BID CLARIFICATION #1 - University of Connecticut · Factory Mutual Insurance ... FM Global Property...

12
BID CLARIFICATION #3 December 11, 2014 DUE DATE: January 9, 2015 TIME: 2:00 p.m. PROJECT: Replace Gampel Cooling Towers PROJECT NO: #901795 LOCATION: University of Connecticut Capital Projects & Contract Administration 3 North Hillside Road Storrs, CT 06269 Attn: Amy Allen Please note the following information must be incorporated into your bid for the Replace Gampel Cooling Towers, Project #901795: 1) The pre-bid sign in sheet dated December 10, 2014 is attached below. 2) The proposed site logistics plan is attached below. 3) A second site walkthrough will be held on Wednesday December 17, 2014 at 2:30PM. We will meet at the entrance next to the temporary cooling tower. 4) The RFI due date has been extended from Monday December 15, 2014 at 2PM to Monday December 22, 2014 at 2PM. 5) Temporary Chiller: a) Regarding note 4 on drawing M-1.00 and M-101: A temporary chiller is already in place. The University has rented this chiller from Aggreko, and this rental period will end on February 27, 2015. After that date, the contractor will be responsible for providing a rental chiller to maintain chilled water service while the cooling towers are being replaced. Refer to drawings M-100, M-101, M-301, E-101 and E- 201 for hook-up details. b) Regarding the electrical hookups for the temporary chiller as shown on E-101 and E-201, the disconnect switch will be relocated for the outside of the wall to the inside of the wall. 6) Revision of Paragraph 1.6A.1 in section 01-1000 Summary of Work to state 1. The successful bidder shall obtain the Certificate of Substantial Completion as defined in the Contract Documents within 240 calendar days of the Notice to Proceed.7) Contractor is responsible for completing the FM Global for 2688 (attached below) as coordinated with the requirements outlined in the FM Global Review document dated June 26, 2014 attached below. 8) Contractor shall manage all employees entering/exiting the building (Gampel Pavilion) via daily sign-in and sign-out sheet, the sheet must be submitted to the University. 9) Contractor shall closely coordinate all activities with UConn PM, UConn personnel and UConn operations, to allow for proper access or escorted access into the spaces, and to minimize downtime of impacted areas. 10) Contractor shall not disrupt operations in the Laundry Room area until after May 1, 2015. In the event the contractor needs to work in this room prior to May 1, 2015, contractor shall make the necessary temporary connections to allow for continuous operations of all affected equipment in the Laundry Room, mainly washers and dryers. The University of Connecticut Bid Submission Requirements: All bidders must submit their Form of Proposal along with all required forms and any associated bid clarifications as your firm’s bid proposal. All required forms must be completed. All bidders must initial the bottom of each page within their bid proposal and associated Bid Clarifications attesting to the fact that you have reviewed, read, understood, and accepted the information and terms and conditions within, without exception.

Transcript of BID CLARIFICATION #1 - University of Connecticut · Factory Mutual Insurance ... FM Global Property...

BID CLARIFICATION #3

December 11, 2014

DUE DATE: January 9, 2015

TIME: 2:00 p.m.

PROJECT: Replace Gampel Cooling Towers

PROJECT NO: #901795

LOCATION: University of Connecticut

Capital Projects & Contract Administration

3 North Hillside Road

Storrs, CT 06269

Attn: Amy Allen

Please note the following information must be incorporated into your bid for the

Replace Gampel Cooling Towers, Project #901795:

1) The pre-bid sign in sheet dated December 10, 2014 is attached below.

2) The proposed site logistics plan is attached below.

3) A second site walkthrough will be held on Wednesday December 17, 2014 at 2:30PM. We will meet at the

entrance next to the temporary cooling tower.

4) The RFI due date has been extended from Monday December 15, 2014 at 2PM to Monday December 22, 2014

at 2PM.

5) Temporary Chiller:

a) Regarding note 4 on drawing M-1.00 and M-101: A temporary chiller is already in place. The

University has rented this chiller from Aggreko, and this rental period will end on February 27, 2015.

After that date, the contractor will be responsible for providing a rental chiller to maintain chilled water

service while the cooling towers are being replaced. Refer to drawings M-100, M-101, M-301, E-101 and E-

201 for hook-up details.

b) Regarding the electrical hookups for the temporary chiller as shown on E-101 and E-201, the

disconnect switch will be relocated for the outside of the wall to the inside of the wall.

6) Revision of Paragraph 1.6A.1 in section 01-1000 Summary of Work to state “1. The successful bidder shall

obtain the Certificate of Substantial Completion as defined in the Contract Documents within 240 calendar

days of the Notice to Proceed.”

7) Contractor is responsible for completing the FM Global for 2688 (attached below) as coordinated with the

requirements outlined in the FM Global Review document dated June 26, 2014 attached below.

8) Contractor shall manage all employees entering/exiting the building (Gampel Pavilion) via daily sign-in and

sign-out sheet, the sheet must be submitted to the University.

9) Contractor shall closely coordinate all activities with UConn PM, UConn personnel and UConn operations, to

allow for proper access or escorted access into the spaces, and to minimize downtime of impacted areas.

10) Contractor shall not disrupt operations in the Laundry Room area until after May 1, 2015. In the event the

contractor needs to work in this room prior to May 1, 2015, contractor shall make the necessary temporary

connections to allow for continuous operations of all affected equipment in the Laundry Room, mainly washers

and dryers.

The University of Connecticut Bid Submission Requirements:

All bidders must submit their Form of Proposal along with all required forms and any associated bid

clarifications as your firm’s bid proposal. All required forms must be completed.

All bidders must initial the bottom of each page within their bid proposal and associated Bid

Clarifications attesting to the fact that you have reviewed, read, understood, and accepted the

information and terms and conditions within, without exception.

YOUR BID PROPOSAL MAY BE CONSIDERED NON-RESPONSIVE AND MAY NOT BE

REVIEWED FOR FAILURE TO SUBMIT ALL OF THE ABOVE DOCUMENTATION (ALONG

WITH ANY OTHER DOCUMENTATION DETAILED IN THE BID DOCUMENTS AND

SPECIFICATIONS)

All bid awards must be approved by the University of Connecticut. After review of all factors,

terms and conditions, including price, the University of Connecticut reserves the right to reject any

and all proposal, or any part thereof, or waive defects in same, or accept any proposal deemed to be

in the best interest of the University of Connecticut

University of Connecticut Amy Allen, Purchasing Agent II

kav08006
Text Box
NEW BBALL FACILITY

Plan Review

Factory Mutual Insurance Company (FM Global) has developed this report for insurance underwriting purposes. The report is provided to you for informational purposes only to reduce the possibility of loss to insured property by bringing to your attention certain potential hazards or conditions. Life, safety, or health issues are not

addressed. You must make the decision whether to take any action. FM Global undertakes no duty to you or any other party by providing this report or the activities on

which it is based. The liability of FM Global is limited to that contained in its insurance policies.

7281A (03/13)

State of Connecticut

“University of Connecticut - Storrs Campus”

85 Walters Avenue

Storrs Mansfield, CT 06269-9027

USA

Index-Rec No: 17725.05-02

Account No: 30882

Date of Review: June 26, 2014

Review No: 189505

Plans Submitted By: Mr. Michael Rocchetti, University of Connecticut

Subject: Construction drawings and specs for Gampel Cooling Towers – Project 901795

Executive Summary: This project involves the removal of two 400 ton cooling towers at the Gampel building. The towers will be

replaced with modern units to be located atop a new heated mechanical room in the same area.

This submittal is not in accordance with FM Global Standards. Completion of review comment No. 2 is

required for design acceptance of this submittal. Additionally, several other review comments in this letter are

requesting additional information to be provided when it becomes available. This information will be needed for

full design review of this project.

Scope of Review: This confirms the receipt and review of:

Drawing package dated June 5, 2014

The table of contents for the project manual associated with this project

Draft Construction Cost Estimate Document

The existing 400 ton cooling towers will be removed. The existing exterior mechanical walled compound will be

enclosed to create a heated mechanical room space that will house the following components: A large remote

sump tank for the cooling tower water, new condenser water pumps, piping, valves and controls. The mechanical

room will also be built with two new 4 in. floor drains and a sump pump. The new 400 ton towers will be located

on the roof of this mechanical room. New piping connections and valves will be provided for the condenser water

supply and return lines from the two existing 400 ton chillers in the adjacent mechanical room. The new towers

will be equipped with make up water line and water level controls and the new towers will be integrated into the

existing building management system.

The replacement towers will be modern 400 ton induced draft cross flow cooling towers.

Review Comments: Cooling Towers:

1. Drawing M-501 of this submittal package calls for two FM Approved cooling towers Baltimore Aircoil

Model 3455C_LM/QV. This is considered acceptable per the FM Global approval guide only when

Page 2 of 4

Factory Mutual Insurance Company (FM Global) has developed this report for insurance underwriting purposes. The report is provided to you for informational purposes only to reduce the possibility of loss to insured property by bringing to your attention certain potential hazards or conditions. Life, safety, or health issues are not addressed. You must make the decision whether to take any action. FM Global undertakes no duty to you or any other party by providing this report or the activities on

which it is based. The liability of FM Global is limited to that contained in its insurance policies.

installed in multi-cell (two or more cells) fashion. The exact number of cells chosen is determined by the

application and its anticipated seasonal operating strategy which includes consideration of cell outage due

to fire damage, mechanical failure and preventive maintenance such that sufficient cooling capacity is

available to enable normal business and manufacturing operations to continue throughout the year. Please

provide documentation confirming that these cooling towers will be installed with a cell arrangement

that is in accordance with their FM Approval listing.

This drawing also indicates that the mechanical contractor may propose a substitute model and if this is

done, the replacement tower must be an FM Approved model. Please notify FM Global if a substitute

tower is selected and provide manufacturers cut sheets so that approval listing can be confirmed.

Roof:

2. This project involves the installation of an EPDM roof over the new mechanical room that will be

constructed in the location of the existing cooling towers. Full details of this roof cover were not included

in this submittal; however, loading and uplift design criteria were specified on the drawings. The specified

criteria are not acceptable. The following should be used instead: Snow load - 35 psf, Wind Speed – 100

mph, Importance Factor - 1.15, Exposure Classification – C. Please provide a detailed roof submittal

utilizing these design criteria. The roof submittal should include an FM Global RoofNav number

that specifies all roofing components as an assembly. Additionally, FM Global should be forwarded

the completed FM Global Form 2688, Checklist for Roofing System (attached)

3. Steel deck fastening should be specified in any new roof submittals. Fastening rates should be selected in

accordance with FM Global Property Loss Prevention Data sheet 1-29 Roof Deck Securement and Above

Deck Roof Components.

4. Perimeter flashing and nailer assemblies are specified to be designed and installed per Data Sheet, 1-49,

Perimeter Flashing. Please submit materials and shop drawings that demonstrate compliance with the

specifications.

5. The design of the roof drainage system should be in accordance with Data Sheet 1-54, Roof Loads for New

Construction and capable of handling the 60 min. rainfall event within the primary and secondary

drainage.

Construction:

6. Any new acoustic ceiling tiles, sound attenuation blankets, HVAC duct insulation or building insulation

should be made of FM Approved Class 1 materials or noncombustible materials. It is also acceptable to

use non-plastic material which have been tested to ASTM E-84 and have shown a flame spread rating of

25 or less. Please provide specifications confirming this.

7. The wall material to be used for the new mechanical room could not be located in this submittal. Please

provide additional details. If composite wall panels are to be used please provide documentation

confirming that FM Approved wall panels are to be used.

Sprinkler Protection:

8. The sprinkler system for the new mechanical room should be designed to achieve a density of 0.2 gpm/sq.

ft. over an operating area of 2,500 sq. ft. with a hose stream allowance of 250 gpm. Please provide

hydraulic calculations confirming this. All hydraulic calculations should be based on a water supply test

Page 3 of 4

Factory Mutual Insurance Company (FM Global) has developed this report for insurance underwriting purposes. The report is provided to you for informational purposes only to reduce the possibility of loss to insured property by bringing to your attention certain potential hazards or conditions. Life, safety, or health issues are not addressed. You must make the decision whether to take any action. FM Global undertakes no duty to you or any other party by providing this report or the activities on

which it is based. The liability of FM Global is limited to that contained in its insurance policies.

that is no more than 12 mo. old to ensure an adequate water supply is still available for the proposed

designs.

9. All new fire protection equipment being utilized in this project should be FM Approved. Please provide

FM Global with copies of manufacturer’s technical data sheets for all components being utilized for this

project when they become available.

10. The drawings provided call for listed fire proofing material to be used at all penetrations. Please submit

manufacturers cut sheets for the material to be used so that the listing can be verified.

11. Any new fire alarm system should utilized all FM Approved equipment and be designed, installed and

tested in accordance with Data Sheet 5-40, Fire Alarm Systems. Please submit manufactures cut sheets for

all fire alarm equipment being utilized for review and comment when it becomes available.

Recommendations to Reduce Hazards during Installation: 12. Prohibit smoking in areas where combustibles are stored, where ignitable liquids are stored or dispensed,

near piles of debris, and on the roof. Post “No Smoking” signs. Permit smoking only in designated areas

equipped with proper receptacles.

13. Keep automatic sprinkler in service as long as possible or as long as conditions necessitating sprinklers

exist. In cold weather, where wet pipe sprinkler systems are provided, maintain heat in sprinklered areas.

Take sprinkler piping out of service section by section, to the extent practical and cap as demolition

progress. Check the sprinkler control valve at the end of each work ay to ensure it is open.

14. Any required shutdown of the fire protection control valves should utilized the FM Global Red Tag

Permit system.

15. The FM Global Hot Work Permit system should be used to supervise all hot work operations (such as

cutting, welding, brazing, grinding, soldering, etc.,) performed outside of any designated welding areas. A

written policy statement should specify who has the authority to issue permits on all shifts. In addition, the

constant fire watch should be continued for 1 hr. and the area should be periodically monitored for an

additional 3 hr. after work is completed.

16. Limit the amount of combustibles in the construction area and dispose of combustible rubbish safely and

promptly.

Please respond to the above recommendations to our office within 14 days of receipt of this letter. If there are any

questions or concerns regarding this review, you can contact the Boston Operations Lead Engineer via e-mail at

[email protected] or phone (781) 440-8241. In addition, the assigned FM Global Project

Coordinator for this project, William Skene, can be contacted at [email protected], for further

assistance.

This review is for property insurance purposes only in accordance with FM Global standards and guidelines.

Nothing should be inferred from this review regarding compliance with any rules, regulations or requirements of

government agencies, state or local codes or any other jurisdictional authority. We are retaining the copy of your

submitted plans for our files.

Page 4 of 4

Factory Mutual Insurance Company (FM Global) has developed this report for insurance underwriting purposes. The report is provided to you for informational purposes only to reduce the possibility of loss to insured property by bringing to your attention certain potential hazards or conditions. Life, safety, or health issues are not addressed. You must make the decision whether to take any action. FM Global undertakes no duty to you or any other party by providing this report or the activities on

which it is based. The liability of FM Global is limited to that contained in its insurance policies.

Sincerely,

Matthew Waddell

Consultant Engineer

Loss Prevention Resources: FM Global Property Loss Prevention Data Sheets (http://www.fmglobaldatasheets.com)

FM Global Loss Prevention Training (https://fmglobaltraining.skillport.com)

Approval Guide (http://www.approvalguide.com)

RoofNav (http://roofnav.fmglobal.com)

Distribution: [email protected]

Mr. Bill Santos, FM Global [email protected]

Mr. Alfred Tanguay, People’s United Ins. [email protected]

Ms. Daria Cirish, State of CT [email protected]

Attachments: FM Global Form 2688, Checklist for Roofing System

CHECKLIST FOR ROOFING SYSTEM

CONTACT INFORMATION: INDEX NUMBER:

ROOFING CONTRACTOR (NAME & ADDRESS)

TELEPHONE NO.:

FAX:

E-MAIL ADDRESS:

CONTACT:

CLIENT (NAME & ADDRESS)

TELEPHONE NO.:

FAX:

E-MAIL ADDRESS:

CONTACT:

OVERVIEW OF WORK: (Submit 1 form per roof area)

Building Name & Number: Building Dimensions: Length: ft/m; Width: ft/m.; Height ft/m. Roof Slope: Parapet Height ,max (in./m): Parapet Height ,min (in /m): Type of Work: New Construction Recover (New roof over existing Roofing System) Reroof (New cover/remove existing roofing system to deck) Other FM Approved RoofNav Assembly Numbers:

ROOF SURFACING:

None Coating (Trade Name/Application Rate) Granules (Application Rate) Gravel/Slag (Application Rate) Ballast: Stone Size Pavers (Beveled or square edge); Other:

Ballast Weight (psf): Field: Perimeter: Corners: ROOF COVER/MEMBRANE: (Please provide ALL applicable details including trade name, type, number of plies, thickness, reinforced, adhesive)

Panel: Through Fastened Metal Standing Seam metal Fiber Reinforced Plastic (FRP) Other:

Built Up Roofing (BUR) Modified Bitumen Single Ply: Adhered Fastened Ballasted Spray Applied Other:

BASE SHEET: (Please include Trade Name, Type, and Width)

None Trade Name: Width: 36 In. 1 meter (39 In.)

Fastened Adhered Secured per RoofNav OR Per FM Global Loss Prevention Data Sheet 1-29

Comments: Air Retarder Vapor Retarder

INSULATION

Layer Trade Name Thickness (In.)

Fastened Adhered Tapered

1. Top 2. Next 3. Next 4. Next

Glass Fiber/Mineral Wool/Batt Facer Type/Vapor Barrier Thermal Barrier

X2688 ENGINEERING (Rev. January 2011)

CHECKLIST FOR ROOFING SYSTEM

Other: None

DECK: (Please include manufacturer, type, yield strength, thickness/gage, etc.)

Steel: LWIC (Form Deck): Cementitious Wood Fiber: Concrete: Pre-cast panels or Cast in Place Wood Fiber Reinforced Cement Fiber Reinforced Plastic Gypsum: Plank Poured Other:

Comments: ROOF STRUCTURE (Include Size, Gage, Etc.):

Purlins “C” OR “Z” Joists Wood OR Steel Beams Wood OR Steel Other:

Spacing: Field: Perimeter: Corners: Comments:

FASTENERS USED IN ROOF ASSEMBLY:

Roof Cover Fasteners: Trade Name: Length: Diameter: Stress Plate/Batten: Spacing: Field: X Perimeter: X Corners: X Insulation Fasteners: Trade Name: Type: Size: Stress Plate: Spacing: Field: Perimeter: Corners: Deck Or Roof Panels Fasteners: Trade Name:

Type:

Length: Size Washer: If Weld: Size: Weld: Washer: Deck Side Lap Fasteners: Field: X Perimeter: X Corners: X Spacing: Field: X Perimeter: X Corners: X Base Sheet Fasteners Trade Name:

Type:

Head Diameter: Length: Spacing: (Attached Sketches as necessary) Spacing Along Laps: Field:

Perimeter:

Corners:

No. Intermediate Rows: Field: Perimeter: Corners: Spacing Along Intermediate Rows: Field: Perimeter: Corners:

PERIMETER FLASHING: (Attach a detailed sketch of metal fascia, gravel stop, nailer, coping, etc.)

FM Approved Flashing Per FM Global Loss Prevention Data Sheet 1-49 Other: Comments:

DRAINAGE:

For new construction: Has roof drainage been designed by a Qualified Engineer per FM Global Loss Prevention Data Sheet 1-54 and the local building code? Yes No (Attach details) For re-roofing and recovering: will the roof drainage be changed from the original design (for example: drain inserts, drains covered or removed, new expansion joints, blocked or reduced scupper size? Yes No If yes, were the changes reviewed by a Qualified Engineer? Yes No (Attach details) Is secondary (emergency) roof drainage provided per FM Global Data Sheet 1-54? Yes No (Attach details)

X2688 ENGINEERING (Rev. January 2011)

CHECKLIST FOR ROOFING SYSTEM

FM Global OFFICE REVIEW (Please leave blank for FM Global Office Review) WIND:

Design Wind Speed: (mph) Ground Terrain: B C D Uplift Pressure in field: (psf) Uplift Rating Required: Adequate Uplift Rating Provided: Adequate? Yes No

FIRE:

Internal Assembly Rating: Class 1 Class 2 Non-Combustible External Fire Rating: Class A Class B Class C None Concealed Spaces? Yes No Sprinklers below Roof? Yes No Adequate? Yes No

HAIL:

Hail Rating Needed? SH MH None Hail Rating Provided? SH MH None Adequate? Yes No

COLLAPSE:

If standing seam, has collapse been reviewed? Yes No COMMENTS:

X2688 ENGINEERING (Rev. January 2011)