BID CLARIFICATION #1 - University of Connecticut · Factory Mutual Insurance ... FM Global Property...
-
Upload
nguyenkhue -
Category
Documents
-
view
214 -
download
0
Transcript of BID CLARIFICATION #1 - University of Connecticut · Factory Mutual Insurance ... FM Global Property...
BID CLARIFICATION #3
December 11, 2014
DUE DATE: January 9, 2015
TIME: 2:00 p.m.
PROJECT: Replace Gampel Cooling Towers
PROJECT NO: #901795
LOCATION: University of Connecticut
Capital Projects & Contract Administration
3 North Hillside Road
Storrs, CT 06269
Attn: Amy Allen
Please note the following information must be incorporated into your bid for the
Replace Gampel Cooling Towers, Project #901795:
1) The pre-bid sign in sheet dated December 10, 2014 is attached below.
2) The proposed site logistics plan is attached below.
3) A second site walkthrough will be held on Wednesday December 17, 2014 at 2:30PM. We will meet at the
entrance next to the temporary cooling tower.
4) The RFI due date has been extended from Monday December 15, 2014 at 2PM to Monday December 22, 2014
at 2PM.
5) Temporary Chiller:
a) Regarding note 4 on drawing M-1.00 and M-101: A temporary chiller is already in place. The
University has rented this chiller from Aggreko, and this rental period will end on February 27, 2015.
After that date, the contractor will be responsible for providing a rental chiller to maintain chilled water
service while the cooling towers are being replaced. Refer to drawings M-100, M-101, M-301, E-101 and E-
201 for hook-up details.
b) Regarding the electrical hookups for the temporary chiller as shown on E-101 and E-201, the
disconnect switch will be relocated for the outside of the wall to the inside of the wall.
6) Revision of Paragraph 1.6A.1 in section 01-1000 Summary of Work to state “1. The successful bidder shall
obtain the Certificate of Substantial Completion as defined in the Contract Documents within 240 calendar
days of the Notice to Proceed.”
7) Contractor is responsible for completing the FM Global for 2688 (attached below) as coordinated with the
requirements outlined in the FM Global Review document dated June 26, 2014 attached below.
8) Contractor shall manage all employees entering/exiting the building (Gampel Pavilion) via daily sign-in and
sign-out sheet, the sheet must be submitted to the University.
9) Contractor shall closely coordinate all activities with UConn PM, UConn personnel and UConn operations, to
allow for proper access or escorted access into the spaces, and to minimize downtime of impacted areas.
10) Contractor shall not disrupt operations in the Laundry Room area until after May 1, 2015. In the event the
contractor needs to work in this room prior to May 1, 2015, contractor shall make the necessary temporary
connections to allow for continuous operations of all affected equipment in the Laundry Room, mainly washers
and dryers.
The University of Connecticut Bid Submission Requirements:
All bidders must submit their Form of Proposal along with all required forms and any associated bid
clarifications as your firm’s bid proposal. All required forms must be completed.
All bidders must initial the bottom of each page within their bid proposal and associated Bid
Clarifications attesting to the fact that you have reviewed, read, understood, and accepted the
information and terms and conditions within, without exception.
YOUR BID PROPOSAL MAY BE CONSIDERED NON-RESPONSIVE AND MAY NOT BE
REVIEWED FOR FAILURE TO SUBMIT ALL OF THE ABOVE DOCUMENTATION (ALONG
WITH ANY OTHER DOCUMENTATION DETAILED IN THE BID DOCUMENTS AND
SPECIFICATIONS)
All bid awards must be approved by the University of Connecticut. After review of all factors,
terms and conditions, including price, the University of Connecticut reserves the right to reject any
and all proposal, or any part thereof, or waive defects in same, or accept any proposal deemed to be
in the best interest of the University of Connecticut
University of Connecticut Amy Allen, Purchasing Agent II
Plan Review
Factory Mutual Insurance Company (FM Global) has developed this report for insurance underwriting purposes. The report is provided to you for informational purposes only to reduce the possibility of loss to insured property by bringing to your attention certain potential hazards or conditions. Life, safety, or health issues are not
addressed. You must make the decision whether to take any action. FM Global undertakes no duty to you or any other party by providing this report or the activities on
which it is based. The liability of FM Global is limited to that contained in its insurance policies.
7281A (03/13)
State of Connecticut
“University of Connecticut - Storrs Campus”
85 Walters Avenue
Storrs Mansfield, CT 06269-9027
USA
Index-Rec No: 17725.05-02
Account No: 30882
Date of Review: June 26, 2014
Review No: 189505
Plans Submitted By: Mr. Michael Rocchetti, University of Connecticut
Subject: Construction drawings and specs for Gampel Cooling Towers – Project 901795
Executive Summary: This project involves the removal of two 400 ton cooling towers at the Gampel building. The towers will be
replaced with modern units to be located atop a new heated mechanical room in the same area.
This submittal is not in accordance with FM Global Standards. Completion of review comment No. 2 is
required for design acceptance of this submittal. Additionally, several other review comments in this letter are
requesting additional information to be provided when it becomes available. This information will be needed for
full design review of this project.
Scope of Review: This confirms the receipt and review of:
Drawing package dated June 5, 2014
The table of contents for the project manual associated with this project
Draft Construction Cost Estimate Document
The existing 400 ton cooling towers will be removed. The existing exterior mechanical walled compound will be
enclosed to create a heated mechanical room space that will house the following components: A large remote
sump tank for the cooling tower water, new condenser water pumps, piping, valves and controls. The mechanical
room will also be built with two new 4 in. floor drains and a sump pump. The new 400 ton towers will be located
on the roof of this mechanical room. New piping connections and valves will be provided for the condenser water
supply and return lines from the two existing 400 ton chillers in the adjacent mechanical room. The new towers
will be equipped with make up water line and water level controls and the new towers will be integrated into the
existing building management system.
The replacement towers will be modern 400 ton induced draft cross flow cooling towers.
Review Comments: Cooling Towers:
1. Drawing M-501 of this submittal package calls for two FM Approved cooling towers Baltimore Aircoil
Model 3455C_LM/QV. This is considered acceptable per the FM Global approval guide only when
Page 2 of 4
Factory Mutual Insurance Company (FM Global) has developed this report for insurance underwriting purposes. The report is provided to you for informational purposes only to reduce the possibility of loss to insured property by bringing to your attention certain potential hazards or conditions. Life, safety, or health issues are not addressed. You must make the decision whether to take any action. FM Global undertakes no duty to you or any other party by providing this report or the activities on
which it is based. The liability of FM Global is limited to that contained in its insurance policies.
installed in multi-cell (two or more cells) fashion. The exact number of cells chosen is determined by the
application and its anticipated seasonal operating strategy which includes consideration of cell outage due
to fire damage, mechanical failure and preventive maintenance such that sufficient cooling capacity is
available to enable normal business and manufacturing operations to continue throughout the year. Please
provide documentation confirming that these cooling towers will be installed with a cell arrangement
that is in accordance with their FM Approval listing.
This drawing also indicates that the mechanical contractor may propose a substitute model and if this is
done, the replacement tower must be an FM Approved model. Please notify FM Global if a substitute
tower is selected and provide manufacturers cut sheets so that approval listing can be confirmed.
Roof:
2. This project involves the installation of an EPDM roof over the new mechanical room that will be
constructed in the location of the existing cooling towers. Full details of this roof cover were not included
in this submittal; however, loading and uplift design criteria were specified on the drawings. The specified
criteria are not acceptable. The following should be used instead: Snow load - 35 psf, Wind Speed – 100
mph, Importance Factor - 1.15, Exposure Classification – C. Please provide a detailed roof submittal
utilizing these design criteria. The roof submittal should include an FM Global RoofNav number
that specifies all roofing components as an assembly. Additionally, FM Global should be forwarded
the completed FM Global Form 2688, Checklist for Roofing System (attached)
3. Steel deck fastening should be specified in any new roof submittals. Fastening rates should be selected in
accordance with FM Global Property Loss Prevention Data sheet 1-29 Roof Deck Securement and Above
Deck Roof Components.
4. Perimeter flashing and nailer assemblies are specified to be designed and installed per Data Sheet, 1-49,
Perimeter Flashing. Please submit materials and shop drawings that demonstrate compliance with the
specifications.
5. The design of the roof drainage system should be in accordance with Data Sheet 1-54, Roof Loads for New
Construction and capable of handling the 60 min. rainfall event within the primary and secondary
drainage.
Construction:
6. Any new acoustic ceiling tiles, sound attenuation blankets, HVAC duct insulation or building insulation
should be made of FM Approved Class 1 materials or noncombustible materials. It is also acceptable to
use non-plastic material which have been tested to ASTM E-84 and have shown a flame spread rating of
25 or less. Please provide specifications confirming this.
7. The wall material to be used for the new mechanical room could not be located in this submittal. Please
provide additional details. If composite wall panels are to be used please provide documentation
confirming that FM Approved wall panels are to be used.
Sprinkler Protection:
8. The sprinkler system for the new mechanical room should be designed to achieve a density of 0.2 gpm/sq.
ft. over an operating area of 2,500 sq. ft. with a hose stream allowance of 250 gpm. Please provide
hydraulic calculations confirming this. All hydraulic calculations should be based on a water supply test
Page 3 of 4
Factory Mutual Insurance Company (FM Global) has developed this report for insurance underwriting purposes. The report is provided to you for informational purposes only to reduce the possibility of loss to insured property by bringing to your attention certain potential hazards or conditions. Life, safety, or health issues are not addressed. You must make the decision whether to take any action. FM Global undertakes no duty to you or any other party by providing this report or the activities on
which it is based. The liability of FM Global is limited to that contained in its insurance policies.
that is no more than 12 mo. old to ensure an adequate water supply is still available for the proposed
designs.
9. All new fire protection equipment being utilized in this project should be FM Approved. Please provide
FM Global with copies of manufacturer’s technical data sheets for all components being utilized for this
project when they become available.
10. The drawings provided call for listed fire proofing material to be used at all penetrations. Please submit
manufacturers cut sheets for the material to be used so that the listing can be verified.
11. Any new fire alarm system should utilized all FM Approved equipment and be designed, installed and
tested in accordance with Data Sheet 5-40, Fire Alarm Systems. Please submit manufactures cut sheets for
all fire alarm equipment being utilized for review and comment when it becomes available.
Recommendations to Reduce Hazards during Installation: 12. Prohibit smoking in areas where combustibles are stored, where ignitable liquids are stored or dispensed,
near piles of debris, and on the roof. Post “No Smoking” signs. Permit smoking only in designated areas
equipped with proper receptacles.
13. Keep automatic sprinkler in service as long as possible or as long as conditions necessitating sprinklers
exist. In cold weather, where wet pipe sprinkler systems are provided, maintain heat in sprinklered areas.
Take sprinkler piping out of service section by section, to the extent practical and cap as demolition
progress. Check the sprinkler control valve at the end of each work ay to ensure it is open.
14. Any required shutdown of the fire protection control valves should utilized the FM Global Red Tag
Permit system.
15. The FM Global Hot Work Permit system should be used to supervise all hot work operations (such as
cutting, welding, brazing, grinding, soldering, etc.,) performed outside of any designated welding areas. A
written policy statement should specify who has the authority to issue permits on all shifts. In addition, the
constant fire watch should be continued for 1 hr. and the area should be periodically monitored for an
additional 3 hr. after work is completed.
16. Limit the amount of combustibles in the construction area and dispose of combustible rubbish safely and
promptly.
Please respond to the above recommendations to our office within 14 days of receipt of this letter. If there are any
questions or concerns regarding this review, you can contact the Boston Operations Lead Engineer via e-mail at
[email protected] or phone (781) 440-8241. In addition, the assigned FM Global Project
Coordinator for this project, William Skene, can be contacted at [email protected], for further
assistance.
This review is for property insurance purposes only in accordance with FM Global standards and guidelines.
Nothing should be inferred from this review regarding compliance with any rules, regulations or requirements of
government agencies, state or local codes or any other jurisdictional authority. We are retaining the copy of your
submitted plans for our files.
Page 4 of 4
Factory Mutual Insurance Company (FM Global) has developed this report for insurance underwriting purposes. The report is provided to you for informational purposes only to reduce the possibility of loss to insured property by bringing to your attention certain potential hazards or conditions. Life, safety, or health issues are not addressed. You must make the decision whether to take any action. FM Global undertakes no duty to you or any other party by providing this report or the activities on
which it is based. The liability of FM Global is limited to that contained in its insurance policies.
Sincerely,
Matthew Waddell
Consultant Engineer
Loss Prevention Resources: FM Global Property Loss Prevention Data Sheets (http://www.fmglobaldatasheets.com)
FM Global Loss Prevention Training (https://fmglobaltraining.skillport.com)
Approval Guide (http://www.approvalguide.com)
RoofNav (http://roofnav.fmglobal.com)
Distribution: [email protected]
Mr. Bill Santos, FM Global [email protected]
Mr. Alfred Tanguay, People’s United Ins. [email protected]
Ms. Daria Cirish, State of CT [email protected]
Attachments: FM Global Form 2688, Checklist for Roofing System
CHECKLIST FOR ROOFING SYSTEM
CONTACT INFORMATION: INDEX NUMBER:
ROOFING CONTRACTOR (NAME & ADDRESS)
TELEPHONE NO.:
FAX:
E-MAIL ADDRESS:
CONTACT:
CLIENT (NAME & ADDRESS)
TELEPHONE NO.:
FAX:
E-MAIL ADDRESS:
CONTACT:
OVERVIEW OF WORK: (Submit 1 form per roof area)
Building Name & Number: Building Dimensions: Length: ft/m; Width: ft/m.; Height ft/m. Roof Slope: Parapet Height ,max (in./m): Parapet Height ,min (in /m): Type of Work: New Construction Recover (New roof over existing Roofing System) Reroof (New cover/remove existing roofing system to deck) Other FM Approved RoofNav Assembly Numbers:
ROOF SURFACING:
None Coating (Trade Name/Application Rate) Granules (Application Rate) Gravel/Slag (Application Rate) Ballast: Stone Size Pavers (Beveled or square edge); Other:
Ballast Weight (psf): Field: Perimeter: Corners: ROOF COVER/MEMBRANE: (Please provide ALL applicable details including trade name, type, number of plies, thickness, reinforced, adhesive)
Panel: Through Fastened Metal Standing Seam metal Fiber Reinforced Plastic (FRP) Other:
Built Up Roofing (BUR) Modified Bitumen Single Ply: Adhered Fastened Ballasted Spray Applied Other:
BASE SHEET: (Please include Trade Name, Type, and Width)
None Trade Name: Width: 36 In. 1 meter (39 In.)
Fastened Adhered Secured per RoofNav OR Per FM Global Loss Prevention Data Sheet 1-29
Comments: Air Retarder Vapor Retarder
INSULATION
Layer Trade Name Thickness (In.)
Fastened Adhered Tapered
1. Top 2. Next 3. Next 4. Next
Glass Fiber/Mineral Wool/Batt Facer Type/Vapor Barrier Thermal Barrier
X2688 ENGINEERING (Rev. January 2011)
CHECKLIST FOR ROOFING SYSTEM
Other: None
DECK: (Please include manufacturer, type, yield strength, thickness/gage, etc.)
Steel: LWIC (Form Deck): Cementitious Wood Fiber: Concrete: Pre-cast panels or Cast in Place Wood Fiber Reinforced Cement Fiber Reinforced Plastic Gypsum: Plank Poured Other:
Comments: ROOF STRUCTURE (Include Size, Gage, Etc.):
Purlins “C” OR “Z” Joists Wood OR Steel Beams Wood OR Steel Other:
Spacing: Field: Perimeter: Corners: Comments:
FASTENERS USED IN ROOF ASSEMBLY:
Roof Cover Fasteners: Trade Name: Length: Diameter: Stress Plate/Batten: Spacing: Field: X Perimeter: X Corners: X Insulation Fasteners: Trade Name: Type: Size: Stress Plate: Spacing: Field: Perimeter: Corners: Deck Or Roof Panels Fasteners: Trade Name:
Type:
Length: Size Washer: If Weld: Size: Weld: Washer: Deck Side Lap Fasteners: Field: X Perimeter: X Corners: X Spacing: Field: X Perimeter: X Corners: X Base Sheet Fasteners Trade Name:
Type:
Head Diameter: Length: Spacing: (Attached Sketches as necessary) Spacing Along Laps: Field:
Perimeter:
Corners:
No. Intermediate Rows: Field: Perimeter: Corners: Spacing Along Intermediate Rows: Field: Perimeter: Corners:
PERIMETER FLASHING: (Attach a detailed sketch of metal fascia, gravel stop, nailer, coping, etc.)
FM Approved Flashing Per FM Global Loss Prevention Data Sheet 1-49 Other: Comments:
DRAINAGE:
For new construction: Has roof drainage been designed by a Qualified Engineer per FM Global Loss Prevention Data Sheet 1-54 and the local building code? Yes No (Attach details) For re-roofing and recovering: will the roof drainage be changed from the original design (for example: drain inserts, drains covered or removed, new expansion joints, blocked or reduced scupper size? Yes No If yes, were the changes reviewed by a Qualified Engineer? Yes No (Attach details) Is secondary (emergency) roof drainage provided per FM Global Data Sheet 1-54? Yes No (Attach details)
X2688 ENGINEERING (Rev. January 2011)
CHECKLIST FOR ROOFING SYSTEM
FM Global OFFICE REVIEW (Please leave blank for FM Global Office Review) WIND:
Design Wind Speed: (mph) Ground Terrain: B C D Uplift Pressure in field: (psf) Uplift Rating Required: Adequate Uplift Rating Provided: Adequate? Yes No
FIRE:
Internal Assembly Rating: Class 1 Class 2 Non-Combustible External Fire Rating: Class A Class B Class C None Concealed Spaces? Yes No Sprinklers below Roof? Yes No Adequate? Yes No
HAIL:
Hail Rating Needed? SH MH None Hail Rating Provided? SH MH None Adequate? Yes No
COLLAPSE:
If standing seam, has collapse been reviewed? Yes No COMMENTS:
X2688 ENGINEERING (Rev. January 2011)