BMGN_N470_LO4_2014-15-sem1 - Time - Part 2

download BMGN_N470_LO4_2014-15-sem1 - Time - Part 2

of 19

Transcript of BMGN_N470_LO4_2014-15-sem1 - Time - Part 2

  • 7/26/2019 BMGN_N470_LO4_2014-15-sem1 - Time - Part 2

    1/19

    PowerPoint Presentation by Charlie CookPowerPoint Presentation by Charlie CookCopyrightCopyright 2006 The McGraw-Hill Companies. ll rights reser!e".2006 The McGraw-Hill Companies. ll rights reser!e".

    THE MANAGERIAL PROCESS Clifford F. GrayEric W. Larson

    Third Edition

    Pr ojec tManagementPr ojec tManagement

    BMGNBMGN

    N470N470

    Reducing Project DurationReducing Project Duration

  • 7/26/2019 BMGN_N470_LO4_2014-15-sem1 - Time - Part 2

    2/19

    CopyrightCopyright 2006 The McGraw-Hill Companies. All rights reserved.2006 The McGraw-Hill Companies. All rights reserved. McGraw-Hill!rwin "McGraw-Hill!rwin "##22

    Rationale for Reducing Project DurationRationale for Reducing Project Duration

    Time s !oney" Cost#Time Tradeoffs$Reducing the time of a critical acti%ity usually incurs

    additional direct costs.

    Cost-time solutions focus on reducing (crashing)activities on the critical path to shorten overall durationof the project.

    $Reasons for im&osed &roject duration dates"

    Customer requirements and contract commitments

    Time-to-market pressures

    Incentive contracts (bonuses for earl completion)

    !nforeseen delas

    "verhead costs

    #ressure to move resources to other projects

  • 7/26/2019 BMGN_N470_LO4_2014-15-sem1 - Time - Part 2

    3/19

    CopyrightCopyright 2006 The McGraw-Hill Companies. All rights reserved.2006 The McGraw-Hill Companies. All rights reserved. McGraw-Hill!rwin "McGraw-Hill!rwin "##$$

    '&tions for (ccelerating Project Com&letion'&tions for (ccelerating Project Com&letion

    (dding Resources

    'utsourcing Project Wor)

    *cheduling '%ertime

    Esta+lishing a Core Project Team

    Do t T,ice-Fast and Correctly

    '&tions ,ith unconstrained resources

  • 7/26/2019 BMGN_N470_LO4_2014-15-sem1 - Time - Part 2

    4/19

    CopyrightCopyright 2006 The McGraw-Hill Companies. All rights reserved.2006 The McGraw-Hill Companies. All rights reserved. McGraw-Hill!rwin "McGraw-Hill!rwin "##%%

    '&tions for (ccelerating Project Com&letion'&tions for (ccelerating Project Com&letion

    Fast#Trac)ing

    Reducing Project *co&e

    Com&romise uality

    '&tions ,ith constrained resources

  • 7/26/2019 BMGN_N470_LO4_2014-15-sem1 - Time - Part 2

    5/19

    CopyrightCopyright 2006 The McGraw-Hill Companies. All rights reserved.2006 The McGraw-Hill Companies. All rights reserved. McGraw-Hill!rwin "McGraw-Hill!rwin "##&&

    E/&lanation of Project CostsE/&lanation of Project Costs

    Project ndirect Costs$Costs that cannot +e associated ,ith any &articular

    ,or) &ac)age or &roject acti%ity.

    $upervision% administration% consultants% and interest

    $Costs that %ary 0increase1 ,ith time.&educing project time directl reduces indirect costs.

    Direct Costs

    $2ormal costs that can +e assigned directly to a

    s&ecific ,or) &ac)age or &roject acti%ity.'abor% materials% equipment% and subcontractors

    $Crashing acti%ities increases direct costs.

  • 7/26/2019 BMGN_N470_LO4_2014-15-sem1 - Time - Part 2

    6/19

    CopyrightCopyright 2006 The McGraw-Hill Companies. All rights reserved.2006 The McGraw-Hill Companies. All rights reserved. McGraw-Hill!rwin "McGraw-Hill!rwin "##66

    Reducing Project Duration to ReduceReducing Project Duration to Reduce

    Project CostProject Cost

    Compute total costs for specific durations andCompute total costs for specific durations andcompare to benefits of reducing project time.compare to benefits of reducing project time.

    Search critical activities for lowest direct-costSearch critical activities for lowest direct-costactivities to shorten project duration.activities to shorten project duration.

    Identifying direct costs to reduce project timeIdentifying direct costs to reduce project time

    ather information about direct and indirectather information about direct and indirectcosts of specific project durations.costs of specific project durations.

  • 7/26/2019 BMGN_N470_LO4_2014-15-sem1 - Time - Part 2

    7/19CopyrightCopyright 2006 The McGraw-Hill Companies. All rights reserved.2006 The McGraw-Hill Companies. All rights reserved. McGraw-Hill!rwin "McGraw-Hill!rwin "##''

    Project CostProject Cost-Duration Gra&h-Duration Gra&h

    !I"R# $.%

  • 7/26/2019 BMGN_N470_LO4_2014-15-sem1 - Time - Part 2

    8/19CopyrightCopyright 2006 The McGraw-Hill Companies. All rights reserved.2006 The McGraw-Hill Companies. All rights reserved. McGraw-Hill!rwin "McGraw-Hill!rwin "##((

    Constructing a Project CostConstructing a Project Cost-Duration Gra&h-Duration Gra&h

    Find total direct costs for selected &rojectdurations.

    Find total indirect costs for selected &roject

    durations.

    *um direct and indirect costs for these selected

    &roject durations.

    Com&are additional cost alternati%es for

    +enefits.

  • 7/26/2019 BMGN_N470_LO4_2014-15-sem1 - Time - Part 2

    9/19CopyrightCopyright 2006 The McGraw-Hill Companies. All rights reserved.2006 The McGraw-Hill Companies. All rights reserved. McGraw-Hill!rwin "McGraw-Hill!rwin "##""

    Constructing a Project Cost-Duration Gra&hConstructing a Project Cost-Duration Gra&h

    Determining (cti%ities to *horten$*horten the acti%ities ,ith the smallest increase in cost

    &er unit of time.

    $(ssum&tions"

    The cost relationship is linear.ormal time assumes lo-cost% e*cient methods to

    complete the activit.

    Crash time represents a limit+the greatest timereduction possible under realistic conditions.

    $lope represents a constant costper unit of time.

    ,ll accelerations must occur ithin the normal andcrash times.

  • 7/26/2019 BMGN_N470_LO4_2014-15-sem1 - Time - Part 2

    10/19CopyrightCopyright 2006 The McGraw-Hill Companies. All rights reserved.2006 The McGraw-Hill Companies. All rights reserved. McGraw-Hill!rwin "McGraw-Hill!rwin "##)0)0

    (cti%ity Gra&h(cti%ity Gra&h

    !I"R# $.&

  • 7/26/2019 BMGN_N470_LO4_2014-15-sem1 - Time - Part 2

    11/19CopyrightCopyright 2006 The McGraw-Hill Companies. All rights reserved.2006 The McGraw-Hill Companies. All rights reserved. McGraw-Hill!rwin "McGraw-Hill!rwin "##))))

    CostCost-Duration Trade#off E/am&le-Duration Trade#off E/am&le

    !I"R# $.'

  • 7/26/2019 BMGN_N470_LO4_2014-15-sem1 - Time - Part 2

    12/19

    CopyrightCopyright 2006 The McGraw-Hill Companies. All rights reserved.2006 The McGraw-Hill Companies. All rights reserved. McGraw-Hill!rwin "McGraw-Hill!rwin "##)2)2

    CostCost-Duration Trade#off E/am&le 0cont3d1-Duration Trade#off E/am&le 0cont3d1

    !I"R# $.' (cont)d*

  • 7/26/2019 BMGN_N470_LO4_2014-15-sem1 - Time - Part 2

    13/19

    CopyrightCopyright 2006 The McGraw-Hill Companies. All rights reserved.2006 The McGraw-Hill Companies. All rights reserved. McGraw-Hill!rwin "McGraw-Hill!rwin "##)$)$

    CostCost-Duration Trade#off E/am&le 0cont3d1-Duration Trade#off E/am&le 0cont3d1

    !I"R# $.+ (cont)d*

  • 7/26/2019 BMGN_N470_LO4_2014-15-sem1 - Time - Part 2

    14/19

    CopyrightCopyright 2006 The McGraw-Hill Companies. All rights reserved.2006 The McGraw-Hill Companies. All rights reserved. McGraw-Hill!rwin "McGraw-Hill!rwin "##)%)%

    CostCost-Duration Trade#off E/am&le 0cont3d1-Duration Trade#off E/am&le 0cont3d1

    !I"R# $.+ (cont)d*

  • 7/26/2019 BMGN_N470_LO4_2014-15-sem1 - Time - Part 2

    15/19

    CopyrightCopyright 2006 The McGraw-Hill Companies. All rights reserved.2006 The McGraw-Hill Companies. All rights reserved. McGraw-Hill!rwin "McGraw-Hill!rwin "##)&)&

    CostCost-Duration Trade#off E/am&le 0cont3d1-Duration Trade#off E/am&le 0cont3d1

    !I"R# $.+ (cont)d*

  • 7/26/2019 BMGN_N470_LO4_2014-15-sem1 - Time - Part 2

    16/19

    CopyrightCopyright 2006 The McGraw-Hill Companies. All rights reserved.2006 The McGraw-Hill Companies. All rights reserved. McGraw-Hill!rwin "McGraw-Hill!rwin "##)6)6

    *ummary Costs +y Duration*ummary Costs +y Duration

    !I"R# $.,

  • 7/26/2019 BMGN_N470_LO4_2014-15-sem1 - Time - Part 2

    17/19

    CopyrightCopyright 2006 The McGraw-Hill Companies. All rights reserved.2006 The McGraw-Hill Companies. All rights reserved. McGraw-Hill!rwin "McGraw-Hill!rwin "##)')'

    Project CostProject Cost-Duration Gra&h-Duration Gra&h

    !I"R# $.

  • 7/26/2019 BMGN_N470_LO4_2014-15-sem1 - Time - Part 2

    18/19

    CopyrightCopyright 2006 The McGraw-Hill Companies. All rights reserved.2006 The McGraw-Hill Companies. All rights reserved. McGraw-Hill!rwin "McGraw-Hill!rwin "##)()(

    Practical ConsiderationsPractical Considerations

    4sing the Project Cost-Duration Gra&h Crash Times

    Linearity (ssum&tion

    Choice of (cti%ities to Crash Re%isited

    Time Reduction Decisions and *ensiti%ity

  • 7/26/2019 BMGN_N470_LO4_2014-15-sem1 - Time - Part 2

    19/19

    CopyrightCopyright 2006 The McGraw-Hill Companies. All rights reserved.2006 The McGraw-Hill Companies. All rights reserved. McGraw-Hill!rwin "McGraw-Hill!rwin "##)")"

    What if Cost5 2ot Time is the ssue6What if Cost5 2ot Time is the ssue6

    Commonly 4sed '&tions for Cutting Costs$Reduce &roject sco&e

    $7a%e o,ner ta)e on more res&onsi+ility

    $'utsourcing &roject acti%ities or e%en the entire &roject

    $8rainstorming cost sa%ings o&tions