BIM AND DRONES …FOR INFRASTRUCTURE THOMAS GROENINGER BUSINESS UNIT MANAGER DIGITALIZATION

Transcript of BIM AND DRONES …FOR INFRASTRUCTURE · bim and drones …for infrastructure thomas groeninger...

  • BIM AND DRONES …FOR INFRASTRUCTURE

    THOMAS GROENINGER

    BUSINESS UNIT MANAGER DIGITALIZATION

  • Digitalization,

    more than tablets on the

    construction sites

    © STRABAG 2

    ‘‘ ’’

  • © STRABAG 3

    GOAL: TO DELIVER ALL THE INFORMATION OF THE PROJECT

  • © STRABAG 4

  • © STRABAG 5

    THE SERVICE OF NEW TECHNOLOGY…

  • DRONES FOR MAPPING

  • Image source: Google Maps

    © STRABAG 7

    DRONE LOCATIONS AT STRABAG

  • • Fast data collection Surveyor spends less time on site

    • Reach inaccessible areas More areas can be surveyed

    • Safe work area Surveys can be performed from safe locations

    © STRABAG 8

    DATA ACQUISITION WITH UAV

  • PROGRESS MONITORING

    © STRABAG 9

    APPLICATIONS

  • A.I. BASED CLASSIFICATION OF THE POINT CLOUD

    © STRABAG 10

  • © STRABAG 11

    A.I. BASED CLASSIFICATION OF THE POINT CLOUD

  • © STRABAG 12

    OVERVIEW OF CURRENT PROJECTS

  • MOBILE MAPPING

  • • Dual laserscanner for corridor mapping

    Absolut accuracy 1-2 cm

    Relative accuracy 5 mm

    • Panorma camera

    • Precise mapping of infrastructure at high speed (up to 110 km/h) and in active traffic

    • Detailed point clouds

    © STRABAG 14

    MOBILE MAPPING

  • © STRABAG 15

    MOBILE MAPPING

  • BIM FOR INFRASTRUCTURE

  • © STRABAG 17

    MODEL BASED QUANTITY CALCULATION

    BIM

    5D®

    ● Project A5 Drasenhofen

    ● 5 km

    ● Monthly flight

  • © STRABAG 18

    MODEL BASED QUANTITY CALCULATION

    BIM

    5D®

    terrain

    UAV Flight

    02. August 2018

    UAV Flight

    02. September 2018

    ● Project A5 Drasenhofen

    ● 5 km

    ● Monthly flight

  • © STRABAG 19

    BIM

    5D® terrain UAV Flight 02. August 2018 UAV Flight

    02. September 2018

    MODEL BASED QUANTITY CALCULATION

  • © STRABAG 20

    MODEL BASED QUANTITY CALCULATION

    Planning

    model

    Stationing

    BIM

    5D® Axis Volume

    asphalt

    2.145,50 m²

    Volume frost

    protection layer

    3.957,80 m²

    Volume

    shoulder

    3.197,50 m²

    Volume soil

    12.565,60 m²

    Drone

    point cloud

  • © STRABAG 21

    OUR VISION TO CONNECT THE SYSTEMS WITHIN THE CORPORATE AND REDUCTION OF THE MEDIA BREAKS

  • DR. THOMAS GRÖNINGER

    STRABAG AG

    TEL. +49 941 464406-15

    MOBIL +49 170 3358462

    [email protected]

    WWW.3D-SURVEY.STRABAG.DE

    http://www.3d-survey.strabag.de/http://www.3d-survey.strabag.de/http://www.3d-survey.strabag.de/http://www.3d-survey.strabag.de/