Bond Construction Update Facilities Advisory Committee

21
Bond Construction Bond Construction Update Update Facilities Advisory Facilities Advisory Committee Committee Long Beach Community College District November 17, 2010 EDUCATE ENGAGE EMPOWER 1

description

Bond Construction Update Facilities Advisory Committee. Long Beach Community College District November 17, 2010. EDUCATE  ENGAGE  EMPOWER. Agenda. Current & Upcoming Construction Projects LAC Building A, Student Services Retrofit LAC Parking Structure LAC Building O Complex - PowerPoint PPT Presentation

Transcript of Bond Construction Update Facilities Advisory Committee

Page 1: Bond Construction Update  Facilities Advisory Committee

Bond Construction Bond Construction UpdateUpdate

Facilities Advisory Facilities Advisory CommitteeCommittee

Bond Construction Bond Construction UpdateUpdate

Facilities Advisory Facilities Advisory CommitteeCommittee

Long Beach Community College District November 17, 2010

EDUCATE ENGAGE EMPOWER 1

Page 2: Bond Construction Update  Facilities Advisory Committee

Agenda

Current & Upcoming Construction Projects LAC Building A, Student Services Retrofit LAC Parking Structure LAC Building O Complex LAC Infrastructure Improvements Project and District Wide –

Energy Efficiency Project LAC Building I (Bookstore) PCC MDAB (Multi-Disciplinary Academic Building) PCC Building CC Retrofit District Wide – Electronic Signage Plan LAC South Walkway Extension LAC Math Technology Building

Q & A

2

Page 3: Bond Construction Update  Facilities Advisory Committee

Current and UpcomingConstruction Projects

LAC Building A – Student Services RetrofitLAC Building A – Student Services Retrofit

Measure E 2008Measure E 2008

3

Received final DSA approval on 10/7/2010. Project currently in bid process. Bids due 11/30. Adds 6,500 Sq. Ft. to existing building Will house A&R, Counseling, Health Services, Cashier, Transfer Ctr., etc. Estimated start of construction Winter 2010.

Page 4: Bond Construction Update  Facilities Advisory Committee

Current and UpcomingConstruction Projects

LAC Parking Structure – Measure E 2008LAC Parking Structure – Measure E 2008

4

Spaces for 900 Vehicles Currently work is being done on the façade Anticipated end of Construction Fall 2011

Page 5: Bond Construction Update  Facilities Advisory Committee

Current and UpcomingConstruction Projects

LAC Building O Complex – Measure E 2008LAC Building O Complex – Measure E 2008

5

Two structures totaling 87,000 square feet Renovation of Building O1 began April 2010 Anticipated completion Winter of 2010

Page 6: Bond Construction Update  Facilities Advisory Committee

6

LAC Infrastructure Improvement Project and District LAC Infrastructure Improvement Project and District Wide Energy Efficiency Project Measure E Wide Energy Efficiency Project Measure E

20082008

Current and UpcomingConstruction Projects

Project to be completed in a phased construction schedule

Total annual estimated savings of 1.5 million Kwh

Project started Fall 2009; currently working on phase 6,7, and 8A

Landscaping upgrades to be implemented in conjunction with infrastructure project phasing

Majority of existing building HVAC systems to be upgraded and connected to the Central Plant

Exterior lighting and controls upgrades in progress

Anticipated end of construction Winter 2011

Page 7: Bond Construction Update  Facilities Advisory Committee

Current and UpcomingConstruction Projects

7

Adds additional 4,000 square feet to existing building Architecture to match LAC Mediterranean Theme BOT approved (10/26) for G2K Constr. Notice To Proceed 11/15/10 End of Construction anticipated Fall 2011

LAC Building I - Measure E 2008LAC Building I - Measure E 2008

Page 8: Bond Construction Update  Facilities Advisory Committee

Current and UpcomingConstruction Projects

PCC MDAB PCC MDAB (Multi-Disciplinary Academic Building) - Measure E 2002(Multi-Disciplinary Academic Building) - Measure E 2002

8

Notice To Proceed issued on 7/29/10 Currently in phase 1 of construction (DD and EE in construction) Portables for swing space installed Summer 2010 complete

and occupied(MD Trailers) Project to be completed in two phases

Page 9: Bond Construction Update  Facilities Advisory Committee

Current and UpcomingConstruction Projects

PCC Building CC Retrofit - Measure E 2008PCC Building CC Retrofit - Measure E 2008

9

Currently in DSA for plan check (Structural) Houses the Fitness Center, Gymnasium, Weight Room, and

Faculty and Staff Offices Swing space located on PCC Campus (Bldg. GG) To be completed concurrently with MDAB project phase 1 Anticipated end of construction 2012

Page 10: Bond Construction Update  Facilities Advisory Committee

Current and UpcomingConstruction Projects

District Wide – Electronic Signage PlanDistrict Wide – Electronic Signage Plan Measure E 2008Measure E 2008

10

District Wide Signage Plan complete for LAC & PCC LAC Daktronics digital sign going through final installation PCC Daktronics digital sign currently being installed Anticipated construction completion of Marquee Signs Fall

2010

Page 11: Bond Construction Update  Facilities Advisory Committee

Current and UpcomingConstruction Projects

LAC South Walkway ExtensionLAC South Walkway Extension Measure E 2008Measure E 2008

11

99% complete Currently going through final punch-list Continues Master Plan pedestrian corridor

Page 12: Bond Construction Update  Facilities Advisory Committee

Current and UpcomingConstruction Projects

Completed Schematic Design Will house Math and Culinary Arts instructional

program as well as Reprographics Estimated start of construction Winter 2013

LAC Math Technology Building – Measure E 2008LAC Math Technology Building – Measure E 2008

12

Page 13: Bond Construction Update  Facilities Advisory Committee

l i b

e r

a l

a r

t s

Liberal Arts CampusSite Plan

Page 14: Bond Construction Update  Facilities Advisory Committee

p a

c i f

i c

c

o a

s t

Pacific Coast CampusSite Plan

Page 15: Bond Construction Update  Facilities Advisory Committee

Planned Phasing of Future Projects

15

2010-11 Begin construction of Building A at LAC – Fall 2010

Begin Schematic Design for Buildings C and F at LAC

Submit plans to DSA no later than Summer 2011

Page 16: Bond Construction Update  Facilities Advisory Committee

Planned Phasing of Future Projects

16

2011-12 Infrastructure project complete at LAC – Winter 2011 Submit plans to DSA for Math/Technology Building at LAC –

Summer 2012

Construction completion of Buildings DD and EE at PCC – Fall 2011

Begin construction of Buildings AA, BB and CC at PCC – Fall 2011

Anticipated construction completion of Building I (Bookstore) at LAC – Fall 2011

Anticipated construction completion of Parking Structure at LAC – Fall 2011

Page 17: Bond Construction Update  Facilities Advisory Committee

Planned Phasing of Future Projects

17

2012-13 Move Buildings C and F programs into Swing Space (M/N

Building) and begin construction – Summer 2012

Anticipated Construction completion of Building A at LAC – Summer 2012

Submit plans to DSA for M/N Building at LAC and Building MM (Phase 1) at PCC – Summer 2012

Begin Schematic Design for Building P at LAC and Building MM (Phase 2) at PCC – Summer 2012 Submit to DSA – Spring 2013

Begin construction of Math/Technology Building at LAC – Winter 2013

Page 18: Bond Construction Update  Facilities Advisory Committee

Planned Phasing of Future Projects

18

2012-13 (continued)

Begin Schematic Design for Building D and E renovations – Fall 2013

Anticipated Construction completion of Buildings AA, BB and CC at PCC – Summer 2013

Page 19: Bond Construction Update  Facilities Advisory Committee

Planned Phasing of Future Projects

19

2013-14 Anticipated Construction completion of Buildings C and F at

LAC – Fall 2013

Begin construction of Buildings M/N at LAC and MM (Phase 1) at PCC – Fall 2013

Submit plans to DSA for Buildings D and E renovations at LAC – Fall 2013

Schematic design for Performing Arts Building (G & H) and Building R at LAC – Spring 2014

Page 20: Bond Construction Update  Facilities Advisory Committee

Planned Phasing of Future Projects

20

2014-15 Anticipated Construction completion of Math/Technology

Building at LAC – Summer 2014

Begin construction on Buildings D and E at LAC – Fall 2014

Submit plans to DSA for Performing Arts Building and Building R (Gym) at LAC – Spring 2015 Anticipate construction start – Spring 2016

Anticipated construction completion of Buildings M/N at LAC and MM at PCC – late Spring 2015

Begin construction on Buildings P at LAC and MM (Phase 2) at PCC – Spring 2015

Page 21: Bond Construction Update  Facilities Advisory Committee

QUESTIONS&

ANSWERS