Implementing VDC
for Building SiteworkJohn Prince, P.E.
April 24, 2012
2012 San Antonio, TX
4/24/2012
2
VDC for Building Sitework
Introduction
Results, Lessons Learned, Suggestions
Internal Impacts of VDC Implementation
External Impacts of VDC Implementation
4/24/2012
7
3D Laser Scanning
3DSite Survey
3D Surveying
Miramar College Interim Library Topo
• Traditional Surveying with3D Processing
• Site Features Generated Automatically
• Accurate Surface Model Readyfor VDC
• Detailed Site Culture to Meet Needs
4/24/2012
8
• Various Reference Sources
• Ready for VDC
• Embedded System Information
3D Laser Scanning
3DSite Survey
3D ExistingUtility
Modeling
3D Surveying
4/24/2012
9
−Dynamic 3D Environment
−Detailed Surface Integral with Site Plan
−Data-Rich Utilities and Structures
3DSurveying
3DSite Design
Alpine Blvd Widening
Miramar College Student Union
RBF Experiences/Services
3DSite Design
3DSurveying
Camp Pendleton
BEQ 8Conversion Modeling
−Model any Site Utility System
−Phase Utilities or Grading to meet Contractors Need
−Staking of Dry Utilities
−Up-To-Date Model with Construction Changes/As-Built
RBF Experiences/Services
.NWDfrom each Discipline
.NWDfrom each Discipline
.NWFMaster Model
.NWFMaster Model
Clash Analysis
Clash Analysis
BIM Coordination
Meeting
BIM Coordination
Meeting
Design Revisions and Coordination
Design Revisions and Coordination
RepeatRepeat
3DSite Design
3DSurveying
Site BIM Management
Conversion Modeling
RBF Experiences/Services
― Real-World Coordinates― Tied by existing conditions/constraints― Design includes existing and proposed conditions, not just all new― Different authoring software than building design― Authoring software is geared more toward public works type projects― Less prefabricated elements or “system” components― Site BIM Management techniques differ
Civil Engineering Design & TechnologyKey Differences with Sitework
VDC for Building Sitework
Introduction
Results, Lessons Learned, Suggestions
Internal VDC Implementation Impacts
External VDC Implementation Impacts
― Better documentation of existing utility conditions― Detailed surface improves fine grading and ADA design― Model Based/Dynamic Design and Plan Production = Increased
Efficiency, Fewer Errors, and Better Quality End Product
So, Why BIM for RBF?Internal Impacts
Complete shift in QA/QC process using collaboration software― General Visual QC/Layers― Utility Clashes― Utility Cover― Utility Structure at Grade
Internal Impacts
Complete shift in QA/QC process using collaboration software― Grading Impacts on Existing Utilities or Early Install Utilities― Water/Sewer/Recycled Water separation― Pipe/Structure Connections
Internal Impacts
VDC for Building Sitework
Introduction
Results, Lessons Learned, Suggestions
Internal Impacts of VDC Implementation
External Impacts of VDC Implementation
― Tighter/More Detailed Design = Less RFI’s― Increased Clarify of Design Changes
― Use of different authoring software between site and building consultants requires some traditional 2D coordination (for now)…
External Impacts
Coordination Using VDC Methods(collaboration software, BIM tools, etc.)
NEXT
External Impacts
―Vertical Utility Coordination―Grading Impacts to Early Utilities
Coordination Using VDC Methods(collaboration software, BIM tools, etc.)
NEXT
External Impacts
―Vertical Utility Coordination―Grading Impacts to Early Utilities―Formation/Soil Layer Analysis
Coordination Using VDC Methods(collaboration software, BIM tools, etc.)
NEXT
External Impacts
―Vertical Utility Coordination―Grading Impacts to Early Utilities―Formation/Soil Layer Analysis―Utility Equipment Sizing―Structural Footing Conflicts―Structural Load Influence Conflicts
Coordination Still Using Traditional Methods(overlays, coordination print review)
External Impacts
―Architectural Site Plan―Horizontal Site Utility Coordination―Building Utility POC Info―Discipline References across Plan Sheets―Pavement Types and Sections―Existing Utility Accuracy and Potholing―Dissemination of Changes
VDC for Building Sitework
Introduction
Results, Lessons Learned, Suggestions
Internal Impacts of VDC Implementation
External Impacts of VDC Implementation
Results, Lessons Learned, Suggestions
― File/Building Alignment is Very Important― Need Building Consultants Align with Civil Site
― Building/Site Coordination Tools― Efficient/Repetitive File Sharing/Overlay― Building Doors and Utility POC’s― Site Utilities― Surfaces― Confident Alignment in Collaboration
VDC Implementation has proven beneficial
The effect of VDC on Sitework needs attention
The VDC Process needs to follow the Design Process/Schedule
Full Buy-in from all consultants is needed for success
Well developed processes/execution are necessary for benefits to be realized
Take-Aways