Bill of Material for Foundation

download Bill of Material for Foundation

of 8

Transcript of Bill of Material for Foundation

  • 8/2/2019 Bill of Material for Foundation

    1/8

    Qty Rate Unit Amount

    1 Soil investigation 30 2850 m 85500

    2 Earthwork excavation incl blasting 1000 225 cum 225000 3

    3 Supply for PCC M25 25 4400 cum 110000

    4 Labour for PCC M25 25 300 cum 7500 1

    5 Labour for steel reinforcement 49 5500 MT 269500 5

    6 Supply of Fe500 steel 49 46000 MT 2254000

    7 Supply of RCC M37 438 4910 cum 2150580

    8 Labour for RCC M37 438 250 cum 109500 2

    9 Shuttering 92 275 sqm 25300 1

    10 PVC conduit placing LS 17500

    11 Curing LS 12000

    12 Backfilling 480 100 cum 48000

    13 Re Engg, if any LS

    14 Hard topping LS

    15 Leveling, re vegetation etc LS

    16 Supervision, Materials testing, LS 35000

    Embed placing, Safety, overhead etc

    0

    17 High resistance grouting

    5349380 12

    Cost Saving with anchor bolt foundation = 4.40 LEffective working days with anchor bolt foundation = 6 days more than embed foundatio

    FOUNDATION COST DIFFERENECE ANALYSI

    S.No Work description

    Embed section foundationNo of Days

    Say Rs.53.50L

    Total Cost =

  • 8/2/2019 Bill of Material for Foundation

    2/8

    Qty Rate Unit Amount

    30 2850 m 85500

    1400 225 cum 315000 4

    27 4400 cum 118800

    27 300 cum 8100 1

    55 5500 MT 302500 8

    55 46000 MT 2530000

    226 4910 cum 1109660

    226 300 cum 67800 3

    160 450 sqm 72000 2

    15000

    20000

    1145 150 171750

    LS 35000

    LS 60000

    4911110 18

    (Approx)

    Total cost =

    S

    No of Days

    Say Rs.49.10L

    Anchor bolt foundation (Approx)

  • 8/2/2019 Bill of Material for Foundation

    3/8

    S.NOPosition

    NoDescription

    Diameter of

    Rebar (mm)

    Length

    (mm)

    Nos of

    Rods

    As per

    Drawing

    Qty as per

    Drawings

    Qty as

    per ManualUnits

    2

    Supporting Bars

    Connection

    System with tower

    0 0 0 29.92 29.92 Kg

    3.1 Type

    Reiniforcement25 2370 296 2700.86 2706.65 Kg

    3.2 Type

    Reiniforcement20 2310 296 1688.88 1688.40 Kg

    4.1Star Reinforcement

    in Walls32 8360 8 422.01 422.77 Kg

    4.2Star Reinforcement

    in Walls25 7370 8 227.00 227.48 Kg

    5.1Circular Type

    Reinforcement20 6390 8 126.27 126.23 Kg

    5.2Circular Type

    Reinforcement 20 7900 8 156.10 156.06 Kg

    5.3Circular Type

    Reinforcement20 8180 8 161.64 161.59 Kg

    6 Cleaning Concrete 0 0 0 26.88 26.88 m3

    7 Structural Concrete 0 0 0 213.74 213.74 m3

    8Structural Concrete

    In the Last 0.3 Mts0 0 0 11.29 11.29 m

    3

    9 Pipes for cables

    10 ElectricalEarthing Rods

    20 750 4 15.00 11.29 Kg

    11 Ducting Prism

    12.1

    Slab Basic Lower

    Reinforcement 1

    ( A+B)

    25 8300 40 1293.60 1293.60 Kg

    12.2

    Slab Basic Lower

    Reinforcement 2

    ( A+B)

    25 12000 146 6745.20 6759.69 Kg

    12.3

    Slab Basic Lower

    Reinforcement 3

    ( A+B)

    25 5415 148 3085.47 3092.09 Kg

    13

    Slab Additional Lower

    Reinforcement 1

    ( A+B+C+D)

    25 8150 192 6024.48 6037.42 Kg

    14

    Slab Additional Lower

    Reinforcement 2

    ( A+B+C+D)

    25 3730 160 2450.44 2450.44 Kg

    15

    Slab Additional Lower

    Reinforcement 3

    ( A+B+C+D)

    25 3625 80 1121.12 1121.12 Kg

    ANCHOR BOLT FOUNDATION BILL OF MATERIAL

    3

    4

    5

    12.1

  • 8/2/2019 Bill of Material for Foundation

    4/8

    S.NOPosition

    NoDescription

    Diameter of

    Rebar (mm)

    Length

    (mm)

    Nos of

    Rods

    As per

    Drawing

    Qty as per

    Drawings

    Qty as

    per ManualUnits

    ANCHOR BOLT FOUNDATION BILL OF MATERIAL

    16 16.1

    Slab Basic

    Upper

    Reinforcement 1( E+F)

    25 8300 40 1293.60 1293.60 Kg

    16.2

    Slab Basic

    Upper

    Reinforcement 2

    ( E+F)

    25 12000 146 6745.20 6759.69 Kg

    16.3

    Slab Basic

    Upper

    Reinforcement 3

    ( E+F)

    25 6055 148 3450.14 3457.55 Kg

    17Slab Additional

    Reinforcement12 8000 72 512.64 512.03 Kg

    18.1Flexural

    Reinforcement

    of Walls ( A1)

    25 3010 112 1330.25 1330.25 Kg

    18.2

    Flexural

    Reinforcement

    of Walls ( A1 4B-1)

    20 4250 64 696.34 696.34 Kg

    18.3

    Flexural

    Reinforcement of

    walls

    16 5670 64 594.59 594.59 Kg

    18.4

    Flexural

    Reinforcement of

    walls

    16 6870 16 174.94 173.71 Kg

    19Shear Reinforcement

    of Walls

    20 2587.5 704 4499.35 4498.06 Kg

    20Pedestal

    Reinforcement16 3290 24 125.14 124.78 Kg

    21

    Principal

    Reinforcement

    in PCB Ext.Neck

    16 5370 74 627.86 628.00 Kg

    22.1Angular Upper rings

    in Pedestal Ext Neck16 7483 2 23.65 23.65 Kg

    22.2Angular Upper rings

    in Pedestal Ext Neck16 5943 2 18.78 18.78 Kg

    22.3Angular Upper rings

    in Pedestal Ext Neck16 5311 2 16.78 16.79 Kg

    22.4Angular Upper rings

    in Pedestal Ext Neck16 4609 4 29.14 29.14 Kg

    23Lateral Rings

    in Ped.Neck16 8860 36 503.96 504.07 Kg

    24.1a

    Slab Shear

    Reinforcement

    Zone 1

    14 3940 16 98.35 98.35 Kg

    24.1b

    Slab Shear

    Reinforcement

    Zone 1

    14 5290 64 305.11 409.64 Kg

    16

    18

    22

    24

  • 8/2/2019 Bill of Material for Foundation

    5/8

    S.NOPosition

    NoDescription

    Diameter of

    Rebar (mm)

    Length

    (mm)

    Nos of

    Rods

    As per

    Drawing

    Qty as per

    Drawings

    Qty as

    per ManualUnits

    ANCHOR BOLT FOUNDATION BILL OF MATERIAL

    24.2

    Slab Shear

    Reinforcement

    Zone 2

    12 3990 240 852.27 851.25 Kg

    25

    Upper Interface

    Radial

    Reinforcement

    25 2060 222 1760.68 1764.46 Kg

    26 26.1

    Upper Interface

    Circular

    Reinforcement

    20 6250 6 92.63 92.60 Kg

    26.2

    Upper Interface

    Circular

    Reinforcement

    20 7200 6 106.71 106.67 Kg

    26.3

    Upper Interface

    Circular

    Reinforcement

    20 8150 6 120.78 120.75 Kg

    26.4

    Upper Interface

    Circular

    Reinforcement

    20 8915 6 132.12 132.08 Kg

    1.1Bars of 36 Dia with

    threaded ends36 3750 148 4435.00 4440.28 Kg

    1.4Lower Anchorage

    Flange1643.00 1643.00 Kg

    1.5Upper Anchorage

    Template

    947.00 947.00 Kg

    1.6 Tower Bottom Flange 2513.00 2513.00 Kg

    1.9Hight Resistance

    Grout0.28 0.28 m

    3

    50329.08 50521.60 Kg

    9538.00 9543.28 Kg

    251.91 251.91 m3

    0.28 0.28 m

    3

    Comments :

    Qty of High Resistance Grout

    Summary

    Qty of Steel

    Qty of Anchore Bolts

    Qty of Concrete

    DETAILS OF ANCHOR ROD

  • 8/2/2019 Bill of Material for Foundation

    6/8

  • 8/2/2019 Bill of Material for Foundation

    7/8

    S.N

    Positio

    n

    No

    Description

    Diameter

    of

    Rebar

    (mm)

    Length

    (mm)

    Nos of

    Rods

    As per

    Drawing

    Qty as per

    Drawings

    Qty as

    per ManualUnits

    EMBEDDED SECTION FOUNDATION BILL OF MATERIAL

    21 23 UpperReinforcements

    ( Central to Sides T1)

    25 5580 12 258 258.35 Kg

    22 24

    Upper

    Reinforcements

    ( Central to Sides T2)

    25 5720 8 176.3 176.55 Kg

    23 25

    Upper

    Reinforcements

    ( Central to Sides T3)

    25 5960 8 183.7 183.96 Kg

    24 26

    Upper

    Reinforcements( Central to Sides T4)

    25 6380 8 196.92 196.93 Kg

    25 27

    Upper

    Reinforcements

    ( Central to Sides T5)

    25 7070 4 109.12 109.11 Kg

    26 28

    Upper

    Reinforcements

    (Central - T1)

    25 3490 12 161.58 161.58 Kg

    27 29

    Upper

    Reinforcements

    Central - T2

    25 3630 8 112.04 112.04 Kg

    28 30

    Upper

    Reinforcements

    (Central - T3)

    25 3865 8 119.3 119.30 Kg

    29 31

    Upper

    Reinforcements

    (Central - T4)

    25 4290 8 132.43 132.42 Kg

    30 32

    Upper

    Reinforcements

    (Central - T5)

    25 4980 4 76.86 76.86 Kg

    31 33L Reinforcement

    Inside the Pedestal20 2275 68 381.9 382.00 Kg

    32 34

    Rings of Central

    Reinforcements of

    Pedestal

    20 10950 3 81.17 81.12 Kg

    33 35 Upper Reinforcementof Pedestal - T1 20 1900 8 37.53 37.53 Kg

    34 36Upper Reinforcement

    of Pedestal - T220 2490 12 73.78 73.78 Kg

    35 37Upper Reinforcement

    of Pedestal - T320 3090 18 137.34 137.34 Kg

    36 38

    Principal

    Reinforcements in

    Ext Neck of Pedestal

    16 2095 102 337.7 337.70 Kg

    37 39Rings in Exterior

    Neck of Pedestal16 12000 7 132.75 132.75 Kg

  • 8/2/2019 Bill of Material for Foundation

    8/8

    S.N

    Positio

    n

    No

    Description

    Diameter

    of

    Rebar

    (mm)

    Length

    (mm)

    Nos of

    Rods

    As per

    Drawing

    Qty as per

    Drawings

    Qty as

    per ManualUnits

    EMBEDDED SECTION FOUNDATION BILL OF MATERIAL

    38 40

    Auxillary Reinf Int.

    Ring Ext . NeckPedestal

    16 1750 1 2.765 2.77 Kg

    39 41

    Auxillary Reinf Mid.

    Ring Ext . Neck

    Pedestal

    16 2170 1 3.43 3.43 Kg

    40 42

    Auxillary Reinf Ext.

    Ring Ext . Neck

    Pedestal

    16 2600 1 4.11 4.11 Kg

    41 43

    Contour

    Auxil.Reinforcing

    Neck Ped

    16 2750 4 17.38 17.38 Kg

    1 261 261.00 Kg

    2 12108 12108.00 Kg

    57273.21 57337.94 Kg

    12369.00 12369.00 Kg

    414.00 414.00 m3

    Comments :

    Foundation Levelling System

    Foundation section

    DM 3740 T40 1288 M42

    Summary

    Qty of Steel

    Qty of Anchore Bolts

    Qty of Concrete

    EMBED SECTION DETAILS