Boiler Commissioning Presentation

download Boiler Commissioning Presentation

of 80

Transcript of Boiler Commissioning Presentation

  • 7/31/2019 Boiler Commissioning Presentation

    1/80

    24 May 2012 PMI Revision 00 1

    BOILERCOMMISSIONING

  • 7/31/2019 Boiler Commissioning Presentation

    2/80

    24 May 2012 PMI Revision 00 2

    COMMISSIONING :It is the later stage of

    erection and starting stage of operation.It includes 14 days of continuous

    operation with 72 hrs of full load operation.

  • 7/31/2019 Boiler Commissioning Presentation

    3/80

    24 May 2012 PMI Revision 00 3

    Commissioning Activities before taking over aplant.

    Purpose

    To check that plant is supplied as per design

    Quality of erection and commissioning

    Plant operates reliably, safety & design

    performance. Finding out reason for any failure to achieve the

    design performance.

  • 7/31/2019 Boiler Commissioning Presentation

    4/80

    24 May 2012 PMI Revision 00 4

    Organization

    Steering committee Policy and priorites.Ensures adequate resource. Approval ofdocuments. Headed by G.M.

    Commissioning panel

    Control & progress ofday to day activities. Coordination betweenTest teams and Working groups. Erection &O&M dept.

    Working groups

    Looks after requirement ofTest team.

    Test Team Conducting testing &commissioning.

  • 7/31/2019 Boiler Commissioning Presentation

    5/80

    24 May 2012 PMI Revision 00 5

    Documentation

    1. Papers of principle Prepared jointly byErection and corporate O.S.

    To set out principles & objectives

    Established design data to compareplant.

    Define documentation requirement

  • 7/31/2019 Boiler Commissioning Presentation

    6/80

    24 May 2012 PMI Revision 00 6

    Documentation

    2.Testing & commissioning Schedule

    To meet the requirement of the paper ofprinciple

    Plant under cover

    Detail test method & programme

    Safety

    Emergencies

    Individual responsibility

    Results

  • 7/31/2019 Boiler Commissioning Presentation

    7/80

    24 May 2012 PMI Revision 00 7

    Documentation

    3.Standard checklist

    Ensuring completion of erection

    Limited extent operation Test conductance in consistent

    manner

    Instrument providing Schedule withrange & resolution and calibrationvalidation.

  • 7/31/2019 Boiler Commissioning Presentation

    8/80

    24 May 2012 PMI Revision 00 8

    Documentation

    4.Design change notification5. Test reports

    Recording of resultOmission reportAnalysis

    6. Safety procedure7. Plant certification

    Safety clearance certificateRecord of initial operationClearance for station operation certificate

    Initial taking over certificateFinal internal contract clearance completion of guarantee

    period8. Plant completion report. PG test evaluation and acceptance

  • 7/31/2019 Boiler Commissioning Presentation

    9/80

    24 May 2012 PMI Revision 00 9

  • 7/31/2019 Boiler Commissioning Presentation

    10/80

    24 May 2012 PMI Revision 00 10

    INSTRUMENTS: PRESSURE GUAGE

    TP REF: 1.5.1.

    No. Activity

    Remarks

    DEFECTS & OMISSIONS CONTINUATION OVERLEAF

    REMARKS

    NTPC SIGNATURE

    CONTRACTORS SIGNATURE DATE

  • 7/31/2019 Boiler Commissioning Presentation

    11/80

    24 May 2012 PMI Revision 00 11

    Steps Pre-commissioning checks

    Trial run of equipments

    e.g. Fans and APH commissioning

    Hydraulic Test

    Chemical cleaning Gas Tightness Test

    ESP commng.

    Fuel Oil System

    Preparation for first light-up

    Steam blowing Safety v/v settings

    Other boiler Aux. commissioning

  • 7/31/2019 Boiler Commissioning Presentation

    12/80

    24 May 2012 PMI Revision 00 12

    Pre commissioning checks

    Physical inspection

    Ensuring tightness

    Lubrication check

    Setting of relief v/v

    Operation test on v/vs and fittings

    Insulation test on cable/ motor

    Rotation checks

    Flushing out the oil system

    Trial run of motor with all protection for 8 hrs

    Coupling of fan with motor

  • 7/31/2019 Boiler Commissioning Presentation

    13/80

    24 May 2012 PMI Revision 00 13

    Trial run of equipments

    Commissioning checks

    Checking of IGV/ pitch control mechanism

    Operation of lub oil pump system Operation of Discharge damper

    Starting the fan as recommended by mfd.

    8 hrs trial run conductance

    Logging parameters.

  • 7/31/2019 Boiler Commissioning Presentation

    14/80

    24 May 2012 PMI Revision 00 14

    Pre commissioning checks for boiler

    Hydraulic test

    For both drainable and non drainable portions

    Filled with DM water. Add 10 ppm ammonia and 200 ppm

    hydrazine

    All drainable and non drainable parts to be filled through theirbottom drains.

    High pressure positive displacement pump is used.

    Test pressure as per IBR recommendation.

    Pressure should be raised gradually.

    After pressurization hold and inspect.

    Wet preservation done after draining

  • 7/31/2019 Boiler Commissioning Presentation

    15/80

    24 May 2012 PMI Revision 00 15

  • 7/31/2019 Boiler Commissioning Presentation

    16/80

    24 May 2012 PMI Revision 00 16

    BOILER HYDRAULIC TEST

  • 7/31/2019 Boiler Commissioning Presentation

    17/80

    24 May 2012 PMI Revision 00 17

    CHEMICALS REQUIREMENT

  • 7/31/2019 Boiler Commissioning Presentation

    18/80

    24 May 2012 PMI Revision 00 18

  • 7/31/2019 Boiler Commissioning Presentation

    19/80

    24 May 2012 PMI Revision 00 19

  • 7/31/2019 Boiler Commissioning Presentation

    20/80

    24 May 2012 PMI Revision 00 20

  • 7/31/2019 Boiler Commissioning Presentation

    21/80

    24 May 2012 PMI Revision 00 21

  • 7/31/2019 Boiler Commissioning Presentation

    22/80

    24 May 2012 PMI Revision 00 22

    Pre commissioning checks for boiler

    Gas tightness check

    Through smoke generator. 24 MKS,40 IBS wt.from defance store.

    Run FD and ID.

  • 7/31/2019 Boiler Commissioning Presentation

    23/80

    24 May 2012 PMI Revision 00 23

  • 7/31/2019 Boiler Commissioning Presentation

    24/80

    24 May 2012 PMI Revision 00 24

  • 7/31/2019 Boiler Commissioning Presentation

    25/80

    24 May 2012 PMI Revision 00 25

    AIR AND GAS TIGHTNESS TEST OF

    FURNACE AND DUCTS

    STAGE 1 : FD fan to air inlet damper of APH

    300

    mmWC

    STAGE II : APH inlet damper to wind box. - 300

    mmWC

    STAGE III : Wind box to APH gas O/L damper. - 75

    mmWC

    STAGE IV : APH O/L damper to ESP I/L gate. - 300

    mmWC

  • 7/31/2019 Boiler Commissioning Presentation

    26/80

    24 May 2012 PMI Revision 00 26

    AIR AND GAS TIGHTNESS TEST OF

    FURNACE AND DUCTS

    STAGE V : ESP O/L damper to ID fan I/L damper - 300

    mmWC

    STAGE VI : ID fan I/L damper to stack.kerosene test.

    STAGE VII : PA fan to PAPH I/L damper. (SCAPH bypass,

    cold air duct and seal air pipes. - 500 mmWC

    STAGE VIII : PAPH air I./L to hot air gates500 mmWC

    ESP is tested by air in leak test.

  • 7/31/2019 Boiler Commissioning Presentation

    27/80

  • 7/31/2019 Boiler Commissioning Presentation

    28/80

    24 May 2012 PMI Revision 00 28

    PROTOCOL ON SMOKE GENERATOR TEST

    OF THE BOILER

  • 7/31/2019 Boiler Commissioning Presentation

    29/80

    24 May 2012 PMI Revision 00 29

    ESP commissioning

    Physical inspection.

    Electrical inspection

    Gas distribution test Air load test

  • 7/31/2019 Boiler Commissioning Presentation

    30/80

    24 May 2012 PMI Revision 00 30

    Fuel oil system

    Physical inspection.

    Flushing of lines.

    Trial of pumps. Ignitor and burner housing check.

  • 7/31/2019 Boiler Commissioning Presentation

    31/80

    24 May 2012 PMI Revision 00 31

    Alkali boil-out

    Purpose: Chemical cleaning of boiler water & steamsystem to remove loose foreign material, oil, grease etc.

    Water Washing

    Temporary water filled arrangement. Itcontinues till conductivity of inlet/ outlet water equals.

    Process continued nos. of time till conductivity ofwashing water matches with fresh filtered water.

  • 7/31/2019 Boiler Commissioning Presentation

    32/80

    24 May 2012 PMI Revision 00 32

    Alkali boil-out

    Alkali boil out Fill water with DM water. Add Trisodium phosphate(1000 PPM 0.1%), Do Decca Hydrate & Hydrazine Hydrate (200PPM 0.02 %)

    Filling upto 180 mm. Boiler light up with AB elevation

    Pressure raised to 40 Kg/ Cm2.

    Hourly blow down given to remove impurities and feeding maintain tokeep drum level.

    Oil gun to cut out during blowing

    Boiler expansion noted

    At the end boiler will be boxed up and hot draining done when pr.is1.5 Kg./Cm2.

  • 7/31/2019 Boiler Commissioning Presentation

    33/80

    24 May 2012 PMI Revision 00 33

    COMMISSIONING PROTOCOL FOR ALKALI BOIL OUT

    TRISODIUM PHOSPHATE Kgs ppm

    REMARKS:

    Manufacturer Customer Engineer

  • 7/31/2019 Boiler Commissioning Presentation

    34/80

    24 May 2012 PMI Revision 00 34

    Acid cleaning

    Covering steam and water ckt., economiser,waterwall, Boiler Drum excluding super heaters,reheater & associated piping.

    Stage I Acid washingII DM water rinsing

    III Citric acid water rinsing

    IV DM water rising

    V Neutralising with sodium carbonate.VI Passivation 1st stage.

    VII Inspection

    VIII Passivation 2nd stage.

  • 7/31/2019 Boiler Commissioning Presentation

    35/80

    24 May 2012 PMI Revision 00 35

    Acid cleaning

    HCL 4-6 % conc.

    Ammonia Bifluoride 1%

    Rodine 213 special 0.1 % inhibitor.

    Lime

    Nitrogen Gas capping arrangement.

    Removal of Drum internals

    Down comer fitted with orifice. Sup heater steamopening at drum to be plugged by rubber stamp.

    S/H to be kept pressurised at 5 Kg/Cm2 withhydrazine.

  • 7/31/2019 Boiler Commissioning Presentation

    36/80

    24 May 2012 PMI Revision 00 36

    Acid cleaning procedure

    Fill boiler with water and a circulation flow of 400t/Hr is maintained.

    Heat water to 65 deg cen. With steam.

    Inhibitor charged and half quantity of ammonia

    bifluoride. When the above mixture get dissolved, start acid

    dosing.

    Concentration should not exceed 6 %.

    Temp. is maintained below 70 Deg.

    HCL and Iron Conc. Intially goes high then comesdown and became steady.

    Constant value of HCL and iron conc. Denotecompletion of acid washing.

    Cleaning soln. drained through neutralising pit.

  • 7/31/2019 Boiler Commissioning Presentation

    37/80

    24 May 2012 PMI Revision 00 37

    Rinsing with water.

    System filled with water

    Temp. raised to 65 Deg.

    Water circulation continue.

    Water is dump under nitrogen capping.

  • 7/31/2019 Boiler Commissioning Presentation

    38/80

    24 May 2012 PMI Revision 00 38

    Citric acid rinsing.

    System filled with water

    Temp. raised to 65 Deg.

    Citric acid 0.2 % by weight.

    Water is recirculated

    When inlet outlet sample matches then

    declare overWater is dump under nitrogen capping.

  • 7/31/2019 Boiler Commissioning Presentation

    39/80

    24 May 2012 PMI Revision 00 39

    Neutralisation.

    System filled with water

    Temp. raised to 80 Deg.

    Sodium Carbonate 1 %..

    Water is recirculated

    When inlet outlet sample matches then

    declare overWater is dump under nitrogen capping.

  • 7/31/2019 Boiler Commissioning Presentation

    40/80

    24 May 2012 PMI Revision 00 40

    Passivation 1st stage.

    Purpose building uniform layer of Magnetite onbare surface obtained after acid cleaning.

    System filled with water

    Temp. raised to 85 Deg.

    300 ppm Hydrazine (9.6 pH)

    Water is recirculated

    Maintain hydrazine concentration to 150 ppm.

    When inlet outlet sample matches then declareover

    Water is dump under atmospheric capping.

  • 7/31/2019 Boiler Commissioning Presentation

    41/80

    24 May 2012 PMI Revision 00 41

    Passivation 2nd stage.

    Purpose building uniform layer of Magnetite onbare surface obtained after acid cleaning.

    System filled with water

    Temp. raised to 85 Deg.

    300 ppm Hydrazine (9.6 pH)

    Boiler lighted up. 40 Kg pr. Raised. Maintain for 20

    Hrs. Maintain hydrazine concentration to 150 ppm.

    Hot drain at 90 deg.

    Water is dump under atmospheric capping.

  • 7/31/2019 Boiler Commissioning Presentation

    42/80

    24 May 2012 PMI Revision 00 42

    STEAM BLOWING

    OF

    BOILER AND

    ASSOCIATED STEAM LINE

    INCLUDING

    AUXILIARY STEAM LINES

  • 7/31/2019 Boiler Commissioning Presentation

    43/80

    24 May 2012 PMI Revision 00 43

    CLICK ON THE STAGE TO SEE THE ANIMATION

    THEORY OF STEAM BLOWING

    SCHEME OF STEAM BLOWING

    STAGE-1 STEAM BLOWING (SH,M.S LINE UP TO ESV)

    STAGE-2A STEAM BLOWING (SH,M.S, CRH LINE)

    STAGE-2B STEAN BLOWING (SH,MS,HRH&CRH UP TO DESH)

    STAGE-3A STEAM BLOWING (SH, MS, CRH, RH, HRH, UP TO IV)

    STAGE-3B STEAM BLOWING (SH, MS, CRH, RH, HRH & LPBP )

    STAGE-4A STEAM BLOWING (EXTRN TO BFPDT-A, FROM CRH)

    STAGE-4B STEAM BLOWING (EXTRN TO BFPDT-B, FROM CRH)

    CLICK / ENTER, AFTER EVERY EVENT IN THE SCHEME TO SEE THESEQUENCE OF EVENTS

    STEAM BLOWINGBACK TO

    INDEX

  • 7/31/2019 Boiler Commissioning Presentation

    44/80

    24 May 2012 PMI Revision 00 44

    STEAM BLOWING

    OBJECTIVE: PURPOSE OF STEAM BLOWING IS TO REMOVESCALES, LOOSE MATERIAL, IRON CUTTINGS etc. THAT MIGHT HAVEBEEN ENTRAPPED IN S.H, STEAM PIPING, REHEATERS DURINGMANUFACTURE.

    TECHNIQUE: STEAM BLOWING IS CARRIED OUT BY PUFFINGMETHOD.THIS TECHNIQUE WILL GIVE A THERMAL SHOCK TO THECONTOUR BEING PURGED TO DISLODGE THE SCALES etc. WHICH WILLSUBSEQUENTLY BE REMOVED BY EXPANDING STEAM.

    PROCEDURE: FOR BLOWING THE STEAM, RAISE THE BOILER DRUMPRESSURE UPTO 40 TO 50 Ksc; SHUT OFF BOILER FIRING AND OPENTHE ELECTRICALLY OPERATED TEMPORARY VALVES (EOTVs) / BOILERM.S. STOP VALVES AS SHOWN IN THE FOLLOWING SCHEMES.

    DRUM LEVEL SHOULD BE MAINTAINED AT LOWEST PORT (VISIBLE

    LIMIT) BEFORE THE START OF EACH BLOW TO AVOID WATERDROPLETS CARRYOVER TO THE SATURATED STEAM PIPING.

    NUMBER OF BLOWS PER DAY ARE LIMITED TO 8 WITH AN INTERVALOF 1 Hrs.FOR COOLING IN ADDITION TO OVER NIGHT COOLING

    SCHEME: STEAM BLOWING IS DONE IN SEVEN STAGES AS

    DESCRIBED IN THE FOLLOWING SLIDES.

    INDEX

    EOTV ASTEAM BLOWING SCHEME BACK TOINDEX

  • 7/31/2019 Boiler Commissioning Presentation

    45/80

    24 May 2012 45

    LPBP V/V

    LPBP V/V

    TO CONDENSER

    HRH LINE

    RHI

    HDR

    RHOHDR

    SH

    IH

    SH

    OH

    MS STOP V/V

    M

    SL

    ESV

    ESVCR

    H

    NR

    V

    CRH LINE

    HPBP SPOOLPIECE 450

    THRO / BLANKFLANGE

    DE

    SH

    EOTV

    AB B

    C

    C

    D

    D

    E

    E

    --THRO / BLANK FLANGE

    --TARGET PLATE-- OPEN INDICATION

    -- CLOSE INDICATION

    -- R.H & HRH LINE

    -- LPBP LINE

    -- S.H & MS LINE

    -- CRH & HPBP

    -- TEMPORARY PIPING

    -- PERMANENT PIPING

    --UN TREATED PIPE

    HPBP LINE

    EOTV

    ELECTRICALLY OPERATEDTEMPORARY VALVE

    HOTVs

    HOTV-HAND OPERATEDTEMPORARY VALVE

    INDEX

    ASTAGE-I EOTVBACK TO

    INDEX

  • 7/31/2019 Boiler Commissioning Presentation

    46/80

    24 May 2012 PMI Revision 00 46

    LPBP V/V

    LPBP V/V

    TO CONDENSE

    HRH LINE

    RH

    IHDR

    RHOHDR

    S

    HIH

    S

    HOH

    MS STOP V/V

    MSL

    ESV

    ESV

    C

    RH

    N

    RV

    CRH LINE

    HPBP SPOOLPIECE 450

    THRO / BLANKFLANGE

    D

    ESH

    EOTV

    --THRO / BLANK FLANGE

    A

    C

    BB

    D

    D

    E

    E

    --TARGET PLATE

    STAGE I

    -- OPEN

    -- CLOSE

    -- R.H & HRH

    -- LPBP

    -- S.H & MS LINE

    -- CRH & HPBP

    -- TEMPORARY PIPING

    -- PERMANENT PIPING

    --UN TREATED PIPE

    MS STOP VALVES IN

    OPEN CONDITION

    FLANGES "B,"C,"D&"E

    ARE BLANKED, "A ISOPENED

    STEAM BLOWING IS TO BE

    CARRIED OUT USING EOTVS

    C

    BLOW OFF V/V OPENED AT 50

    Ksc & CLOSED AT 25 KscDRUM PRESSURE

    STAGE-1 COVERS SUPER

    HEATERS & MS LINE UP TOESV

    HPBP LINE

    HOTVs

    INDEX

    STAGE-IIA EOTVBACK TO

    INDEX

  • 7/31/2019 Boiler Commissioning Presentation

    47/80

    24 May 2012 PMI Revision 00 47

    LPBP V/V

    LPBP V/V

    TO CONDENSER

    HRH LINE

    R

    HIHDR

    RHOHDR

    SHIH

    SHOH

    MS STOP V/V

    MSL

    ESV

    ESVCRH

    NRV

    CRH LINE

    HPBP SPOOLPIECE 450

    THRO / BLANKFLANGE

    DESH

    EOTV

    A

    A

    C

    C

    BB

    D

    D

    E

    E

    STAGE IIA

    --THRO / BLANK FLANGE

    --TARGET PLATE

    -- OPEN

    -- CLOSE

    -- R.H & HRH

    -- LPBP

    -- S.H & MS LINE

    -- CRH & HPBP

    -- TEMPORARY PIPING

    -- PERMANENT PIPING

    --UN TREATED PIPE

    MS STOP VALVES IN

    OPEN CONDITION

    FLANGES A,B,"D&"E

    ARE BLANKED, C ISOPENED

    STEAM BLOWING IS TO BE

    CARRIED OUT USING EOTVS

    SUGGESTED BLOWING

    PRESSURE IS FROM 50KscTO25 Ksc

    STAGE-2 COVERS S.H, MS

    LINE,JUMPER CONNECTINGESV & CRH LINE

    DESH IN CRH LINE IS NOT TO

    BE ERECTED

    JUMPER LINE CONN. TO CRH IS

    TO BE TAKEN AFTER EOTVsINSTALLED FOR STAGE-1

    EOTV

    HPBP LINE

    HOTVs

    INDEX

    STAGE-IIB EOTVBACK TO

    INDEX

  • 7/31/2019 Boiler Commissioning Presentation

    48/80

    24 May 2012 PMI Revision 00 48

    LPBP V/V

    LPBP V/V

    TO CONDENSER

    HRH LINE

    R

    HIHDR

    RHOHDR

    SHIH

    SHOH

    MS STOP V/V

    MSL

    ESV

    ESVCRH

    NRV

    CRH LINE

    HPBP SPOOLPIECE 450

    THRO / BLANKFLANGE

    DESH

    EOTV

    A

    A

    C

    C

    BB

    D

    D

    E

    E

    STAGE IIB

    --THRO / BLANK FLANGE

    --TARGET PLATE

    -- OPEN

    -- CLOSE

    -- R.H & HRH

    -- LPBP

    -- S.H & MS LINE

    -- CRH & HPBP

    -- TEMPORARY PIPING

    -- PERMANENT PIPING

    --UN TREATED PIPE

    EOTVs ARE IN CLOSED

    CONDITION

    FLANGES A,"D&"E ARE

    BLANKED, B&C AREOPENED

    STEAM BLOWING IS TO BE

    CARRIED OUT USING MSSTOP VALVES

    STAGE-2B COVERS S.H, MS

    LINE,H.P BYPASS LINE& CRHLINE

    DESH IN CRH LINE IS NOT TO

    BE ERECTED

    EOTV

    HPBP LINE

    HOTVs

    INDEX

    ASTAGE-IIIA EOTV

    BACK TOINDEX

  • 7/31/2019 Boiler Commissioning Presentation

    49/80

    24 May 2012 PMI Revision 00 49

    LPBP V/V

    LPBP V/V

    TO CONDENSER

    HRH LINE

    R

    HIHDR

    RHOHDR

    SHIH

    SHOH

    MS STOP V/V

    MSL

    ESV

    ESVCRH

    NRV

    CRH LINE

    HPBP SPOOLPIECE 450

    THRO / BLANKFLANGE

    DESH

    EOTV

    A

    A

    C

    C

    BB

    D

    D

    E

    E

    STAGE IIIA

    --THRO / BLANK FLANGE

    --TARGET PLATE

    -- OPEN

    -- CLOSE

    -- R.H & HRH

    -- LPBP

    -- S.H & MS LINE

    -- CRH & HPBP

    -- TEMPORARY PIPING

    -- PERMANENT PIPING

    --UN TREATED PIPE

    MS STOP VALVES ARE

    IN OPEN CONDITION

    FLANGES A,B&"E ARE

    BLANKED, C&D AREOPENED

    STEAM BLOWING IS TO BE

    CARRIED OUT USING EOTVs

    STAGE-3A COVERS S.H, MS

    LINE,JUMPER CONNG. ESV&CRH LINE CRHLINE R.H HRH

    DESH IN CRH LINE CAN BE

    ERECTED

    SUGGESTED BLOWING

    PRESSURE IS 50 KscTO 25Ksc

    EOTV

    HPBP LINE

    HOTVs

    INDEX

    ASTAGE-IIIB EOTVBACK TO

    INDEX

  • 7/31/2019 Boiler Commissioning Presentation

    50/80

    24 May 2012 PMI Revision 00 50

    LPBP V/V

    LPBP V/V

    TO CONDENSER

    HRH LINE

    RH

    IHDR

    RH

    OHDR

    S

    HIH

    S

    HOH

    MS STOP V/V

    MSL

    ESV

    ESVCRH

    NRV

    CRH LINE

    HPBP SPOOLPIECE 450

    THRO / BLANKFLANGE

    DESH

    EOTV

    A

    A

    C

    C

    BB

    D

    D

    E

    E

    STAGE IIIB

    --THRO / BLANK FLANGE

    --TARGET PLATE

    -- OPEN

    -- CLOSE

    -- R.H & HRH

    -- LPBP

    -- S.H & MS LINE

    -- CRH & HPBP

    -- TEMPORARY PIPING

    -- PERMANENT PIPING

    --UN TREATED PIPE

    MS STOP VALVES IN

    OPEN CONDITION

    FLANGES A,B&"D ARE

    BLANKED, C,"E AREOPENED

    STEAM BLOWING IS TO BE

    CARRIED OUT USING EOTVS

    STAGE-3B COVERS S.H, MS

    LINE,JUMPER CONNG.ESV &CRH CRH LINE R.H HRH LPBP

    DESH IN CRH LINE CAN BE

    ERECTED

    HPBP LINE

    HOTVs

    INDEX

    STAGE-IV A BACK TOINDEX

  • 7/31/2019 Boiler Commissioning Presentation

    51/80

    24 May 2012 PMI Revision 00 51

    FROM CRH

    NEAR DEAERATORFROM IP / LP CROSSAROUND TO DEAERATORFROM CROSS

    AROUND PIPES

    FROM IP / LP CROSSAROUND PIPE

    FROM APRDSHEADER TDBFP-A TDBFP-B

    CRH-1 CRH-3

    CRH-2 CRH-4

    INDEX

    STAGE-IV B BACK TOINDEX

  • 7/31/2019 Boiler Commissioning Presentation

    52/80

    24 May 2012 PMI Revision 00 52

    NEAR DEAERATOR

    FROM CRHFROM IP / LP CROSSAROUND TO DEAERATORFROM CROSS

    AROUND PIPES

    FROM IP / LP CROSSAROUND PIPE

    FROM APRDSHEADER TDBFP-A TDBFP-B

    CRH-1CRH-3

    CRH-2CRH-4

    INDEX

  • 7/31/2019 Boiler Commissioning Presentation

    53/80

    24 May 2012 53

  • 7/31/2019 Boiler Commissioning Presentation

    54/80

    24 May 2012 PMI Revision 00 54

    HYDROTEST OF LUB OIL LINES.

    HYDROTEST OF COOLERS.

    ACID CLEANING OF LUB OIL LINES.

    TRIAL RUN LUB OIL MOTORS.

    OIL FILLING

    LUB OIL FLUSHING.

    CONNECTION OF LUB OIL LINES.

  • 7/31/2019 Boiler Commissioning Presentation

    55/80

    24 May 2012 PMI Revision 00 55

    1.DM WATER FLUSHING FOR 10min.

    2.SOAKING WITH 5%HCL SOLUTION AND INHIBITOR0.2% RHODINE 213 SPL.SOAKING TIME-4 HRS.

    3.DRAINIG OF ACID SOLUTION AND FLUSHING WITHDM WATER FOR 10MIN.

    4.SOAKING WITH SODIUM NITITRITE(2%) AND LIQUORAMMONIA 5% FOR 30MIN.

    5. FLUSHING WITH DM WATER FOR 10MIN.

    6.CLEANING OF ALL PIPES BY BLOWING WITHCOMPRESSED AIR FOR DRYING PURPOSE.

    7. FILLING OF OIL PIPELINE AND ENSURING UNIFORMCOATING OF OIL FILM OVER ENTIRE INNERPERIPHERY.

  • 7/31/2019 Boiler Commissioning Presentation

    56/80

    24 May 2012 PMI Revision 00 56

    LUB OIL FLUSHING WITH BYPASSING BRGSAND SERVOMOTOR.

    LUB OIL FLUSHING WITH BRGS. AND

    SERVOMOTOR IN CIRCUIT. COOLING WATER GOING TO LUB OIL

    COOLERS FLUSHING.

    RELIEF VALVE PRESSURE ADJUSTMENT.

  • 7/31/2019 Boiler Commissioning Presentation

    57/80

  • 7/31/2019 Boiler Commissioning Presentation

    58/80

    24 May 2012 PMI Revision 00 58

    CHECK FOR THE FREENESS OF FAN ROTOR.

    CHECK FOR THE INDICATION OF RTD ANDVIBRATION PICKUPS.

    CHECK THE OPERATION BLADE PITCH INCONTROL ROOM AS WELL AS IN LOCAL.

    CHECK FOR THE OPERATION OF DISCHARGE

    DAMPER/GATE.

  • 7/31/2019 Boiler Commissioning Presentation

    59/80

    24 May 2012 PMI Revision 00 59

    CHECK WHETHER ALL PROTECTIONS ANDPERMISSIVES ARE IN SERVICE.

    CHECK FOR THE CLEANLINESS OF

    DISCHARGE DUCT AND ALL OTHERINTERCONNECTION OF DUCTS.

    CHECK FOR THE CLEANLINESS OF SUCTIONCHAMBER.

    CHECK FOR BLADE CLEARANCES FROM THEFAN CASING.

  • 7/31/2019 Boiler Commissioning Presentation

    60/80

    24 May 2012 PMI Revision 00 60

    CHECK FOR THE AVAILABLITY OF COOLINGWATER.

    CHECK WHETHER LUB OIL COOLERS ARE

    CHARGED FROM WATER SIDE. TAKE THE TRIAL RUN OF FAN AFTER GETTING

    CLEARANCES FROM VERIOUR CONCERNEDDEPARTMENTS.

    BRG TEMP,VIBRATION READINGS TO BERECORDED ON HOURLY BASIS.

  • 7/31/2019 Boiler Commissioning Presentation

    61/80

    24 May 2012 PMI Revision 00 61

    CHECK FOR THE CABLING OF MOTOR.

    CHECK FOR PROPER EARTHING OF MOTOR.

    CHECK FOR ROTOR FREENESS.

    CHECK FOR CONTROL ROOM INDICATIONS OFBRG TEMP AND VIBRATIONS.

    CHECK FOR THE LOCATION OF EPB.

  • 7/31/2019 Boiler Commissioning Presentation

    62/80

    24 May 2012 PMI Revision 00 62

    CHECK FOR THE AVAILABILITY OF MOTORCOOLING WATER.

    CHECK FOR OIL LEVEL IN BRGS.

    CHECK FOR THE HEALTYNESS OF COOLINGWATER FLOW SWITCH.

    ENSURE THE FLUSHING COOLING WATER

    LINES TO MOTOR.

  • 7/31/2019 Boiler Commissioning Presentation

    63/80

    24 May 2012 PMI Revision 00 63

    CHECK FOR THE FREENESS OF FAN ROTOR.

    CHECK FOR THE INDICATION OF RTD ANDVIBRATION PICKUPS.

    CHECK THE OPERATION OF IGV IN CONTROLROOM AS WELL AS IN LOCAL.

    CHECK FOR THE OPERATION OF DISCHARGE

    GATE/INLET AND OUTLET GATES.

  • 7/31/2019 Boiler Commissioning Presentation

    64/80

    24 May 2012 PMI Revision 00 64

    CHECK WHETHER ALL PROTECTIONS ANDPERMISSIVES ARE IN SERVICE.

    CHECK FOR THE CLEANLINESS OF

    DISCHARGE DUCT AND ALL OTHERINTERCONNECTION OF DUCTS.

    CHECK FOR THE CLEANLINESS OF SUCTIONCHAMBER.

    CHECK FOR BLADE CLEARANCES FROM THEFAN CASING.

  • 7/31/2019 Boiler Commissioning Presentation

    65/80

    24 May 2012 PMI Revision 00 65

    ENSURE THE FLUSHING OF JACKET COOLINGWATER DONE BEFORE.

    ENSURE LUB OIL LINE VALVES GOING TO

    INDIVIDUAL BRGS ARE IN OPEN CONDITION. FAN TO BE STARTED AND TRIAL RUN TO BE

    TAKEN FOR 8HRS.

  • 7/31/2019 Boiler Commissioning Presentation

    66/80

    24 May 2012 PMI Revision 00 66

    CHECK FOR RADIAL CLEARANCE OF RADIALSEALS AS PER DESIGN.

    CHECK FOR AXIAL CLEARANCE OF AXIAL

    SEALS AS PER DESIGN. CHECK FOR PROPER CLEARANCE OF

    CIRCUMFERENTIAL SEALS.

    CHEACK FOR THE CLEANLINESS OF AIRPREHEATER BASKETS.

  • 7/31/2019 Boiler Commissioning Presentation

    67/80

    24 May 2012 PMI Revision 00 67

    ENSURE THE CLEANING OF PROTECTIVECOATING OF AIRPREHEATER.

    CHECK FOR TRAVEL PATH OF AIRPREHEATER

    SOOTBLOWING.

    ENSURE THAT NO LOOSE PARTS ARE HANGING.

    BEFORE STARTING AIRPREHEATER ALL MANUAL

    DOORS ARE PROPERLY TIGHTENED.

  • 7/31/2019 Boiler Commissioning Presentation

    68/80

    24 May 2012 PMI Revision 00 68

    ENSURE THE COMPLETION OF MOTOR NOLOAD TRIAL RUN FOR 8HRS.

    ENSURE THE COMPLETION OF LUB OIL

    FLUSHING OF SUPPORT/GUIDE BRGS. FLUSH THE COOLING WATER LINES.

    CHECK FOR THE CLEANLINESS OF AIR

    RECEIVER TANK. FLUSH THE SERVICE AIR LINES GOING TO AIR

    RECEIVER TANK.

  • 7/31/2019 Boiler Commissioning Presentation

    69/80

    24 May 2012 PMI Revision 00 69

    FLUSH THE OIL CARRYOVER PROBE COOLINGLINES.

    FLUSH AIRPREHEATER WATER WASH LINES.

    ENSURE THE CLEANLINESS OF WATER WASHLINE NOZZLES.

    ENSURE THAT FIRE FIGHTING LINES ARE

    CONNECTED AS PER DRAWING.

  • 7/31/2019 Boiler Commissioning Presentation

    70/80

    24 May 2012 PMI Revision 00 70

    ENSURE FLUSHING OF FIRE WATER LINES.

    ENSURE THE CLEANLINESS OF FIRE FIGHTINGNOZZLES.

    CHECK FOR THE PROPER PLACING FIRESENSING PROBES.

    FLUSH AIR LINE COMING FROM AIR RECEIVER

    TANK.

  • 7/31/2019 Boiler Commissioning Presentation

    71/80

    24 May 2012 PMI Revision 00 71

    CHECK FOR HEALTHINESS OF SUPPORTBRG/GUIDE BRG RTDS.

    ROTATE FREELY WITH HAND AND OBSERVE

    ANY ABNORMAL SOUND. START AIR PREHEATER WITH AIRMOTOR AND

    ROTATE IT FOR SOMETIME.

    START MAIN DRIVE OF AIRPREHEATER.

  • 7/31/2019 Boiler Commissioning Presentation

    72/80

    24 May 2012 PMI Revision 00 72

    CHECK THE AIRPREHEATER MAIN DRIVE TOAIRMOTOR CHANGEOVER INTERLOCKHEALTINESS.

    CHECK FOR VIBRATIONS OF MAIN DRIVE. CHECK FOR THE HEALTHYNESS OF

    AIRMOTOR PRESSURE SWITCHES.

    READINESS FOR FIRST BOILER LIGHT UP

  • 7/31/2019 Boiler Commissioning Presentation

    73/80

    24 May 2012 PMI Revision 00 73

  • 7/31/2019 Boiler Commissioning Presentation

    74/80

    24 May 2012 PMI Revision 00 74

  • 7/31/2019 Boiler Commissioning Presentation

    75/80

    24 May 2012 PMI Revision 00 75

  • 7/31/2019 Boiler Commissioning Presentation

    76/80

    24 May 2012 PMI Revision 00 76

  • 7/31/2019 Boiler Commissioning Presentation

    77/80

    24 May 2012 PMI Revision 00 77

  • 7/31/2019 Boiler Commissioning Presentation

    78/80

    SAFETY VALVE FLOATING OF MAIN BOILER

  • 7/31/2019 Boiler Commissioning Presentation

    79/80

    24 May 2012 PMI Revision 00 79

    Test all the safety valves one by one by actually raising the pressure of

    the boiler to set values of the valves and also to set the blowdown of

    the valve within 3% - 5% of the set value.

    Safety valve with higher set pressure will be floated first followed by

    other valves in descending order of set valves. If set pressures are samefor few valves, then any valve can be taken for floating.

    When the pressure reaches around 180-190 KSC, the safety

    valves is warmed up by manual popping and for this, the popping

    arrangement provided is made use off through rope. Once or

    twice the manual popping done to clear the safety valves path and

    also to warm up the valve.

  • 7/31/2019 Boiler Commissioning Presentation

    80/80