Bhavnath Temple
-
Upload
nipathbelani -
Category
Documents
-
view
155 -
download
6
Transcript of Bhavnath Temple
Executive Summary:
The case deals with the problems faced while building a dam
across the rivers Lokmata and Sadmata in northern Gujarat and
further issues encountered while a proposal is made to raise the
control levels of it. The objective of the case is to maximize the
irrigation potential of the dam while respecting the religious
sentiments of the people. The options are either to implement
the former plan in its present form or the latter by convincing
the people of its benefits and deal with the issues faced. The
conclusion is to try and implement the new plan resulting in
maximization of irrigation and revenues.
Word Count: 104
2
Situational Analysis:
The setting of the case is in North Gujarat in the period just after
independence. The government has proposed to build an earthen
dam across the rivers Lokmata and Sadmata to improve
irrigational facilities in three districts. India was then a primarily
agrarian economy and agriculture was largely dependent on rain
and North Gujarat being a water starved area would benefit
immensely from the construction of this dam by making water
available all throughout the year. The authorities have made a
new proposal to raise the level of dam which would result in the
submergence of the Bhavnath temple located in the projected
reservoir and this has resulted in the villagers strongly opposing
the project. The central issue that the Bhavnath Temple Case
deals with is the balance between economic development and
religious sentiments of the people.
Under Plan A the dam was to impound 4700 million cu.ft of
water irrigating 92,000 acres of land at a cost of 1.7 crores. It
was expected that the increase in agricultural production would
be 30,400 tons every year and this was valued at 1.4774 crores.
The new plan (Plan B) called for raising the irrigation potential
of the dam by raising the level the three control levels. The dam
would now hold 5,700 million cu.ft of water and was estimated
Case Study: Bhavnath Temple
3
to cost 1.9 crores. Therefore, an 11.7 % increase in cost could
result in the area under irrigation, agricultural production and
revenues to increase by 21.2 %. But the new plan would result
in the temple being completely submerged and could not be
saved with the steps taken to save the temple incorporated in the
former. As a consequence the villagers have vehemently
opposed the raising of the dam levels.
The objective of the case is to maximize the irrigation potential
of the dam while respecting the religious sentiments of the
people.
Options:
1. Move ahead with the revised plan by convincing the
people of its benefits and relocate the temple.
2. Continue with the execution of Plan A.
1. The new plan raises the irrigation potential and revenues from
the project as stated above (para 2) There is only a marginal
addition to the cost of construction of the canal system for the
irrigation facilities to spread to a larger area. The compensation
Case Study: Bhavnath Temple
4
paid to the villages and providing for new houses had already
been factored and had been added to the direct cost of
constructing the dam in Plan A. The people seemed happy with
this arrangement(for relocation) and there would be no extra
cost added for compensation paid as there is no mention that
additional people have been displaced to implement Plan B.
There is also no increase in the effort put in by the authorities to
provide the displaced people with new sources of livelihood. As
there was widespread poverty in the country the increase in
revenue has to be given a lot of weight age because as
mentioned earlier, the economy was largely agrarian and
agriculture was the major source of income. The increase in
agricultural production as a result of increasing the control
levels of the dam would also contribute to the food security of
the area if not to the country.
The only negative of Plan B is that the Bhavnath temple would
be submerged in spite of the steps taken to protect it in Plan A.
The temple was very important to the inhabitants of the area and
the temple fair attracted people from far which could have been
a source of income to the locals. The authorities had suggested
that the temple deities be shifted to an alternative location
observing full religious rites, but this could still hurt the
Case Study: Bhavnath Temple
5
religious sentiments of a section of the people including the
temple priests whose livelihood depends on the temple.
2. Plan A calls for the FSL and HFL levels to be fixed at 592
and 596 respectively. This plan has in principle been agreed to
by the people living in the area and they seemed to be happy
with it. The temple could be protected from submergence by
building a water weir and also all weather access was to be
provided by the government. This plan protected the religious
sentiments of the people.
But Plan A does not realize the full irrigation potential of the
project by not maximizing agricultural production and thus
revenues with only a minimal increase in costs.
Based on the evaluation of the options, Plan B should be
implemented.
The action plan would include:
1. Providing the extra funding (20 lakhs) for the project to
raise the FSL and the HFL levels.
2. Educating and convincing the people of the benefits of
raising the dam levels. This would include the fact that
Case Study: Bhavnath Temple
6
the land under irrigation would increase and as a direct
consequence the amount of revenue earned by the people
in the area would increase and also the food security of
the area would improve. Also, the dam could be a tourist
attraction and attract people from the surrounding areas
thus generating extra revenue.
3. Holding consultations with the village heads as well as
the temple priests and decide upon how the temple
should be relocated and finding a suitable alternative
location for it.
4. Generation of a political will on the part of the
government to implement a plan which might turn out to
be a sensitive issue but would provide long term
economic growth for the area.
Contingency Plan:
If the people are still opposed to the implementation of Plan B,
Plan A in its present form should be implemented as it has been
agreed to by them. A dam would not only provide water for
Case Study: Bhavnath Temple
7
irrigation all year round but also protect the area from floods in
case of heavy rains.
Word Count: 964.
Case Study: Bhavnath Temple
8
Exhibits:
Specifications of the dam:
Specification: Value:
Irrigation Area 92,000 acres
Catchment Area 230 sq. Miles
Villages effected 20
Villages completely
submerged
8
Average rainfall 34”
Increase agricultural
production
30,400 tons
Case Study: Bhavnath Temple
9
Component
Original
Specifications
of dam
Modified
Specifications
of dam under
new proposal
FSL-Full
Supply Level
592 595
HFL-Highest
Flood Level
596 606
RL-Reduced
Level
601 601
Cost 1.7 crores 1.9 crores
Reservoir
Capacity
4700 million cu. ft. 5700 million cu. ft.
Approximate increase in cost of the project by implementing
Plan B = 20 lakhs / 1700 lakhs
= 11.7%
Case Study: Bhavnath Temple
10
Approximate increase in the area under irrigation, agricultural
production, revenues and reservoir capacity = 1000 mil cu.ft /
4700 mil cu.ft
= 21.2 %
NOTE: The figure of 21.2% has been arrived upon by only
calculating the increase in the reservoir capacity. It has been
assumed that the area irrigation and revenue would
proportionally increase.
Case Study: Bhavnath Temple