Black Lagoon Site - US EPA · 2016-02-20 · Black Lagoon Project Costs • Total cost...

40

Transcript of Black Lagoon Site - US EPA · 2016-02-20 · Black Lagoon Project Costs • Total cost...

Page 1: Black Lagoon Site - US EPA · 2016-02-20 · Black Lagoon Project Costs • Total cost approximately $9.3 million $6 million Legacy Act funds $3.3 Clean Michigan Initiative funds
Page 2: Black Lagoon Site - US EPA · 2016-02-20 · Black Lagoon Project Costs • Total cost approximately $9.3 million $6 million Legacy Act funds $3.3 Clean Michigan Initiative funds

Black Lagoon SiteBlack Lagoon Site Trenton, MITrenton, MI

First Great Lakes Legacy ActFirst Great Lakes Legacy Act Sediment CleanSediment Clean--up Projectup Project

Page 3: Black Lagoon Site - US EPA · 2016-02-20 · Black Lagoon Project Costs • Total cost approximately $9.3 million $6 million Legacy Act funds $3.3 Clean Michigan Initiative funds

Refuge•

McLouth S• A

Black Lagoon Site

Approximately 2-acre exposed cove on Trenton Channel of Detroit River

Part of Detroit River Area of Concern & Detroit River International Wildlife

Located immediately downstream of former teel plant (closed in 1995)

cted as settling basin for past 50 years

Page 4: Black Lagoon Site - US EPA · 2016-02-20 · Black Lagoon Project Costs • Total cost approximately $9.3 million $6 million Legacy Act funds $3.3 Clean Michigan Initiative funds
Page 5: Black Lagoon Site - US EPA · 2016-02-20 · Black Lagoon Project Costs • Total cost approximately $9.3 million $6 million Legacy Act funds $3.3 Clean Michigan Initiative funds

• Multiple joint historical

• ver 400,000 cy contaminated sediments in Trenton Channel

Black Lagoon Site Contamination

sampling efforts

• One of six major contaminated areas of Trenton ChannelO

Page 6: Black Lagoon Site - US EPA · 2016-02-20 · Black Lagoon Project Costs • Total cost approximately $9.3 million $6 million Legacy Act funds $3.3 Clean Michigan Initiative funds

– O– Total PCBs: 1.12 mg/kg– Mercury: 1.40 mg/kg– Lead: 146 mg/kg

Black Lagoon Site Contamination

Site contributed approximately 115,000 cy of contaminated sediments Average contaminant thickness was 8-15 feet Average contaminant concentrations:

il & Grease: 6,280 mg/kg

• •

Page 7: Black Lagoon Site - US EPA · 2016-02-20 · Black Lagoon Project Costs • Total cost approximately $9.3 million $6 million Legacy Act funds $3.3 Clean Michigan Initiative funds

Great Lakes Legacy Act of 2002…

Great Lakes sediment remediation toolbox

…a new “tool” in the

Page 8: Black Lagoon Site - US EPA · 2016-02-20 · Black Lagoon Project Costs • Total cost approximately $9.3 million $6 million Legacy Act funds $3.3 Clean Michigan Initiative funds

• The Legacy Act authorizes $50M per year from FY2004 through FY2008 for contaminated sediment projects in the Great Lakes

• Funds can be used for clean-ups, research, and public outreach in AOCs

• $10 Million appropriated in FY2004• $22 Million appropriated in FY 2005• Black Lagoon Site submitted by MDEQ

Great Lakes Legacy Act

Page 9: Black Lagoon Site - US EPA · 2016-02-20 · Black Lagoon Project Costs • Total cost approximately $9.3 million $6 million Legacy Act funds $3.3 Clean Michigan Initiative funds

– G

– D– Grand Haven Area Office– Pointe Mouillee Confined Disposal Facilty

Multi-Agency Cooperative Effort

U.S. EPA Region V reat Lakes National Program Office

– Superfund Division (Emergency Response Contract)

Surface Water Quality Section • Michigan Department of Environmental Quality

• US Army Corps of Engineers etroit District & Detroit Area Office

Page 10: Black Lagoon Site - US EPA · 2016-02-20 · Black Lagoon Project Costs • Total cost approximately $9.3 million $6 million Legacy Act funds $3.3 Clean Michigan Initiative funds

Multi-Agency Cooperative Effort

• American Heritage River Initiative

• •

Greater Detroit

City of Trenton Private land-owners

Page 11: Black Lagoon Site - US EPA · 2016-02-20 · Black Lagoon Project Costs • Total cost approximately $9.3 million $6 million Legacy Act funds $3.3 Clean Michigan Initiative funds

Primary Objectives

Reduce risks to human health, wildlife, and aquatic life in Detroit River AOC

Restore the aquatic habitat in Black Lagoon • • Prepare for recreational and economic

redevelopment of Black Lagoon

Page 12: Black Lagoon Site - US EPA · 2016-02-20 · Black Lagoon Project Costs • Total cost approximately $9.3 million $6 million Legacy Act funds $3.3 Clean Michigan Initiative funds

•• Truck Transport to CDF• Final Sediment Placement at CDF

Black Lagoon Clean-up Plans

Lagoon Isolation/Silt Curtain Installation

• Environmental Controls

Mechanical Dredging• • Barge Transport to Pointe Mouillee CDF

Sediment Solidification at CDF

Page 13: Black Lagoon Site - US EPA · 2016-02-20 · Black Lagoon Project Costs • Total cost approximately $9.3 million $6 million Legacy Act funds $3.3 Clean Michigan Initiative funds

” x 8”

intervals • F

steel beam support at bottom

Lagoon Isolation/Silt Curtain

Approximately 2,000 ft long and 24 ft deep• Fifty foot sections of laminated vinyl-

• polyester fabric with heat-treated seams

8 x 48” EPS foam block floats • Initially connected to pipe piles at 50 ft

inal connection at 10-15 ft intervals with

Page 14: Black Lagoon Site - US EPA · 2016-02-20 · Black Lagoon Project Costs • Total cost approximately $9.3 million $6 million Legacy Act funds $3.3 Clean Michigan Initiative funds

Lagoon Isolation/Silt Curtain

Page 15: Black Lagoon Site - US EPA · 2016-02-20 · Black Lagoon Project Costs • Total cost approximately $9.3 million $6 million Legacy Act funds $3.3 Clean Michigan Initiative funds

Lagoon Isolation/Silt Curtain

Page 16: Black Lagoon Site - US EPA · 2016-02-20 · Black Lagoon Project Costs • Total cost approximately $9.3 million $6 million Legacy Act funds $3.3 Clean Michigan Initiative funds

H– A– Shoreline – Work Barges

Environmental Controls

• Equipment at Lagoon – arbor Boom

bsorbent Boom

Oil Spill Protection

Page 17: Black Lagoon Site - US EPA · 2016-02-20 · Black Lagoon Project Costs • Total cost approximately $9.3 million $6 million Legacy Act funds $3.3 Clean Michigan Initiative funds

1– 2

– C

– Repeat throughout shift

– Continuous feed units

Environmental Controls

• – Station Upstream

Stations Downstream

ollect data 2 hours after start of shift

Turbidity Monitoring

– Handheld readings

Page 18: Black Lagoon Site - US EPA · 2016-02-20 · Black Lagoon Project Costs • Total cost approximately $9.3 million $6 million Legacy Act funds $3.3 Clean Michigan Initiative funds

S

CDF– R

and particulates– Biweekly Sampling

for PCBs, Lead and Mercury

Environmental Controls

• Sampling – everal locations at

both Lagoon &

eal-time VOCs

Air Monitoring &

Page 19: Black Lagoon Site - US EPA · 2016-02-20 · Black Lagoon Project Costs • Total cost approximately $9.3 million $6 million Legacy Act funds $3.3 Clean Michigan Initiative funds

• M• W

Mechanical Dredging

Two work barges with steel hoppers• CAT 235DL excavator with environmental

clamshell for top sediment Long-reach 320L excavator for finer

sediments aterial transferred to transport barges

eekly soundings conducted for volume measurements (GPS/total station)

Page 20: Black Lagoon Site - US EPA · 2016-02-20 · Black Lagoon Project Costs • Total cost approximately $9.3 million $6 million Legacy Act funds $3.3 Clean Michigan Initiative funds

Mechanical Dredging

Page 21: Black Lagoon Site - US EPA · 2016-02-20 · Black Lagoon Project Costs • Total cost approximately $9.3 million $6 million Legacy Act funds $3.3 Clean Michigan Initiative funds

Barge Transport to Pointe Mouillee Confined Disposal Facility (CDF)

Sediments loaded over silt curtain into transport barges

• Barges hold approximately 1800 cy

• Spill prevention steel plate used for transferTransport barges travel down Detroit River

Channel to CDF in Lake Erie

Page 22: Black Lagoon Site - US EPA · 2016-02-20 · Black Lagoon Project Costs • Total cost approximately $9.3 million $6 million Legacy Act funds $3.3 Clean Michigan Initiative funds

Barge Transport to Pointe Mouillee CDF

Page 23: Black Lagoon Site - US EPA · 2016-02-20 · Black Lagoon Project Costs • Total cost approximately $9.3 million $6 million Legacy Act funds $3.3 Clean Michigan Initiative funds

•• U

and Harbor Act of 1970

Pointe Mouillee CDF

Designed to contain 18 million cy of contaminated dredged sediments from the Detroit and Rouge Rivers

• 700-acre crescent-shape dike in Lake Erie• Structure is 3.5 miles long and 1,400 ft wide

Constructed in sections from 1976 – 1981 SACE authorized to manage under River

Page 24: Black Lagoon Site - US EPA · 2016-02-20 · Black Lagoon Project Costs • Total cost approximately $9.3 million $6 million Legacy Act funds $3.3 Clean Michigan Initiative funds

• on

• S

Sediment Solidification at CDF

Sediments solidified with Calciment transport barge at CDF

• Solidified sediments off-loaded into off-road dump trucks

• Silt curtain in place around barges

ediments off-loaded into either temporary storage pit or directly into CDF cell

Page 25: Black Lagoon Site - US EPA · 2016-02-20 · Black Lagoon Project Costs • Total cost approximately $9.3 million $6 million Legacy Act funds $3.3 Clean Michigan Initiative funds

Sediment Solidification at CDF

Page 26: Black Lagoon Site - US EPA · 2016-02-20 · Black Lagoon Project Costs • Total cost approximately $9.3 million $6 million Legacy Act funds $3.3 Clean Michigan Initiative funds

Sediment Solidification at CDF

Page 27: Black Lagoon Site - US EPA · 2016-02-20 · Black Lagoon Project Costs • Total cost approximately $9.3 million $6 million Legacy Act funds $3.3 Clean Michigan Initiative funds

•remainder of project

Truck Transport to CDF

Project delays due to increased volume and inclement weather conditions

Transport by barge no longer possible • • Initiated solidification at Lagoon with

transport by truck to CDF

Continued truck transportation for

Page 28: Black Lagoon Site - US EPA · 2016-02-20 · Black Lagoon Project Costs • Total cost approximately $9.3 million $6 million Legacy Act funds $3.3 Clean Michigan Initiative funds

Truck Transport to CDF

Page 29: Black Lagoon Site - US EPA · 2016-02-20 · Black Lagoon Project Costs • Total cost approximately $9.3 million $6 million Legacy Act funds $3.3 Clean Michigan Initiative funds

D– L– S

• I

Other Weather Considerations

Turbidity monitoring in River• Silt curtain inspection and repairs

– iver assisted inspections onger sections of impermeable silt curtain econd layer of permeable silt curtain added

ce management in excavation area

Page 30: Black Lagoon Site - US EPA · 2016-02-20 · Black Lagoon Project Costs • Total cost approximately $9.3 million $6 million Legacy Act funds $3.3 Clean Michigan Initiative funds

Winter at the Black Lagoon

Page 31: Black Lagoon Site - US EPA · 2016-02-20 · Black Lagoon Project Costs • Total cost approximately $9.3 million $6 million Legacy Act funds $3.3 Clean Michigan Initiative funds

Two Layers of Silt Curtain

Page 32: Black Lagoon Site - US EPA · 2016-02-20 · Black Lagoon Project Costs • Total cost approximately $9.3 million $6 million Legacy Act funds $3.3 Clean Michigan Initiative funds

•• T• Sediments compacted and graded

Final Sediment Placement at CDF

Cross dike constructed to isolate Black Lagoon sediments

• Outer CDF walls lined with geotextile

• Overflow weir installed to manage oil/waterSolidified sediments placed in 12 inch lifts

wo foot cover material placed on top

Page 33: Black Lagoon Site - US EPA · 2016-02-20 · Black Lagoon Project Costs • Total cost approximately $9.3 million $6 million Legacy Act funds $3.3 Clean Michigan Initiative funds

Final Placement at CDF

Page 34: Black Lagoon Site - US EPA · 2016-02-20 · Black Lagoon Project Costs • Total cost approximately $9.3 million $6 million Legacy Act funds $3.3 Clean Michigan Initiative funds

Final Sediment Placement at CDF

Page 35: Black Lagoon Site - US EPA · 2016-02-20 · Black Lagoon Project Costs • Total cost approximately $9.3 million $6 million Legacy Act funds $3.3 Clean Michigan Initiative funds

• C

• S• C

shoreline restoration

Black Lagoon Site Summary

ooperative Multi-Agency Effort• Dredging occurred over 13 months• Approximately 115,000 cy of contaminated

sediments removed • Excavated area covered with 6 inches of sand and

3 inches of stone and bar area created with stone riprap ity of Trenton received $113,000 grant for

Page 36: Black Lagoon Site - US EPA · 2016-02-20 · Black Lagoon Project Costs • Total cost approximately $9.3 million $6 million Legacy Act funds $3.3 Clean Michigan Initiative funds

140,000Zinc

38,000Lead

Oil and Grease

Black Lagoon Contamination • 115,000 cy of contaminated sediment removed

300,000

360Mercury

160PCBs

AMOUNT (in lbs.)CONTAMINANT

Page 37: Black Lagoon Site - US EPA · 2016-02-20 · Black Lagoon Project Costs • Total cost approximately $9.3 million $6 million Legacy Act funds $3.3 Clean Michigan Initiative funds

••

Black Lagoon Project Costs• Total cost approximately $9.3 million

$6 million Legacy Act funds $3.3 Clean Michigan Initiative funds

(The Clean Michigan Initiative is a(The Clean Michigan Initiative is a $675 million bond used to clean up,$675 million bond used to clean up,

protect and enhance Michigan’sprotect and enhance Michigan’s environmental quality and naturalenvironmental quality and natural

resources).resources).

Page 38: Black Lagoon Site - US EPA · 2016-02-20 · Black Lagoon Project Costs • Total cost approximately $9.3 million $6 million Legacy Act funds $3.3 Clean Michigan Initiative funds

M

– M

– Michelle Jaster (– [email protected]

Black Lagoon Site Contacts

• U.S. EPA Region V GLNPO– arc Tuchman (312) 353-1369

• MDEQ ike Alexander (517) 335-4189

• U.S. EPA Region V Superfund Division734) 692-7683

Page 39: Black Lagoon Site - US EPA · 2016-02-20 · Black Lagoon Project Costs • Total cost approximately $9.3 million $6 million Legacy Act funds $3.3 Clean Michigan Initiative funds

Human Error or Equipment Failure?

Page 40: Black Lagoon Site - US EPA · 2016-02-20 · Black Lagoon Project Costs • Total cost approximately $9.3 million $6 million Legacy Act funds $3.3 Clean Michigan Initiative funds

The Resulting Multifaceted Response