BOND BEHAVIOR OF GROUTED SPIRAL AND SPLICE...
Transcript of BOND BEHAVIOR OF GROUTED SPIRAL AND SPLICE...
BOND BEHAVIOR OF GROUTED SPIRAL AND SPLICE CONNECTION
UNDER DIRECT AXIAL AND FLEXURAL PULLOUT LOAD
SEYED JAMAL ALDIN HOSSEINI
UNIVERSITI TEKNOLOGI MALAYSIA
BOND BEHAVIOR OF GROUTED SPIRAL AND SPLICE CONNECTION
UNDER DIRECT AXIAL AND FLEXURAL PULLOUT LOAD
SEYED JAMAL ALDIN HOSSEINI
A thesis submitted in fulfilment of the
requirements for the award of the degree of
Doctor of Philosophy (Civil Engineering)
Faculty of Civil Engineering
Universiti Teknologi of Malaysia
AUGUST 2015
iii
“To my beloved parents and my lovely wife, for their encouragement and support”
iv
ACKNOWLEDGEMENT
First of all, gratefulness of thanks to our creator, “ALLAH” for his
continuous blessing, which make this work neither the first nor the last.
Special thanks to Assoc. Prof. Dr. Ahmad Baharuddin Abd Rahman for
giving this opportunity to work under his supervision and for sharing his great
knowledge and experience with me.
I would like to convey my deepest gratitude to Mrs. Zeinab Deriss for her
support and encouragement. Appreciation is also extended to all people who gave me
heartfelt corporation and shared their knowledge.
Finally, I would like to send my deep appreciations to my family who
brought me up with love.
v
ABSTRACT
The conventional grouted connections with corrugated aluminium sleeves
have been used widely in precast concrete construction. The main problem of the
conventional grouted sleeve connections is the need for long embedded lengths
reinforcement rebars to achieve full continuity. There is a tendency for the long
rebars to touch the sleeve wall and subsequently preventing penetration of grout
around the rebar. Since the grout inside the sleeve cannot be inspected after
installation, there is doubt that the main rebar is fully bonded. This study proposed a
grouted spiral connection which can overcome the use of long embedded length of
connected rebars. The main objective of this study was to investigate the effect of
spiral confinement on the bond stress-slip relationship. The experimental program
was carried out in two phases, Phase I and Phase II. In Phase I, a total of thirty-six
spiral connections were subjected to increasing direct axial pullout loads. Then, in
Phase II, a total of twelve beams comprising spiral connections were subjected to
flexural pullout loads. Parameters considered in this study were pitch distance and
diameter of spiral connections. The experimental results showed that the use of
smaller pitch distance and spiral diameter resulted in higher bond strength. However,
the spiral diameter had more dominant confinement effect such that it increased the
bond strength of direct and flexural pullout tests very dramatically by 34.5% and
40%, respectively. In addition, lower bond strength from the beam tests was reported
as compared to the axial pullout tests. The bond strengths obtained from the flexural
pullout tests were within the range of 0.74 to 0.79 times the bond strengths of the
axial pullout tests. Finally, analytical equations were proposed to express the bond
stress-slip relationship and bond strength of the grouted spiral connection.
.
vi
ABSTRAK
Penggunaan sambungan grout konvensional dengan salur aluminium telah
digunakan secara meluas dalam pembinaan konkrit pratuang. Masalah utama
daripada sambungan grout konvensional adalah keperluan panjang tambatan untuk
mencapai kekuatan penuh. Terdapat kecenderungan untuk tetulang bar yang panjang
menyentuh dinding salur dan seterusnya menghalang penembusan grout di sekitar
bar. Oleh kerana grout di dalam salur tidak boleh diperiksa selepas pemasangan,
terdapat keraguan tetulang utama tidak terikat sepenuhnya. Kajian ini mencadangkan
satu sambungan gegelung grout yang boleh mengatasi masalah penggunaan tambatan
tetulang keluli yang terlalu panjang. Objektif utama kajian ini adalah untuk
menyiasat kesan kurungan gegelung ke atas hubungan tegasan ikatan-gelinciran.
Program eksperimen telah dijalankan dalam dua fasa, Fasa I dan Fasa II. Dalam Fasa
I, sejumlah tiga puluh enam sambungan gegelung dikenakan tindakan beban
tegangan paksi. Di dalam Fasa II, sebanyak dua belas rasuk dengan sambungan
gegelung dikenakan beban lenturan. Parameter yang dikaji adalah jarak antara
gegelung dan diameter gegelung penyambung. Keputusan eksperimen menunjukkan
bahawa penggunaan jarak antara gegelung dan diameter gegelung yang kecil dapat
meningkatkan kekuatan ikatan. Bagaimanapun, kesan diameter adalah lebih
dominan dalam meningkatkan kekuatan ikatan dengan peningkatan sebanyak 34.5%
dan 40% masing-masing bagi ujikaji beban paksi dan lenturan. Di samping itu,
kekuatan ikatan yang lebih rendah didapati berlaku pada ujian rasuk berbanding
dengan ujian tegangan paksi. Kekuatan ikatan yang diperolehi daripada ujian
lenturan adalah dalam julat 0.74-0.79 kali ganda kekuatan ikatan tegangan paksi.
Akhirnya, persamaan analitik telah dicadangkan untuk menyatakan hubungan
tegasan ikatan- gelinciran dan kekuatan ikatan bagi sambungan gegelung grout.
vii
TABLE OF CONTENTS
CHAPTER TITLE PAGE
DECLARATION ii
DEDICATION iii
AKNOWLEDGMENT iv
ABSTRACT v
ABSTRAK vi
TABLE OF CONTENTS vii
LIST OF TABLES xii
LIST OF FIGURES xiv
LIST OF SYMBOLS xx
LIST OF APPENDICES xxii
1 INTRODUCTION 1
1.1 Introduction 1
1.2 Background of Study 5
1.3 Problem Statements 8
1.4 Objective 10
1.5 Scope of Research 11
1.6 Thesis Organization 13
2 LITERATURE REVIEW 14
2.1 Introduction 14
2.2 Bond Mechanisms 15
2.3 Bond of Steel Reinforcement Bars 17
2.3.1 Mechanical Interlocking 18
viii
2.3.2 Friction 19
2.3.3 Chemical Adhesion 19
2.4 Factors Influencing Bond Behavior 19
2.4.1 Confinement 20
2.4.1.1 Previous Research on the
Confinement
21
2.4.1.2 Effect of Confinement on the
Bond Failure
27
2.4.2 Strength of Bonding Material 29
2.5 Previous Research Studies on Grouted
Connections
30
2.6 Experimental Investigation on the Bond Force
of Splice Bars
35
2.6.1 Comparison with ACI 38
2.7 Bond Stress-Slip 40
2.7.1 Analytical Model of Bond Stress-Slip 40
2.7.1.1 BPE Model 41
2.7.1.2 Haskett et al.’s Model 43
2.7.1.3 Soroushian’s Model 44
2.7.2 Equation od Bond Stress-Slip 46
2.8 Standard Bond Tests 48
2.8.1 Review of Experimental Setups of
Direct Pullout Test
49
2.8.1.1 Single Pullout Test 49
2.8.1.2 Double Pullout Test 50
2.8.2 Review of Experimental Setups of Beam
Tests (Flexural Pullout Test)
51
2.9 Summary 53
3 RESEARCH METHODOLOGY 55
3.1 Introduction 55
3.2 Preliminary Study 58
3.3 Direct Pullout Tests 61
3.3.1 Details of Specimens 61
3.3.1.1 Trial Specimens 61
3.3.1.2 Grouted Spiral Connections 63
3.3.2 Preparations of Specimens
65
ix
3.3.3 Experimental Setup of Direct Pullout
Load Test
67
3.3.4 Data Acquisition System 68
3.4 Experimental Setups of Flexural Pullout Tests 69
3.4.1 Details of Specimens 70
3.4.2 Preparations of Specimens 73
3.4.3 Specifications of Material for the Beam
Specimens
81
3.4.4 Specifications of Material for the
Grouted Spiral Connections
82
3.4.5 Instrumentations 85
3.4.5.1 Measurement of Load 85
3.4.5.2 Measurement of Slip 86
3.4.5.3 Measurement of Steel Strain 87
3.4.6 Data Acquisition System 88
3.4.7 Load Control 89
3.5 Summary 90
4
PHASE I: BEHAVIOR OF GROUTED SPIRAL
CONNECTIONS SUBJECTED TO DIRECT
AXIAL PULLOUT
92
4.1 Introduction 92
4.2 Tensile Test Results of Grouted Spiral
Connections
93
4.2.1 Mechanism of Tensile Force Transfer in
Trial Specimens
96
4.2.2 Mechanism of Tensile Force Transfer in
others Series
102
4.2.2.1 Failure Modes of the Grouted
Spirals
104
4.2.2.2 Behavior of Tensile Strain in the
Connected Main Bars
107
4.3 Structural Behavior 109
4.3.1 Interlocking Mechanism of Grouted
Spiral Connections
111
4.3.2 Splitting Cracks and Effects 113
4.3.3 Confinement Effects 115
4.4 Performance of Grouted Spiral Connections 116
x
4.4.1 Performance of Bond Stiffness and Slip 116
4.4.1.1 Effects of Spiral Configuration
on the Slip
118
4.4.1.2 Behavior of Connection Stiffness 121
4.4.2 Evaluation of Bond Strength 123
4.4.2.1 Effects of Spiral Configuration
on the Bond Strength
124
4.5 Summary 130
5
PHASE II: BEHAVIOR OF GROUTED SPIRAL
CONNECTIONS SUBJECTED TO INCREASING
FLEXURAL PULLOUT
131
5.1 Introduction 131
5.2 Flexural Test Results of Grouted Spiral
Connections
132
5.2.1 Mechanism of Force Transfer in Trial
Specimens
135
5.2.2 Flexural Test Results of other Series 137
5.2.2.1 Failure Modes of the Grouted
Spiral Connections
140
5.2.2.2 Behavior of Tensile Strain in
Connected Main Bars
143
5.3 Comparison of Results between Direct Axial
and Flexural Pullout Loads
144
5.4 Design Recommendation 149
5.5 Summary 151
6 ANALYTICAL BEHAVIOR OF GROUTED
SPIRAL CONNECTION UNDER AXIAL AND
FLEXURAL PULLOUT
153
6.1 Introduction 153
6.2 Bond Stress-Slip Behavior of Grouted Spiral
Connections
155
6.2.1 Analysis of Bond-Slip Relationship by
Curve Fitting
155
6.2.2 Modelling of the Bond Stress-Slip
Relationship
158
6.3 Evaluating the Confinement Effect by Bond
Energy
163
6.4 Prediction of Bond Strength of Spiral
Connections in Deformed Steel Bars
168
6.5 Comparison with Orangun’s Equation 172
xi
6.6 Limitations 179
6.7 Summary 180
7 CONCLUSIONS 181
7.1 Summary 181
7.2 Conclusion 182
7.3 Recommendations for Future Research 185
REFERENCES 187
Appendices A-C 193-210
xii
LIST OF TABLES
TABLE NO. TITLE PAGE
1.1 Comparisons of the commercial and proposed connections
of this research
3
2.1 Application of NMB splice sleeve and Lenton Interlok 32
2.2 Test-prediction ratios for bars confined by transverse
reinforcement [45]
39
2.3 The value of pitch distance studied by other researchers 45
2.4 Assessment of the performance of the prediction models 48
3.1 Preliminary feasibility evaluation of specimens in
preliminary study
60
3.2 Details of trial specimens 62
3.3 Dimension of all series in Phase I 64
3.4 Details of grouted spiral connection in Phase II 73
3.5 Mix proportion of concrete in grade 40 81
3.6 Description of concrete in grade 40 82
3.7 Average specifications of Sika Grout-215 84
3.8 Properties for the rib parameters 84
3.9 Tensile test results of steel reinforcement bars 84
3.10 Specifications of strain gauges for deformed steel main bar 87
3.11 The measured data and accuracies 89
4.1 Summary of test results of grouted spiral connection 94
4.2 Average of test results in trial specimens 96
4.3 Average of test results in Series 𝐷𝑠 25, 𝐷𝑠 35 and 𝐷𝑠 45 103
xiii
4.4 Bond stiffness of the grouted spiral connections, MPa/mm 120
4.5 Strength ratio of specimens 128
4.6 Bond strength, (MPa) with respect to different spiral
diameters
129
4.7 Bond strength, (MPa) with respect to different pitch
distance
129
5.1 Test results of flexural pullout loads 134
5.2 Bond strength, (MPa) with respect to different spiral
diameter
139
5.3 Bond strength, (MPa) with respect to different pitch
distance
140
5.4 Comparison of bond strength between axial and flexural
pullout tests
148
5.5 Calculation of required embedded length 151
6.1 Curve-fitting parameter of α and β 161
6.2 Bond energy of grouted spiral connections tested in
Phase I
167
6.3 Bond energy of grouted spiral connections tested in
Phase II
168
6.4 Comparison between test results in Phase I and proposed
Equation 6.6
171
6.5 Comparison between test results in Phase II and proposed
Equation 6.7
172
6.6 Values of parameters used for Equation 6.8 175
6.7 Comparison between test results in Phase I and Equation
6.9
178
6.8 Comparison between test results in Phase II and Equation
6.9
179
xiv
LIST OF FIGURES
FIGURE NO. TITLE PAGE
1.1 Grouted splice connection in precast concrete components
[13]
4
1.2 Mechanism of load transfer [17] 5
1.3 Spiral confinement in splice connections [29] 8
1.4 Projecting the long embedded length in conventional
grouted sleeve [30]
9
1.5 Cross section through grouted sleeve column splice [31] 10
2.1 Grouted sleeve connection and connecting elements [33] 15
2.2 Distribution of bond stress at different levels of pulling
force [36]
16
2.3 (a) Bond force transfer mechanisms [45], (b) typical bond
stress-slip relationship [46]
18
2.4 (a) Plain round bar, (b) lateral pressure parallel to the
transverse rib, (c) lateral pressure perpendicular to the
transverse rib [54]
22
2.5 Typical failure pattern (a) without spiral, (b)with spiral
[56]
23
2.6 Grouted spiral connection (a) four splice bars inside the
spiral [61], (b) four splice bars outside the spiral
24
2.7 Anchorage of beam reinforcement at exterior joints [55] 25
2.8 Stress-slip responses under confinement of transverse
reinforcement [55]
26
2.9 Effect of confinement on the bond failure (a) by splitting
in an embedded bar without any confinement, (b) by
pullout with present of confinement [66]
28
2.10 Relationships of bond stress versus displacement [72] 30
xv
2.11 Proprietary products tested by Jansson [73] 31
2.12 Fatigue test setup by Jansson [73] 32
2.13 Details of test specimens [7] 33
2.14 Proposed bar splice sleeve [33] 34
2.15 Configuration of test specimens given by Ling et al. [59] 34
2.16 Test-prediction ratios for descriptive equations with
confinement provided by transverse reinforcement [45]
39
2.17 Schematic representation of Eligehausen’s tests [42] 41
2.18 BPE model [42] 42
2.19 Haskett et al.’s model [84] 43
2.20 Typical types of pullout tests [91] 50
2.21 Direct Tension Pullout Bond Test (DTP-BT) [91, 92] 50
2.22 Experimental setup of tensile load test by Einea et al [7] 51
2.23 Diagram and reinforcement of RILEM beam test, test
pattern for 𝑑𝑏 ≥16 mm [95]
52
2.24 Modification of RILEM beam tests by other researchers
[97]
53
3.1 Flow chart of the research carried out 57
3.2 Labelling of the specimens 58
3.3 Series of grouted splices tested in preliminary study [98] 59
3.4 Configuration of trial specimens T1, T2 and T3 62
3.5 Configuration spiral with four splice bars in trial specimen
T3
63
3.6 Details of all specimens comprising main bars, spiral, and
splice bars
64
3.7 The arrangement of connections in the PVC before
casting
65
3.8 Preparation of specimens 66
3.9 Installation of strain gauge 67
3.10 Experimental setup of tensile load test 68
3.11 Data acquisition system of tensile load test 68
3.12 Grouted spiral connections in flexural pullout test 70
xvi
3.13 Details of specimen in Phase II 72
3.14 Preparation of formwork 74
3.15 Preparation of reinforcement cage 75
3.16 Preparing the beam specimen 77
3.17 Casting of ready-mix concrete 79
3.18 Compacting of concrete with a hand-held vibrator 80
3.19 Smoothing the surface of beam specimens 80
3.20 Demoulding and preparing the specimens in final step 81
3.21 Position of grouted spiral connection in beam specimen 83
3.22 The rib geometry of deformed steel bar 83
3.23 Position of load cell 86
3.24 Arrangement of LVDTs 87
3.25 Location of strain gauge attached to the main bar 88
3.26 Data acquisition system for flexural pullout tests 89
3.27 Setup of loading frame for flexural pullout tests 90
4.1 Specimen A-T1-S (a) failure mode, (b) force transfer
mechanism
97
4.2 Specimen A-T2-S (a) failure mode, (b) force transfer
mechanism
98
4.3 Comparison of slip between A-T1-S and A-T2-S 99
4.4 Confinement effects contributed by the splice bars in
A-T3-S
100
4.5 Comparison of bond strength between A-T2-S and
A-T3-S
101
4.6 Failure mode of specimen A-T3-S 102
4.7 Pullout failure mode 104
4.8 Mechanism of bar bond-slip failure 106
4.9 Bond stress distribution (modified from Ferguson model)
[36]
107
4.10 Stress-strain in the main connected bar 108
4.11 Failure mode (a) without radial crack, (b) with radial
crack
110
xvii
4.12 Mechanical interlocking mechanism of bond [108] 112
4.13 Componential stresses of resultant stress [108] 112
4.14 Componential stress 112
4.15 Propagation of splitting cracks and effects [111] 113
4.16 Componential derivation of resultant bearing stress [108] 114
4.17 Reduction of shear area due to splitting cracks [108] 115
4.18 Passive confinement generated by spiral 116
4.19 Best-fit straight lines to calculate the bond stiffness of
connection
117
4.20 Comparison of average bond stiffness in all series 119
4.21 Effect of spiral diameter on the average bond stiffness 119
4.22 Bar slips due to micro-space and compressive
deformations of grout [35]
122
4.23 Bar slips due to micro-space and compressive
deformations of grout
122
4.24 Development of inclined cracks [55] 123
4.25 Bond strength versus pitch distance 125
4.26 Stress transfer mechanism 126
5.1 Flexural pullout experimental (a) beam details showing
the spiral connection, unbonded length of rebar, loads and
LVDTs positions, (b) actual beam tested in the laboratory
133
5.2 Grout fracture initiating the bar pullout 135
5.3 Comparison of bond strength between specimens F-T3-S
with splice bars and F-T2-S without splice bars
136
5.4 Bond strength versus spiral diameter under flexural
pullout
138
5.5 Comparison of confined surface area 138
5.6 Bond strength versus pitch distance 139
5.7 The location of the failure in the left side of the beam in
connector
141
5.8 Failure mode (a)-(b) flexural pullout with the grouted
connection located inside the left beam, (c) pullout of the
main rebar
141
xviii
5.9 Stress-strain of specimens under flexural pullout test (a)
F-P15-D25-S, (b) F-P35-D25-S
143
5.10 Comparion of bond strength between direct axial and
flexural pullout (a) bond strength versus spiral diameter,
(b) bond strength versus pitch distance
145
5.11 Stress-strain in the main steel bar (a) specimen A-P15-
D25-S under direct axial pullout test, (b) specimen
F-P15-D25-S under flexural pullout test
146
5.12 Bond stress-slip relationship (a) specimen A-P15-D25-S
under direct axial pullout test, (b) specimen F-P15-D25-S
under flexural pullout test
147
5.13 Level of bond strength of specimens for different series 150
6.1 Analytical behavior of grouted spiral connection 155
6.2 Curve fitting of experimental bond stress-slip of grouted
spiral connection (a) under direct axial pullout, (b) under
flexural pullout
157
6.3 Comparison of bond stress-slip relationships between
experimental results and curve fitting equation of (a)
specimen A-P25-D35-S direct axial pullout test, (b)
specimen F-P25-D35-S under flexural pullout test
158
6.4 (a) Configuration of specimen in research of Soroushian
model [55], (b) equivalent Soroushian model used in the
spiral connections
159
6.5 Comparison between predicted bond stress-slip
relationships with experimental results (a) A-P15-D25-S
(I), (b) A-P25-D25-S (I), (c) F-P15-D25-S, (d) F-P25-
D25-S
161
6.6 Bond energy (a) A-P15-D25-S, (b) A-P15-D35-S and
(c) A-P15-D35-S in direct axial pullout in Phase I
164
6.7 Bond energy (a) F-P15-D25-S (b) F-P15-D35-S and
(c) F-P15-D35-S in flexural pullout in Phase II
165
6.8 Statistical approach- logarithmic regression method for
predicting parametric response (a) direct axial pullout, (b)
flexural pullout
169
6.9 Grout confined area in grouted spiral connections 174
6.10 Comparison between direct axial pullout and Equation 6.9 177
6.11 Comparison between flexural pullout and Equation 6.9 177
xx
LIST OF SYMBOLS
P - Applied load
𝑑𝑏 - Diameter of main bar
𝑙𝑑 - Embedded length
𝜏 - Average bond stress
U - Bond strength of concrete
ƒ𝑛 - Lateral confining pressure
𝑓𝑐𝑢 - Concrete compressive strength
ƒ𝑏𝑡 - Bond stress
𝑇𝑏 - Bond force
𝐴𝑏 - cross sectional area of spliced bars
𝐴𝑡𝑟 - Area of transverse reinforcement normal to the plane of
splitting through the anchored bars
𝐶𝑚𝑖𝑛 - Smaller of minimum concrete cover or ½ of clear spacing
between bars
𝑓𝑦𝑡 - Yield strength of transverse reinforcement
s - Spacing of transverse reinforcement
n - Number of bars developed or splice at the same location
CSo - Side cover
CSi - 1/2 of the bar clear spacing
CS - Minimum (CSo , CSi + 6.4m)
Cb - Bottom cover
Cmax - Maximum (Cb, CS)
𝜏𝑚𝑎𝑥 - Maximum bond strength
𝑆 - Slip
𝑠1 - Slip at maximum bond strength of 𝜏1
α - a curve-fitting parameter
xxi
𝑓𝑐′ - Tensile strength of concrete
𝑓𝑠 - Steel stress
X - Distance from loaded face pullout bond specimen.
x - Distance from center of embedded bar
D - Diameter of cylindrical grout
𝐷𝑠 - Diameter of spiral
𝑃𝑠 - Pitch distance of spiral
𝐿𝑠 - Length of grouted spiral connection
𝐿𝑒 - Embedded length of main connected bar
𝑁𝑐 - Number of Coil
h - Rib height
c - Rib spacing
ʋ - Rib inclination
fc,g - Compressive strength of grout
σ - Stress
Ks - Stiffness
Rs - Strength ratio
fu,b - Maximum stress at failure
Pu - Load capacity
fsy,b - Specified yield strength
T - Tensile load in the main bars of beam specimen
a - Shear span
j - Distance between the resultant tensile and compressive loads
ɤ - Ratios between bond strength of axial and flexural pullout
β - A curve-fitting parameter
Ag - Confined grout, cross sectional area
𝑓spiral - Tensile stress in spiral
Aspiral - Cross sectional areas of the spiral
𝑑𝑠𝑝𝑖𝑟𝑎𝑙 - Diameter of cross sectional area of spiral
𝑑sb - Diameter of splice bar
𝑃g - Tensile strength of grout in connection
𝑃spiral - Tensile load endured by the spiral
xxii
LIST OF APPENDICES
APPENDIX TITLE PAGE
A Response of grouted spiral connection with deformed steel
bars under direct axial pullout in Phase I
193
B Response of grouted spiral connection with deformed steel
bars under flexural pullout in Phase II
199
C List of publication 210
CHAPTER 1
INTRODUCTION
1.1 Introduction
The construction industry in Malaysia has shifted from conventional
reinforced concrete system to industrialized building system (IBS) through the
application of precast concrete system. The precast concrete system has led the
building market to an extremely competitive environment. Using this system,
considerable amount of building components are fabricated in factories in a fully
controlled condition by means of proper equipment. The precast concrete system has
considerable advantages such as certainty in cost and time, enhancing occupational
health and safety, achieving higher construction productivity and quality, reliance on
manual foreign labor, and decreasing the cost of construction [1].
In 1960, Ministry of Local Government and Housing visited a number of
European countries for evaluation of their housing development program [2], which
led to initiating IBS in Malaysia. Then, the government dedicated about 22.7 acres of
land along Jalan Pekeliling, Kuala Lumpur to a great project that consisted of seven
blocks of 17 stories flat, 3000 units of low-cast flat, and 40 shop lots [3].
In 2006, the Malaysian construction industry re-introduced the IBS system
with the expectation the new technologies in precast concrete can be adopted for
innovative construction techniques. For instance, the Construction Industry Master
2
Plan (CIMP) 2006-2015 published in December 2006 was an attempt to plan the
direction for future developments of the Malaysian Construction Industry. In the
2005 Budget, the construction of 100,000 units of reasonably-priced houses using
IBS was pledged by the government. The Surat Pekeliling Perbendaharaan Bil. 7
Tahun has 2008 strongly asserted that the government’s projects must use IBS in
their construction process not less than 70% of the whole structures [1]. These efforts
demonstrate the situation of IBS in the construction industry of Malaysia.
One of the major concerns that commonly arise with regard to the use of
prefabricated precast concrete components is the needs to develop quality
connections in a way to maintain the structural integrity through the precast sections
[4]. In the precast continuous construction system, both the design and structural
details of the precast connections should have the same features of cast-in-place
connection [5]. In this regard, the America Concrete Institute (ACI) has published
different details on how to emulate cast-in-places in the precast construction sites [6].
On the other hand, still there is not enough supplementary information in the ACI
code regarding the design of precast connections in particular the knowledge related
to continuity and bond in reinforcement bars.
In order to achieve full continuity of reinforcement bars for joining precast
concrete components, grouted splice connectors are preferred and employed (see
Figure 1.1). Grouted splice connectors have shown the capability of being used as
connections in the precast concrete structures. These connectors reduced the splice
length for ensuring the continuity of steel bars considerably [7]. The splice
connectors make the installation process simpler and solve the problems of bar
congestion and detailing, especially in structures that are heavily reinforced[8]. For
the first time, in the late 1960s [9, 10], this splice method was introduced by Dr.
Alfred A. Yee upon the invention of NMB splice sleeve® [10]. From that time,
different types of mechanical couplers such as BarSplice Double Barrel Zap
Screwlok©, Lenton Interlok® [11, 12] Lenton QuickWedge©, etc. have been
developed and commercialised. Most of the splice connectors have been invented by
private individuals and are difficult to obtain the technical details due to the
proprietorship rights. Due to limited literature regarding the behavior of grouted
3
splices connections, researchers prefer to investigate the non-proprietary splice that is
inexpensive. Table 1.1 shows the differences between the commercial connections
and non-proprietary splice connections which were studied in this research. The
commercial splice connections normally required special mould to fabricate and are
made from cast iron. On the other hand, the proposed non-proprietary connectors
required steel pipe, spiral and splice bars only. Concerning the performance, an
adequate splice connector should be capable of providing high quality assurance in
bond strength even with short spliced lengths. In this splices technique, the strength
of the splice joint relies heavily on the anchorage bond.
Table 1.1: Comparisons of the commercial and proposed connections of this
research
Commercial splice connector Proposed splice connector in this research
NMB splice sleeve
Double Barrel Zap Screwlok
Lenton Interlok
Characteristics of commercial splice
connectors:
1. Need special moulds to fabricate
the thread and splice which is
expensive
2. Cast iron is used for the splice
which is brittle
3. Proprietary
Steel pipe with spiral confinement
Spiral confinement with four splice bars
Characteristics of proposed non-proprietary splice
connectors:
1. Steel pipe spiral and splice bars of
connections are easily available in the
market with inexpensive materials
2. These types of connections can be
fabricated easily without any special
mould.
3. Non-proprietary
4
Figure 1.1 Grouted splice connection in precast concrete components [13]
Usually the bond development has strong effect on the interaction between
the grout and splice bar for the grouted splice connections, that are usually used in
connecting precast concrete components. In fact, the mechanism of load transfer
between the precast concrete components depends on the quality of adequate bond
provided by the grouted splice (Figure 1.2) [14]. Investigation works on the factors
that affect the bond were studied greatly over the last 40 years and as a result,
considerable modifications have been introduced to bond clauses in design codes
worldwide [15]. Detailed evaluations of bond strength and bond behavior are
complicated, as the magnitude of bond strength is influenced by a wide range of
factors. For example, the CEB-FIP Model Code 90 [16] includes not less than 10
parameters which influence the anchorage bond behavior.
5
Figure 1.2 Mechanism of load transfer [17]
In the bond aspect, one of the key factors that can improve the value of bond
stress is the present of confinement between the steel bar and grout. The confinement
can influence the anchorage bond and reduces the required embedment length of the
spliced steel bars [7, 18-20]. The application of confinement delays early
development of the splitting cracks either by expansion resistance or bridging of
surrounding materials of the steel bars.
This study concentrates on the behavior of proposed grouted splice
connections with spiral confinement. To investigate the behavior of new splice
connections, it is very essential to know the interactions and also internal stress
distribution among the deformed steel spliced bars and its surrounding materials.
1.2 Background of Study
In reinforced concrete structures, the reinforcement bars attain continuity
through lapping full anchorage lengths of the steel bars [21]. On the other hand, the
long bar lapping lengths may be impractical in cases where there is not adequate
space for the accommodation of the required bar development lengths, especially in
structures that are heavily reinforced and in cases where larger bar sizes are used,
6
leading to impractical lapping lengths, or it may be not permissible to be lap spliced
by codes [8].
In precast concrete structures, prefabricated components such as wall to wall
and column to column need to be jointed together by ensuring the continuity of
rebars from the lower component to upper components. To join the prefabricated
elements of the precast concrete systems, the lengthy lapping system have not been
shown quite appropriate. For example, long extruding starter bars provided for
embedment in the adjoining structural elements in the installation process often cause
problems of transportation and handling. As a result, for ensuring the ease of the
installation and maximizing the speed of construction process, there is a need for
short bar anchorage length
The grouted splice offers a feasible solution to connect the prefabricated
elements during erections. During the assembly process, prior to pouring or pumping
the grout in the sleeves, the short extruding steel bars could be inserted to the pre-
embedded sleeves in the targeted elements. Using this technique, the problem of long
embedded lengths can be solved and the process of handling and installation can be
performed more easily.
In general, using grouted splices, discontinued bars can be spliced at short
embedded bar lengths. Though, the bond performance may be different because of
variations existing in the grouted splice configurations. Knowing these issues, the
grouted splices responses should be investigated, particularly regarding the bond
behavior, for identification of the major factor like confinement that has impact on
the bond mechanism in grouted splices.
The influence of confinement on the ductility and compressive strength of
compression members has been reported by many researchers [22-26]. Their work
was based on the confinement of members along their full length. The confinement
effect using spirals or ties on lap splice lengths and development of the longitudinal
7
reinforcement was investigated in their work. Based on the shape of confinement,
circular spirals provide a continuous confining pressure around their axial axis [27].
The concept of spirally confined lap splices of deformed bar comes from the
above theory to generate the strength required for connecting the reinforcement bars
together (see Figure 1.3). So, In order to employ spiral confinement in grouted
connections, more investigations are required rather than relying on speculated
predictions. Thus, it is essential to understand the responses of the grouted splices
when subjected to the load cases of direct axial and flexural pullout loads. Other
forces that may occur in the splice are axial force-moment and axial compression-
moment. the work by Kuttab and Dougill [28] has shown that most of the grouted
connections in precast column components experienced axial force–moment
interaction characteristics. Hence, multi-phases of experimental studies are carried
out to study the behavior of proposed connections caused by the bond stress-slip
relationship of individual short deformed steel by spiral reinforcement. The
confinement provided by the spirals is part of the proposed short splicing method
which increases the bond strength. The spirals characteristics and properties are
applied in Industrial Building Systems (IBS) where other types of mechanical spliced
connections could be substituted by this connection.
8
Figure 1.3 Spiral confinement in splice connections [29]
1.3 Problem Statements
The problems that need to be addressed in grouted splice connections are:
1. The conventional grouted sleeve connector is one of the famous methods for
joining precast concrete components (see Figure 1.4). According to the
finding of Kuttab [28], the combination of axial and flexural loads interaction
characteristics of grouted sleeve connectors has to be equal to the parent
column. Due to this axial and flexural load interaction, long embedded length
of 35 times bar diameter based on BS 8110 [21] is needed to achieve the full
continuity of reinforcement bars. The main problem in using this connection
is the installation process of the grouted sleeve connectors which is quite
difficult and it is not easy to achieve with any accuracy. The main bars in the
sleeve may not always be perfectly located at the centre of sleeve (See Figure
9
1.5). There is a tendency the long bars to touch the wall of the sleeve in the
precast component, so preventing penetration of grout around the bar and it is
not allowing the grout to fill all the voids inside of the sleeve completely.
Since the grout inside the sleeve cannot be inspected after installation, there is
doubt that the main bar is fully bonded. So, it is necessary to provide the
system which can be assembled by prefilling [8].
2. There is not much research works on the effect of spiral confinement on the
bond behavior of grouted splices. Therefore, there is a need to study the
confinement effects in the grouted splice connectors.
Figure 1.4 Projecting the long embedded length in conventional grouted
sleeve [30]
10
Figure 1.5 Cross section through grouted sleeve column splice [31]
1.4 Objectives
Owing to these important characteristics, the bond behavior of reinforcement
embedded in grout needs to be investigated accordingly. The key factor governing
the anchored-bar behavior in confined grout is the local bond stress-slip relationship.
Consequently, to develop new splice connections, it is important to understand the
internal stress and the local bond stress-slip relationship between various main
connected bars and their surrounding materials. Failure of bond leads to slippage in
reinforcement bars and consequently failure of structural members.
To achieve the task of solving the problems stated above, this research is
outlined with several main objectives as follows:
i. To investigate the performance of spiral confinement and splice bars to the
behavior of connected deformed steel bars in grouted connections under
direct axial and flexural loads.
ii. To study the effect of spiral configurations on the bond stress-slip behavior of
the deformed steel bars under direct axial and flexural loads.
11
iii. To study the comparison of direct axial and flexural pullout loads on the bond
behavior of deformed steel bars in grouted spiral connection.
iv. To propose equations for predicting the bond strength and bond stress-slip
relationship of the grouted spiral connections under direct axial and flexural
loads.
1.5 Scope of Research
The scope of the research program includes:
a. The experimental tests of grouted spiral connections with different
configurations of spiral confinement.
b. The investigation of the performance of the proposed grouted spirals when
subjected to load cases of direct axial and flexural pullout.
c. The study of responses of the grouted spirals towards tree considered parameters,
pitch distance of spiral, diameter of spiral and type of main bars.
d. The development of simplified equations for predicting the responses of the
connections under mentioned load cases
e. Additionally, two major phases of experimental tests involves
i) Testing of thirty-six grouted spiral specimens under monotonic direct axial
pullout to study the behavior of the connections under tension.
ii) Experimental testing of twelve full-scale beam specimens, connected with
grouted spirals, under flexural pullout loads to acquire the response of the
steel deformed bars in grouted spiral connections.
12
Furthermore, the scope of the test results for each phase comprises:
a. Phase I – Direct tensile axial pullout test of grouted spiral connections
i. Failure load capacity
ii. Bond strength
iii. Bond stress-slip behavior
iv. Stress-strain response
v. Failure mode
b. Phase II – Flexural pullout test of the steel deformed bars in grouted spiral
connections
i. Failure load capacity
ii. Bond strength
iii. Bond stress-slip behavior
iv. Stress-strain response
v. Failure mode
Lastly, the scope of analytical research consists of:
a. Analysing the bond stress-slip relationship of the grouted splices under direct
axial and flexural pullout loads from the experimental results in Phases I and II.
b. Deriving equations to predict the bond strength of the grouted spiral connections
under tensile and flexural pullout loads.
c. Evaluating the effect of spiral confinement on the bond stress-slip relationship by
calculating the bond energy
d. Comparison of the experimental test results to other researcher to validate the
data.
13
1.6 Thesis Organization
Chapter 2 presents a review of the available literature and the present state of
knowledge regarding grouted connections and mechanism of bond stress.
Chapter 3 describes the experimental program, including the details of test
specimens, connection configurations, material specifications, instrumentations, test
setup and procedures.
Chapter 4 presents the results and discusses the responses of grouted spiral
specimens when subjected to increasing direct axial pullout loads.
Chapter 5 displays and discusses the test results and response of full-scale
beam specimens, connected with steel deformed bars in grouted spiral connections,
under flexural pullout loads.
Chapter 6 presents the analytical derivations for predicting the bond strength
response and bond stress-slip relationship of the proposed grouted spiral connections
under direct axial and flexural pullout loads.
Chapter 7 summarizes and concludes the entire research carried out.
REFERENCES
1. Hamid, Z.A., Kamar, K. A. M., Raham, A. H. A. Industrialized Building
System (IBS). 2009.
2. Thanoon, W. A. M., Peng, L. W., Abdul Kardir, M. R. The Experiences of
Malaysia and other countries in industrialised building system. Proceeding of
International Conference on Industrialised Building Systems. 2003.
3. Kamar, K., M. Alshawi, and Z. Hamid. Barriers to industrialized building
system (IBS): The case of Malaysia. in In BuHu 9th International
Postgraduate Research Conference (IPGRC), Salford, United Kingdom.
2009.
4. Tibbetts, A.J., M.G. Oliva, and L.C. Bank. Durable fiber reinforced polymer
bar splice connections for precast concrete structures. Composites & Ploycon,
2009. 15-17.
5. American concrete insitute. Design Recommendations for Precast Concrete
Structures, ACI 550. 1993.
6. ACI-ASCE Committee. Emulating Cast-in-Place Detailing in Precast
Concrete Structures. 550. 2001.
7. Einea, A., T. Yamane, and M.K. Tadros. Grout-filled pipe splices for precast
concrete construction. PCI journal, 1995. 40(1). 82-93.
8. American concrete insitute. Mechanical Connections of Reinforcing Bars.
ACI 439. 1991.
9. Splice sleeve North America, I.H.e.o.N.S.S.; Available from:
http://www.splicesleeve.com/history.html.
10. Yee, A.A. Splice sleeve for reinforcing bars with cylindrical shell. U.S.
3552787 A. 1986.
11. Albrigo, J., L.J. Colarusso, and E.D. Ricker. Method of forming concrete
structures with a grout splice sleeve which has a threaded connection to a
reinforcing bar. U.S. 5366, 672. 1994.
12. Albrigo, J., L.J. Colarusso, and E.D. Ricker. Reinforcing bar splice and
system for forming precast concrete members and structures. U.S 5468, 524.
1995
13. Spiral Connector Product Guide, H.D.B.a.B.A.L.
14. Pecce, M., Manfredi, G., Realfonzo, R., and Cosenza, E. Experimental and
analytical evaluation of bond properties of GFRP bars. Journal of materials
in civil engineering, 2001. 282-290.
15. Cairns, J. and G. Plizzari. Towards a harmonised European bond test.
Materials and Structures, 2003. 36(8). 498-506.
16. FIB-Féd. Int. du Béton. CEB-FIP Model Code 1990. 1993.
188
17. kim, Y.m. A study of pipe splice sleeves for use in precast beam-cloumn
connections. Master of sience in enginieering, The University of Texas at
Austin; 2000.
18. Untrauer, R.E. and R.L. Henry. Influence of normal pressure on bond
strength. ACI Journal Proceedings. 1965.
19. Robins, P. and I. Standish. The influence of lateral pressure upon anchorage
bond. Magazine of Concrete Research. 1984. 36(129). 195-202.
20. Moosavi, M., A. Jafari, and A. Khosravi. Bond of cement grouted reinforcing
bars under constant radial pressure. Cement and Concrete Composites, 2005.
27(1). 103-109.
21. British Standard Insitution. Structural Use of Concrete - Part 1: Code of
practice for design and construction. 1997.
22. Pfister, J.F. and A.H. Mattock. High Strength Bars as Concrete
Reinforcement, Part 5: Lapped Splices in Concentrically Loaded Columns.
Portland Cement Association, Research and Development Laboratories,
1963.
23. Pfister, J.F. Influence of Ties on the Behavior of Reinforced Concrete
Columns. ACI Journal Proceedings, 1964.
24. Mander, J.B., M.J. Priestley, and R. Park. Theoretical stress-strain model for
confined concrete. Journal of structural engineering, 1988. 114(8). 1804-
1826.
25. Mander, J., M. Priestley, and R. Park. Observed stress-strain behavior of
confined concrete. Journal of structural engineering, 1984. 114(8). 1827-
1849.
26. Orangun, C., J. Jirsa, and J. Breen. A Reevaulation of Test Data on
Development Length and Splices. ACI Journal Proceedings, 1977.
27. Park, R. Reinforced concrete structures.John Wiley & Sons. 1975.
28. Kuttab, A. and J. Dougill. Grouted and dowelled jointed precast concrete
columns: behaviour in combined bending and compression. Magazine of
Concrete Research, 1988. 40(144). 131-142.
29. Heng, L.J.M.a.J.W.L. Blueprints for Successful Public Housing Development.
Singapore Concrete Institute. 2006.
30. FIB-Féd. Int. du Béton. Structural Connections for Precast Concrete
Buildings: Guide to Good Practice. 2008.
31. Elliott, K.S. and C. Jolly (2013). Multi-storey precast concrete framed
structures. Wiley. 2013.
32. Lancelot, H.B. Mechanical splices of reinforcing bars. Concrete
Construction, 1985. 30(1). 23.
33. Henin, E. and G. Morcous. Non-proprietary bar splice sleeve for precast
concrete construction. Engineering Structures, 2015. 83. 154-162.
34. American concrete insitute. Cement and concrete terminology. ACI Special
Publication. 1967. ACI 116.
35. M. K. Thompson, J. O. Jirsa, J. E. Breen, and R. E . Klingner. Anchorage
behavior of headed reinforcement: literature review. 2002.
36. Ferguson, P.M., J.E. Breen, and J.O. Jirsa. Reinforced concrete fundamentals.
1988.
37. Goto, Y. Cracks formed in concrete around deformed tension bars. ACI
Journal Proceedings. 1971.
38. Mains, R.M. Measurement of the distribution of tensile and bond stresses
along reinforcing bars. ACI Journal Proceedings. 1951.
189
39. Jiang, D., S. Shah, and A. Andonian. Study of the transfer of tensile forces by
bond. ACI Journal Proceedings.1984.
40. Brenes, F.J., S.L. Wood, and M.E. Kreger. Anchorage requirements for
grouted vertical-duct connectors in precast bent cap systems. 2006.
41. Feldman, L.R. and F.M. Bartlett. Bond strength variability in pullout
specimens with plain reinforcement. ACI Structural Journal, 2005. 102(6).
42. Eligehausen, R., E.P. Popov, and V.V. Bertero. Local bond stress-slip
relationships of deformed bars under generalized excitations. 1982.
43. Soroushian, P. and K.-B. Choi. Local bond of deformed bars with different
diameters in confined concrete. ACI Structural Journal, 1989. 86(2).
44. Hussein, L. Analytical modeling of bond stress at steel-concrete interface due
to corrosion. Master of applied sience. Ryerson University, Canada, Torento;
2011.
45. American concrete insitute. Bond and development of straight reinforcing
bars in tension. ACI 408. 2003.
46. Hong, S. and S.-K. Park. Uniaxial bond stress-slip relationship of reinforcing
bars in concrete. Advances in Materials Science and Engineering, 2012.
47. Treece, R.A. and J.O. Jirsa. Bond strength of epoxy-coated reinforcing bars.
ACI Materials Journal, 1989. 86(2).
48. American concrete insitute. Bond Under Cyclic Loads. ACI 408. 1992.
49. Lutz, L.A. The mechanics of bond and slip of deformed reinforcing bars in
concrete. Cornell University; 1966.
50. Wang, H. An analytical study of bond strength associated with splitting of
concrete cover. Engineering Structures,2009. 31(4). 968-975.
51. Gallus Rehm, C Van Amerongen. The basic principles of the bond between
steel and concrete. Cement and Concrete Association, 1968.
52. Quayyum, S. Bond behaviour of fibre reinforced polymer (FRP) rebars in
concrete. Master of applied sience. University of British Columbia; 2010.
53. Ling, J.H., Ahmad Baharuddin Abd. Rahman, Abdul Karim Mirasa, Zuhairi
Abd. Hamid. Performance of cs-sleeve under direct tensile load: part 1:
failure modes. Malaysian Journal of Civil Engineering, 2008. 20(1). 89-106.
54. Xu.F, Zhimin Wu, Jianjun Zheng, Yu Hu, and Qingbin Li. Experimental
study on the bond behavior of reinforcing bars embedded in concrete
subjected to lateral pressure. Journal of materials in civil engineering, 2011.
24(1). 125-133.
55. Soroushian, P., Ki-Bong Choi, Gi-Hyun Park, and Farhang Aslani. Bond of
deformed bars to concrete: effects of confinement and strength of concrete.
ACI Materials Journal, 1991. 88(3).
56. Ichinose, T., Y. Kanayama b, Y. Inoue c, J.E. Bolander Jr. Size effect on
bond strength of deformed bars. Construction and building materials, 2004.
18(7). 549-558.
57. Ling JH, Ahmad Baharuddin Abd. Rahman, Hamid Z (2008). Failure modes
of aluminium sleeve under direct tensile load. 3rd International conference
on postgraduate education. Malaysia: Penang. 2008.
58. Loo, G.K. Parametric Study of Grout-Filled Splice Sleeve Integarated with
Flexible Aluminium Tube for Precast Concrete Connection. Bs.c thesis,
Universiti Teknologi Malaysia; 2009.
59. Ling, J.H., Ahmad Baharuddin Abd. Rahman, Izni Syahrizal Ibrahim, Zuhairi
Abdul Hamid. Behaviour of grouted pipe splice under incremental tensile
load. Construction and building materials, 2012. 33. 90-98.
190
60. Ling, J.H., A.B. Abd Rahman, and I.S. Ibrahim. Feasibility study of grouted
splice connector under tensile load. Construction and building materials,
2014, 50. 530-539.
61. Einea, A., S. Yehia, and M.K. Tadros. Lap splices in confined concrete. ACI
Structural Journal, 1999. 96(6).
62. Darwin, D.; Tholen, M. L.; Idun, E. K.; and Zuo. Splice strength of high
relative rib area reinforcing bars. ACI Structural Journal, 1996.
63. American concrete insitute. Building Code Requirements for Reinforced
Concrete. ACI 318. 1962
64. Tepfers, R.. A theory of bond applied to overlapped tensile reinforcement
splices for deformed bars. Chalmers University of Technology; 1973.
65. Eligehausen, R. Bond in Tensile Lapped Splices of Ribbed Bars with Straight
Anchorages. German Institute for Reinforced Concrete, 1979. 118.
66. Francisco J. Brenes, S.L.W., and Michael E. Kreger. Anchorage
Requirements for Grouted Vertical-Duct Connectors in Precast Bent Cap
Systems. Center for Transportation Research The University of Texas at
Austin; 2006.
67. Darwin, D.; McCabe, S. L.; Idun, E. K.; and Schoenekase, S. P. Development
length criteria: bars not confined by transverse reinforcement. ACI Structural
Journal, 1992. 89(6).
68. Esfahani, M.R. and B.V. Rangan. Local bond strength of reinforcing bars in
normal strength and high-strength concrete (HSC). ACI Structural Journal,
1998. 95(2).
69. Esfahani, M.R. and B.V. Rangan (1998) Bond between normal strength and
high-strength concrete (HSC) and reinforcing bars in splices in beams. ACI
Structural Journal, 1998. 95(3).
70. Farndon, S.J. The Effect of Normal Pressure on Bond in Light-Weight
Concret. Loughborough University; 1982.
71. Tepfers, R. Cracking of concrete cover along anchored deformed reinforcing
bars. Magazine of Concrete Research, 1979. 31(106). 3-12.
72. Alavi-Fard, M. and H. Marzouk. Bond of high-strength concrete under
monotonic pull-out loading. Magazine of Concrete Research, 2004. 56(9).
545-557.
73. Jansson, P.O. Evaluation of grout-filled mechanical splices for precast
concrete construction. 2008.
74. Coogler, K.L., K.A. Harries, and M. Gallick. Experimental study of offset
mechanical lap splice behavior. ACI Structural Journal.2008. 105(4).
75. Lee, S.-H. and H.-K. Kim. Development of Steel Pipe Splice Sleeve for High
Strength Reinforcing Bar (SD500) and Estimation of its Structural
Performance under Monotonic Loading. Journal of the Korea institute for
structural maintenance and inspection, 2007. 11(6). 169-180.
76. Abukawa, M. Mortar-filled type reinforcing bar joint. U.S 6851245 B1.
2005.
77. Hope, P.F. Reinforcing bar coupling system. U.S 4666326 A. 1987.
78. Oh, M.H. and E.J. Wilson, Reinforcing bar splice with cutting edge bolts. U.S
20080172979 A1. 2008.
79. Dahl, K.L. High strength grouted pipe coupler. U.S 6679024 B2. 2004.
80. Oliva, M.G. and L.C. Bank. Splice system for connecting rebars in concrete
assemblies. U.S 8413396 B2. 2013.
191
81. Orangun, C., J. Breen, and J.O. Jirsa. The strength of anchor bars: a
reevaluation of test data on development length and splices.Center for
Highway Research, University of Texas at Austin; 1975.
82. Zuo, J. Bond strength of high relative rib area reinforcing bars., University
of Kansas, Civil and Environmental Engineering; 1998.
83. Zuo, J. and D. Darwin. Splice strength of conventional and high relative rib
area bars in normal and high-strength concrete. ACI Structural Journal, 2000.
97(4).
84. Haskett, M., D.J. Oehlers, and M. Mohamed Ali. Local and global bond
characteristics of steel reinforcing bars. Engineering Structures, 2008. 30(2),
376-383.
85. Adajar, J., Teukai.Y, and Hiroshi.I. An Experimental Study on the Tensile
Capacity of Vertical Bar Joints in a Precast Shearwall. Transaction of the
Japan concrete institue, 1993. 15(2). 1255-1260.
86. Nilson, A.H. Nonlinear analysis of reinforced concrete by the finite element
method. ACI Journal Proceedings, 1968.
87. Kankam, C.K. Relationship of bond stress, steel stress, and slip in reinforced
concrete. Journal of structural engineering. 1997. 123(1). 79-85.
88. Nilson, A.H. Internal measurement of bond slip. ACI Journal Proceedings,
1972.
89. Mirza, S.M. and J. Houde. Study of bond stress-slip relationships in
reinforced concrete. ACI Journal Proceedings, 1979.
90. Rilem/CEB/FIP. Bond test for reinforcing steel: 2.Pullout test. 1970.
91. Tastani, S. and S. Pantazopoulou. Experimental evaluation of the direct
tension-pullout bond test. Bond in concrete from research to standards,
Budapest, Hungary. 2002.
92. Tastani, S. and S. Pantazopoulou. Behavior of corroded bar anchorages. ACI
Structural Journal, 2007. 104(6).
93. Hamza, A.M. and A.E. Naaman. Bond strength of reinforcing bars in
SIFCON. ASCE. 1991.
94. De Larrard, F., I. Shaller, and J. Fuchs (1993). Effect of the bar diameter on
the bond strength of passive reinforcement in high-performance concrete.
ACI Materials Journal, 1993. 90(4).
95. Rilem/CEB/FIP. Bond test for reinforcing steel: 1. Beam test. 1970.
96. E. Cosenza, G. Manfredi, M. Pecce, and R. Realfonzo. Bond between Glass
Fiber Reinforced Plastic Reinforcing Bars and Concrete Experimental
Analysis. ACI Special Publication, 1999. 188.
97. Dancygier, A.N., A. Katz, and U. Wexler. Bond between deformed
reinforcement and normal and high-strength concrete with and without fibers.
Materials and Structures, 2010. 43(6). 839-856.
98. Hosseini, S.J.A. Effect of spiral on the bond stress-slip relationship in the
splice sleeve connector. Ms.c tehsis. Universiti Teknologi Malaysia; 2011.
99. Hosseini, S.J.A., Abd Rahman AB. Effects of spiral diameter on the bond
stress-slip relationship in grouted sleeve connector. Malaysian J Civil Eng,
2013. 12(1).
100. Hosseini, S.J.A., Abd Rahman AB. Analysis of spiral reinforcement in
grouted pipe splices connectors. GRAĐEVINAR Journal, 2013. 65(6). 1-10.
101. Hosseini, S.J.A., Koushfar Kiarash, Abd Rahman AB, Razavi Meysam. The
bond behaviour in reinforced concrete, state of the art, Part 1. Cement-
Wapno-Beton, 2014. (2). 93-105.
192
102. Hosseini, S.J.A., Koushfar Kiarash, Abd Rahman AB, Razavi Meysam. The
bond behaviour in reinforced concrete, state of the art, Part 2. Cement-
Wapno-Beton, 2014. (6).
103. ASTM. Standard Test Methods for Testing Mechanical Splices for Steel
Reinforcing Bars. ASTM A1034/A. 2005.
104. Tran, B.H., Y. Berthuad, and F. Ragueneau. Essais PIAF: Pour Identifier
l'Adhérence et le Frottement. 18ème Congrès Français de Mécanique. 2007.
105. ASTM. Standard Test Method for Comparing Bond Strength of Steel
Reinforcing Bars to Concrete Using Beam-End Specimens. ASTM A944-05.
2005.
106. British Standard Insitution. Steel for the reinforcement of concrete, Weldable
reinforcing steel,Bar, coil and decoiled product, Specification. BS 4449.
2005.
107. Abrams, D.A. Tests of bond between concrete and steel. 1913.
108. Ling, J.H., Ahmad Baharuddin Abd. Rahman, Abdul Karim Mirasa, Zuhairi
Abd. Hamid. Performance of cs-sleeve under direct tensile load: part II:
structural performance. Malaysian Journal of Civil Engineering. 2008. 20(1).
107-127.
109. Gambarova, P. and G. Rosati. Bond and splitting in bar pull-out: behavioural
laws and concrete cover role. Magazine of Concrete Research, 1997. 49(179).
99-110.
110. Lura, P., G. Plizzari, and P. Riva. 3D finite-element modelling of splitting
crack propagation. Magazine of Concrete Research, 2002. 54(6). 481-493.
111. Ling, J.H. Behaviour of grouted splice connections in precast concrete walls
subjected to tensile, shear and flexural loads. PhD thesis. Universiti
Teknologi Malaysia, Faculty of Civil Engineering; 2011.
112. Steuck, K.P. Anchorage of Large-Diameter Reinforcing Bars Grouted into
Ducts. University of Washington; 2007.
113. Kemp, E.L., F. Brezny, and J. Unterspan. Effect of Rust and Scale on the
Bond Characteristcs of Deformed Reinforcing Bars. ACI Journal
Proceedings, 1968.
114. Benmokrane, B. and B. Tighiouart. Bond strength and load distribution of
composite GFRP reinforcing bars in concrete. ACI Materials Journal, 1996.