Bld 102 PracticalBook

29
UNESCO-NIGERIA TECHNICAL & VOCATIONAL EDUCATION REVITALISATION PROJECT-PHASE II YEAR I- SE MESTER II PRACTICAL Version 1: December 2008 NATIONAL DIPLOMA IN BUILDING TECHNOLOGY BUILDING SCIENCE AND PROPERTIES OF MATERIALS II COURSE CODE: BLD102

description

Bld 102 PracticalBoo

Transcript of Bld 102 PracticalBook

  • UNESCO-NIGERIA TECHNICAL & VOCATIONAL EDUCATION

    REVITALISATION PROJECT-PHASE II

    YEAR I- SE MESTER II

    PRACTICAL Version 1: December 2008

    NATIONAL DIPLOMA IN

    BUILDING TECHNOLOGY

    BUILDING SCIENCE AND PROPERTIES OF MATERIALS II

    COURSE CODE: BLD102

  • TABLE OF CONTENT

    WEEK 1 Electrical Effects: Electro- Dynamic Effects Experiment

    WEEK 2 Clay Brick WEEK 3 Hand - Made Bricks WEEK 4 Pressed Bricks Experiment WEEK 5 Determination of Crushing Strength of Bricks Week 6 Strength Tests on Limes WEEK 7 Effect of Grading of Aggregate on the Properties Of Concrete WEEK 8 Slump Test WEEK 9 Compacting factor test

  • WEEK 10 V.B Consistometer test WEEK 11 Determination of the Strength of Concrete WEEK 12 Soundness of Cement Test Week 13 Field Setting Test to Determine Silt Content WEEK 14 Soundness of Cement Test Week 15 Students Excursion

  • WEEK 1

    ELECTRICAL EFFECTS: ELETRO- DYNAMIC EFFECTS ;EXPERIMENT

    Electric currents and magnetic fields have important mutual effects.

    .If an electric current is passed through a wire that is situated in a magnetic field

    as shown in the figure below in {a}

    Figure Force on a conductor in a Magnetic Field

    .The wire tends to move, in the direction motion cutting the lines as shown above

    in {b} it is on this effect that the operation of an electric motor depends. Both

    explained the principle of electric motor.

    .If a current is passed through a coil of wire suspended in a magnetic field as

    shown at {a}, the action on each side of the coil is to cause rotational in the

    direction shown.

    .when the coil passed the vertical position {b}, a change in the direction of the

    current is necessary if rotation is to continue in the same direction.

  • .If a conductor is moved across the line of force in a magnetic field, a current will

    be generated in it. The direction of movement of conductor and the current flow

    as shown in figure below explained the Principle of the Dynamo, the machine by

    which electricity is mostly generated.

    Details of the principle are illustrated below;

    Figure Dynamo principle

    For the direction of rotation shown at {a} current will flow in the coil as shown ;

    as the coil approaches the vertical position{b}, the current dies away because, in

    the position, the conductors are not cutting the line of force , but are running

    parallel to them. In position {c} the direction of flow is revered, and is at its

    maximum with the coil in the horizontal direction, dying away to zero in

    position {d} .this type of output is known as alternating Current.

  • WEEK 2 Clay Brick

    Procedure:

    In manufacturing of clay bricks, it is usual first to grind the clay with water

    to reduce it to the required plasticity for molding. Sometimes two or more

    types of clays are mixed in order to produce a more suitable material. The

    plastic clay is then molded into bricks, which are dried and then burned at

    a high temperature (about 850 1,1000c) in kilns. The burning process

    hardens the clay and gives the bricks the strength and durability required.

  • WEEK 3

    Hand - Made Bricks:

    Bricks are moulded by hand from clay which contains sufficient

    water to render it thoroughly plastic, and the finished product

    usually has a high porosity (about 28 - 35 percent). Their

    durability is, however, quite satisfactory except where

    temperature of burning are not high enough. Under - burned

    bricks may be recognized by their lightness in colour and lack

    of ring when stucks, and should not be used for building

    work. Hand made bricks are usually sand faced, since the

    moulds are dusted with sand to prevent the clay sticking. This

    gives to the bricks a surface texture which contributes greatly to

    their good appearance.

  • WEEK 4

    Pressed Bricks Experiment

    Plastic type: The strongest of all clay bricks are made by moulding under high pressure. Porosities as low as 8 percent

    may be obtained by this means, and the bricks are afterward

    burned at a temperature sufficiently high to give them a

    vitreous surface.

    Semi - Dry or Semi Plastic type: Bricks are also moulded by repeated pressing of clay containing minimum water content.

    High moulding pressures are generally used but high density is

    not always achieved. In fact, English example of this type of

    brick frequently have porosities greater than 25 per cent,

    though this may be due to the nature of the clays used rather

    than to the process itself. The low moisture content allows

    considerable economies to be achieved in burning, and also

    much reduces volume and shape change during burning;

    semi-dry bricks are notable for their regularity of size and

    shape.

  • WEEk 5

    Determination of Crushing Strength of Bricks

    Procedure;

    Three whole bricks should be selectee from each batch to be tested

    and the overall dimensions of each bed face (see Fig. Week5) of

    each brick measured to the nearest 300mm. The area of the face

    having the smaller area is taken as the area of the brick for

    calculating the compressive strength.

    Bricks without frogs are immersed in water for three days before

    testing.

    Bricks with frogs are immersed in water for twenty-four hours. They

    are then removed from the water, allowed to drain for about five

    minutes, wiped free from surplus moisture, and their frogs filled

    with mortar composed of 1 part by weight of Portland cement to 1

    Bed Face

    Figure Week5

  • parts of sand. The bricks are stored under the damp sacks for twenty-

    four hours and afterwards in water until tested seven days after the

    frogs have been filled.

    The bricks are crushed between sheets of 3-ply wood 3mm thick.

    A very large-capacity testing machine is necessary to crush whole

    bricks of the stronger types. If the capacity of the machine available is

    limited to 100 tons or to a lower value, the strengths of bricks may be

    compared by tests on quarter-bricks, the frogs being filled as required

    for whole bricks. The strengths obtained will be lower than if whole

    bricks were tested.

    The strength of bricks is dependent mainly on method of molding

    and on burning temperature, high strengths being associated with

    low porosity and high burning temperatures.

  • WEEK6 STRENGTH TESTS ON LIMES

    Mix 300 gram. of hydrated lime with 195ml of water for five

    minutes. Mix the putty thoroughly with 900 gram of standard cement

    testing sand, and fill six 4 in x 1-in 1-in moulds. The moulds should

    be filled by pressing with the thumbs and smoothed off with a palate

    knife. The specimens are stored in moulds in moist air in a slightly

    warmed oven (250c) for twenty eight days. They are then removed

    from moulds and stored in water half an hour before being tested

    transversely on a 3-in span.

    This experiment may be carried out using hydrated limes of the

    following types

    a. non hydraulic

    b. semi hydraulic

    c. hydraulic and

    d. 75 per cent. Non hydraulic lime: 25 per cent Portland cement

    e. Portland cement. The quantity of water used may have to be

    varied to suit the requirements of different materials

  • WEEK 7 EXPERIMENT; EFFECT OF GRADING OF AGGREGATE ON THE

    PROPERTIES OF CONCRETE

    Mixes are prepared consisting in each case of 1 part (by weight) of cement and 6

    parts aggregate. (48.5kg of cement and 20.1kg) of aggregate give a quantity

    soluble for making one 4 in cube. In different mixes, the proportions of fine and

    coarse aggregate are varied, in table 11 are given mixes whose proportion

    provide

    Table 11

    Proportions by weight

    Mix Cement Sand Gravel

    A

    B

    C

    D

    E

    F

    1

    1

    1

    1

    1

    1

    6

    4

    3

    2

    1

    0

    0

    2

    3

    4

    5

    6

    A suitable range for observation of the effects of grading of aggregate on the

    properties of concrete. Each mix is gauged with sufficient water to produce a

    plastic, workable mix, an attempt being made to produce mixes of comparable

  • workability. The amount of water required for each mix is carefully noted and

    the character of each mix is examined by working it with a trowel. A test

    specimen is then made from mix, care being taken to compact the concrete

    thoroughly, and its crushing strength determined after seven days or other

    convenient interval. A typical set of result from the experiment are given in the

    following table.

    Table 12

    Effect of aggregate grading on concrete properties

    Mix Water content percentage by weight of

    cement

    Crushing strength at seven days

    lb. per square inch

    A

    B

    C

    D

    E

    F

    86

    73

    66

    60

    49

    40

    280

    88

    1,480

    2,220

    1,760

    730

    It will be observed that, as the proportion of fine aggregate in the mix increase,

    so also does the amount of mixing water required. Also mixes E and F, deficient

    in sand , will be found to work very harshly, and no amount of added water will

    make them plastic. Mixes, A,. B and C on the other hand, provided sufficient

    water is added, give very attractive mixes, plastic and workable. From the

    appearance of the cubes and the crushing test results, mix F will be seen to be

    very porous, and not very strong; mix E though still porous, should give good

  • strength. The other mixes appear satisfactorily dense, but the strength will fall off

    rapidly from mix D, which should give good strength not very different from

    mix E, to mix A, whose strength will probably be even lower than that of F

    whose appearance is so unpromising.

  • WEEK 8

    TITLE: SLUMP TEST

    OBJECTIVE:

    To assess the workability of concrete.

    Apparatus:

    Truncated conical mould 100mm diameter at the top, 200mm at the

    bottom and 300mm height.

    Steel tamping rod 16mm diameter, 600mm long rounded at one end,

    Diagram:

  • Figure: slump cone

    Theory:

    The slump is the difference between the height of concrete before

    removing a slump cone and after removing it.

    Procedure:

  • 1. The inside of the mould should be cleaned before each test

    and the mould placed on a hard, flat, impervious surface.

    2. The mould should be filled in three layers of concrete of

    approximately equal depth. Each layer is rode with 25 stokes

    of the rounded end of the tamping rod; after the top layer

    has been rode, the surface of the concrete is struck off level

    with the top of the mould with a trowel or the rod. Any

    spillage is cleaned away from around the base of the mould,

    and the mould is then lifted vertically from the concrete.

    3. The slump is the difference between the height of the

    concrete before and the greatest height after the removal of

    the mould. If any specimen collapses or shears off laterally,

    the test should be repeated with another sample of the same

    concrete; if in the repeat test, the specimen should again

    shear; the slump should be recorded together with the fact

    that the specimen sheared.

    4. If after the slump measurement has babe completed, the side

    of the concrete is tapped with a rod, a well-proportioned

  • cohesive mix will gradually slump further but a harsh no

    cohesive mix is likely to collapse.

  • WEEK 9 Title: compacting factor test

    Objectives:

    This test is a more sensitive method of measuring the workability of

    concrete than the slump test, as it is designed to give a figure as a

    measure of workability for any kind of concrete mix made with

    aggregate not over 38mm maximum size.

    Apparatus:

    Compacting factor apparatus

    Hand scoop

    Balance capable of weighing 7kg and accuracy 1g

    Trowel;

    Diagram

  • Figure: compacting factor apparatus

    Theory:

    Included in procedure:

    Procedure:

    1. The doors of the hoppers are closed and the lower cylinder is

    fixed centrally in position and covered.

    2. The top hoppers filled with the sample of concrete of this

    hopper is released and the concrete is allowed to fall into the

    lower hopper; than the concrete is similarly released from

    the lower hopper and fall into the cylinder. Cohesive mixes

    have a tendency to stick in one or both of the hoppers, and, if

    this happens, the concrete may be helped through by

    pushing a rod gently into the concrete from the top.

    3. The excess concrete is struck off by two trowels working

    inwards and the full cylinder then removed and weighed,

    giving the partially compacted weight.

  • 4. The cylinder is emptied ad refilled in layers approximately

    50mm deep and heavily rammed or vibrated (if of low

    workability), and completely filled. The concrete in the

    cylinder is again weighed.

    Compacting factor (CF) = 1st net weight

    2nd net weight

    A higher value indicates greater workability.

    WEEK 10 Title: V.B Consistometer test

    Objective:

    This test can be regarded as an extension of the slump test which

    is performed in the same apparatus, being the first part of this test.

    Apparatus:

    a. Consistometer (see figure) consisting of a vibrating table T,

    on which is fixed a cylinder container C. A slump cone S (of

    size as for slump which rest centrally in the container. A

    funnel F is held on a; swivel arm A, for filling with concrete.

    On the swivel arm on the opposite side is a rod R, holding a

  • transporatent disc D, with a weight w (270g) including the

    rod and disc).

    b. Tamping road, 16mm diameter, 600mm long.

    c. Stop watch accuracy 0.5s.

    Diagram

    Figure: V-B Consistometer

    Theory:

    Included in the procedure

    Procedure;

  • 1. The cone is filled with concrete as for the slump test. The set

    screw G is loosened and the funnel is swung to one side. The

    surface of the concrete is struck off. The mould is removed

    carefully and the slump is measured if required. This can be

    done when the disc is swung round into position and

    lowered down the rod just to touch the slump concrete. The

    slump may be read off the rod scale.

    2. With the arm fixed in this position, holding the disc resting

    on the concrete and with stop watch ready, thee watch is

    started the instant that vibration is begun; and the watch is

    stopped at the moment the concrete has been fully

    compacted as compacted as observed through the disc, i.e

    when the disc is fully covered underneath with cement

    grout. The result is the time in seconds recorded to nearest

    0.5s being expressed as V-B degrees.

    An approximate guide to compacting factors, slump, and vebe

    degrees suitable for concrete for different purposes are given in

    the following table:

  • The presence of salt salts out and coagulates the colidal particles

    which may be present, and which otherwise would remain in

    suspension in the water layer.

  • WEEK 11 DETERMINATION OF THE STRENGTH OF CONCRETE After the casting of concrete, the concrete should be cured for 7 days -14 days. .To demonstrates to student how Schmidt Hammer is used to determine the strength of concrete on site. .the lower pitch sound indicates that the strength of the concrete is low. .The higher pitch sound gives the higher strength of concrete. Week. 12 Title: SOUNDNESS OF CEMENT TEST Objectives: To Determine the Soundness of cement test. Apparatus: le chatelier apparatus Diagram Procedure

    mix10gofcementwiththequantityofwaterrequiredtogiveapasteofstandardconsistency,vigorouslyfor240sonanonporoussurfacebymeansoftwotrowels.

    Placethemouldononeglassplateandfillitwiththepastetakingcaretokeepthesplitofthemouldgentlyclosedwhilethisoperationisbeingperformed.

    Coverthemouldwithotherglass,uponwhichasmallweightisplaced. Immersethewholeimmediatelyinwateratatemperatureof20+10Candleavethese

    fortwentyfourhours.

    Removethemouldfromthewaterthenmeasurethedistanceseparatingtheindicatorpointstothenearest0.5mm.

    Immersethewholeandbringthewatertoboilin2530minutesandkeepboilingfor1hour.

    Removethemouldfromthewatertocool. Measurethedistanceseparatingtheindicatorpointtothenearest0.5mm.

    Result

    The difference between the two measurements represents the expansion of the cement to the nearest 1mm

  • Week 13 FIELD SETTING TEST TO DETERMINE SILT CONTENT Prepare an approximately 1m solution of common salt by dissolving 2.5g of sodium chloride in 250ml of tap water. Pour 50ml of this solution into a 250ml measuring cylinder and then add sand until the volume of sand is about 100ml; add more of the salt solution until the total volume in the measuring cylinder is 150ml. Placing the palm of the hand over the open end of the cylinder, shake vigorously, place on a level bench, tap until the sand surface is level. Allow to stand for three hours. Record the height of the sand, and of the silt above it.

    Calculate the percentage of silt present. Report on the suitability of the sand as fine aggregates in the preparation of

    concrete.

    Note: the presence of salt out and coagulates the colloidal particles which may be present and which otherwise would remain suspension in the water layer.

  • WEEK 14

    Title: Soundness of Cement Test.

    Objective: To determine Soundness of Cement

    Apparatus: Le Chatelier Apparatus

    See week 7 for the theoretical explanation of this test.

    Mix 10g of cement with quantity of water required to give a paste standard consistency vigorously for 240s on a non porous surface by means of two trowels.

    Place the mould on one glass plate and fill it with paste taken care to keep the split of the mould gently closed while this operation is being performed.

    Cover the mould with other glass, upon which a small weight is placed. Immerse the whole immediately in water at a temperature of 20 10C and leave

    these for twenty four hours.

    Remove the mould from the water then measure the distance separating the indicator points to the nearest 0.5mm.

    Immerse the whole and bring the water to boil in 25 30 minutes and keep boiling for 1hour.

    Remove the mould from the water to cool. Measure the distance separating the indicator point to the nearest 0.5mm.

    Result

    The difference between the two measurements represents the expansion of the

    cement to the nearest 1mm

  • WEEK 15. STUDENTSEXCURSION. Pictures on excursion from Ajaokuta steel rolling mill at Kogi state, Nigeria.

    The process of the production is described by the arrows.

    CoverTABLE OF CONTENTWEEK 1WEEK 2WEEK 3WEEK 4WEEk 5WEEK 6WEEK 7WEEK 8WEEK 9WEEK 10WEEK 11Week. 12Week 13WEEK 14WEEK 15.Return to Table