BIM project execution

83
BIM Project Execution BIM Project Execution Stephen AU Stephen AU Oct. 17, 2013 Lecture Class BRE398: Building Information Modeling BRE398: Building Information Modeling

Transcript of BIM project execution

Page 1: BIM project execution

BIM Project ExecutionBIM Project Execution

Stephen AUStephen AU

Oct. 17, 2013

Lecture Class BRE398: Building Information Modeling

BRE398: Building Information Modeling

Page 2: BIM project execution

TopicsTopics

BIM Project Execution PlanProject Organization Structurej gBIM Data Model StructureP j t I l t ti P & C i tiProject Implementation Process & CommunicationQuality & Risk Management

BRE398: Building Information Modeling

Page 3: BIM project execution

Lecture Objectives and ResultsLecture Objectives and Results

ObjectivesTo understand how BIM project is implemented and its challenges

QuestionHow to execute a successful BIM project?

BRE398: Building Information Modeling

Page 4: BIM project execution

TopicsTopics

BIM Project Execution PlanProject Organization Structurej gBIM Data Model StructureP j t I l t ti P & C i tiProject Implementation Process & CommunicationQuality & Risk Management

BRE398: Building Information Modeling

Page 5: BIM project execution

BIM Business ModelBIM Business Model

lProperty DeveloperEmploy an independent BIM consultant to create the As-Design As Construct and As Build BIM model for design & Design, As-Construct and As-Build BIM model for design & construction verification

Architect / Structure / MEP ConsultantArchitect / Structure / MEP ConsultantUse in house BIM team to build the As-Design model for design verification

Main Contractor / Specialised Sub-ContractorEither employ an independent BIM consultant or by in house BIM team to do the As-Construction BIM model to reduce the construction errors and delivery time

BRE398: Building Information Modeling

Page 6: BIM project execution

BIM Benefits vs LeadershipBIM Benefits vs Leadership

Ref: http://changeagents.blogs.com/thinkspace/

BRE398: Building Information Modeling

e ttp //c a geage ts b ogs co /t space/

Page 7: BIM project execution

Objective of BIM Project Execution Plan

To successfully implement Building Information Modelling (BIM) on a project, the project team has to develop a

MBIM Project Execution Plan. The BIM Project Execution Plan defines uses for BIM on the building construction project from design, engineering, construction to facility management, along with a collaboration process for executing BIM on the project.The goal of the BIM Project Execution Plan is to manage and control the quality of the BIM deliverables

BRE398: Building Information Modeling

Page 8: BIM project execution

BIM Project Execution Plan Blue PrintBIM Project Execution Plan Blue Print

Ref: http://changeagents.blogs.com/thinkspace/

Page 9: BIM project execution

Quality for BIM ProjectQuality for BIM Project

Q lit ti t ’ ( d) i t f l Quality means meeting customers’ (agreed) requirements, formal and informal, at lowest cost, first time every time. To success, we should understand the current and future customer

d h ld d d needs, should meet customer requirements and strive to exceed customer expectations. We should create and maintain an internal environment in which people can become fully involved in achieving the project’s objectives. A desired result is achieved more efficiently when activities and related resources are managed as a process. So identifying, understanding and managing interrelated processes as a system are required. Further continual improvement of the overall performance should be a permanent objective of the organization.

BRE398: Building Information Modeling

Page 10: BIM project execution

PDCAPDCA

PLAN l d f b dPLAN: Develop product specifications based on customer needs. Develop performance measures and the means to check themthe means to check them.DO: Design the processes that will produce the products and services Work the processes and collect products and services. Work the processes and collect quality, service, and management data.CHECK: Develop variances of actual performance to CHECK: Develop variances of actual performance to plan and develop improvement initiatives to correct deficiencies.ACT: Implement the process improvement program and incorporate new technologies as appropriate.

BRE398: Building Information Modeling

Page 11: BIM project execution

Project ScopeProject Scope

Type of buildingDesign briefingg gAreasTi t d liTime to deliveryBudgetStakeholders…..…..

BRE398: Building Information Modeling

Page 12: BIM project execution

BIM Project MissionBIM Project Mission

D fi th j t t t t d if h th Define the project statement and specify how the implementation of BIM technologies and processes enhances that performance of building construction project.

Project Mission Statement

e.g. To minimize the construction risk due to the 1st mega project building g g p j gin China, that the developer project team has to collaborate with local construction team.

BIM Enhancement Mission

F A d i BIM t t C t ti BIM ith ite.g. From As-design BIM propagate to Construction BIM with on site engineer support

BRE398: Building Information Modeling

Page 13: BIM project execution

Project ObjectivesProject Objectives

BIM Goal Measureable Objective

Achieved If(measurable KPI)

Projected Timeframe

I i ibilit f d i f ll t k h ld P d hit t BIM Th d l i d b th M h 2010Improve visibility of design for all stakeholders Produce architecture BIM model for DC and BP submission

The model is approved by the architect and developer

March 2010 –January 2011

Prepare BIM model to be transferred between project stakeholders tominimize duplication of effort

Conduct conflict resolution analysis during design to eliminate designclashes, resulting in a well-coordinated model prior to construction

Utilize model for 3D Design Reviews to assist with equipmentclearances and owner design decisionsg

Conduct coordination review of key systems with constructionmanager and specialty trade contractors during construction

Develop an accurate Record Model and As-Built Model to be used forintegration into facility management system(s) within the traditionalintegration into facility management system(s) within the traditionalstandard of care provisions that govern the design and constructionof the project. Model should include and/or link all approvedsubmittals, shop drawings, O&M Manuals, building control drawings,construction photos, inspection reports, and commissioning data asrequired

BRE398: Building Information ModelingPrepare accurate design documents and construction documentsderived from the model to establish basis of design within thetraditional standard of care provisions that govern the design of theproject

Page 14: BIM project execution

Purposes of the BIM ModelPurposes of the BIM Model

E bli h i l i i f i i l hi l d Establish a single primary repository for critical architectural geometry and informationFacilitate rapid design changes that are automatically reflected in the ancillary ddocumentsProvide automatically coordinated drawings to the architectsFacilitate full 3D modeling of structure by the structural engineerg y gEliminate conflicts that typically arise with the integration of MEPAllow automated reporting of certain quantities for the QSProvide an easily accessible source of accurate information for tenderingProvide a constructionally accurate rendering modelAllow contractors to visualize construction sequencing and anticipate possible Allow contractors to visualize construction sequencing and anticipate possible delaysBecome the basis for facilities management work after construction

BRE398: Building Information Modeling

Page 15: BIM project execution

Purposes of the BIM ModelPurposes of the BIM Model

B tt d i t l th h b tt t di ti & Better design control through better team coordination & collaborationSingle database of integrated informationSingle database of integrated informationProject seen as process ecosystemRisk reduction (lack of claims ) Reduction of Change Orders on site (lower rate on projects for non-scope items)C T ki (b i i d i h d i Cost Tracking (better estimating during the design process –quantities)Better Coordination of 2D Drawings generated from Better Coordination of 2D Drawings generated from resolved 3D Model3D Information exchange with consultants and fabricators

BRE398: Building Information Modeling

Page 16: BIM project execution

BIM DeliverablesBIM Deliverables

BRE398: Building Information Modeling

Page 17: BIM project execution

Models, Content and Authoring ToolsModels, Content and Authoring Tools

Model Name Model Content Project Stage Authoring Tool

Architectural Massing Model

Building massing studies with indicative dimensions, area, volume, location, and orientation.

Conceptual Design Autodesk® Revit® Architecture RhinoCatia V5 R20

Architectural Model As per Singapore BIM Guide Appendix B.

Preliminary Design and Detailed Design

Autodesk® Revit® Architecture Catia V5 R20

Coordination Model Architectural, structural, and MEP components of main

Detailed Design Autodesk® Navisworks ManageCatia 3dxml viewer and 3D PDFp

building.

Civil Model

Structural Model

MEP Model

Curtain Wall/ Facade

Interior Design

Construction Model

A B ilt M d l

BRE398: Building Information Modeling

As-Built Model

Page 18: BIM project execution

Analysis Services and Tools (1/2)Analysis Services and Tools (1/2)Analysis Services Analysis Reports Project

Stages Analysis Tool

Design Review Review design development / progress and require feedback based Design Autodesk® Revit®Design Review g p p g qon design Design Architecture, Catia V5

Design Co-ordination Determine and resolve major system design conflicts prior to construction Design

Autodesk® NavisworksManage, Catia 3dxml viewer and 3D PDF

EnergyConduct energy assessments for building design, inspect building energy standard compatibility, and optimize proposed design to reduce facility lifecycle costs

PlanningDesign

Structural Analyze model based on structural specifications Construction Autodesk® Revit®Architecture Catia V5Architecture, Catia V5

Interference Checking

• A “hard” interference is where the geometry of the objects in question actually overlaps

• A “soft” interference is where it is a predefined clearance between objects that is in question

Design and construction

Autodesk® Revit®Architecture, Catia V5

• A “programmed” interference is where the software being used allows the user to pre-program variable interference requirements based on a set of rules and object types.

Spatial AnalysisAssess design performance in regards to spatial requirements ieanalyse space and understand complexity of space standards and

Design and construction

Autodesk® NavisworksManage Catia 3dxmlSpatial Analysis analyse space and understand complexity of space standards and

regulations.construction Manage, Catia 3dxml

viewer and 3D PDF

Scheduling/4D Linking 3D model elements with a construction programme enabling real time visualisation of build sequence.

Autodesk® Revit®Architecture, Catia V5

Generate accurate quantity take-offs and cost estimates. ProvidingCost Analysis/5D

Generate accurate quantity take offs and cost estimates. Providing ‘what if’ analysis capabilities to assess modifications to design or programme.

Page 19: BIM project execution

Analysis Services and Tools (2/2)Analysis Services and Tools (2/2)Model Name Model Content Project Stage Authoring Tool

Daylight/Lighting Analyze lighting systems based on design specifications PlanningDesign

3D AnimationUse of visualisation technologies to develop high quality renders and animations. Provide life-like experience and show the major building equipment space clearance reservations

Design Cortona3D

equipment space clearance reservations.

Knowledge base engineering

Analyze spatial program and requirements and accurately assess design performance in regard to space standards and regulations

PlanningDesign

Safety Analyse the safety measure and risk potential on the site work environment

Construction Cortona3D

Construction Method Statement

Demonstrate the working sequences before the physical work start Construction Cortona3D

Site AnalysisEvaluate site to determine if site meets the required criteria according to project requirements, technical factors and/or financial factors

Planning

Integration of 3D models with Rapid Prototyping processes to createRapid Prototyping

Integration of 3D models with Rapid Prototyping processes to create and test physical models under controlled conditions eg wind tunnel testing.

Digital M f t i

Considering opportunities for future fabrication, i.e. communicating information in a format that enables prefabrication of objects directly

Manufacturing from a 3D model.

Page 20: BIM project execution

BIM Maturity ModelBIM Maturity Model

Ref: NBIMS CMM Chart (download the MS Excel file from http://bit ly/NBIMS)Ref: NBIMS CMM Chart (download the MS Excel file from http://bit.ly/NBIMS) -See more at: http://www.bimthinkspace.com/2009/09/episode-12-bim-performance-measurement.html#.dpuf

Page 21: BIM project execution

Project ScheduleProject Schedule

Th h d l t b t h d ith th d i t ti The schedule must be matched with the design construction master plan and be flexible.

W k d i ti

Design stage Construction stage

2013 2014 2015 2016 2017 2018 2019

5 6 7 8 9 10 11 12 1 4 7 10 1 4 7 10 1 4 7 10 1 4 7 10 1 4 7 10 1 4 7 10

Modeling works

Underground

B2

Works description 2013 2014 2015 2016 2017 2018 2019

B2

B1

G/F

1/F

2/F2/F

3/F

5/F

6/F

Tower 3-11 (high-rise building)Tower 3 11 (high rise building)

Tower L1-L9 (low-rise building)

Clash review and design review

Site co-ordination

As-built model

BRE398: Building Information Modeling

Page 22: BIM project execution

Resources PlanningResources Planning

Personal Productivity Unit (PPU)Time to build one floor of XX sq. m BIM model for structural design. Architect design, MEP design etc.

Time to output the deliverables to client (BT)p ( )No. of Modeler (NM) required for a required floor area for a specific discipline say: Structural Design area for a specific discipline, say: Structural Design is

NM = BT / PPUNM = BT / PPU

BRE398: Building Information Modeling

Page 23: BIM project execution

TopicsTopics

BIM Project Execution PlanProject Organization Structurej gBIM Data Model StructureP j t I l t ti P & C i tiProject Implementation Process & CommunicationQuality & Risk Management

BRE398: Building Information Modeling

Page 24: BIM project execution

Participation PartiesParticipation Parties

Properties OwnerArchitectStructural EngineeringMEP C lt tMEP ConsultantsQuantity SurveyorInterior DesignLocal Design Institute (for China Project)Local Design Institute (for China Project)……

BRE398: Building Information Modeling

Page 25: BIM project execution

BIM Project Team OrganizationDeveloper BIM Consultant

BIM Project Team OrganizationDeveloper BIM Consultant

• ExperienceC dibl

• Project Management• Experience with

ojec

t ge

men

t

• Credible• Co-ordination with MTECH

Team Project Manager

Experience with Industrial application

• Facilitates co-ordination with Client Team

Client Manager

Technical

Pro

Man

ag Project Manager

Technical Manager /

Project Leader

Key FunctionalTechnical

Architectural 3D Modeler

• Design errors checking

• 3D Modeling Design change updateKey Functional

RepsKey Functional RepsKey Consultant

Reps

Technical TeamTechnical

TeamClient Project Team

ojec

t Tea

m Structure 3D Modeler

MEP 3D Modeler

• Design change update• Reporting• Deliverables

demonstration• Support of client

Pro • Current project

knowledge• Respected by peers

• Functional• Respected by peers• Empowered

I/T Infrastructure Support

Page 26: BIM project execution

Project Team StructureProject Team StructureBIM Consultant Client Manager

Owner Project Director

Owner Project Manager

BIM Project Manager

Project Leaders /Model Manager

BIM Methodology & Process Consultant Design consultants

ArchitectStructure/Model Manager

TrainerStructure MEPLocal Design InstituteOther design consultants…

Design Team AModoler 1, Modoler 2Modoler 3, Modoler 4 Modoler 5 , Modoler 6

BIM Team Leader Lead Designer A

TEAM A

Remark: The team can be separated by building zone and /or by

Design Team BModoler 1, Modoler 2Modoler 3, Modoler 4 BIM Team Leader Lead Designer B

TEAM Bdisciplines: arch, structure, civil, HVAC, drainage, electrical, fire,….

Modoler 5 , Modoler 6

Page 27: BIM project execution

Project Team RelationshipProject Team RelationshipArchitect

Developer

3DMaster

Main ConstructorInboxOutbox

ModelStructure ConsultantStructure sub-

contractor•Participants

ibl f

MEP ConsultantMullion sub-contractor

responsible for providing geometry in 2D for BIM team to build the BIM model

Other Consultants

BIM Consultants

BRE398: Building Information Modeling

Other sub-contractors

Page 28: BIM project execution

Role of BIM Support Team

Methodology & Process consultantProject Manager

Role of BIM Support Team

Methodology & Process consultant• Technical analysis & development• Define modeling methodology• Best practices development

Project Manager• External communication & management • 3D modeling management• Monitor overall process & deliverables

• Software training to the BIM modeler and users

• Advanced training and technical support• MTECH resource planning

BIM ModelersTeam Leader• Project schedule / resource planning &

monitoring• Architectural & structural design analysis

• BIM model creation by disciplines• General Issue report• Checking the model integrity

Architectural & structural design analysis• Define & manage outputs of BIM e.g.

Quantitative export, Design co-ordination, etc. • Daily technical support to Arch / Structural

modeling team

BIM Model co-ordinator• Monitoring overall deliverables of modeling

teamAnalysis of BIM modelmodeling team • Analysis of BIM model

• Quality control for the BIM Model• Consolidate and release the Issue report to

client

BRE398: Building Information Modeling

Page 29: BIM project execution

Skill ManagementSkill Management

I di t j t t b ’ t BIM kill b li ti l Indicate project team members’ current BIM skills by listing personnel type, number of employees of each type, and average skill level

Personnel Type No. of Staff Average BIM Skill / Knowledge Levely g g

Project Director 1 Novice

BIM Manager 1 Average

Project Leader 2 Average

Modeller 1 Expert in Revit5 Expert in CATIA Architecture

Expert in CATIA MEP

Rendering Engineer 2 Expert in 3dsmaxE t i Vi t lExpert in VirtoolsExpert in Dreamweaver

3D Simulation Engineer 2 Expert in Cortona3D

BRE398: Building Information Modeling

Page 30: BIM project execution

Software Resources PlanningSoftware Resources Planning

BIM Software3D2D

Rendering SoftwareRendering SoftwareProject Management SoftwareData Management & Process control SoftwareMS Office…..

BRE398: Building Information Modeling2013/10/17MTECH..............Confidential

Page 31: BIM project execution

Hardware Resources PlanningHardware Resources Planning

Design OfficeGraphic WorkstationpPrinterD t S d B kData Server and BackupNetwork

BRE398: Building Information Modeling

Page 32: BIM project execution

TopicsTopics

BIM Project Execution PlanProject Organization Structurej gBIM Data Model StructureP j t I l t ti P & C i tiProject Implementation Process & CommunicationQuality & Risk Management

BRE398: Building Information Modeling

Page 33: BIM project execution

Model and Database StructureModel and Database Structure

P j N i C iProject Naming ConventionsFile Naming Conventions

Field 1_Field 2_Field 3_Field 4_Field 5.xxxxField 1: Project code, Field 2: Zone, Field 3: Trade, Field 4: Floor, Field 5: Type of servicesField 5: Type of servicesExample: ABC_POD_MEP_1F_VAC

Numbering ConventionsgPOD : Podium, TOW: Tower, FLR: Architectural, STR: Structural, MUL: Curtain wall, MEP: E&M, VAC: Air

di i i d R f i i ELE El i l FSV Fi conditioning and Refrigeration, ELE: Electrical, FSV: Fire services, PLM: Plumbing, DRN: Drainage, TG: Town Gas

BRE398: Building Information Modeling

Page 34: BIM project execution

Model StructureModel Structure

The success of a BIM enabled project delivery process is highly dependent upon the level at The success of a BIM enabled project delivery process is highly dependent upon the level at which the entire project team can communicate and work collaboratively for the duration of the project.For buildings with a large footprint or multiple floors, the project team may split the model into

l ( fl ) ith th di t dseveral zones (or floors) with the corresponding tradesAll trades will be modeled at the correct elevationAll elements of the building must be represented in only one file and should be modeled by their specific trade. (For example, the architectural model provided for 3D Coordination p ( p , pshould not include any of the structural elements contained in the structural model. Lights should be modeled by the electrical engineer, not the architect)All 3D model files must strip extraneous 2D and/or 3D elements from the model before submission for clash detectionsubmission for clash detectionThe architectural ceilings should contain information of lights, diffuser, speaker, CCTV, etc. as required by design. (For example, lights are to be centered on a grid with proper spacing)All models should include separate 3D representations of required clearances and/or access

i f i li h l h d bl Th requirements for equipment access, light clearances, overhead cable tray access, etc. These clearance/access models should be in a separate layer(s)/level(s) per each trade and labeled as such

BRE398: Building Information Modeling

Page 35: BIM project execution

Model Element Requirements by Discipline

S /C MOSITE/CIVIL MODELARCHITECTURAL MODELSTRUCTURAL MODELMEP MODEL

Mechanical ModelElectrical ModelPlumbing ModelFire Protection ModelDrainage Modeletc

BRE398: Building Information Modeling

Page 36: BIM project execution

Level of DevelopmentLevel of Development

LOD 100 The model equivalent of conceptual design the model would consist of overall LOD 100 – The model equivalent of conceptual design, the model would consist of overall building massing and the downstream users are authorized to perform whole building types of analysis (volume, building orientation, cost per square foot, etc) LOD 200 – Model that includes basic elements including windows walls and doors. This level of

d li i f i li ti d b i l i d i i il t th h ti d i modeling is for visualization and basic energy analysis and is similar to the schematic design or design development. It consists of generalized systems or assemblies with approximate quantities, size, shape, location, and orientation. LOD 300 – Model elements are suitable for construction and are the equivalent of traditional

t ti d t d h d i Thi d l l l ld b it bl f l i d construction documents and shop drawings. This model level would be suitable for analysis and simulation of detailed elements and systems. LOD 400 – Model level of development considered suitable for fabrication and assembly. This model will include all as-constructed details for the CLIENT’s use to manage the facility. This is h i l f b il d i i h di i l i the equivalent of as-built drawings in the traditional construction process.

LOD 500 – The final level of detail represents the project as it has been constructed including property assets itemized with key parameters required by the CLIENT added to the model. All as-built record drawings and documentation at the time of turnover must be provided in the CAD f l f El l d d h d l b d l d b h h 2D d 3D CAD native file format. Elements included in the model must be detailed in both the 2D and 3D documentation for CLIENT use. Elements must be clearly marked or tagged and visual in both the 2D and 3D documentation.

BRE398: Building Information Modeling

Page 37: BIM project execution

Example of LODExample of LOD

Structure beam, column, slab and staircase Curtain wall/window wall

Chilled water pump and valveFan coil unit, air duct and chilled water pipe

Page 38: BIM project execution

Best Practice DevelopmentBest Practice Development38

f d l / f l f l d lDefining model / file organization for large model assemblyS d di i d li h d l f h / & Standardizing modeling methodology of arch / stru. & MEP modeling

Predefined modeling procedure and skill set > ensure Predefined modeling procedure and skill set -> ensure stability and quality of model assembly

Building up feature / knowledge driven modeling / Building up feature / knowledge driven modeling / catalog for reuse

Structural (beams, columns)( , )Architectural (doors, staircase, etc)MEP (VAV boxs, sprinklers)

BRE398: Building Information Modeling

Page 39: BIM project execution

TopicsTopics

BIM Project Execution PlanProject Organization Structurej gBIM Data Model StructureP j t I l t ti P & C i tiProject Implementation Process & CommunicationQuality & Risk Management

BRE398: Building Information Modeling

Page 40: BIM project execution

Co-ordination of BIM to Design Process

3D d l t d i

Revise in Design

3D model acts as design verification tools for issued 2D drawing I f d

Design consultantsnext design DesignInformation extracted

from 3D model feedbacks to improve d i d l t

Design drawings

DeveloperLogging / Issue

design development Developer forms the central point of co-

di i d i drawingsReportordination and monitors

& manages the distribution / transfer of design information BIM Modeling team

BIM model

design information

BRE398: Building Information Modeling

Page 41: BIM project execution

Collaboration: Conceptual ViewCollaboration: Conceptual View

Project Manager

ArchitectWork Model W

o

MEP

ork Subm

is

WorkBIM Master

Model

sions

Work ModelQS

Issued Master

ArchiveMaster

Update

StructuralWork Model

MasterModel

Model

Review & Approval

QSWork

3D CoordinatorInbox

Architect

Approval Work Model

Page 42: BIM project execution

Operation FlowOperation FlowBIM Model & Reportsode & epo s

OwnerArchitect

Structural Eng.

Subm

MEP Eng.

it Draw

BIMTeam

Others

wings

MTECH ENGINEERING CO LTD - Page

Page 43: BIM project execution

Project Design PhasingMaster Layout Plan Submission Drawing

Design consultants BIM Modeling Team

Project Design Phasing

Individual Building Submission

y

Drawing

Extended Preliminary Design Submission Drawing

Arch. dwg. Structural dwg. MEP dwg. BIM ModelingModeling

Construction Drawing Submission

Drawing

g

Tendering1st Issue BIM Model

Consent & ConstructionNth Issue BIM Model

Page 44: BIM project execution

Typical BIM Modeling Workflow Input of architectural / structural / MEP dwg.

Typical BIM Modeling Workflow

Drawing analysis and define modeling content

Revised design

Define modeling methodology(to comply output requirement of BIM) Design co-ordination

Modeling schedule / resource planning / task assignment to modeling team

M d li / i d d liIssue report to

Inform consultant

Modeling / revised modeling of BIM Identify

modeling errorsIdentify design errors

Developer / Consultants

Review and check BIM Model

Define scope / process of BIM output with consultants

design errors

e.g. quantity & attribute take-off, 2D drawing production

Export BIM relevant information

Page 45: BIM project execution

Coordination and Conflict ResolutionCoordination and Conflict Resolution

When conflicts are discovered in the model, regardless of project phase or LOD, the discovering party shall promptly notify the Model Element Author. Upon notification, the Model Element Author shall act promptly to mitigate the conflict. All project stakeholders and responsible parties must post their models to the designated shared server on a weekly basis as specified.y p

BRE398: Building Information Modeling

Page 46: BIM project execution

Design Collaboration (1/3)Design Collaboration (1/3)Design error checking by clash detection among building components

Cl hArch. dwg.

Clash detect

Structural dwg.

MEP dwg.

Clash detection and reporting

3D

2D dwg

modeling

Modeler CATIA V5 BIM

2D dwg. cleaning

Page 47: BIM project execution

3D Co-ordinated M&E Model3D Co ordinated M&E ModelDirect and automatic detection of design errorDirect and automatic detection of design errorDirect and automatic detection of design errorDirect and automatic detection of design error

Page 48: BIM project execution

Design Collaboration (2/3)Design Collaboration (2/3)Design review discussing design revision and revised modeling

Design revision is followed to eliminateDesign revision is followed to eliminate detected errors in CATIA V5 BIM

Design review and collaboration amongDesign review and collaboration among architect, structural engineer and MEP engineer

Design & 3D Modeling

Design Co-ordinate ti

Revised 3D d li

Simplified workflow of design collaboration

Modeling error checking

meeting modeling

Page 49: BIM project execution

Design Collaboration (3/3)Design Collaboration (3/3)

D t t d t l hi d t d i t I Detected system clashing documented into Issue Report by XML or PDF format for releasing purposepurpose

Summary of detected clashes Detail report of detected clashes

BRE398: Building Information Modeling

Page 50: BIM project execution

Issue ReportIssue ReportReport of design errors was logged and meetings

h ld li / d i l / were held among clients / design consultants / support team for design revision

Page 51: BIM project execution

Co-ordination Meeting ProceduresCo ordination Meeting Procedures

MEETING TYPE PROJECT STAGE FREQUENCY PARTICIPANTS LOCATION

BIM Requirements Kick-off Planning Once

ClientBIM Management Staff

C lt t TTBDKick off Consultant Team

BIM Plan Review ALL MonthlyClient

BIM Management StaffConsultant Team

TBD

D i D t3D Design Coordination

Design DocumentsConstruction Documents

Bi-weekly BIM Project ManagerConsultant Team TBD

M h i l S Design Documents ClientBIM P j t MMechanical Space

Review

Design DocumentsConstruction Documents

TBD BIM Project ManagerConsultant Team

Construction Team

TBD

Model C i i i

Construction D t 75% TBD BIM M t St ff TBDCommissioning

ChecksDocuments, 75%

Submittal ApprovalTBD BIM Management Staff TBD

3D Construction Coordination Construction Weekly BIM Project Manager

Construction Team TBD

BRE398: Building Information Modeling

Page 52: BIM project execution

BIM Model PresentationBIM Model Presentation

Th h ti ftThrough native softwareBy CAD native ViewerB 3rd P t ViBy 3rd Party Viewers

3D Adobehttp://get.adobe.com/reader/http://get.adobe.com/reader/

VRMLhttp://www.cortona3d.com/cortona3d viewersna3d-viewers

3DXMLhttp//www.3ds.com/products-

/ / / /services/3dvia/3d-xml/1/…..

BRE398: Building Information Modeling

Page 53: BIM project execution

Selection of 3D ViewerSelection of 3D Viewer

Data compatibilityFunctions

Model SizeContents

3D ViewNavigation

Supporting PlatformPCNavigation

SectioningAnimation

PCWebM bil d iAnimation

MeasurementMobile devices

SecurityView captureRendering

BRE398: Building Information Modeling

Page 54: BIM project execution

2D dwg, 3D model to CSD and CBW process2D drawing

(Arch, Struct and E&M)

Simplified 2D drawing

Build 3D model(Arch, Struct &

E&M)Clash detection

Clash and Issue Report

Co-ordinated with Main Contractor/Sub-contractor

CBW dwg.

Services adjustmentadjustment

CSD dwg.Confirmed by

Sub-contractor

Page 55: BIM project execution

As-Design BIM Implementation Process

P j er Project Mission

Ow

ne

RequirementsRequirements

BIM standard Nomination B

IM T

eam

standard &

Guidelines

Nomination Guidelines

BIM

Approval

Provide Provide

Approval

Des

ign

B

BIM Execution

Plan

BIM Deliverables

Provide Issue

Reports

Provide program

and space validation

reportBIM Quality

As-

Management Plan

Page 56: BIM project execution

As-Construction BIM Implementation Process

Ow

ner

Approve BEP

Approval

Osi

gn

am BIM BIM COBi

As-

Des

BIM

Tea Execution

PLan

BIM Deliverable

COBieData

ruct

ion

eam

BIM Execution

PLan

BIM Deliverable

COBieData

Provide scheduling & phasing

models

Operations Planning

Set

Provide cost

estimate

As-

Con

stB

IM T

e models

Coordination with Design

Team & Owner

Provide issue

reports

Beneficial Occupancy

Set

Provide issue

reportsA Owner

Page 57: BIM project execution

As-Build BIM Implementation Process

Ensure no er Identify major

equipment

Identify required

fields

Ensure no errors or omissionsO

wne

Coordinate fields,

Equipments,documentation

Validate data

Populate

data in fieldsD

esig

n T

eam

Owner as

fields

Update Add field

As-

DB

IMtio

n am Validate

field dataValidate

field data

Owner as-build data deliverable

data from

approved submittals

data when

installed

As-

Con

stru

ctB

IM T

ea

Add performance data from

C

Validated field data

Validate fields,

equipments

Validate data

mis

sion

ing

Team

C

Cxequipments

Com

m T

Page 58: BIM project execution

Communication ProceduresCommunication Procedures

El i C i i dElectronic Communication proceduresCommunication protocol should be established between all project team members to ensure smooth collaboration project team members to ensure smooth collaboration. Electronic communication between stakeholders can be created, uploaded, sent out and archived through the , p , gproject management system. Copies of all the project related communication should be

d f f k d f f saved for safekeeping and future reference. Document management (file folder structure, permissions and access folder maintenance folder notifications file naming access, folder maintenance, folder notifications, file naming convention, etc.) should also be resolved and set up at the earliest possible time.

BRE398: Building Information Modeling

Page 59: BIM project execution

File Transfer ProtocolFile Transfer Protocol

A l k f F l T f P l (FTP) An electronic workspace of File Transfer Protocol (FTP) or Asset Lifecycle Management system (ALM) will be established for the purpose of efficient and timely transfer established for the purpose of efficient and timely transfer of model and database files. This workspace will provide a collaborative location where the current contract BIM files, coordination files, and fully coordinated submittal files will reside.

h M d b d bEach BIM coordination team member stores and obtains data from this location. Project team members are to upload updated copies of their files, provide notification, and to updated copies of their files, provide notification, and to make collaboration comments and annotations as often as necessary to maintain project schedule.

BRE398: Building Information Modeling

Page 60: BIM project execution

Communication ProceduresCommunication Procedures

M i C i i P dMeeting Communication ProceduresA schedule for initial delivery of each model to the BIM P j M d h d l f d i h Project Manager, and a schedule for updating each model after the coordination session.Procedure and protocol for the submission and Procedure and protocol for the submission and approval of the model including electronic stamping.IT-related issues: file format to be used file-naming IT related issues: file format to be used, file naming and object-naming conventions, file structure, software used, and interoperability of applications.Coordination and scheduling of conflict detection and resolution procedure.

BRE398: Building Information Modeling

Page 61: BIM project execution

Network File StructureNetwork File Structure

BRE398: Building Information Modeling

Page 62: BIM project execution

Ftp Server Submission & Approval Process

Architect

ArchitectWork Model

5. Review model with Architect

3. Checks email

2. Email for notification of

Structural

3D Coordinator8. Update status –Updated in current model

notification of upload the BIM model

StructuralWork Model

1 C fil t f ld

7. Update files toCurrent Model

Mail Inbox

MEPWork Model \\ftp\bim\transfer\inbox

1. Copy files to folder

\\ft \bi \ k \3d

BRE398: Building Information Modeling

Model \\ftp\bim\transfer\inbox \\ftp\bim\workspace\3d

Page 63: BIM project execution

Information ExchangesInformation Exchanges

The project team should document the information exchanges created as part of the planning process when creating the BIM Plan. The level of development (LOD) for each model p ( )element is based on the model content criteria. The LOD will assist in determining the level of LOD will assist in determining the level of involvement for each project stakeholder from project conception through project turnover. project conception through project turnover.

BRE398: Building Information Modeling

Page 64: BIM project execution

Data Exchange for Different PurposesData Exchange for Different Purposes

BRE398: Building Information Modeling

Page 65: BIM project execution

Data Propagation in the ProjectData Propagation in the Project

BRE398: Building Information Modeling

Page 66: BIM project execution

Data Exchange in Between Applications

BRE398: Building Information Modeling

Page 67: BIM project execution

Data Exchange in Between SoftwaresData Exchange in Between Softwares

BRE398: Building Information Modeling

Page 68: BIM project execution

Standard Data Exchange Format for CAD

IGESSTEP XMLIGES

DXF

XML

STLDWG DXF STL

VRMLIFC

+ CAD Native Format Direct Interface

BRE398: Building Information Modeling

Page 69: BIM project execution

BIM Data Exchange - IFCBIM Data Exchange IFC

IFC stands for Industry Foundation ClassIFC is an international standard - ISO16739IFC is authored / maintained by buildingSMART, formerly known as the International Alliance for formerly known as the International Alliance for Interoperability (AIA)b ildi SMART UK i b th B ildi R h buildingSMART UK is run by the Building Research Establishment (BRE)

BRE398: Building Information Modeling

Page 70: BIM project execution

COBie DefinitionCOBie Definition

Construction Operations Building Information Exchange (COBie) is a data format for the publication of a subset of building model information focused on delivering building information not geometric modeling. It is closely associated with building information modeling (BIM) approaches to design, construction and management of built assets.g

BRE398: Building Information Modeling

Page 71: BIM project execution

IFC vs COBieIFC vs COBie

A BIM with just the A full BIM contains all f th t tiinformation from

the CAD modelof the construction information about the building

BRE398: Building Information Modeling

building

Page 72: BIM project execution

COBie (Construction Operations Building Information Exchange)

Ideal World

BRE398: Building Information Modeling

Page 73: BIM project execution

COBie exchange to IFCCOBie exchange to IFC

M MThe xBIM Toolkit can allow a user to create a BIM model in IFC format. xBIM performs validation on th BIM d l d th t th l t the BIM model, and then exports the relevant information into COBie format.Si COBi i i d h (h d bl ) Since COBie is in a spreadsheet (human-readable) format, a user can easily update the COBie file.A d d COB h d b k h An updated COBie is then imported back with changes propagating to the IFC BIM model, and

b tl th IFC fil l b i t d i t subsequently the IFC file can also be imported into any proprietary software such as Autodesk Revit.

BRE398: Building Information Modeling

Page 74: BIM project execution

Real worldReal worldReal world Real world We cannot avoid data lost We cannot avoid data lost for CAD data exchange in for CAD data exchange in

between different software !between different software !between different software !between different software !

Even within the same software…..

BRE398: Building Information Modeling

Page 75: BIM project execution

Model Delivery/ Exchange schedule for Submission and Approval

INFORMATION EXCHANGE

FILE SENDER

FILE RECEIVER FREQUENCY START

DATEMODEL

FILEMODEL

SOFTWARENative File

Type

File EXCHANGE

TYPE

Design A thoring

BIM PM Consultant Team Monthly TBD Revit

CatiaRevitCatia

RVTCATIA Prod ct

Nwd3dxml

pdfAuthoring –3D Design

Coordination

Product pdf

Design –Construction BIM PM Consultant

Team Bi-weekly TBD RevitCatia

RevitCatia

RVTCATIA

Nwd3dxmlConstruction Team Catia Catia Product pdf

Construction Document for

Bidding

ClientConsultant BIM PM TBD TBD Revit

CatiaRevitCatia

RVTCATIA Product

Nwd3dxml

pdf

BIM PMConsultant

T W kl TBD Revit Revit RVTCATIA

Nwd3d l3D

Construction Coordination

BIM PM TeamSub-contractor

Weekly TBD RevitCatia

RevitCatia CATIA

Product3dxml

pdf

3D Si l ti3D Simulation for

Construction Sequences

BIM PMMain

ContractorSub-contractor

TBD TBD CortonaDelmia

CortonaDelmia VMP HTM

WRL

Construction

BRE398: Building Information Modeling

Page 76: BIM project execution

TopicsTopics

BIM Project Execution PlanProject Organization Structurej gBIM Data Model StructureP j t I l t ti P & C i tiProject Implementation Process & CommunicationQuality & Risk Management

BRE398: Building Information Modeling

Page 77: BIM project execution

Quality ChallengesQuality Challenges

BRE398: Building Information Modeling

Page 78: BIM project execution

Quality ManagementQuality Management

I d t d l lit i j t h t l In order to assure model quality in every project phase, control procedures need to be set in place. Each of the models created during project progression and d l d b l d d d l development needs to be pre-planned considering model content, level of detail, format and responsible party for updates, quality and distribution of the model to all the parties involved in the

di ti ff t coordination efforts. Each of the parties contributing to the BIM model should have a responsible person or Model Manager to handle the model. Model Managers, as part of the core BIM team, are in charge of participating in design reviews and coordination sessions along with taking care of all the issues that might arise with keeping the model updated, accurate and comprehensive.

BRE398: Building Information Modeling

Page 79: BIM project execution

Quality Control ChecksQuality Control ChecksCHECKS DEFINITION

Vi l h k Ensure there are no unintended model components and theVisual check Ensure there are no unintended model components and the design intent has been followed

Interference check

Detect problems in the model where two building components are clashing including soft and hardcheck components are clashing including soft and hard

Section check Cut section to compare with the 2D drawing and take measurement for critical areas

Standard check Ensure that the BIM and AEC Standard have been followed (fonts, dimensions, line styles, levels/layers, color, etc)

Model integrity check

Describe the QC validation process used to ensure that the Project Facility Data set has no undefined, incorrectly defined or duplicated elements and the reporting process on non-compliant elements and corrective action plans

Random check Checking any missing, un-reasonable and clash matter thro’ the model

BRE398: Building Information Modeling

t e ode

Page 80: BIM project execution

Quality Checking Work FlowQuality Checking Work FlowDrawing received Modeling Deliverable c/w model 

reference list

Alignment checking

Drawing checking by Alva/Max/Jerome

Model checking  by Alva/Max/Jerome  Visual 

checking

Check

Clash analysis checkingDrawing 

vesion i

Error

Model inter‐cross checking  by Alva/Max/Jerome

Referencedrawing checking

Visual checking

comparsion

Sectioning checking

Check

Sectioning checking

Error

Model checking  by Alva

Check

checking

Reference drawing checking

Error

Model checking  by Brian Visual checking

ErrorCheck

Page 81: BIM project execution

Risk ManagementRisk Management

Th BIM d l t l t th d li The BIM modelers cannot complete the modeling on time Client’s project manager doesn’t buy inClient s project manager doesn t buy inDesign changes frequentlyMembers change from the project teams Members change from the project teams No commitment from the consultantsDesign drawings are delayedDesign drawings are delayedH5N1Software bugs and blockedSoftware bugs and blockedProject stopped by Owner

BRE398: Building Information Modeling

Page 82: BIM project execution

Contingency PlanContingency Plan

Th BIM d l t N it t f th The BIM modelers cannot complete the modeling on time

T t d t

No commitment from the project manager and consultants

M ti ti d f i dl Top management needs to give a handNotice in advance

Motivation and friendly communicationHighlight the values of BIM

Members change from the project team

Back up resources

H5N1Schedule extensionHome office

Ask additional resources for re-training

Design drawings are delayed

Software bugs and blockedWork around methods

P j d b Og g yor design change frequently

Ask for extension

Project stopped by OwnersEnsure committed deliverables

BRE398: Building Information Modeling

Page 83: BIM project execution

Questions & Answers

[email protected]

BRE398: Building Information ModelingBRE398: Building Information Modeling