RATE AMOUNT
IT.NO DESCRIPTION UNIT QTY (Rs.) (Rs.)
A FLOORING WORK
1 Fixing of ceramic tiles (300mm x 300mm ) in floor over a
cement mortar (1:4) bed of 20mm thickness including
pointing with pigments of matching colour and cleaning
all complete. Sqm ####### 322
2 Fixing of glazed tiles (300mm x 200mm) or (200mm x
150mm) in dado over 15mm thick (1:3) cement mortar
including pointing with pigments of matching colour and
cleaning all complete. Sqm #######
3Fixing of ceramic tiles in skirting (150mm high) over
12mm thick cement mortar (1:4) including pointing with
pigments of matching colour aqnd cleaning all complete. RM 5037.00
4 Fixing of marbles in floor over a cement mortar (1:4) bed
of 20mm thickness and filling the joints with pigments ofmatching colour including ordinary polishing and
cleaning all complete. Sqm 8332.00
ALTFixing of marbles in floor with white cement slurry over a
cement mortar (1:4) bed of 20mm thickness and filling
the joints with pigments of matching colour including
ordinary polishing and cleaning all complete. Sqm
5 i) x ng o mar e n s rt ng mm g ) over a cement
mortar of 12mm thickness (1:4) including pointing with
pigments of matching colour including ordinary polishing
and cleaning all complete. RM 7516.00
ALT i) Fixing of marble in skirting (75mm high) in white cement
slurry over a cement mortar of 12mm thickness (1:4)
including pointing with pigments of matching colour
including ordinary polishing and cleaning all complete. RM
ii) Fixing of ceramic tiles in skirting (75mm high) over a
cement mortar of 12mm thickness (1:4) including
pointing with pigments of matching colour and cleaning
all complete. RM #######
6 Supplying and fixing of vitrified tiles (size 400mm x400mm ) in corridor floor over a bed of cement sand
mortar (1:4) of thickness 20mm including pointing and
cleaning all complete. SQM 3427.00
ALT x ng o v tr e t es s ze mm x mm ) n
corridor floor over a bed of cement sand mortar (1:4) of
thickness 20mm including pointing and cleaning all
complete. SQM
-
7/27/2019 Blank Boq - Finishing(II)-Hiland Park
2/13
RATE AMOUNT
IT.NO DESCRIPTION UNIT QTY (Rs.) (Rs.)
7 Supplying and fixing of vitrified tiles in corridor skirting
(75mm high) over a cement sand mortar of 20mm
thickness (1:4) including pointing and cleaning all
complete. RM 3799.00
ALT Fixing of vitrified tiles in corridor skirting (75mm high)
over a cement sand mortar of 20mm thickness (1:4)
including pointing and cleaning all complete. RM
8 Supplying and fixing of glazed tiles (size 200mm x
200mm or 150mm x 150mm) in corridor dado over a
cement mortar (1:3) of 12mm thickness including
pointing and cleaning all complete. Sqm 876.00
9 Fixing of granite in kitchen counter over a cement mortar
(1:4) bed of 20mm thickness and filling the joints with
pigments of matching colour including ordinary polishing
and cleaning all complete. Sqm 550.00
10 Fixing of granite in facia of kitchen counters (75mm
high) over a cement mortar of 12mm thickness (1:4)
including pointing with pigments of matching colour
including ordinary polishing and cleaning all complete. RM 900.00
11 Supplying & fixing of wall pannelling with 9mm thick
ply over hard wood framework and finished with
sunmica. SQM 1320.00
Total for Flooring Work
B DOOR WORK
1 Fixing of main door (panelled) made of 2nd class Teak
wood having single leaf including polishing but
excluding cost of accessories at all levels. No 426.00
2 Fixing of internal flush doors of different sizes including
two coats of synthetic enamel paint (ICI/Berger/Asian
Paint make) over a coat of primer but excluding cost of
accessories at all levels. No 2556.00
3 Fixing of balcony doors fully glazed of different sizes
including two coats of synthetic enamel paint
(ICI/Berger/Asian Paint make) over a coat of primer butexcluding glazing & cost of accessories at all levels.
No 852.00
4 Fixing of glass in balcony doors including putty at all
levels but excluding cost of wooden bead. Sqm 1951.00
-
7/27/2019 Blank Boq - Finishing(II)-Hiland Park
3/13
RATE AMOUNT
IT.NO DESCRIPTION UNIT QTY (Rs.) (Rs.)
5 Fixing of fire door at corridor including painting but
excluding cost of accessories at all levels (size 1m x
2.05m ) No 142.00
6 Fixing of electrical panel room door with louver (Teak
wood) including two coats of synthetic enamel paint
(ICI/Berger/Asian Paint ) over a coat of primer but
excluding cost of accessories at all levels. No 142.00
7 Supplying and fixing of Teak wood moulding (size
50mm x 12.5mm ) including polishing at all levels. RM 3833.00
8 Supplying and fixing of Badam wood moulding (size
50mm x 12.5mm ) including two coats of synthetic
enamel paint. RM #######
Total for Wood Work
C MISCELLANEOUS WORKS
1 Supplying & Fixing of glass blocks (190mm x 190mm x
80mm ) in electrical rooms including filling the joints
with silicon sealant. Nos 852.00
2 Fixing of steel louvers ( 075m x 0.6m ) No 852.00
4 Supplying & applying of waterproof cement paint of
approved brand to give an even shade with a coat of
primer Sqm #######
5 Fixing of door sills (Marble / Granite / Jaisalmir Stone)
in floor with cement mortar of Size 65mm wide &
20mm thick. Rm
6 Supplying and Fixing of Wooden Skirting 75mm high &
12mm thick with adhesive at all levels complete. Rm
7 Providing two coats of White Wash with lime at all levels
complete. Sqm
8 Fixing of Kotah Stone in stair case over a cement mortar
(1:4) bed of 20mm thickness including pointing with
pigments of matching colour complete. Sqm
9 Fixing of broken tiles in deck level over a cement mortar
(1:4) bed of 20mm thickness including pointing with
pigments of matching colour complete. Sqm
-
7/27/2019 Blank Boq - Finishing(II)-Hiland Park
4/13
RATE AMOUNT
IT.NO DESCRIPTION UNIT QTY (Rs.) (Rs.)
10Fixing of Jaisalmir Stone coping on stair case railing over
a cement mortar (1:4) bed of 20mm thickness including
pointing with pigments of matching colour complete. Sqm
11 Supplying & Fixing of CI grating in drains. Kg
12 Supplying & Fixing of 150mm dia CI grating. Nos
13 Providing and laying IPS flooring in stair case, deck,
ramp including finishing all complete.
a) 25 mm thick Sqm
b) 40 mm thick Sqm
c) 50 mm thick Sqm
14 Providing and fixing 0.75m x 0.6m ply (12mm thickness)
for AC cutout covering including painting all complete.Nos
15 Providing and filling with brick bats outside toilet in 'B'
type flat at all levels complete. Sqm
16 Providing and fixing 50mm x50mm x6mm support angle
below kitchen counter at all levels. Kg
17Fixing of door frame in concrete surface. With fasteners Nos
18 Mixing water prrofing compound (Cico No.1) in 12mm
thick plaster (1:4) inside flats. (Plastering shall be paid in
BOQ iitem no. 19 of finishing work) Sqm
19 Providing neat cement punning 150 mm high on sides of
stair case at all levels complete. Sqm
20 Water Proofing Treatment to Roof Garden:
a) i) Cleaning the roof surface by means of wire brush
ii) Application of "Bitcote"- Heavy Bodied Bitumen
Coating on the roof surface) ay ng o rmours e - tact c o ypropy ene
Waterproofing Membrane Reinforced with non-woven
polyester by Thermofusing adopting ' Torch-on'
appliction method, on the entire surface treated with
'Bitcote' (Surface area shall be measured) Sqm
b) Providing & laying 50mm thick(Av)screed concrete
(1:2:4) of required thickness with chicken wire mesh over
' Armourshield' Sqm
21 Fixing of counter top basin without accessories No
Total for Miscellaneous Work
-
7/27/2019 Blank Boq - Finishing(II)-Hiland Park
5/13
RATE AMOUNT
IT.NO DESCRIPTION UNIT QTY (Rs.) (Rs.)
TOTAL FOR FINISHING WORKS(B+C)
-
7/27/2019 Blank Boq - Finishing(II)-Hiland Park
6/13
M/s. SPCL
Unit RATE AMOUNT
No. DESCRIPTION UNIT QTY (Rs.) (Rs.)
C FLOORING WORK
1 Handling, lifting & fixing of ceramic tiles of specified
size, approved shade and make forFlooring at all
levels & heightsover a cement mortar (1:4) bed of
20 mm thickness including cutting whereverrequired, making Hole of traps, pipes, comode &
electric box, cladding, copla, V grove cutting &
polishing, pointing with pigments of matching colour
including cleaning, curing, tools complete in all
respect as per drawing and specifications and as
directed by the Project Manager (Including the cost
of sand but excluding the cost of cement & tiles to
be issued by CMGL).Sqm 27832 322 8961904
2 Handling, lifting & fixing of ceramic tiles of specified
size, approved shade and make forDado at all
levels & heightsover a cement mortar (1:3) bed of15 mm thickness including cutting wherever
required, making Hole of traps, pipes, comode &
electric box, cladding, copla, V grove cutting &
polishing, pointing with pigments of matching colour
including cleaning, curing, tools complete in all
respect as per drawing and specifications and as
directed by the Project Manager (Including the cost
of sand but excluding the cost of cement & tiles to
be issued by CMGL).Sqm 14230 317 4510910
3 Handling, lifting & fixing of ceramic tiles of specified
size, approved shade and make forSkirting
(100mm high) at all levels & heightsover a cement
mortar (1:4) bed of 12 mm thickness including
cutting wherever required, making Hole of traps,
pipes, comode & electric box, cladding, copla, V
grove cutting & polishing, pointing with pigments of
matching colour including cleaning, curing, tools
complete in all respect as per drawing and
specifications and as directed by the Project
Manager (Including the cost of sand but excluding
the cost of cement & tiles to be issued by CMGL).RM 26290 60 1577400
BOQ/Price schedule CMGL
-
7/27/2019 Blank Boq - Finishing(II)-Hiland Park
7/13
M/s. SPCL
Unit RATE AMOUNT
No. DESCRIPTION UNIT QTY (Rs.) (Rs.)
4 Handling, lifting & laying/fixing Marble (of approved
shade) tiles & slabs at all levels in Floor with white
cement slurry over cement mortar base (CM 1:4) of
20mm thick, finished to all shapes (curved or
straight) and filling the joints with matching colour
pigment including making Hole of traps, pipes,
comode & electric box, cladding, copla, V grove,
cutting, polishing, grinding and cleaning with acid as
per drawings, specifications and directions of the
Project Manager (Including the cost of sand, white
cement, acid, pigment but excluding the cost of
cement & marble).Sqm 8332 585 4874220
5 Handling, lifting & laying/fixing Marble (of approved
shade) tiles & slabs at all levels in Skirting (100mm
high) with white cement slurry over cement
mortar base (CM 1:4) of 12mm thick, finished to all
shapes (curved or straight) and filling the joints with
matching colour pigment including making Hole of
traps, pipes, comode & electric box, cladding, copla,
V grove, cutting, polishing, grinding and cleaning
with acid as per drawings, specifications and
directions of the Project Manager (Including the cost
of sand, white cement, acid, pigment but excluding
the cost of cement & marble).RM 8765 85 745025
6 Handling, lifting & fixing of ceramic & vitrif ied tiles of
specified size, approved shade and make for
Skirting (150mm high) at all levels & heightsover a
cement mortar (1:4) bed of 12 mm thickness
including cutting wherever required, making Hole oftraps, pipes, comode & electric box, cladding, copla,
V grove cutting & polishing, pointing with pigments
of matching colour including cleaning, curing, tools
complete in all respect as per drawing and
specifications and as directed by the Project
Manager (Including the cost of sand but excluding
the cost of cement & tiles to be issued by CMGL).RM 4500 60 270000
.7 Handling, lifting & fixing of vitrif ied ti les of specified
size, approved shade and make for corridor floor at
all levels & heightsover a cement mortar (1:4) bed
of 20 mm thickness including cutting whereverrequired, making Hole of traps, pipes, comode &
electric box, cladding, copla, V grove cutting &
polishing, pointing with pigments of matching colour
including cleaning, curing, tools complete in all
respect as per drawing and specifications and as
directed by the Project Manager (Including the cost
of sand but excluding the cost of cement & tiles to
be issued by CMGL).SQM 3427 400 1370800
BOQ/Price schedule CMGL
-
7/27/2019 Blank Boq - Finishing(II)-Hiland Park
8/13
M/s. SPCL
Unit RATE AMOUNT
No. DESCRIPTION UNIT QTY (Rs.) (Rs.)
8 Handling, lifting & fixing of ceramic tiles of specified
size, approved shade and make forCorridorDado
opp. lift well at all levels & heightsover a cement
mortar (1:3) bed of 15 mm thickness including
cutting wherever required, making Hole of pipes,
dedectors, electric box, cladding, copla, V grove
cutting & polishing, pointing with pigments of
matching colour including cleaning, curing, tools
complete in all respect as per drawing and
specifications and as directed by the Project
Manager (Including the cost of sand but excluding
the cost of cement & tiles to be issued by CMGL).Sqm 876 317 277692
9 Handling, lifting and laying/f ixing pre-polished
Granite (of approved shade) over RCC kitchen
counter at all levels & heights, over cement mortar
base (CM 1:4) of 20mm thick, finished to all shapes
(curved or straight), making Hole of traps, pipes,electric box, cutting openings for Kitchen sink,
Cladding, copla, V grove cutting & polishing and
filling the paper joints with matching colour pigment
as per drawings, specifications and directions of the
Project Manager (Including the cost of sand but
excluding the cost of granite and cement).Sqm 805 600 483000
10 Handling, lifting and laying/fixing pre-polished
Granite (of approved shade) skirting/facia at all
levels & heights of kitchen counter, with a uniform
layer of aralditeand POP on top of granite for
holding till araldite dries, finished to all shapes(curved or straight) making Holes, Cladding, copla,
V grove cutting & polishing and filling the paper
joints with matching colour pigment as per
drawings, specifications and directions of the
Project Manager (Including the cost of araldite but
excluding the cost of granite). RM 1778 400 711200
11 Supplying, handling, lifting & fixing of wall
pannelling at all levels & height all around the lif t
openings in corridor of each floor with 6mm thick ply
over hard wood framework and finished with
sunmica including all consumables as per the
approved sample to be made under the directionand satisfaction of CMGL. SQM 1320 1750 2310000
Total for Flooring Work (C) 26092151
D DOOR WORK
BOQ/Price schedule CMGL
-
7/27/2019 Blank Boq - Finishing(II)-Hiland Park
9/13
M/s. SPCL
Unit RATE AMOUNT
No. DESCRIPTION UNIT QTY (Rs.) (Rs.)
1 Handling, lifting and Fixing of main door (panelled)
made of 2nd class Teak wood having single leaf at
all levels including fixing all accessories like brass
handle on both side, door stoper, buffer, hinges,
godrej tribolt lock etc. including polishing complete,
as per the direction of the Project Manager including
supply of screws but excluding cost of accessories
& door No 390 2000 780000
2 Handling, lifting & Fixing of internal flush doors of
different sizes at all levels including fixing all
accessories like hinges, buffer, cylindrical locks,
supply & application of two coats of synthetic
enamel paint (ICI/Berger/Asian Paint make) over a
coat of primer complete as per the direction of the
Project Manager, including supply of screw but
excluding cost of accessories & flush door. No 2556 950 2428200
3 Handling, lifting & fixing of balcony doors fullyglazed (2 & 3 shutter) of different sizes at all levels
including fixing all accessories like hinges, SS
handle, tower bolt, buffer, supply & application of
two coats of synthetic enamel paint
(ICI/Berger/Asian Paint make) over a coat of primer
complete as per the direction of the Project
Manager, including supply of screws but excluding
cost of glass, accessories & shutters. No 852 1270 1082040
4 a Handling, lifting and Fixing of glass in balcony
shutter glazed doors at all levels including applying
putty but excluding cost of wooden bead. (overall
area of door shutter shall be measured)Sqm 1951 110 214610
b Supply of 5mm thick clear Modi float glass including
wooden beading of good quality as same as that of
the door wood quality and to the satisfaction of the
Project Manager (overall area of door shutter shall
be measured) Sq.m. 1951 350 682850
5 Handling, lifting and Fixing of fire door (flush door)
at all levels with accessories like hinges, lock, door
closure, supply & application of two coats of
synthetic enamel paint (ICI/Berger/Asian Paintmake) over a coat of primer complete, as per the
direction of the Project Manager, including supply of
screw but excluding cost of accessories & flush
door. No 142 950 134900
BOQ/Price schedule CMGL
-
7/27/2019 Blank Boq - Finishing(II)-Hiland Park
10/13
M/s. SPCL
Unit RATE AMOUNT
No. DESCRIPTION UNIT QTY (Rs.) (Rs.)
6 Handling, lifting and Fixing of Electrical panel door
(teak wood or marbau) at all levels with accessories
like hinges, lock, buffer, supply & application of two
coats of synthetic enamel paint (ICI/Berger/Asian
Paint make) over a coat of primer complete, as per
the direction of the Project Manager, including
supply of screw but excluding cost of accessories &
door. No 142 950 134900
7 Supplying, handling lifting and fixing of Teak wood
moulding (size 50mm x 12.5mm ) all around the
door frames including polishing at all levels &
heights as per the direction and satisfaction of the
Project Manager. RM 3833 150 574950
8Supplying, handling, lifting and fixing of Badam
wood or equivalent approval moulding (size 50mm x
12.5mm ) all around the door frames including two
coats of synthetic enamel paint over a coat of primerat all levels and heights as per the direction &
satisfaction of the Project Manager. RM 15331 100 1533100
Total for Wood Work ( D) 7565550
Note:
E MISCELLANEOUS WORKS
1 Supplying & Fixing of good quality glass blocks
(190mm x 190mm x 80mm ) in electrical rooms with
white cement mortar including sealing the joints with
silicon sealant from outside as per the direction of
the Project Manager (Glass Block sample to be
approved by CMGL). Nos 852 180 153360
2 Supplying & application of good quality exterior
emulsion paint of approved shade & brand (2 or
more coats) at all levels & height to give an even
shade over a coat of primer including surface
preparation, scafolding, jhulla, l ifting of materials
etc. complete as per the direction & satisfaction of
the Project Manager (A guarantee certificate of
minimum 5 years is to be submitted at the end of
completion of painting). Any price benefit derived
out of joint negotiation with paint vendor shall be
passed on to CMGL Sqm 78300 80 6264000
The supply rate of all accessories/fixtures like hinges, Godrej trivolt lock, cylindrical lock, tower bolt,
handles, buffer, door stopper etc. required for fixing of doors shall be jointly negotiated with vendor
and over the vendor rate (all inclusive delivery at site), 15% extra will be paid to SPCL towards
handling, wastage, overhead & profit.
BOQ/Price schedule CMGL
-
7/27/2019 Blank Boq - Finishing(II)-Hiland Park
11/13
M/s. SPCL
Unit RATE AMOUNT
No. DESCRIPTION UNIT QTY (Rs.) (Rs.)
3Supply & application of good quality internal paint of
approved shade and brand (2 or more coats)at all
levels and hieght to given an even shade over a
coat of primer including surface preperation,
scafolding, lifting of material etc. Complete as per
the direction & satisfaction of the Project manager.
Any price benefit derived out of joint negotiation withpaint vendor shall be passed on to CMGL
a Staircase walls of tower including landing and part
of Servant toilet Sqm. 10460 50 523000b Parapet walls of staircase Sqm. 14325 70 1002750c Basement wall and ceiling of tower Sqm. 7900 40 316000d Corridor walls of each floor Sqm. 6630 75 497250
4 Supply & application of good quality Primer of
approved brand at all levels and hieght inside flat to
given an even & smooth finish including surface
preperation, scafolding, lifting of material etc.
Complete as per the direction & satisfaction of theProject manager. Any price benefit derived out of
joint negotiation with paint vendor shall be passed
on to CMGL Sqm. R.O. 28
5 Handling, lifting & Fixing of door sills (Marble /
Granite / Jaisalmir Stone) of varying width from
65mm to 360mm as required in floor at all levels
with cement mortar (1:4) of 20mm thick including
cutting, polishing etc. complete as per the direction
of the Project Manager, including the cost of sand,
white cement pigment etc. but excluding the cost of
cement & stone Rm 1500 50 75000
6Supply & application of two coats of White Wash
with lime at all levels in Electrical rooms including
surface preperation, scafolding etc. complete as per
the direction of the Project manager . Sqm 1615 16 25840
7 Handling, lifting & Fixing of Kota Stone in stair case
over a cement mortar (1:4) bed of 20mm thickness
including pointing with pigments of matching colour
etc. complete as per the direction of the Project
Manager, excluding the cost of cement & kota stone
supplied by CMGL. Sqm 102 450 45900
8Handling, lifting & Fixing of broken tiles in deck level
over a cement mortar (1:4) bed of 20mm thickness
including pointing with pigments of matching colour,
breaking of tiles etc. complete as per the direction of
the Project Manager, excluding the cost of cement &
tiles supplied by CMGL. Sqm 300 400 120000
BOQ/Price schedule CMGL
-
7/27/2019 Blank Boq - Finishing(II)-Hiland Park
12/13
M/s. SPCL
Unit RATE AMOUNT
No. DESCRIPTION UNIT QTY (Rs.) (Rs.)
9Handling, lifting & Fixing of Jaisalmir Stone coping
on stair case railing over a cement mortar (1:4) bed
of 20mm thickness including pointing with pigments
of matching colour etc. complete as per the direction
of the Project Manager, excluding the cost of
cement & stone supplied by CMGL. Sqm 50 400 20000
10 Supplying & Fixing of CI grating in drains as per the
direction of Project manager and section/sample
approved. Kg 200 50 10000
11Providing and laying IPS flooring in stair case, deck,
ramp including finishing, red oxide pigment etc.all
complete as per the directionof the Project Manager. 0a) 25 mm thick Sqm 500 200 100000b) 40 mm thick Sqm 3020 250 755000c) 50 mm thick Sqm 3000 300 900000
12 Providing and fixing wooden frame (section
75mmX50mm) for approx. opening size of 700mm X
800mm of AC cutout including supply & fixing of
5mm thick float glass with silicon sealant from
outside for water proofing etc. complete as per the
direction of the Project Manager and sample
approved. Nos 1120 1350 1512000
13 Providing & fixing PHE duct covering with frame,
shutter, moulding etc. complete (9mm ply & frame
75mm X 50mm) as per the drawing and direction of
the Project Manager in "B" type flat kitchen andDining area (size 850mm X 600mm approx.) and
Duplex area as per site requirement Nos. 150 1000 150000
14Providing and placing of brickbats 1:3:6 (1 cement :
3coarse sand : 6brickbats) outside toilet in 'B' type
flat at all levels after the completion and inspection
of sanitary lines laid in the sunken slab and proper
waterproofing & clearance of testing. The placement
of the brickbats shall be as per specificaion
indicated in the drawings . Any breakage of pipeline
or damage to waterproofing during the entire
operation of brickbat filling shall be to thecontractors account (Cement & bricks will be
supplied by CMGL). Sqm 530 200 106000
15 Providing and fixing 50mm x50mm x6mm support
angle below kitchen counter at all levels as per the
direction of the Project Manager. Kg 100 60 6000
BOQ/Price schedule CMGL
-
7/27/2019 Blank Boq - Finishing(II)-Hiland Park
13/13
M/s. SPCL
Unit RATE AMOUNT
No. DESCRIPTION UNIT QTY (Rs.) (Rs.)
16Providing & Fixing of door frame in concrete surface
with anchor fasteners (6 nos.) as per the direction of
the Project Manager & sample approved. Nos 140 500 70000
17 Supply & Mixing of water proofing compound (Cico
No.1) in 12mm thick plaster (1:4) inside flats as per
the product literature and direction of the Project
Manager. (Plastering shall be paid in BOQ iitem no.
19 of finishing work) Sqm R.O. 7
18 Handling, lifting & Providing neat cement punning
150 mm high on sides of stair case at all levels
including curing etc.complete as per the direction of
the Project Manager, excluding the cost of cement
supplied by client. Sqm 250 27 6750
19 Providing & fixing with all materials for shoring work
comprising 5.0 metre long eucalptus ballah of
200mm dia driven about half the length into theground by monkey at a very clossed spacing side by
side and providing 2 nos. of eucalyptus runner of
75mm dia including cost of all materials and one
coat of coaltar painting to all ballahs and inlcuding
hire and labour charges for necessary driving
appliances and all tackles etc. complete as per
direction of EIC RM 220 2614 575000
Total for Miscellaneous Work (E) 13233850
TOTAL FOR FINISHING WORKS(A+B+C+D+E) 102307664