Critical path Analysys Project : Sampling Start date: 8th may End Date: 8th June sl Activity Predecessor Days A Trend Analysis 5 B Design Chart 5 C customer profile A 1 D prediction A 1 E Spec sheet C 1 F Meeting with sir A,B,C,D 1 G Mood board A,B,C,D,E 1 H primary design A,B,C,D,E,F,G 2 i final design H 2 J 1st fit sample I 6 k Fit analysys J 1

description

Book1

Transcript of Book1

Sheet1Critical path AnalysysProject : SamplingStart date: 8th mayEnd Date: 8th JuneslActivityPredecessorDaysATrend Analysis5BDesign Chart5Ccustomer profileA1DpredictionA1ESpec sheetC1FMeeting with sirA,B,C,D1GMood boardA,B,C,D,E1Hprimary designA,B,C,D,E,F,G2ifinal designH2J1st fit sampleI6kFit analysysJ1