities (Utility Owners)

    Confirm Utilities (Pothole) (Excavator) Protect (Excavator)

  • 7/31/2019 Boyce Tues 830

    78/85

  • 7/31/2019 Boyce Tues 830

    79/85

    As-Builts, Operator Logs, Notes

    Contractor is responsible for marking theplans to indicate any and all vertical andhorizontal deviations between the design

    and actual installation Operator logs/notes should be maintainedand updated daily by the Contractor andshould include Pipe number, depth, pitch, steering

    commands, and notes

  • 7/31/2019 Boyce Tues 830

    80/85

  • 7/31/2019 Boyce Tues 830

    81/85

  • 7/31/2019 Boyce Tues 830

    82/85

    Damage Avoidance

  • 7/31/2019 Boyce Tues 830

    83/85

    Trenchless Training Courses

    Horizontal Directional Drilling GoodPractices

    Pipe Bursting Good Practices New Installation Methods Good Practices Cured-in-Place Pipe (CIPP) Good

    Practices Sewer Laterals Rehabilitation &

    Replacement(www.nastt.org)

    C lt I t T i i g

  • 7/31/2019 Boyce Tues 830

    84/85

    Caltrans Inspector Training

    Classroom

    Field Exercises

    Conclusions

  • 7/31/2019 Boyce Tues 830

    85/85

    Conclusions

    Well-written specificationsare important to minimizeclaims

    Hiring a competentcontractor can be achievedthrough pre-qualification

    There are numerousavailable trenchlesstechnology options