    Baseline assessment, Design, Business plan and Construction Supervision for Water Supply and Sanitation in Nthailre 160418024.xls.m

    ITEM

    No.

    PAYMENT

    REFERS

    DESCRIPTION UNIT QTY RATE AMOUNT (M

    SABS 1200A BILL NO. 1: PRELIMINARY AND GENERAL

    SCHEDULED FIXED-CHARGE AND VALUE RELATED

    ITEMS

    8.3.1 Contractual Requirements:

    A Allow for Performance Bond in accordance with Clause 10 of the

    Conditions of Contract

    Sum 1 950,000.00 950,000

    B Allow for Insurance of the Works in accordance with the

    Conditions of Contract

    Sum 1 1,000,000.00 1,000,000

    C Allow for all other Insurance in accordance with the provisions of

    the Contract.

    Sum 1 1,000,000.00 1,000,000

    8.3.2 Site Establishment

    8.3.2.1 Facilities for The Engineer

    Note: The following services are only to be provided by the

    Contractor on the written instructions of the Engineer.

    Payment will only be due where services have been so

    requested and properly provided to the satisfaction of the

    Engineer.

    D PS 1.40.1 Office building in accordance with the Specifications and

    Drawings for the duration of the Contract.

    sum 0 -

    E Capital costs for electricity and water to the office buildings for the

    duration of the Contract.

    sum 0 -

    F PS 1.46 Office furniture and equipment as specified in Schedule 1.1 for theduration of the Contract. ( The Contractor shall enter basic prices

    for each item in the schedule)

    sum 1 500,000.00 500,000

    G PS 1.41 Survey equipment as specified in Schedule 1.2 for the duration of

    the Contract, ( The Contractor shall enter basic prices for each item

    in the schedule)

    sum 1 3,000,000.00 3,000,000

    H PS 1.35 Capital costs for the provision of an individual lines for telephone,

    fax and internet required for the Engineer's offices for the duration

    of the Contract.

    sum 0 -

    I Allow for provision of 2 No. rented accomodation for use by

    Engineer for the duration of the Project

    sum 1 30,000.00 30,000

    J Allow for fuel, lubricants and maintenance of Engineer's vehicle

    according to specification

    sum 1 1,500,000.00 1,500,000

    7,980,000Carried to Collection

  • 7/27/2019 Bills of Quantities for a Water Supply Scheme

    2/28

    Baseline assessment, Design, Business plan and Construction Supervision for Water Supply and Sanitation in Nthailre 160418024.xls.m

    ITEM

    No.

    PAYMENT

    REFERS

    DESCRIPTION UNIT QTY RATE AMOUNT (M

    A PS 1.37 Supply safety and First Aid equipment as specified in Clause 1.37

    of the General Specifications.

    sum 1 75,000.00 75,000

    8.3.2.2 Facilities for Contractor

    Offices

    B Buildings sum 1 500,000.00 500,000

    C Water supplies, sewer and electric power connections, security and

    other services.

    sum 1 1,000,000.00 1,000,000

    D Workshops and storage sheds sum 1 1,000,000.00 1,000,000

    E PS 1.37 First Aid, safety clothing and shoes, dust masks, rubber boots etc sum 1 200,000.00 200,000

    F Plant tools and equipment sum 1 500,000.00 500,000

    Accommodation

    H Facilities for senior supervisory staff. sum 1 500,000.00 500,000

    I Water supplies, sewer and electric power connections, security and

    other services.

    sum 1 1,000,000.00 1,000,000

    Labour Camp

    J Labour cabins sum 1 750,000.00 750,000

    K Ablution and latrine facilities sum 1 350,000.00 350,000

    L Canteen facilities sum 1 150,000.00 150,000

    M Water supplies, sewer and electric power connections, security and

    other services.

    sum 1 1,000,000.00 1,000,000

    N Allow for Contractor's liaison with all necessary authorities to

    establish Contractor's camp site.

    sum 1 1,000,000.00 1,000,000

    O PS 1.45 Allow for the provision, erection and maintenance of 2No. Sign

    Boards as per Drawing No. ISP/STD/002

    sum 1 125,000.00 125,000

    P 8.3.4 Allow for the removal of all the provisions and constructions such

    as listed above on completion of the Works.

    sum 1 30,000.00 30,000

    Q 8.3.3 Other fixed charges (specify below) sum 1 -

    8,180,000Carried to Collection

  • 7/27/2019 Bills of Quantities for a Water Supply Scheme

    3/28

    Baseline assessment, Design, Business plan and Construction Supervision for Water Supply and Sanitation in Nthailre 160418024.xls.ms

    ITEM

    No.

    PAYMENT

    REFERS

    DESCRIPTION UNIT QTY RATE AMOUNT (MK

    8.4 SCHEDULED TIME - RELATED ITEMS

    8.4.2 Provide services, operate and maintain facilities on site for the

    duration of the contract.

    8.4.2.1 Facilities for The Engineer

    PS 1.40.1 Offices

    A Provision of electricity, water, refuse removal, sewage disposal and

    24 hour Security services.

    month 10 100,000.00 1,000,000.

    B Provide a cleaner and cleaning material for the duration of the

    Contract.

    Man -

    month

    10 25,000.00 250,000.

    C Provide a surveyor and 2 No. experienced chainmen for the

    Engineer for the duration of the Contract.

    Man -

    month

    10 150,000.00 1,500,000.

    D PS 1.41 Maintain survey equipment month 10 50,000.00 500,000.

    E PS 1.37 Maintain safety and first aid equipment. month 10 25,000.00 250,000.

    F Allow for provision of rented office facilities month 10 50,000.00 500,000.

    8.4.2.2 Facilities for Contractor

    Offices

    G Maintain Buildings month 10 50,000.00 500,000.

    H Provision of Water supplies, sewer, electric power,

    telecommunications, security and other services.

    month 10 100,000.00 1,000,000.

    I Maintain Workshops and storage sheds month 10 35,000.00 350,000.

    J PS 1.37 Provision of First Aid, safety clothing and shoes, dust masks,

    rubber boots etc

    month 10 40,000.00 400,000.

    K Operate and Maintain Plant, Tools and Equipment month 10 50,000.00 500,000.

    Accommodation

    L Provision of Facilities for senior supervisory staff. month 10 50,000.00 500,000.

    M Provision of Water supplies, Sewer and electric power connections,

    security and other services.

    month 10 75,000.00 750,000.

    Labour camp

    N Maintain Labour cabins month 10 30,000.00 300,000.

    O Maintain Ablution and latrine facilities month 10 40,000.00 400,000.

    P Maintain Canteen facilities month 10 30,000.00 300,000.

    Q Provision Water supplies, sewer and electric power connections,

    security and other services.

    month 10 150,000.00 1,500,000.

    R 8.4.3/4 Supervision, Company and Head Office overhead costs month 10 450,000.00 4,500,000.

    S 8.4.5 Other time-related charges (to be specified) month 10 50,000.00 500,000.

    15,500,000.Carried to Collection

  • 7/27/2019 Bills of Quantities for a Water Supply Scheme

    4/28

    Baseline assessment, Design, Business plan and Construction Supervision for Water Supply and Sanitation in Nthailre 160418024.xls.ms

    ITEM

    No.

    PAYMENT

    REFERS

    DESCRIPTION UNIT QTY RATE AMOUNT (MK

    8.5 Provisional Sums

    The use of Provisional Sums listed below shall be governed by

    the provisions of Clause 35 of the Conditions of Contract.

    A 8.5 (a) Allow for material testing as directed by the Engineer sum 1 500,000.00 500,000.

    B 8.5 (b) Overheads, charges and profits. % 25.00 125,000.

    C 8.5 (a) Provision of transport, accommodation and catering for si te

    meetings or as instructed by the Engineer.

    sum 1 500,000.00 500,000.

    D 8.5 (b) Overheads, charges and profits. % 25.00 125,000.

    E 8.5 (a) Payment of account for telephone service for the Engineer's office. sum 1 120,000.00 120,000.

    F 8.5 (b) Overheads, charges and profits. % 25.00 30,000.

    G 8.5 (a) Provision of office consumables, stationery, etc for the duration of

    the Contract.

    sum 1 300,000.00 300,000.

    H 8.5 (b) Overheads, charges and profits. % 25.00 75,000.

    I 8.5 (a) Provision of Petty Cash for payment of miscellaneous accounts as

    instructed by the Engineer

    sum 1 240,000.00 240,000.

    J 8.5 (b) Overheads, charges and profits. % 25.00 60,000.

    K Allow for purchase of SABS 1200 1 400,000.00 400,000.

    L Overheads, charges and profits. % 25.00 100,000.

    M 8.5 (a) Allow for payment of compensation to local community as per

    recommendation from department responsible for land valuations

    sum 0 - -

    N 8.5 (b) Overheads, charges and profits. % - -

    O 8.5 (a) Allow for training of operating staff including provision of

    Operation and Maintenance Manuals

    sum 1 500,000.00 500,000.

    P 8.5 (b) Allow for Dayworks sum 1 500,000.00 500,000.

    Q Allow for implementation of Environmental and Social Sum 1 1,000,000.00 1,000,000.

    Management Plan

    R Allow for working within built-up areas Sum 1 500,000.00 500,000.

    Other Works

    S The contractor shall describe hereunder inserting relevant Clause

    Nos., prices and any other works or obligation that may be referred

    to in the Contract and for which he wishes to make a separate

    charge. (The charge shall be carried to the amount column)

    Sum 1 - -

    5,075,000.Carried to Collection

  • 7/27/2019 Bills of Quantities for a Water Supply Scheme

    5/28

    Baseline assessment, Design, Business plan and Construction Supervision for Water Supply and Sanitation in Nthailre 160418024.xls

    ITEM

    No.

    PAYMENT

    REFERS

    DESCRIPTION UNIT QTY RATE AMOUNT (M

    8.7 Daywork (Rates only)

    Note:

    i) Dayworks will apply irrespective of the percentage increase inquantities and payments for dayworks will be according to Clause

    50 of the General Conditions of Contract .

    ii) In addition to the plant listed here, the tenderer must state the

    capacity and corresponding rate of other plant that can be used

    ton a separate sheet

    iii) Standing time will be charged at 2/3 of the rate

    A Labour

    Engineer/Surveyor hr R/O 4,500.00

    Ganger/chargehand hr R/O 3,500.00

    Artisan hr R/O 2,500.00

    Experienced chainman hr R/O 350.00

    Driver hr R/O 200.00

    Labourer hr R/O 85.00

    Machine operator hr R/O 350.00

    B Plant & Equipment

    Tractor-loader-backhoe as JCB 2C or equivalent hr R/O 30,000.00

    Wheel loader minimum rated bucket capacity 1.0 cubic metre. hr R/O 30,000.00

    Bulldozer minimum power 75 kW hr R/O 30,000.00

    Crawler mounted hydraulic excavator, minimum power 50 kW,

    with minimum rated bucket capacity of 0.75 cubic metre.

    hr R/O 28,000.00

    Crawler mounted hydraulic excavator, minimum power of 100kW,

    minimum rated bucket capacity of 1.0 cubic metre.

    hr R/O 38,000.00

    Grader minimum power 100 kW hr R/O 28,000.00

    Tipper truck minimum 5 cubic metre. hr R/O 16,500.00

    Dumper minimum 0.5 cubic metre capacity hr R/O 25,000.00

    Carried to Collection

  • 7/27/2019 Bills of Quantities for a Water Supply Scheme

    6/28

    Baseline assessment, Design, Business plan and Construction Supervision for Water Supply and Sanitation in Nthailre 160418024.xls.m

    ITEM

    No.

    PAYMENT

    REFERS

    DESCRIPTION UNIT QTY RATE AMOUNT (M

    Pedestrian roller as Bomag W25 or equivalent hr R/O 15,850.00

    Water bowser minimum capacity 2 cubic metre. hr R/O 2,500.00

    Compressor minimum 5 cubic metre/min. hr R/O 11,420.00

    Rock drills, paving breakers, chipping hammers, scaling hammers,

    tampers, sand rammers and compressed air pocker vibrators

    inclusive of hoses, moil points, chises and the like.

    day R/O 30,000.00

    Concrete mixer minimum output volume 75 litres. day R/O 22,000.00

    Water pump petrol/diesel driven outlet diameter 50 mm complete

    with suction and delivery hoses.

    day R/O 15,000.00

    Poker vibrator petrol driven including power pack. day R/O 25,000.00

    Welding unit minimum 150 A including rod, leads, etc. day R/O 19,500.00

    Generator set minimum 5 kVA. da R/O 25,000.00

    A Materials

    Cement Bag R/O 3,570.00

    Building sand m R/O 2,850.00

    Crushed stones (19mm) m R/O 9,860.00

    250mm Upvc Class 16 m R/O 8,500.00

    250mm Upvc Class 12 m R/O 7,750.00

    250mm Upvc Class 9 m R/O 7,250.00

    200mm uPVC Class 9 pipes m R/O 6,100.00

    200mm uPVC Class 12 pipes m R/O 6,800.00

    200mm uPVC Class 16 pipes m R/O 7,450.00

    160mm uPVC Class 9 pipes m R/O 5,100.00

    160mm uPVC Class 12 pipes m R/O 5,900.00

    160mm uPVC class 16

    110mm uPVC Class 9 pipes m R/O 1,170.00

    90mm uPVC Class 9 pipes m R/O 980.00

    63mm uPVC Class 9 pipes m R/O 516.00

    250mm GS Pipe m R/O 75,000.00

    150mm GS Pipe m R/O 25,950.00

    100mm GS Pipe m R/O 12,096.00

    Carried to Collection

  • 7/27/2019 Bills of Quantities for a Water Supply Scheme

    7/28

    Baseline assessment, Design, Business plan and Construction Supervision for Water Supply and Sanitation in Nthailre

    ITEM

    No.

    PAYMENT

    REFERS

    DESCRIPTION UNIT QTY RATE

    COLLECTION

    Page 1

    Page 2

    Page 3

    Page 4

    Page 5

    Page 6

    TOTAL BILL No. 1 PRELIMINARY AND GENERAL TO MAIN SUMMARY

  • 7/27/2019 Bills of Quantities for a Water Supply Scheme

    8/28

    Baseline Assessment, Design, Business Plan and Construction Supervision for Water Supply and Sanitation in Nthalire 16041

    ITEM

    No.

    PAYMENT

    REFERENDESCRIPTION UNIT QTY RATE AM

    BILL NO.2: BOREHOLE DRILLING, CIVIL WORKS & PUMP

    INSTALLATION (4 No. BOREHOLES)

    BOREHOLE DRILLING AND TEST PUMPING

    2.1.0 MOBILISATION

    2.1.1 Allow for mobilisation/demobilisation and transport of the drilling sub-

    contractor Sum 0.5

    500,000.00

    2.1.2 Rigging Up No. 2 25,000.00

    2.1.3 Allow for transportation of materials Sum 0.5 250,000.00

    2.1.4 Allow for transportation of water Sum 0.5 350,000.00

    2.2.0 BOREHOLE DRILLING

    2.2.1 8" 0 - 200m m 12 18,500.00

    2.2.2 6" 0 - 200m m 140 17,000.00 2

    2.2.11 Extra over all dril ling for inclined drill ing per degree of inclination. Max.

    30 degrees off vertical m

    17,500.00

    2.3.0 INSTALLATION OF CASING

    2.3.1 6" - 8" m 12 4,500.00

    2.3.2 8" - 10" m RO 8,900.00

    2.4.0 GROUTING

    2.4.1 Injection of cement (1 cu. m per borehole) m3

    2 80,000.00

    2.5.0 DEVELOPMENT

    2.5.1 Air lift pumping using drill rods m 120 8,500.00 1

    4Carried to Collection

  • 7/27/2019 Bills of Quantities for a Water Supply Scheme

    9/28

    Baseline Assessment, Design, Business Plan and Construction Supervision for Water Supply and Sanitation in Nthalire 1604180

    ITEM

    No.

    PAYMENT

    REFERENDESCRIPTION UNIT QTY RATE AMO

    2.11.0 BOREHOLE CIVIL WORKS

    SABS 1200D SECTION: EARTHWORKS

    CLEARING (SABS 1200C)

    2.11.1 8.3.1 (a) Clear Site including removal of trees up to 1 m girth and cart to approved

    areas off Site m2

    200

    550.00 1

    8.3.1 (b) Remove trees of girth:

    2.11.2 over 1,0 m and up to 2,0 m No. 2 5,500.00

    2.11.3 over 2.0m and up to 3.0m No 1 9,500.00

    EXCAVATION

    8.3.1(b) Excavate in all materials and use for embankment or backfill or

    dispose as ordered:

    2.11.4 Excavate in normal material for borehole base slabs (provisional) m3

    2 550.00

    2.11.5 Form, compact and trim fill to low areas of site as directed (provisional) m3

    2 550.00

    2.11.6 Supply and build in selected materials as directed (provisional) m3

    2 650.00

    2.11.7 Supply, place and compact hardcore fill m3

    2 18,000.00

    CONCRETE

    2.11.8 Grade 15/20 blinding concrete 50mm thick under floor slab m3

    2 56,500.00

    2.11.9 Grade 35/20 conctrete to base slabs m3

    2 75,000.00 1

    REINFORCEMENT

    2.11.10 High yield steel reinforcement, 10mm diameter and larger Kg 200 375.00

    2.11.11 Square Mesh Fabric reinforcement Ref. No. 395 m2

    50 1,500.00

    FORMWORK AND SURFACE FINISHES

    2.11.12 Formwork Class F1 to sides of floor slab not exceeding 300mm wide m 4 1,500.00

    2.11.13 Extra over formwork for F2 finish to exposed surfaces m 4 1,500.00

    2.11.14 U2 finish to floor slab m2

    4 1,500.00

    SWITCHBOARD/CONTROL PANEL BUILDING

    2.11.15 Provide all materials, build and commission borehole switchboard/control

    panel building including all finishes in accordance with specificationsNo. 2 320,000.00 6

    1,2Carried to Collection

  • 7/27/2019 Bills of Quantities for a Water Supply Scheme

    10/28

    Baseline Assessment, Design, Business Plan and Construction Supervision for Water Supply and Sanitation in Nthalire 16041

    ITEM

    No.

    PAYMENT

    REFERENDESCRIPTION UNIT QTY RATE AM

    2.12.0 SABS 1200 L SECTION: PIPEWORK AND FITTINGS

    8.2.1 Galvanised Mild Steel Pipes: Supply, handle, fix, test, and disinfect

    (potable water pipes) complete with couplings:

    2.12.1 100 mm diam. m 60 12,096.00

    2.12.2 80mm diam. m 60 11,042.00

    SABS 1200 L SPECIALS AND FITTINGS

    Extra over 2.12.1 to 2.12.3 for jointing galvanised mild steel to uPVC

    pipe, including flange adaptors,bolts, gasket:-

    2.12.3 110mm diam uPVC to 100 mm diam GMS No 4.5 30,000.00

    2.12.4 100mm diam CI socketed flanged adaptor No 1.5 42,000.00

    2.12.5 75mm diam CI socketed flanged adaptor No 1.5 39,000.00

    2.12.6 500mm diam CI socketed flanged adaptor No 1.5 150,000.00

    VALVES

    8.2.3 Supply, fix, joint complete with fittings, incl cutting pipes where

    necessary, test, valves

    Gate Valves Class 16 on pipe sizes:

    2.12.7 Flanged gate valve on 100mm diam GMS No 2 75,000.00

    Single Orifice Air Valves (VENT-O-MAT or similar approved) on pipe

    sizes:

    2.12.13 25mm RBX [anti-shock] or similar approved on 100mm diam. 100mm

    GMS pipe No. 2

    123,000.00

    2Carried to Collection

  • 7/27/2019 Bills of Quantities for a Water Supply Scheme

    11/28

    Baseline Assessment, Design, Business Plan and Construction Supervision for Water Supply and Sanitation in Nthalire 16041802

    ITEM

    No.

    PAYMENT

    REFERENDESCRIPTION UNIT QTY RATE AMOU

    WATER METERS

    Supply, lay, joint complete with fitting including cutting pipes where

    necessary and all necessary connections, test.

    2.12.16 Meinecke Cosmos WPD-200 or similar approved water meter

    No 2

    350,000.00 70

    2.12.17 Meinecke Cosmos strainer WPD or similar approved strainer box No 2 350,000.00 70

    ANCILLARIES

    8.2.11 Anchor/Thrust blocks and pedestals for the following pipe diameters

    as described on Drawing No. E125/BH/002: Note that thrust blocks are

    measured as a number where the type of thrust blocks include tees,

    bends, reducers and end caps.

    2.12.18 100mm diam. uPVC No. 4 25,000.00 10

    3.10.2 75mm diam. uPVC No. 4 23,000.00 9

    3.11 BOREHOLE MECHANICAL INSTALLATIONS

    Supply, deli ver to site, unl oad, store on site ,install ,test commission and

    set to wor k

    3.13.1 SUBMERSIBLE PUMP & EXTERNAL PIPEWORK

    3.13.1 Discharge pipework, with the foll owing detail s:

    3.13.1.1Pipework as detailed for the outflow of the pump c/w instrumentation and

    accessories as shown in the specificationSum 0.5 500,000.00 250,00

    3.13.2 PUMP & ACCESSORIES

    Submersible pump complete with accessories as billed and specified inthe datasheets

    3.13.2.1Grundfos Pump cw pump motor unit (pumping characterictics

    characteristics Q = 2litres/sec; H = 200m; Power = 7.5Kw)No 2 950,000.00 1,900,0

    3.13.2.2 Boreline Flexible rising main m 60 2,000.00 120,00

    3.13.2.3 Mild Steel Wellhead c/w base plate , bolts,nuts and washers Sum 2 25,000.00 50,000

    3.13.2.4 Stainless steel adapters to connect boreline to the pump and wellhead No 6 25,000.00 150,00

    3.13.2.5 40mm HDPE dipper Tube Sum 0.5 25,000.00 12,500

    3.13.2.6 50mm sq x 3 core submersible electrical cable m 80 1,950.00 156,00

    3.13.2.7 Joint Kit No 0.5 24000 12,000

    3.13.3 TEST AND COMMISSIONING

    3.13.3.1Test the performance of pump- motor set to ascertain compliance in the

    presence of Electro-Mechanical EngineerSum 0.5 15,000.00 7,500

    3.14 BOREHOLE ELECTRICAL SUPPLY

    3.14.1 Allow for supply of power from the national grid to all pumps cw with all

    controls Sum 0.510,000,000.00 5,00

    3.14.2 Allow for supply, installation, testing and commission of 10Kw diesel

    standby generator No. 22,000,000.00 4,00

    13,25Carried to Collection

  • 7/27/2019 Bills of Quantities for a Water Supply Scheme

    12/28

    Baseline Assessment, Design, Business Plan and Construction Supervision for Water Supply and Sanitation in Nthalire

    ITEM

    No.

    PAYMENT

    REFERENDESCRIPTION UNIT QTY RATE

    COLLECTION

    Page 8

    Page 9

    Page 10

    Page 11

  • 7/27/2019 Bills of Quantities for a Water Supply Scheme

    13/28

    Baseline Assessment, Design, Business Plan and Construction Supervision for Water Supply and Sanitation in Nthalire 160418024.xls.ms_offic

    ITEM

    No.

    PAYMENT

    REFERENDESCRIPTION UNIT QTY RATE AMOUNT

    1200 DB BILL NO.3: BOREHOLE COLLECTOR PIPE NETWORK

    SABS 1200D SECTION: EARTHWORKS

    3.1.0 CLEARING (SABS 1200C)

    3.1.1 8.3.1 (a) Clear Site including removal of trees up to 1 m girth and cart to

    approved areas off Site m 3000300.00

    900,000.00

    8.3.1 (b) Remove trees of girth:

    3.1.2 over 1,0 m and up to 2,0 m No 10 4,500.00 45,000.00

    3.1.3 over 2.0m and up to 3.0m No 10 9,500.00 95,000.00

    3.2.0 8.3.2 EXCAVATION

    8.3.2(a) Excavate in all materials as specified for trenches, backfill,

    compact, and dispose of surplus/unsuitable material, for

    pipes:

    110 mm diam for total trench depth

    3.2.1 Exceeding 0,0 but not exceeding 1,5 m m 3000 800.00 2,400,000.00

    3.2.2 Exceeding 1,5 m but not ecxeeding 2,5 m m - - -

    Excavation for valve Chambers

    3.2.3 Not exceeding 1,5m m3

    60 1,500.00 90,000.00

    3.2.4 Exceeding 1,5 but not exceeding 2,5m m3

    5 2,000.00 10,000.00

    8.3.2(b) Extra-over items 3.2.1 to 3.2.4 incl. for (prov):

    3.2.5 3.1.2 Hard Rock excavation m3

    50 20,000.00 1,000,000.00

    3.2.6 8.3.2(c) Excavate and dispose of unsuitable material from trench bottom

    (Provisional) m3

    5015,000.00

    750,000.00

    8.3.3 EXCAVATION. ANCILLARIES Make up deficiency in

    backfill material (Provisional)

    3.2.7 8.3.3.1(a) from other necessary excavations on site m3

    100 800.00 80,000.00

    3.2.8 8.3.3.1(b) by importation from designated borrow pits m3

    50 6,500.00 325,000.00

    8.3.3.4 Overhaul (provisional)

    3.2.9 Limited overhaul (0.5-1Km) m3.km 100 1,500.00 150,000.00

    3.2.10 Long overhaul (Exceeding 1Km) m3.km - -

    3.3.0 SABS 1200 L SECTION: PROVISION OF BEDDING

    Available from trench within 0,5 km (Subclause 3.4.1)

    3.3.1 8.2.1 a) Selected granular material m3

    200 6,500.00 1,300,000.00

    3.3.2 b) Selected fill material m3

    100 7,500.00 750,000.00

    7,895,000.00Carried to Collection

    Bill No. 3 Collectorpipes Interconsult in association with GK Works 13 of 2

  • 7/27/2019 Bills of Quantities for a Water Supply Scheme

    14/28

    Baseline Assessment, Design, Business Plan and Construction Supervision for Water Supply and Sanitation i n Nthalire 160418024.xls.ms_off

    ITEM

    No.

    PAYMENT

    REFERENDESCRIPTION UNIT QTY RATE AMOUNT

    Imported from:

    8.2.2.1 a) Other necessary excavations within 0.5 km (Provisional)

    3.3.3 1) Selected granular material m3

    50 6,500.00 325,000.00

    3.3.4 2) Selected fill blanket m3

    1000 7,500.00 7,500,000.00

    8.2.2.2 b) Borrow pits (Provisional)

    3.3.5 1) Selected granular material m3

    750 2,500.00 1,875,000.00

    3.3.6 2) Selected fill material m3

    500 3,500.00 1,750,000.00

    3.4.0 SABS 1200L SECTION : PIPEWORK AND FITTINGS

    8.2.1 uPVC pipes Class 9: Supply, handle, cut as required,lay, bed,

    test, and disinfect (potable water pipeline) complete with

    couplings:

    3.4.1 110 mm dia m 2500 1,170.00 2,925,000.00

    8.2.1 Supply, handle, lay in bedding, joint with couplings, test, and

    disinfect steel pipes inclusive of threaded joints and couplings

    3.4.2 100mm diam m 200 12,096.00 2,419,200.00

    80mm diam m 300 11,042.00 3,312,600.00

    3.5.0 SABS 1200 L SPECIALS AND FITTINGS

    8.2.2 Supply, lay, bed, joint, incl cutting pipes to length where

    required, test and disinfect: Extra-over item 3.4.1 for

    pipelaying

    Bends uPVC Class 16 Plain-ended incl(No.)/(type) couplings

    3.5.1 110mm diam 90 deg No 8 2,750.00 22,000.00

    3.5.2 110mm diam 45 deg No 8 2,750.00 22,000.00

    3.5.3 110mm diam 22.5 deg No 8 2,750.00 22,000.00

    3.5.4 110mm 11.25 deg No 8 2,750.00 22,000.00

    uPVC Tees

    Note: Where reducing tee is required to be made up of two ormore components,the price shall include for all the

    components required

    3.5.5 110x110 mm Equal Tee No 3 7,385.00 22,155.00

    CI Reducers

    3.5.7 80x110 reducer No 4 25,000.00 100,000.00

    uPVC End caps

    3.5.8 110mm dia end cap No 4 500.00 2,000.00

    20,318,955.00Carried to Collection

    Bill No 3 Collectorpipes Interconsult in association with GK Works 14 of

  • 7/27/2019 Bills of Quantities for a Water Supply Scheme

    15/28

    Baseline Assessment, Design, Business Plan and Construction Supervision for Water Supply and Sanitation in Nthalire 160418024.xls.ms_office

    ITEM

    No.

    PAYMENT

    REFERENDESCRIPTION UNIT QTY RATE AMOUNT

    3.6.0 VALVES:

    3.6.1 SABS 1200

    L 8.2.3

    PS 2.2.6.7

    Supply, install, test and commission PN16 Flanged Orifice Air

    Valve ND 25mm with Anti Shock Orifice Mechanism on 110mm

    Dia. uPVC (including all necessary pipework, fittings, etc as

    detailed on

    No. 1 135,000.00 135,000.00

    3.6.2 SABS 1200

    L 8.2.3

    PS 2.2.6.7

    Supply, install, test and commission Wash Out Valve ND 90mm

    on 110mm dia. uPVC (including all necessary pipework, fittings,

    etc as detailed)

    No. 3 125,000.00 375,000.00

    3.6.3 SABS 1200

    L 8.2.3

    PS 2.2.6.7

    Supply, install, test and commission Sluice/Isolation Valve ND

    160mm including all necessary pipework, etc as specified No. 4 165,000.00 660,000.00

    3.7.0 ANCILLARIES

    3.7.1 SABS 1200

    L 8.2.11

    PS 2.2.6.20

    Anchor/Thrust blocks and pedestals for the following pipe

    diameters as described on Drawing No. E125/STD/003: Note

    that thrust blocks are measured as a number where the type

    of thrust blocks include tees, bends, reducers and end caps.

    3.7.2 110mm dia.. No. 8 25,000.00 200,000.00

    3.7.3 80mm dia.. No. 4 23,000.00 92,000.00

    Valve Chambers:

    3.7.4 SABS 1200

    DB 8.3.2 (a)

    SABS 1200

    L 8.2.13

    PS 2.2.6.9

    Excavate in normal material to depths up to 2.5m for Air Valve

    Chamber and construct chamber in reinforced concrete base

    Grade 25/20, 230mm thick reinforced brickwall plastered

    internally and externally including all formwork, precast concrete

    cover slab, Medium Duty C.I. manhole cover and frame to SABS

    558 Type 9A, Type 11A valve boxes, locking bar and padlock,

    vent pipe, dowel bars and lifting hooks, cast iron step irons, thrust

    blocks, etc as described on Drawing . After construction backfillwith selected material and compact in 150mm layers to 90%

    MOD AASHTO including the removal of all excess excavated

    No. 1 135,000.00 135,000.00

    3.7.5 Ditto for combined Wash Out and Sluice/Isolation Valve chamber

    as describedNo. 3 135,000.00 405,000.00

    3.7.6 Ditto for Wash Out Valve as described on No. 4 135,000.00 540,000.00

    3.7.7 Supply and place grouted stone pitching 150mm thick to Wash

    Out spill chamber outfalls as detailed on Drawings or as instructed

    by the Engineer.

    m2 10 6,500.00 65,000.00

    Marker Posts:

    3.7.8 PS 2.2.6.21 Supply and install precast concrete Marker Posts as described on

    Drawing No. E125/STD/011, painted 3 coats of approved color

    No. 16

    20,000.00

    320,000.00

    3.7.9 Allow for additional fittings, valves and thrust blocks as directed

    by the Engineer PS 1500,000.00

    500,000.00

    3.7.10 Percentage addition for the Contractor on Item 2.7.10 for

    attendance. %25.00 125,000.00

    3,552,000.00Carried to Collection

    Bill No. 3 Collectorpipes Interconsult in association with GK Works 15 of 28

  • 7/27/2019 Bills of Quantities for a Water Supply Scheme

    16/28

    Baseline Assessment, Design, Business Plan and Construction Supervision for Water Supply and Sanitation in Nthalire 160

    ITEM

    No.

    PAYMENT

    REFERENDESCRIPTION UNIT QTY RATE AMOU

    COLLECTION

    Page 13 7,895

    Page 14 20,318

    Page 15 3,552

    31,765TOTAL BILL No. 3: BOREHOLE COLLECTOR NETWORK

  • 7/27/2019 Bills of Quantities for a Water Supply Scheme

    17/28

    Baseline assessment, Design, Business Planning and Construction Supervision for Water Supply and Sanitation in Bolero

    ITEM

    No.

    PAYMENT

    REFERS

    DESCRIPTIONUNIT QTY RA

    BILL No. 6 - DISTRIUBUTION MAIN

    SABS 1200 C Site Clearance.

    A

    SABS 1200 DB

    8.3.1 (a)

    Clear route of pipeline of all grass, roots, rubbish, dead vegetation,

    weeds and scrub etc and thorn bushes, saplings and trees not

    exceeding 1000mm girth (measured 1000mm above ground level),

    grub up roots, fill in all holes and roughly level site ready

    m 12,300

    B

    8.3.1 (a) Cut down trees exceeding 1000 mm girth (measured 1000 mm above

    ground level ) but not exceeding 2000mm girth, grub up roots, log

    up and burn or remove from site and fill up holes and roughly level

    surface of filling

    No. 50 4

    C 8.3.1 (b) Ditto exceeding 2000mm but not exceeding 3000mm ditto. No. 25 6

    D 8.3.1 (b) Ditto exceeding 3000mm but not exceeding 5000mm ditto. No. 5 10

    Excavation

    8.3.2 (a)

    PS 2.6.1

    Excavate in normal material to width 500mm greater than the

    pipe nominal bore for pipe trenches, stockpile approved material

    for backfill and dispose of surplus/unsuitable material, lay, water

    and compact selected bedding material to specified densities,

    levels and slopes including all necessary planking and strutting,

    keeping excavations free from rain, surface and percolating

    water, mud and silt.

    110mm, for total trench depth not exceeding 1.5m m 470

    Ditto but trench exceeding 1.5m but not exceeding 3.0m m 0 2

    E 90mm, for total trench depth not exceeding 1.5m m 2,500

    F Ditto but trench exceeding 1.5m but not exceeding 3.0m m 1,500 1

    63mm, for total trench depth not exceeding 1.5m m 7,825

    G PS 2.3 E.O. items E through F for excavation of rock m 2,000 6

    HE.O. excavation for hand excavation in close proximity to existing

    services as ordered by the Engineer.m 300 1

    PS 2.8 Backfill with selected material from stockpile in layers not

    exceeding 150mm thick, well watered and rammed and

    consolidated as specified as follows:

    I 110mm dia. uPVC m 470

    K 90mm dia. uPVC m 3,500

    L 63mm dia. uPVC m 7,825

    M 80mm dia. GMS m 500

    Carried to Collection

  • 7/27/2019 Bills of Quantities for a Water Supply Scheme

    18/28

    Baseline assessment, Design, Business Planning and Construction Supervision for Water Supply and Sanitation in Bolero

    ITEM

    No.

    PAYMENT

    REFERS

    DESCRIPTIONUNIT QTY R

    APS 2.21 E.O. Item A for importing pipe surround material from a site beyond

    10 km.m

    3-km R.O

    B Ditto but bedding material. m3-km R.O

    CPS 2.21 E.O. items A for disposal of excess and/or unsuitable material to tip

    beyond 10 km as instructed by the Engineer. m-km R.O

    SABS 1200 L Pipe Laying

    8.2.1 Supply, lay, joint, test and disinfect pipes complete with couplings

    D PS 7.5 90mm dia.. uPVC Class 9 m 3,500

    E 160mm dia. uPVC Class 9 m R.O

    F 160mm dia. uPVC Class 20 m R.O

    G 110mm dia. uPVC Class 9 m 470

    H 63mm dia. uPVC Class 9 m 7,825

    Supply, lay, test and disinfect GS Socketed "Lula" or Similar

    approved

    I ND 80mm m 500

    J ND 100mm m

    K ND 150mm m R.O

    L ND 50mm m R.O

    8.2.2 Extra over pipe laying for supplying and laying/fixing of the

    following fittings complete with couplings

    Bends

    M PS 7.5 110mm dia. uPVC 22.5 degrees Bend Class 9 No. 0

    N 90mm dia. uPVC 45 degrees Bend Class 9 No. 5

    O 90mm dia. uPVC 90 degrees Bend Class 9 No. 0

    P 90mm dia. uPVC 22.5 degrees Bend Class 9 No. 0

    Q 90mm dia. uPVC 11.25 degrees Bend Class 9 No. 2

    R 63mm dia. uPVC 45 degrees Bend Class 9 No. 6

    S 63mm dia. uPVC 22.5 degrees Bend Class 9 No. 11

    T 63mm dia. uPVC 11.25 degrees Bend Class 9 No. 8

    U 63mm dia. uPVC 90 degrees Bend Class 9 No. 3

    V 110mm dia. uPVC 45 degrees Bend Class 9 No. 0

  • 7/27/2019 Bills of Quantities for a Water Supply Scheme

    19/28

    Baseline assessment, Design, Business Planning and Construction Supervision for Water Supply and Sanitation in Bolero

    ITEM

    No.

    PAYMENT

    REFERS

    DESCRIPTIONUNIT QTY

    A uPVC Tees

    Note: Where reducing tee is required to be made up of two or

    more components, the price shall include for all the componentsrequired

    110/90 dia. Unequal Tees No. 1

    90/40 Unequal Tees No. R.O

    90/63 Unequal Tees No. 156

    63/40 Unequal Tees No. 234

    110mm dia. Equal Tees No. 1

    90mm dia. Equal Tees No. 5

    63mm dia. Equal Tees No. 4

    B uPVC Reducers

    90x63 reducer No. 4

    90/40 reducer No. 20

    63/40 reducer No. 20

    uPVC END CAPS

    40 mm dia. end cap No. 10

    90 mm dia. end cap No. 1

    110mm dia end cap No. R.O

    160mm dia end cap No. R.O

    Carried to Collection

  • 7/27/2019 Bills of Quantities for a Water Supply Scheme

    20/28

    Baseline assessment, Design, Business Planning and Construction Supervision for Water Supply and Sanitation in Bolero

    ITEM

    No.

    PAYMENT

    REFERS

    DESCRIPTIONUNIT QTY RA

    Valve Chambers

    A

    SABS 1200 DB

    8.3.2 (a)SABS 1200 L

    8.2.13

    PS 7.9

    Excavate in normal material to depths up to 2.5m for Air Valve

    Chamber and construct chamber in reinforced concrete base Grade25/20, 230mm thick reinforced brickwall plastered internally and

    externally including all formwork, precast concrete cover slab,

    Medium Duty C.I. manhole cover and frame to SABS 558 Type 9A,

    Type 11A valve boxes, locking bar and padlock, vent pipe, dowel

    bars and lifting hooks, cast iron step irons, thrust blocks, etc as

    described on Drawing No. ISP/WS/STD/008. After construction

    backfill with selected material and compact in 150mm layers to 90%

    MOD AASHTO including the removal of all excess excavated

    material.

    No. 7 150,0

    B Ditto for wash out valves No. 9 120,0

    C Ditto for isolation valves No. 14 120,0

    Valves and Pipeworks

    D

    SABS 1200 L

    8.2.3

    PS 7.7

    Supply, install, test and commission PN16 Flanged Orifice Air Valve

    ND 25mm with Anti Shock Orifice Mechanism including all

    necessary pipework, fittings, etc as detailed on Drawing No.

    ISP/WS/STD 008

    No. 7 135,0

    E

    SABS 1200 L

    8.2.3

    PS 7.7

    Supply, install, test and commission Wash Out Valve ND 80mm

    including all necessary pipework, fittings, etc as detailed on Drawing

    Nos. ISP/WS/STD 009

    No. 9 75,0

    F

    SABS 1200 L

    8.2.3

    PS 7.7

    Supply, install, test and commission Sluice/Isolation Valve ND

    80mm including all necessary pipework, etc as specified on Drawing

    Nos. E118/STD/007 and 008

    No. 25 195,0

    8.2.3 Supply, lay, joint complete with fittings, incl cutting pipes where

    necessary, test, hand closing, rising spindle, with handwheel/cap

    top Gate Valves Class 16 on pipe sizes

    G 110mm dia. No. 2 135,0

    H 90mm dia. No. 9 125,0

    I 63mm dia. No. 16 115,0

    SABS 1200 L

    8.2.11

    PS 7.20

    Anchor/Thrust blocks and pedestals for the following pipe

    diameters as described on Drawing No. ISP/WS/STD 0017: Note

    that thrust blocks are measured as a number where the type of

    thrust blocks include tees, bends, reducers and end caps.

    J 160mm dia. No. R.O. 20,0

    K 110mm dia. No. 2 15,0

    L 90mm dia. No. 10 10,0

    M 63mm dia. No. 12 6,0

    N

    PS 7.21 Supply and install precast concrete Marker Posts as described on

    Drawing No. ISP/WS/STD 0014, painted wth 3 coats of approved

    paint

    No. 85 5,0

    OAllow for additional fittings, valves and thrust blocks as directed by

    the EngineerPS 1 500,0

    P Percentage addition for the Contractor on Item J for attendance. %

    SABS 1200 DB

    8.3.6

    Allow for pipe protection at gravel/dirty road crossings including

    backfilling and compacting with selected material, precast concrete

  • 7/27/2019 Bills of Quantities for a Water Supply Scheme

    21/28

    Baseline assessment, Design, Business Planning and Construction Supervision for Water Supply and Sanitation in Bolero

    ITEM

    No.

    PAYMENT

    REFERS

    DESCRIPTIONUNI

    COLLECTION

    Page 17

    Page 18

    Page 19

    Page 20

    TOTAL BILL No.5 - DISTRIUBUTION MAIN

  • 7/27/2019 Bills of Quantities for a Water Supply Scheme

    22/28

    Baseline assessment, Design, Business planning and Construction Supervision for Water Supply and Sanitation in Nthalire 160418024.xls.ms_office

    ITEM

    No.

    CLAUSEDESCRIPTION UNIT Q'TY RATE TOTAL

    BILL No. 7 - SERVICE RESERVOIRS

    PS 8.2

    PS 8.3

    Design, supply , transport to site, erect, clean, and

    commission GS panel ground tank as specified

    complete with fittings, plate covers, access and inletladders, walkways, handrails, all four pipe

    connections (inlet, outlet, overflow and scour

    pipework as specified on drawing No. ISP/WS/STD

    0020), level indicators, level control valves, access

    manholes, ventilators and holding down bolts in

    accordance with the manufacturers instructions

    including all the necessary site clearing and leveling,

    removal of rocks and boulders, excavations for

    foundations in normal material and in rock,

    foundation preparation, backfilling, concrete works

    and reinforcement.

    A 150m3

    Tanks No. 1 15,000,000.00 15,000,000.00

    C Allow for connection of tank to inlet and outllet pipes sum 1 1,000,000.00 1,000,000.00

    PS 8.4 Disinfection and Water Testing

    Allow for all costs connected with preparing for and

    carrying out the procedures described in the Project

    Specification for the disinfection and water testing of

    the reservoirs complete:

    D Primary disinfection No. 1 200,000.00 200,000.00

    E Water Testing No. 1 200,000.00 200,000.00

    F Bacteriological testing No. 1 50,000.00 50,000.00

    G Secondary disinfection No. 1 100,000.00 100,000.00

    H PS 12.1 Supply all materials and construct 1.8m high rust-proof

    security boundary fence around reservoir with all posts

    and bases including excavation, concrete and backfilling

    as required. m 80 15,000.00 1,200,000.00

    17,750,000.00Carried to Collection

    Bill No. 5StorageRes Interconsult pvt Limited in association with GK Works 22 of 28

  • 7/27/2019 Bills of Quantities for a Water Supply Scheme

    23/28

    Baseline assessment, Design, Business planning and Construction Supervision for Water Supply and Sanitation in Nthalire 160418024.xls.ms_office

    ITEM

    No.

    CLAUSEDESCRIPTION UNIT Q'TY RATE TOTAL

    WATER METERS

    Supply, lay, joint complete with fitting including

    cutting pipes where necessary and all necessary

    connections, test according to drawing number

    ISP/WS/STD 0015

    A

    Meinecke Cosmos WPD-200 or similar approved water

    meter

    No. 2 350,000.00 700,000.00

    B

    Meinecke Cosmos strainer WPD or similar approved

    strainer boxNo. 2 350,000.00 700,000.00

    1,400,000.00Carried to Collection

    Bill No. 5StorageRes Interconsult pvt Limited in association with GK Works 23 of 28

  • 7/27/2019 Bills of Quantities for a Water Supply Scheme

    24/28

    Baseline assessment, Design, Business planning and Construction Supervision for Water Supply and Sanitation in Nthalire 160418024.xls

    ITEM

    No.

    CLAUSEDESCRIPTION UNIT Q'TY RATE TOTAL

    COLLECTION

    Page 24 17,750,000.00

    Page 25 1,400,000.00

    19,150,000.00

    TOTAL BILL No. 6 - SERVICE RESERVOIRS TO MAIN SUMMARY

  • 7/27/2019 Bills of Quantities for a Water Supply Scheme

    25/28

    Baseline assessment, Design, Business planning and Construction Supervision for Water Supply and Sanitation in Nthalire 160418024.xls.ms_office

    ITEM

    No.

    CLAUSEDESCRIPTION UNIT Q'TY RATE TOTAL

    BILL No. 10 - SANITATION

    1MARKET CENTRE VIP LATRINE (8 No. Double

    Door Latrines)

    SUBSTRUCTURE

    A Excavation pit trench 0 to 1500mm deep m2 23 6,000.00 140,640.00

    B Ditto 1500 to 4000mm m2 40 7,000.00 280,000.00

    C Lean concrete filling around foundation brick work m 24 39,000.00 936,000.00

    DExcavated material from excavations, transported

    deposited and spread on site in 150mm layers.m 40 7,000.00 280,000.00

    E Extra-over for excavating in rock m 24 7,500.00 180,000.00

    CONCRETE WORK

    FPlain in-situ concrete (class 21n/mm2/20mm) in

    basement 100mm thick.m 16 49,000.00 784,000.00

    SUBSTRUCTURE BLOCKWORK

    G

    220mm thick concrete hollow blocks wall bedded in

    sand and cement mortar (1:4) and reinforced every

    fourth coarse

    m2 128 6,700.00 857,600.00

    REINFORCED CONCRETE

    H 100mm thick slab 2000x1000mm wide m 44 60,700.00 2,670,800.00

    FORM WORK

    I Sawn form work to soffit slab m 44 2,500.00 110,000.00

    J Ditto to edge of slab 100 to 150mm wide m 52 3,000.00 156,000.00

    SUPER STRUCTURE

    BLOCK WORK

    K

    240mm thick Stabilised soil block wall bedded in sand

    and cement mortar (1:4) reinforced every fourth coarse. m 80 7,500.00 600,000.00

    6,995,040.00CARRIED TO COLLECTION

    Bill No. 8 Sanitation Interconsult pvt Limited in association with GK Works 25 of 28

  • 7/27/2019 Bills of Quantities for a Water Supply Scheme

    26/28

    Baseline assessment, Design, Business planning and Construction Supervision for Water Supply and Sanitation in Nthalire 160418024.xls.ms_office

    ITEM

    No.

    CLAUSEDESCRIPTION UNIT Q'TY RATE TOTAL

    ROOFING

    M

    28 gauge Corrugated Iron roof sheets fixed to 100 x

    50mm softwood timber purlins with screws and sealed

    polythane washers.

    m 40 5,000.00 200,000.00

    CARPENTRY

    Unless otherwise stated all timber is Kiln Dried

    Pressure Treated Soft Wood

    N 150 x 50mm timber rafters m 44 1,500.00 66,000.00

    O 100 x 50mm wall plate m 32 1,000.00 32,000.00

    P 100 x 50mm purlins m 84 1,000.00 84,000.00

    PLASTER WORK

    20mm rendering sand and cement mortar (1:4)finished in wood float on:

    Q Internal brick wall m 80 745.00 59,600.00

    SELECTED BRICKS IN COMPOSITION

    MORTAR (1:3) BUILT TO A FAIR FACE WITH

    10 mm RECESSED FLAT HORIZONTAL JOINTS

    AND 10 mm RECESSED FLAT PERPENDS

    R Fair face and pointing m 80 600.00 48,000.00

    PAINTING AND DECORATING

    S Two coats lime wash on internal rendered walls m 80 350.00 28,000.00

    ROOF ANCHORAGE

    12mm dia rods as anchor straps, min 1500 long, built

    into brickwork and bent over rafters at top and bottom kg 20 375.00 7,500.00

    REINFORCED CONCRETE (GRADE 20/20)

    215x215 reinforced beams under crosswalls m3 2 49,000.00 117,600.00

    MILD STEEL BAR REINFORCEMENT (All

    Provisional)

    6 mm Diameter bars kg 64 375.00 24,000.00

    HIGH TENSILE DEFORMED BAR

    REINFORCEMENT (All Provisional)

    12 mm Diameter bars kg 64 375.00 24,000.00

    SAWN FORMWORK

    Sides and soffits of lintols m2 12 5,000.00 60,000.00

    750,700.00Carried to Collection

    Bill No. 8 Sanitation Interconsult pvt Limited in association with GK Works 26 of 28

  • 7/27/2019 Bills of Quantities for a Water Supply Scheme

    27/28

    Baseline assessment, Design, Business planning and Construction Supervision for Water Supply and Sanitation in Nthalire 160

    ITEM

    No.

    CLAUSEDESCRIPTION UNIT Q'TY RATE TOTAL

    Page 64 6,995,040.0

    Page 65 750,700.0

    7,745,740.0

    COLLECTION

    TOTAL BILL No.9 - SANITATION TO MAIN SUMMARY

  • 7/27/2019 Bills of Quantities for a Water Supply Scheme

    28/28

    Baseline assessment, Design Business plan and Construction Supervision for Water Supply and Sanitation in Nthalire 160418024.xls.ms_office

    ITEM

    NO.

    DESCRIPTION AMOUNT (MK)

    MAIN SUMMARY

    1 BILL No.1: PRELIMINARY AND GENERAL 36,735,000.00

    2 BILL No. 2: BOREHOLE DRILLING, CIVIL WORKS AND PUMP INSTALLATION21,164,530.00

    3 BILL No. 3: BOREHOLE COLLECTOR PIPES 31,765,955.00

    4 BILL No. 4: DISTRIBUTION MAIN 58,371,987.00

    5 BILL No. 5: STORAGE RESERVOIRS 19,150,000.00

    6 BILL No. 6: MISCELLANEOUS 0.00

    7 BILL No. 7: OFFICE BUILDING 0.00

    8 BILL No. 8: SANITATION 7,745,740.00

    9 BILL NO. 9 PLOT CONNECTIONS 0.00

    SUB TOTAL174,933,212.00

    Add 16.5% VAT28,863,979.98

    TOTAL BID 203,797,191.98