Bleach Plant Report December 2012 Envoy Development, LLC.

68
Bleach Plant Report December 2012 Envoy Development, LLC

Transcript of Bleach Plant Report December 2012 Envoy Development, LLC.

Page 1: Bleach Plant Report December 2012 Envoy Development, LLC.

Bleach Plant ReportDecember 2012

Envoy Development, LLC

Page 2: Bleach Plant Report December 2012 Envoy Development, LLC.

Key Comments From Last Month’s Report• From Sep 26 to Oct 20 costs dropped somewhat to trend to the long term average

($19.39 per ton)• On Oct 21 costs increased to $21.15, an increase of $1.76/ton• Costs are up equally across all stages• FIBER LENGTH: 338-AI-BT5400A

– Has been very high since the same time cost increased. Would this have a significant impact on cost? How does it impact control?

• E CAUSTIC TOTPD RATIO: 338-FR-262– Caustic use has been higher, but recently dropped off; costs fell then as well

• D0 WSHR LOWER POND FLOW: 338-FIC-218– Lower pond flows are at a historical low; there is a correlation between lower lower pond flows

and higher costs.

• E WSHR UPPER POND FLOW: 338-FIC-317; E WSHR LOWER POND FLOW: 338-FIC-318– Decreased around the same time that cost increased; could be impacting the pH treatment of the

pulp going to the D1 stage– Lower pond flow is up while upper flow is down. Why?

• D0 STAGE RAW BRIGHTNESS: 338-AI-257A– Has been very low at around 47 recently. Decrease occurred after cost, though. Suggests a higher

incoming K number or less work in the D0 stage.

Page 3: Bleach Plant Report December 2012 Envoy Development, LLC.

BP CHEMICALS COST/TON

• This month’s report focuses on the increase in cost that occurred on November 18– Nov 9 to Nov 18

• $18.79

– Nov 18 to Dec 2• $20.67

– Costs are even higher since Nov 27• $21.86

• The inflection point on October 20 has also continued to stick, averaging $20.44 since then– This was the focus of last month’s

report. We will review these changes here as well.

Page 4: Bleach Plant Report December 2012 Envoy Development, LLC.

Summary• This month’s report focuses on the increase in cost that occurred on November 18 as

well as the spike on Nov 27– Nov 9 to Nov 18

• $18.79– Nov 18 to Dec 2

• $20.67– Costs are even higher since Nov 27

• $21.86• pH is extremely low in the E, D1 mixer, D1 washer, and going to storage

– If the pH meter is correct, this needs to be corrected; pH meters are so inexpensive we can’t believe this is the case

– Peroxide use and D1 mixer ClO2 use is high; peroxide is at 20 lbs, which is a red flag there is a serious issue

• Any peroxide residual will act as an anti-chlor– There is a chance that there is a mechanical issue with the E washer– D0 raw brightness is high and k number is average, indicating the problem exists past the

D0 washer– PEROXIDE FLOW TO E STAGE: 366-FIC-479

• Peroxide flow increased by 100% but lbs/ton has not increased. Is the lbs/ton controller even being used? Is the make down system working correctly?

Page 5: Bleach Plant Report December 2012 Envoy Development, LLC.

Other Observations• DEFOAMER FLOW TO WASHERS: 732-FYI-186

– Has been at a historical high since around the time cost increased. Has the defoamer vendor changed? Are the washers washing poorly?

• FIBER LENGTH: 338-AI-BT5400A– Fiber length remains above average. Longer fiber length, higher costs. Did HW wood

species change?• KAPPA D0 TEMP TARGET: 338-TR-BT5400A

– Higher D0 temps have never produced low costs. The difference is huge. Why not target 130?

• ALKALINE SEWER TEMPERATURE: 338-TI-638– Stepped up to a historical high on November 28 the day after costs spiked. Is the E

temperature reading correctly? Perhaps the tower is hotter than it is showing.

Page 6: Bleach Plant Report December 2012 Envoy Development, LLC.

KPI Overview

Tag Name Tag Description Low Cost Nov 9 to Nov 18

High Cost Nov 18 to Dec 2

Diff of Means

Pct of Means

Z-Score Null Hypothesis

Significant 95%

338-MONY-472 BP CHEMICALS COST/TON 18.73 20.67 1.94 9.4% 7.13 yes

338-FI-138B STOCK FLOW TO PR-WASHR TPD 1136.39 1136.31 0.08 0.0% 0.01 no

PMHWK#.L Pulp Mill HWD K# 10.07 9.96 0.11 1.1% 1.78 yes

338-CI-144 PRE-WASHR FILT CONDUCTVITY 2818.25 2794.17 24.08 0.9% 0.16 no

338-CI-257C D0 STAGE CONDUCTIVITY 4606.96 4701.84 94.88 2.0% 5.92 yes

331-CI-216 BS CONDUCTIVITY 3224.74 3069.28 155.46 5.1% 0.80 no

BPDFBRT.L D1 Washer Brightness 86.50 86.16 0.34 0.4% 0.87 no

• Kappa was higher with the lower cost. Overall, though, the correlation between kappa and cost is very low.• D0 Stage Conductivity increased by 95 with the recent high cost.•Production and brightness did not change significantly.

Page 7: Bleach Plant Report December 2012 Envoy Development, LLC.

STOCK FLOW TO PR-WASHR TPD: 338-FI-138BProduction has remained high since Oct 30

Page 8: Bleach Plant Report December 2012 Envoy Development, LLC.

Pulp Mill HWD K#: PMHWK#.LAlmost no correlation to cost

Page 9: Bleach Plant Report December 2012 Envoy Development, LLC.

PRE-WASHR FILT CONDUCTVITY: 338-CI-144No correlation to cost

Page 10: Bleach Plant Report December 2012 Envoy Development, LLC.

D0 STAGE CONDUCTIVITY: 338-CI-257CConductivity was very low when cost was low; there is a slight correlation to cost

Page 11: Bleach Plant Report December 2012 Envoy Development, LLC.

BS CONDUCTIVITY: 331-CI-216No correlation to cost

Page 12: Bleach Plant Report December 2012 Envoy Development, LLC.

D1 Washer Brightness: BPDFBRT.LBrightness has been very low since Nov 30. Cost has been very high recently, as well,

indicating the operators are having trouble making brightness.

Page 13: Bleach Plant Report December 2012 Envoy Development, LLC.

Cost Per Stage• Costs increased at every stage

• D1 Stage saw the largest increase at 15%• This strongly implies more should be done in the D0 stage.

Tag Name Tag Description Low Cost Nov 9 to Nov 18

High Cost Nov 18 to Dec 2

Diff of Means

Pct of Means

Z-Score Null Hypothesis

Significant 95%

338-MONY-276 D0 STAGE COST/TON 10.52 11.45 0.93 8.1% 4.86 yes

338-MONY-368 E STAGE COST/TON 4.21 4.50 0.29 6.3% 2.88 yes

338-MONY-470D1 STAGE CHEMICAL COST/TON 4.00 4.73 0.73 15.4% 7.09 yes

338-MONY-472BP CHEMICALS COST/TON 18.73 20.67 1.94 9.4% 7.13 yes

Page 14: Bleach Plant Report December 2012 Envoy Development, LLC.

D0 STAGE COST/TON: 338-MONY-276Correlates very well with total cost and is currently high, but has been at higher levels in

the past.

Page 15: Bleach Plant Report December 2012 Envoy Development, LLC.

E STAGE COST/TON: 338-MONY-368Increased by nearly $2 last weekend. This appears to be a result of the increased

peroxide flows. Why did this increase so much?

Page 16: Bleach Plant Report December 2012 Envoy Development, LLC.

PEROXIDE FLOW TO E STAGE: 366-FIC-479Peroxide flow increased by 100%. Unreacted peroxide will act as an antichlor. We will

show later that it appears the lbs/ton controller is not being used.

Page 17: Bleach Plant Report December 2012 Envoy Development, LLC.

PEROXIDE FLOW TO E STAGE: 366-FIC-479.COPV vs CO. Flow does appear to be accurate.

Page 18: Bleach Plant Report December 2012 Envoy Development, LLC.

50% PROXID TO DILUITON TNK: 366-FIC-474

Page 19: Bleach Plant Report December 2012 Envoy Development, LLC.

D1 STAGE CHEMICAL COST/TON: 338-MONY-470Increased with total cost on November 18. Has been near a historical high for the last

week and jumped when peroxide use increased.

Page 20: Bleach Plant Report December 2012 Envoy Development, LLC.

Flow Meter Evaluation

Page 21: Bleach Plant Report December 2012 Envoy Development, LLC.

STOCK FLOW TO PRE-WASHER: 338-FIC-138.COGood correlation

Page 22: Bleach Plant Report December 2012 Envoy Development, LLC.

Actual - Predicted Flow: Act-PredNo major changes.

Page 23: Bleach Plant Report December 2012 Envoy Development, LLC.

Mixer flows - FI157: MixerFlow-FI157Has continued to hover around 0, showing that ClO2 is accurate.

Page 24: Bleach Plant Report December 2012 Envoy Development, LLC.

Recent Cost Spike

Page 25: Bleach Plant Report December 2012 Envoy Development, LLC.

D0 STAGE RAW BRIGHTNESS: 338-AI-257AHas been trending up for the last two weeks. Generally, this correlates with lower cost, but this is

currently not the case, an indication the issue is past the D0 washer.

Page 26: Bleach Plant Report December 2012 Envoy Development, LLC.

10% CAUSTIC TO D0 REPULP FLOW: 338-FZ-262Low, which correlates with very low pH. Why is the flow so low when pH is low and costs are high?

Page 27: Bleach Plant Report December 2012 Envoy Development, LLC.

E Final pH: BPEOFPH.LThis pH is way too low and is causing the D1 stage pH to be low as well. Is the pH meter reading correctly?

Page 28: Bleach Plant Report December 2012 Envoy Development, LLC.

PEROXIDE FLOW TO E STAGE: 366-FIC-479Peroxide flow increased by 100% but lbs/ton has not increased. Is the lbs/ton controller even being used?

Page 29: Bleach Plant Report December 2012 Envoy Development, LLC.

LBS/TON PEROXIDE TO E STAGE HW: 366-HIC-479HLbs/ton is at normal levels, so why is the flow 100% higher? Stock flow has certainly not doubled.

Page 30: Bleach Plant Report December 2012 Envoy Development, LLC.

D1 Mixer pH: BPDMXPH.LThis pH is way too low and it appears to be driving costs quite high.

Page 31: Bleach Plant Report December 2012 Envoy Development, LLC.

D1 Washer pH: BPDFPH.LHas been decreasing rapidly over the last week. More evidence D1 stage pH is way too low.

Page 32: Bleach Plant Report December 2012 Envoy Development, LLC.

pH to Storage: BPSTGPH.LpH to storage is at historical lows.

Page 33: Bleach Plant Report December 2012 Envoy Development, LLC.

November 18 Changes

Page 34: Bleach Plant Report December 2012 Envoy Development, LLC.

DEFOAMER FLOW TO WASHERS: 732-FYI-186Has been at a historical high since around the time cost increased. Has the defoamer vendor

changed? Are the washers washing poorly?

Page 35: Bleach Plant Report December 2012 Envoy Development, LLC.

E WSHR UPPER POND FLOW: 338-FIC-317Started to increase at the beginning of November and has been at a historical high the past few weeks. We

recommended increasing this in last month’s report, but there doesn’t seem to be any significant effect.

Page 36: Bleach Plant Report December 2012 Envoy Development, LLC.

BS WASHER DILUTION FACTOR: 331-FYI-206Increased around the same time as cost, implying the BSW are not washing effectively.

Page 37: Bleach Plant Report December 2012 Envoy Development, LLC.

ALKALINE SEWER pH: 338-AI-639Stepped up on November 20, but appears to be a calibration issue.

Page 38: Bleach Plant Report December 2012 Envoy Development, LLC.

ACID SEWER FLOW: 338-FI-611Stepped down on November 7 and has continued to decrease. Are pond flows lower?

Page 39: Bleach Plant Report December 2012 Envoy Development, LLC.

D0 TOWER CHUTE FLUSH: 338-HIC-263Why is this lower if the production rate is higher?

Page 40: Bleach Plant Report December 2012 Envoy Development, LLC.

D0 WSHR H UNIT FLUD PRSUR: 338-PI-228Low pressure suggests poor washing.

Page 41: Bleach Plant Report December 2012 Envoy Development, LLC.

SLT SLURRY TO RC MXMUM FLW: 366-FI-226M

Page 42: Bleach Plant Report December 2012 Envoy Development, LLC.

Review of October 20 Changes

• Last month we looked into the October 20 changes. This inflection point continues to stick. Here is a review of those changes.

Page 43: Bleach Plant Report December 2012 Envoy Development, LLC.

E WSHR DRUM SPEED: 338-SI-312Drum speed was very low when cost increased in October. Overall, there is a slight inverse correlation between drum

speed and cost. This seems counterintuitive since higher drum speeds are typically indicative of poor washing.

Page 44: Bleach Plant Report December 2012 Envoy Development, LLC.

D1 WASHER DRUM SPEED: 338-SI-412Drum speed was very low when cost increased in October. Overall, there is a slight

inverse correlation between drum speed and cost.

Page 45: Bleach Plant Report December 2012 Envoy Development, LLC.

BLEACH PLANT 35# STEAM TMP: 338-TI-052Stepped down from about 340 to 310 when cost increased.

Page 46: Bleach Plant Report December 2012 Envoy Development, LLC.

D0 WSHR POND FLOW RATIO: 338-FY-217AStepped up on October 19 and has steadily increased further since then.

Page 47: Bleach Plant Report December 2012 Envoy Development, LLC.

FIBER LENGTH: 338-AI-BT5400AFiber length remains above average. Longer fiber length, higher costs. Did HW wood species change?

Page 48: Bleach Plant Report December 2012 Envoy Development, LLC.

BLEACH LOAD: 338-AI-BT5400

Page 49: Bleach Plant Report December 2012 Envoy Development, LLC.

KAPPA CLO2 ADDITION TARGET: 338-FR-BT5400A

Page 50: Bleach Plant Report December 2012 Envoy Development, LLC.

KAPPA D0 TEMP TARGET: 338-TR-BT5400AHigher D0 temps have never produced low costs. The difference is huge. Why not target 130?

Page 51: Bleach Plant Report December 2012 Envoy Development, LLC.

PRE-WSHR FZ-P DIFF PRESURE: 338-PDI-110Has been below average since October 20.

Page 52: Bleach Plant Report December 2012 Envoy Development, LLC.

D0 THCK STK PP DSCH PRSUR: 338-PI-135Has been decreasing slightly since October 20.

Page 53: Bleach Plant Report December 2012 Envoy Development, LLC.

KNOTTER ACCEPTS PRES: 732-PI-050BHas been above average since October 20.

Page 54: Bleach Plant Report December 2012 Envoy Development, LLC.

Other Recent Changes

Page 55: Bleach Plant Report December 2012 Envoy Development, LLC.

D0 WSHR REPULPER DIL: 338-MIC-222Stepped down from 58 to 48 on November 28. This could be indicative of drainage

issues on the washer – the mat is wetter coming off the deck.

Page 56: Bleach Plant Report December 2012 Envoy Development, LLC.

D0 WSHR HOOD PRESSURE: 338-PIC-207Stepped down on November 28

Page 57: Bleach Plant Report December 2012 Envoy Development, LLC.

BLEACH PLANT 35# STEAM FLW: 338-FI-050Has been at a historical high of 43 for the last few days.

Page 58: Bleach Plant Report December 2012 Envoy Development, LLC.

10% CAUSTIC TO D0 REPULP FLOW: 338-FQI-262LDropped to a historical low on November 28.

Page 59: Bleach Plant Report December 2012 Envoy Development, LLC.

ALKALINE HEAT EXCHANGR CND: 338-CI-031Recently dropped close to 0.

Page 60: Bleach Plant Report December 2012 Envoy Development, LLC.

ACID HEAT EXCHANGER COND: 338-CI-036Has also been low recently.

Page 61: Bleach Plant Report December 2012 Envoy Development, LLC.

#13 BLCH TRANS TO PM'S FLW: 338-FI-548ARecently reached a historical high.

Page 62: Bleach Plant Report December 2012 Envoy Development, LLC.

KNOTTER FEED FLOW: 732-FIC-010.SPSet point fell to 0, but PV did not change; obviously not running in manual, but if it gets

put in manual there will be no flow.

Page 63: Bleach Plant Report December 2012 Envoy Development, LLC.

KNOTTER FEED FLOW: 732-FIC-010PV for previous slide.

Page 64: Bleach Plant Report December 2012 Envoy Development, LLC.

D0 WSHR INLET BOX PRESURE: 338-PI-208

Page 65: Bleach Plant Report December 2012 Envoy Development, LLC.

ALKALINE SEWER TEMPERATURE: 338-TI-638Stepped up to a historical high on November 28. Is the E temperature reading correctly? Perhaps

the tower is hotter than it is showing?

Page 66: Bleach Plant Report December 2012 Envoy Development, LLC.

50% CAUSTIC FLOW TO RCOVRY: 366-FI-308

Page 67: Bleach Plant Report December 2012 Envoy Development, LLC.

Black Liquor NaOH: PMBLNA.L

Page 68: Bleach Plant Report December 2012 Envoy Development, LLC.

#6 BROKE TANK LEVEL: 338-LI-559