    12B30 / 12C30 / CET - B04 Slide # 1

    CONSIDERATIONS

    1. The crater must be long enough to tie intoother obstacles.

    2. Must be covered by fire to be effective.

    3. Employ where the terrain will assist.

    4. Crater will be more effective if angledacross the road.

    5. Integrate or supplement craters with:a. Minesb. Wirec. Water

  • 7/27/2019 BO4-DEMO

    2/30

    12B30 / 12C30 / CET - B04 Slide # 2

    IDEAL LOCATIONS

    1. Dense woods

    2. Swamps

    3. Cuts and fills

    4. Side hill cuts

    5. Hill crest

    6. Built up areas

  • 7/27/2019 BO4-DEMO

    3/30

    12B30 / 12C30 / CET - B04 Slide # 3

    IDEAL LOCATIONS (cont.)

    7. Inside tunnels

    8. Airstrips, runways, helipads

    9. Bridges & approaches

    10. Fords and ferry landings

    11. Causeways12. Sharp curves

  • 7/27/2019 BO4-DEMO

    4/30

    12B30 / 12C30 / CET - B04 Slide # 4

    METHODS FOR BOREHOLES

    MANUAL

    MECHANICAL

    EXPLOSIVES

  • 7/27/2019 BO4-DEMO

    5/30

    12B30 / 12C30 / CET - B04 Slide # 5

    15LBS

    40LBS

  • 7/27/2019 BO4-DEMO

    6/30

    12B30 / 12C30 / CET - B04 Slide # 6

    Shaped Demolition Charges

    Charge

    Demolition

    Shaped

    40 pounds

    M3A1

    ChargeDemolition

    Shaped

    M2A4

    M2A4, 15 pound shaped demolition charge0.11-LB booster, composition A3

    11.5-LB main charge, composition B

    7

    14 15/16

    M3A1, 40 pound shaped demolition charge

    0.11-LB booster, composition A3

    29.5 LB main charge, composition B

    9

    15 standoff

    15 1/2

    6 standoff

  • 7/27/2019 BO4-DEMO

    7/30

    12B30 / 12C30 / CET - B04 Slide # 7

    Characteristics of shaped demolition charges

    Type Explosive Weight Size(in.) Packing &total weight

    Charge, Demolition:Shaped 15-lb M2A3

    Charge, Demolition:Shaped 15-lb M2A4

    Charge, Demolition:Shaped 40-lb M2A4

    Charge, Demolition:Shaped 40-lb M3A1

    Pentolite or composi-tion B, with 50/50pentolite booster

    Composition B, with50/50 pentolite booster

    Composition B, withcomposition B booster

    15lb

    15lb

    40lb

    40lb

    14 15/16 x 7" w/

    fiberboard standoff

    14 15/16 x 7" w/

    fiberboard standoff

    151/2

    x 9" lessstandoff

    15 1/2 x 9" less

    standoff

    1.2per woodenbox.wt. 58lbs

    2.

    3per woodenbox.wt. 65lbs

    3per woodenbox.wt. 65lbs

    1per wooden

    box.wt. 65lbs

    1per woodenbox.wt. 65lbs

    Composition B w/comp. B3 booster

  • 7/27/2019 BO4-DEMO

    8/30

    12B30 / 12C30 / CET - B04 Slide # 8

    Characteristics of boreholes made by shaped charges

    Material Specifications M2A4 M3A1

    Shaped Charge Shaped Charge

    (15-pound) (40-pound)

    Armor plate Penetration 12.00 in At least 20.00 in

    Average hole diameter 1.50 in 2.50 in

    Reinforced Maximum wall thickness 36.00 in 60.00 in

    concrete Penetration depth in thick walls 30.00 in 60.00 in

    Average hole diameter 2.75 in 3.50 inConcrete pavement Optimum standoff 42.00 in 60.00 in

    (10-in with 21-in Minimum penetration depth 44.00 in 71.00 in

    rock base course) Maximum penetration depth 91.00 in 109.00 in

    Minimum hole diameter 1.75 in 6.75 in

    Concrete pavement Optimum standoff 42.00 in -

    (10-in with 21-in Minimum penetration depth 38.00 in -

    rock base course) Maximum penetration depth 90.00 in -

    Minimum hole diameter 3.75 in -

    Ice Hole depth (42-inch standoff) 7.00 ft 12.00 ft

    Hole diameter (42-inch standoff) 3.50 in 6.00 in

    Soil Hole depth (30-inch standoff) 7.00 ft -

    Hole depth (48-inch standoff) - 7.00 ft

    Hole diameter (30-inch standoff) 7.00 in -

    Hole diameter (48-inch standoff) - 14.50 in

    Gravel roads Hole depth (30-inch standoff) 7.00 ft -

    Hole depth (48-inch standoff) - 9.00 ft

    Hole diameter (30-inch standoff) 7.00 in -

    Hole diameter (48-inch standoff) - 7.00 in

    * A dash in the M2A4 Shaped Charge column indicates that a M3A1 shaped charge is required.

    ** A dash in the M3A1 Shaped Charge column indicates that a M2A4 shaped charge is sufficient.

  • 7/27/2019 BO4-DEMO

    9/30

    12B30 / 12C30 / CET - B04 Slide # 9

    CRATERING CHARGES

    CLEAT

    DETONATING

    CORD TUNNEL

    LOWERING RING

    CHARGECRATERIN

    G

    40

    LBS

    NSN

    EXPLOSIVES

    00

    -000

    -0000

    -0000

    CAP WELL

  • 7/27/2019 BO4-DEMO

    10/30

    12B30 / 12C30 / CET - B04 Slide # 10

    BREACHING

    HARD-SURFACEPAVEMENT

    Pavement6" Thick

    A. One pound of explosive for each 2" of pavement thickness

    B. Tamping is twice as thick as pavement

    EXAMPLE

    1. 6" - 2" = 3 x 1lb = 3 lbs explosive per charge..

    2. 6" x 2 = 12" tamping per charge

    Tamping

  • 7/27/2019 BO4-DEMO

    11/30

    12B30 / 12C30 / CET - B04 Slide # 11

    TYPES OF ROAD CRATERS

    HASTY

    DELIBERATE

    RELIEVED FACE

  • 7/27/2019 BO4-DEMO

    12/30

    12B30 / 12C30 / CET - B04 Slide # 12

  • 7/27/2019 BO4-DEMO

    13/30

    12B30 / 12C30 / CET - B04 Slide # 13

    RULES: ("Rule of Thumb")

    1. Holes spaced 5 feet apart.

    2. Depth: Minimum 5 feet (all same depth).

    3. Use 10 lbs explosive per foot of hole(Minimum of 3 holes).

    4. Number of holes = N = L - 165

    +1

  • 7/27/2019 BO4-DEMO

    14/30

    12B30 / 12C30 / CET - B04 Slide # 1450-lb charges

    20

    8appro

    x

    8approx

    5

    5

    5

    5

    5 (min)

    PLACEMENT FOR HASTY ROAD CRATER

  • 7/27/2019 BO4-DEMO

    15/30

    12B30 / 12C30 / CET - B04 Slide # 15

    PROBLEM

    Calculate the amount of TNT for a hasty

    road crater 100 feet long. The holesare to be 6 feet deep. Show all workin the six step problem solving format.

  • 7/27/2019 BO4-DEMO

    16/30

    12B30 / 12C30 / CET - B04 Slide # 16

    SOLUTION

    Step 1. Holes..6' deep, Crater..100',use TNT, Hasty crater

    Step 2. 6 feet deep holes at 10 lbsper foot = 60 lbs per hole

    Step 3. N/A

    Step 4. Round up to whole poundsize = 60 1lb blocks of TNT

    (Already in whole packages however, if acombination of cratering charges and TNT....20 lbsTNT and ONE 40 lb cratering charge per hole)

  • 7/27/2019 BO4-DEMO

    17/30

    12B30 / 12C30 / CET - B04 Slide # 17

    SOLUTION

    Step 5. Determine number of holes

    Step 6. 18 holes= 12 x 60 lbs per hole =1080 1lb blocks of TNT

    N = L - 16 100 - 16

    5 5

    17.8 Holes 18 Holes

    +1 = 17.8 Holes+1 =

    18 Holes = 18 Charges

  • 7/27/2019 BO4-DEMO

    18/30

    12B30 / 12C30 / CET - B04 Slide # 18

  • 7/27/2019 BO4-DEMO

    19/30

    12B30 / 12C30 / CET - B04 Slide # 19

    DELIBERATE ROAD CRATER

    RULES:

    1. Holes spaced 5 feet apart.

    2. Must be a 7 foot hole on each end.

    3. Alternate 5 and 7 foot holes.

    4. There can't be two 5 foot holes adjacent to eachother.

    5. Explosives per hole: 5' hole = 40 lbs per hole7' hole = 80 lbs per hole

    6. Number of holes: N = L -16

    5+1

  • 7/27/2019 BO4-DEMO

    20/30

    12B30 / 12C30 / CET - B04 Slide # 20

    PLACEMENT for DELIBERATE ROADCRATER

    5'5'

    5'5'

    8'approx.

    8'approx.

    7'7'

    5'

    7'

    25'

    80 lb

    80 lb80 lb

    80 lb

    5'

    7' 5'

    40 lb

    40 lb

    Crater is approximately 8' deep.

  • 7/27/2019 BO4-DEMO

    21/30

    12B30 / 12C30 / CET - B04 Slide # 21

    PROBLEM

    Calculate the amount of explosives requiredto construct a deliberate crater 76 feetlong.

    Use: Cratering charges and TNT

    Show all work to include sketch ofplacement

  • 7/27/2019 BO4-DEMO

    22/30

    12B30 / 12C30 / CET - B04 Slide # 22

    SOLUTION

    Step 1. Crater..76', use crateringcharges & TNT, Deliberate

    Step 2. 7 foot holes at 80 lbs5 foot holes at 40 lbs

    Step 3. N/A

    Step 4. Round up to whole pound size:80 lb = 2 cratering charges40 lb = 1 cratering charge and 1 1lb block of TNT

  • 7/27/2019 BO4-DEMO

    23/30

    12B30 / 12C30 / CET - B04 Slide # 23

    SOLUTION

    6 holes x 1 1lb block TNT =

    6 1lb block TNT

    Step 5. Determine number of holesN = L - 16 76 - 16

    5 5

    Step 6. 13 Holes = 7 at 7 foot6 at 5 foot

    Therefore: 7 holes x 2 cratering charges = 14 cc

    6 holes x 1 cratering charge = 6 cc

    Total: 20 cratering charges6, 1lb block of TNT

    Holes

    7 5 7 5 7 5 7 5 7 5 7 75

    + 1= + 1 =13 holes

  • 7/27/2019 BO4-DEMO

    24/30

    12B30 / 12C30 / CET - B04 Slide # 24

    76'

    80 lbs 40 lbs

    NOTES: 1. 5' spacing2. Alternate 5' and 7' holes3. Dual priming - 40 lb cratering charge

    PLACEMENT SOLUTION

  • 7/27/2019 BO4-DEMO

    25/30

    12B30 / 12C30 / CET - B04 Slide # 25

    Enemy side Friendly side

    25 minimumslope

    40 maximumslope

    o o

    RELIEVED FACE ROADCRATER

  • 7/27/2019 BO4-DEMO

    26/30

    12B30 / 12C30 / CET - B04 Slide # 26

    RELIEVED FACE CRATER

    Rules1. Enemy row = 4' deep and 30 lbs explosives per hole

    2. Friendly row = 5' deep and 40 lbs explosives per hole

    3. Holes: 7' apart within row

    4. Rows: 8' apart and offset (12' on hard surface)

    5. Initiate enemy row .5 to 1.5 seconds before friendly

    6. Number of holes on friendly row:

    7. Number of holes in enemy row is one less than in thefriendly row

    NF = L - 10

    7

    :

    + 1

  • 7/27/2019 BO4-DEMO

    27/30

    12B30 / 12C30 / CET - B04 Slide # 27

    DUALPRIMING

    Enemy Row

    Friendly Row

    8'

    31/2'

  • 7/27/2019 BO4-DEMO

    28/30

    12B30 / 12C30 / CET - B04 Slide # 28

    RELIEVED FACE

    PLACEMENT

    Enemy side Friendly side

    25 minimumslope

    40 maximumslope

    o o

    8'

    4'5'30 lb

    40 lb

  • 7/27/2019 BO4-DEMO

    29/30

    12B30 / 12C30 / CET - B04 Slide # 29

    PROBLEMRelieved Face

    How many cratering charges and how many1lb blocks of TNT are needed to createa relieved face road crater 110 feet long?

  • 7/27/2019 BO4-DEMO

    30/30

    12B30 / 12C30 / CET - B04 Slide # 30

    SOLUTION

    Step 1. Relieved face, CC and TNT, 110 ft craterStep 2. 4 ft holes at 30 lbs per hole 5 ft holes at40 lbs per hole

    Step 3. N/A

    Step 4. 4 ft holes = 30 1lb blocks of TNT per hole5 ft holes = 1 cc & 1 pkg TNT per hole

    Step 5. NF = L - 10

    7110 - 10

    716

    Friendly side = 16 holes

    Enemy side = 15 holes

    15 x 30 1lb block of TNT = 450 1lb block of TNT

    Step 6. Friendly = 16 x 1cc = 16cc

    16 x 1 1lb block of TNT = 16 1lb blocks of TNT

    TOTAL: 16cc and 466 1lb block of TNT

    Enemy =

    + 1= + 1 = 15.28