Big Pipeline Crossing Protection Project for Williams on the Guadalupe River, South of Victoria, TX....

35
Protection Project for Williams on the Guadalupe River, South of Victoria, TX. (near the harbor) 1.3 Million Dollars Took 3 crews 6 weeks to build!! Summer 2005

Transcript of Big Pipeline Crossing Protection Project for Williams on the Guadalupe River, South of Victoria, TX....

Big Pipeline Crossing Protection Project for Williams on the Guadalupe River, South of

Victoria, TX. (near the harbor)

1.3 Million DollarsTook 3 crews 6 weeks to build!!

Summer 2005

DEEP PLANTING HUNDREDS OF

UNROOTED WILLOW POLES WHEN THE

COLDEST DAY WAS 103 DEGREES

• Bank erosion (lateral erosion) has exposed over 100 ft of pipeline, threatening pipeline integrity

• Co-designed by River Research & Design, Inc. & Submar, Inc. Contractor: Submar, Inc.

• Not a flashy stream, stays on the flood for months at a time

• Bed material: sand-silt-clay, not incised, rural.

• Pool-riffle-pool regime, slope < 1%

• Average width 100-150 ft, 10-18 ft tall banks

Guadalupe River @ Williams Pipeline Crossing, South of Victoria, TX (near the harbor)

PRE-PROJECT PHOTOS:

OCTOBER 2004 TO

FEBRUARY 2005

PRE-PROJECT Guadalupe River @ Williams Pipeline-Derrick-Oct 1, 2004

PRE-PROJECT-Looking US at the exposed pipeline, flow splits around island. Split flow always brings its own

challenges!!

PRE-PROJECT Guadalupe River @ Williams Pipeline-Derrick-Oct 1, 2004

PRE-PROJECT-Looking DS at the exposed pipeline.

Flow

THREE BENDWAY WEIRS

Bendway Weir #1BW

#2BW

#3

6 MONTHS LATER-Looking US. Bendway Weirs managing the thalweg.

6 MONTHS LATER-Guadalupe River-Mark Bordelon -3-14-2006

WILLOW PLANTING

Very hot down in Victoria, TX {103 degrees}. This was the

coldest day, it hit 112 degrees some days. We cut several

hundred willow branches & small trunks (3/4” to 1.5” butt

diameter, 6’ to 8 ft long, soaked them for 10 days, then

planted & watered them in (July-Aug time frame).

CONSTRUCTION-Guadalupe River @ Pipeline-John Lewis-July 2005

CONSTRUCTION-The constructed soaking pool for the willows. Pumps kept it full. Willows were cut & soaked for 10 days.

CONSTRUCTION-Guadalupe River @ Pipeline-Derrick – June 3, 2005

Live Siltation above LPSTP

Longitudinal Peaked Stone Toe Protection

CONSTRUCTION-Looking US. LPSTP in. Prepping bank for willows

CONSTRUCTION-Guadalupe River @ Pipeline-John Lewis-July 2005

CONSTRUCTION-Looking down slope @ row of willows above LPSTP, 2/3 in ground, 1/3 out. Riprap above willows.

CONSTRUCTION-Guadalupe River @ Pipeline-John Lewis-June 17, 2005

CONSTRUCTION-Looking US. Watering in live willow poles

CONSTRUCTION-Guadalupe River @ Pipeline-John Lewis-July 2005

CONSTRUCTION-Looking DS @ rows of willows & stone protection.

CONSTRUCTION-Guadalupe River @ Pipeline-John Lewis-June 17, 2005

13 MONTHS LATER-High water. Looking downhill @ riprap & rows of willows starting to flush (grow leaves).

13 MONTHS LATER-Guadalupe River Mark Bordelon 10-12-05

THE BEFORE & AFTERS

LOOKING FROM

UPSTREAM TO

DOWNSTREAM

PRE-PROJECT-Guadalupe River @ Williams Pipeline-Derrick-Oct 1, 2004

PRE-PROJECT-From US project limit, looking DS @ exposed pipe & vertical bank, thalweg slamming straight into bank

26 MONTHS LATER-From US project limits, looking DS. Three Bendway Weirs aligning thalweg along flow arrow

26 MONTHS LATER-Guadalupe River @ Williams Pipeline-Derrick 11-6-07

PRE-PROJECT Guadalupe River @ Williams Pipeline-Derrick-Oct 1, 2004

PRE-PROJECT-Looking DS at the exposed pipeline, thalweg impacting bank.

26 MONTHS LATER-Looking DS @ the protected pipeline, thalweg redirected & willow growth 8 to 16 ft tall after 2 years.

26 MONTHS LATER-Guadalupe River @ Williams Pipeline-Derrick 11-6-07

PRE-PROJECT Guadalupe River @ Williams Pipeline-Derrick-Oct 1, 2004

PRE-PROJECT-Looking DS at the exposed pipeline. Debris on pipeline, thalweg flowing under pipe.

26 MONTHS LATER-Looking DS @ the protected pipeline, great willow growth US & DS of pipeline right-of-way (hydraulic roughness).

26 MONTHS LATER-Guadalupe River @ Williams Pipeline-Derrick 11-6-07

26 MONTHS LATER-Looking DS, good sediment deposition on stone under dense 8 to 16 ft tall, 2”- 4” diameter willows.

26 MONTHS LATER-Guadalupe River @ Williams Pipeline-Derrick 11-6-07

26 MONTHS LATER-Uphill from large willows, great deposition on top of riprap

26 MONTHS LATER-Guadalupe River @ Williams Pipeline-Derrick 11-6-07

26 MONTHS LATER-Uphill from willows, grasses growing on deposited sediment

26 MONTHS LATER-Guadalupe River @ Williams Pipeline-Derrick 11-6-07

26 MONTHS LATER-Close-up on deposition and grasses (not planted).

26 MONTHS LATER-Guadalupe River @ Williams Pipeline-Derrick 11-6-07

26 MONTHS LATER-Thick ridge of deposition DS of willows (shadow).

26 MONTHS LATER-Guadalupe River @ Williams Pipeline-Derrick 11-6-07

26 MONTHS LATER-Thick deposition around planted willow.

26 MONTHS LATER-Guadalupe River @ Williams Pipeline-Derrick 11-6-07

26 MONTHS LATER-Native willow seedlings growing on deposition on top of riprap. We have turned a vertical eroding bank into a depositional area

with volunteer tree growth!!! Success & long-term stability!!

26 MONTHS LATER-Guadalupe River @ Williams Pipeline-Derrick 11-6-07

This PowerPoint presentation was developed & built by Dave Derrick.

Any questions or comments, call my personal cell @ 601-218-7717, or email @ [email protected]

Enjoy the information!!

Peyton & Fred