Biomass gasification at IISc

15
Biomass gasification at IISc Technology Development, Scale-up & Technology Transfer Indian Institute of Science Bangalore Content Background Studies – Fundamental & Lab/Field Trials Technology Development Challenges in Scaling-up Technology Transfer Field Installations Background Gasification research commenced in 1984 Over 350 Man-Years of R&D effort Evolved State-of-the art technology Undergone critical third party evaluation – by various groups Technology commercialized ~ four years Studies – Fundamental & Lab/Field Trials Biomass fuel - size General philosophy: To use as-is- where is condition fuel or use existing fuel processing equipment.

Transcript of Biomass gasification at IISc

Page 1: Biomass gasification at IISc

BBiioommaassss ggaassiiffiiccaattiioonn aatt IIIISScc

TTeecchhnnoollooggyy DDeevveellooppmmeenntt,, SSccaallee--uupp && TTeecchhnnoollooggyy TTrraannssffeerr

IInnddiiaann IInnssttiittuuttee ooff SScciieennccee

BBaannggaalloorree

Content Background Studies – Fundamental & Lab/Field Trials Technology Development Challenges in Scaling-up Technology Transfer Field Installations Background Gasification research commenced in 1984

Over 350 Man-Years of R&D effort

Evolved State-of-the art technology

Undergone critical third party evaluation – by various groups

Technology commercialized ~ four years Studies – Fundamental & Lab/Field Trials Biomass fuel - size General philosophy: To use as-is- where is condition fuel or use existing fuel processing equipment.

Page 2: Biomass gasification at IISc

Chipper provide small size (flakes) - Has serious implications on the process t ~do

2 – particle size influences conversion time (both pyrolysis and char conversion) - implications on gas quality

Moisture content Higher the moisture content lower the thermodynamic efficiency

- lower the cal value and higher the hot gas contamination

3

3.5

4

4.5

5

10 15 20 25 30 35 40Moisture (%) in Biomass

LC

V 3

Casurina

Pine

Pine + Charcoal

Branches

Green

Rice Husk

Page 3: Biomass gasification at IISc

Ash content Ash fusion issues Lower gas conversion efficiency

0

500

1000

1500

2000

2500

0% 10% 20% 30% 40%

Moisture content in biomass

Tar,

mg/

Ncu

m

IISc GasifierOther Gasifiers

Technology DevelopmentTechnology Development

Page 4: Biomass gasification at IISc

• Open Top, twin air entry, re-burn reactor conceptualized

• Reactor

ability to handle agro residues

To handle corrosive environment

scalability

simple for operation

ability to handle varying load conditions

• Gas Processing

ability to handle the gas quality to meet engine/high quality thermal application

ability to remove dry material and reduce the contamination in the cooling water Scalability

• Water treatment

To reuse the water

Meet the local environmental standards

Page 5: Biomass gasification at IISc

Choice of material High temperature zones – insulation, high temperature and high alumina material to take care of temperature and chemical corrosion. Gas contact zones – use stainless steel / non metallic Performance Fuel - Agro residues and briquettes with ash content less than 5 % In house consumption - 8 – 10 % Gas composition - CO: 20 + 1%; CH4 : 3 + 1%, H2 : 20 + 1%, CO2 : 12 + 1% and rest N2. Gasification efficiency - ~ 80 % Clean gas – < 1 ppm on T and P The Package Multi-fuel option including agro residue Capacity: 5 to 1000 kWe Ultra clean gas ~ for turbo charged engines Also, for high quality thermal applications Dual fuel engine - ~ 75 % diesel savings (operating experience >50000 hrs) Gas engine - operating experience (5000 hrs) Also, High pressure gasification for micro turbine Wish list as perceived by a user

• To be able to use all types of fuel; nearly as is where is condition implying multi-fuel option.

- More particular in the developing countries context – use

of agro residue important.

Page 6: Biomass gasification at IISc

- Developed countries generally centralized wood processing and hence woody biomass is available.

• To be able to operate like a liquid fuel system; simplicity in

design technology to be simple, automation.

• Lower down time - reliability of the system; service support.

• Economic viability; return on investment- guaranteed performance.

• Environmentally benign - low on pollutants and emissions

• Should see a system of comparable application/capacity of what

is being intended to be bought; not a guinea pig - no risk option.

• Fuel source to be identified - a necessity for substituting large scale fossil fuel technology package.

Challenges in Scaling-up

- Achieving uniform distribution A feature easily achieved in an open top design

Air Nozzle Location & Numbers Question on Air Nozzle material

- Reducing in-plant power consumption

Vapor absorption chiller ~ waste heat engine

- Biomass processing & conditioning Large throughput cutter (to handle various weeds) Drying ~ 15% moisture (using engine exhaust and heat from

gasifier system) Briquetting agro wastes

- Wash water treatment

For recirculation Zero liquid discharge

Technology Transfer

- Internationally patented technology

Page 7: Biomass gasification at IISc

- One of its kind in Technology transfer – South to North

- Currently 4 in India, 1 each in Europe & Japan

- Addressing large potential in other parts of Asia, Africa and Latin America on project basis

- Open for Technology transfer to other parts of the world

Field Installations

Total installed capacity

Thermal : 12 MWth

Power : 4 MWe

Over 100,000 hours of operation

Saving 18 -20 Tons of fossil fuel/day

4 Licensees in India and 2 in overseas

Page 8: Biomass gasification at IISc

1 MWe Grid Linked – Arashi Hi-tech bio power system

GASIFIER PRIME MOVER

Overall efficiency > 28%

EMISSION ~ Qualifies for CDM Benefits

EFFLUENT TREATMENT

GRID LINKAGE

DRIER

PROCESSOR

FEED STOCK

Flue gas

Producer gas

Electricity @ 440 V

440 V to 11 kV

Recycled water POWER EXPORT

Performance

Fuel used – coconut shells and prosopsis juliflora

Hours of operation – 6800

Units generated – 4.0 million units

Fossil fuel used – diesel, ldo, heavy oil (60 – 100 ml /kWh)

Biomass - 0.72 ± 0.04 kg/kWh

Overall conversion efficiency ~ 28 %

By product – activated charcoal (iodine no. ~ 500 – 650)

Page 9: Biomass gasification at IISc

Lessons learnt

Agro residue is possible to be used as feed material with gas quality acceptable for turbo charged engines.

-Long duration operation possible

-Fuel flexibility is important

-Gas engine an economic option

1.2 MWth - Heat treatment –Tahafet

• Eight furnaces and temperatures vary from 600 C to 1000 C.

• Each furnace is fitted with two burners having air to fuel ratio

control and also a PID controller to oversee the operations. The industry operates on three shifts for about 6 days in a week.

• Typical LDO consumption 1500-2000 Liters/day.

• 300-kg/hr gasifier capacity installed.

• All the eight furnaces are connected to the gasifier using

WESMAN make dual-fuel burner with ratiotrol based A/F control and PID monitor servo controller. The temperatures in the individual furnaces are maintained independently.

• With 8 furnaces connected presently to gasifier saving is about

2000 liters/day.

• Average fuel consumed per day 5.2 T of coconut shells, wood chips

Performance

- Total hours of run 21000 - Total fuel saved 1680 kilo lts

For the month of August 2002

-Hours of run : 470

Page 10: Biomass gasification at IISc

-Total biomass used :109.4 Tons -Total LDO saved : 30000 lts -Savings per day : 320 USD

Performance of the system at Tahafet for the month of August

-1

4

9

14

19

24

1/8/

2001

3/8/

2001

5/8/

2001

7/8/

2001

9/8/

200

11/8

/200

1

13/8

/200

1

15/8

/200

1

17/8

/200

1

19/8

/200

1

21/8

/200

1

23/8

/200

1

25/8

/200

1

27/8

/200

1

29/8

/200

1

31/8

/200

1Hou

rs o

f ope

ratio

n pe

r day

Xylowatt SA

Xylowatt Ltd was founded in February 2000 in Switzerland.

taking back the activities of the CCC (R&D group).

- 5 year of R&D with the support of the Federal

Office Energy

-Industrial prototype 60 kWe tested during 2’000 hours

Integrated into an industrial group

-Active since more than 30 years in CHPP with engine

-with 200 employees in Switzerland and Germany

Set up a demonstration CHPP in 2002

Page 11: Biomass gasification at IISc

Installation in Bule

Page 12: Biomass gasification at IISc

Performance

Wood :54 kg/h, 20 % moisture Ash:1 kg/h (1.5%) Water - Sludge : 14 litre/h - 0.2 kg/h Cal value: 130 Nm3/h, LHV 4.9 MJ/Nm3 Heat – power : 108 kWth (48%) – 50 kWe (22%)

Exhaust gas emission

Page 13: Biomass gasification at IISc

The Sch tic o for gas turbine applicationema f the high pressure gasification system

GAS TURBINE

T2

T4T5

REACTOR

COOLER DUMP COOLER DUMPSUCTIO

T3

N BURNER

HP BURNER

SUCTION BLOWER

HE

AT E

XC

HA

NG

ER

SCREW

T1

T1 = LOCK HOPPER TEMPERATURET2,T3,T4,T5 = REACTOR WALL TEMPERATURET6,T7,T8 = GAS TEMPERATUREP1,P2,P3,P4,P5 = PRESSURESGA = GAS ANALYSIS

T6

CYCLONE

DIR

EC

T C

OO

LE

R

CH

ILL

ER

SC

RU

BB

ER

T7

GAS FLOW

GAS FLOW

GAS FLOW

GA

T8P2

P3

P1

P5

Page 14: Biomass gasification at IISc

Adaptation of the Combustor

Numerical computations to check availability of the right mixture ratio near the igniter.

Stand alone mode experiments to test the combustor.

Experiments on the gas turbine.

Performance

Gas turbine was run at 12 kW load.

Ability to ignite the gas as a liquid fuel system – no changes in the ignition system.

SFC very high (low efficiency).

table for turbine application.

Gas quality accep

Page 15: Biomass gasification at IISc

Overall Summary ia and 2

overseas

Over 35 plants of various capacity

Total system packaging as IPP

-Fuel preparation system, gasification system, ash handling system, water treatment, power generation, power evacuation system.

Total of 100,000 hours of operation for various

applications.

Over 60000 hours of operation on 6 systems for power generation with average diesel savings in the range of 70 – 75 % and thermal systems of 200 – 5000 kWth.

-Fossil fuel 20000 lts per day

Power generation using gas engine at 120 kW capacity

(3000 hrs) in industrial application

Technology transferred to 4 manufacturers in Ind