457 minna street, suite 100, san francisco, ca 94103www.buildgc.com
BuildGroupBarneys New York - Men’s Expansion
APRIL 15, 2015
TABLE OF CONTENTS
TEAM 1
EXPERIENCE 2
PRICING 3
SCHEDULE 4
457 minna street, suite 100, san francisco, ca 94103www.buildgc.com
EXPERIENCE
EXPERIENCE
EXPERIENCE
Experience Let’s show you our stuff!
High-End RetailFine Interiors Group is an extensive tenant build-out team. This division focuses solely on meeting the needs of tenant improvement clients, primarily on high-end retail spaces and restaurants. Fine Interiors Group has completed tenant build-outs for clients including Gucci, John Varvatos, Burberry, Nespresso, and Coach.
On the following pages, we have provided a sampling of our client relationships.
H&M | Union Square | San Francisco
EXPERIENCE
TenantImprovements A snapshot of brands we have worked with.
EXPERIENCE
* Flagship Store
MINNA
1 Metropolitain Club 2 Postrio 3 Donatello Hotel 4 449 Powell 5 Villa Florence Hotel 6 Dr. Marten 7 400 Sutter 8 Hyatt Union Square 9 I. Magnin | Macy’s10 Liberty House | Macy’s11 Gucci*12a Celine*12b Loro Piana*13 Wolford14 Gumps15 Tailored Man 16 Scheuer Linens
Fine Interiors Group/Build Group Offices
Completed Projects
Current Projects
UNIONSQUARE
SUTTER
POST
STOC
KTON
GEARY
POW
ELL
O’FARRELL
ELLIS
GR
ANT
KEARNY
MARKET
MISSIONFIFTH
FOURTH
THIRD
MASO
N
1
2 3
4
5
67
8
9
10
11
12a12b
13
14
15 16
17
24
2549
26
27
3545
36
37
38 39
40
41
42
23
28
29
30
31
32
33
34
1819
20
2122
43
46
47
48
44
San Francisco Retail Experience
17 239 Grant18 Coach Leather*19 Talbots*20 Rizzoli Bookstore*21 100 Grant22 Bottega Veneta*23 Compuserve24 H & M25 H & M*26 Axelle Gallery27 Benetton*28 Pan Pacific Hotel29 Allison Hotel30 Post Street Hotel31 Carolina Herrera*32 Nikko Hotel33 Sisley*
34 Anne Fontaine*35 Longchamp*36 Christofle*37 200 Powell38 152 Geary Street39 46 Geary Street40 533 Sutter Street41 John Varvatos*42 UGG43 Ritz Carleton Spa44 Jimmy Choo*45 77 Maiden Lane Spa46 Westfield Centre - 55+ Retail Stores47 Metreon & City View48 Nespresso*49 Jins Eyewear (under construction)
EXPERIENCE
Bay Area Ports
San Francisco
Oakland
Alameda
UNION SQUARE
PIER STORAGE
Convienient Storage from Port of Oakland
Our Fine Interiors Group San Francisco location has storage space at Pier 50. This is an added benefit for our retail partners looking to ship in merchindise to the Port of Oakland.
Fine Interiors Group San Francisco Office
Union Square
Pier 50 Storage Space
EXPERIENCE
John Varvatos, Flagshipunion square, san francisco, ca
OwnerJohn Varvatos
ArchitectDucDuc (New York)Pollack Associates (SF)
Duration16 weeks
The seventh and the largest of the John Varvatos stores, the San Francisco flagship features two floors of sophisticated interiors, showcasing the Varvatos casual to formal menswear attire. Solid walnut floors are throughout this design/build project.
The construction team coordinated with both architects on the East and West coasts and met a very aggressive schedule.
In addition to the remodel of the interior space, there team also completed a full seismic upgrade on the building.
EXPERIENCE
JINS, Flagship union square, san francisco, ca
OwnerJINS
ArchitectKwan Henmi Architects
Project Duration15 weeks
The 4,300 sf build-out includes various elements that represent the clients ‘fully-customized’ products. The store includes high-end case work, new facade, ardex polished concrete floors, and back of the house conference rooms and bathrooms.
The focal point of the store is the specialty showcase room that will be used to produce all products on-site. The room was built with epoxy flooring and is encased in glass.
EXPERIENCE
Nespresso, Flagshipunion square, san francisco, ca
OwnerNespresso
ArchitectGoring & Straja Architects
Duration19 weeks
The first signature Nespresso in San Francisco, this Union Square build-out features a modern design in a 100-year-old building. A complete structural rebuild of the first and second floors was constructed to make way for café and retail spaces. The team remained on a tight schedule while coordinating vendors from across the U.S. and Europe that completed high-end finishes. Architectural features include a floating staircase leading customers from the upper café area into the lower retail space.
EXPERIENCE
Kate Spade, Retail Storewestfield, san francisco, ca
OwnerKate Spade, NY
ArchitectFreebaim, Smith & Crane
Project Duration8 weeks
The 2,700 sf Kate Spade retail outlet is located in the Westfield San Francisco Centre Mall. The project included wall-to-wall demolition of the existing store in order to redesign with updated corporate aesthetics and branding. The updates include luxury, high-end brass finishes on all fixtures and fit-outs along with a detailed store front system.
EXPERIENCE
Club Monaco, Retail Storewestfield, san francisco, ca
OwnerClub Monaco
ArchitectAtelier Design, LLC
Project Duration22 weeks
Build Group provided the complete build-out of Club Monaco’s retail store in Union Square. Phase One involved the complete demolition of the existing 4,924 sf store. A portion of the Phase Two redesign work involved the high-end finishes, millwork, and hand-painted custom case work that the client is recognized for. Additionally, our team installed white oak wood floors that are a staple of this location. Build Group installed two, custom painted 12-foot-tall entrance doors, while upgrading the store’s facade.
EXPERIENCE
H&M, Flagshipunion square, san francisco, ca
OwnerH&M
ArchitectTEK Architects
Duration20 weeks
H&M’s flagship store in a historic building on Powell St. features new escalators, large video display screens, all new stone flooring, 42 high-end dressing rooms, new restrooms, employee locker rooms, and kitchen, as well as a carefully restored historical ceiling, entry, and 400 linear feet of new sidewalk.
The Post Street store features all new stone flooring, a new glass balcony overlooking the entry, a grand staircase, new exterior sidewalks, new restrooms, and 20 high-end dressing rooms.
Both stores were completed one month ahead of schedule.
EXPERIENCE
Gucci, Flagshiphonolulu, hawaii
OwnerGucci
ArchitectGensler
Duration20 weeks (fast-track schedule)
This project was Gucci’s first design-build turnkey. The store remained in business throughout the entire construction period, and was completed three weeks ahead of schedule with zero change orders.
The store location is set along the city’s waterfront and included a structural upgrade to the building, with a two-story high ornamental storefront finished with stainless steel panels. The store also included imported Italian millwork in high lacquered rosewood. All fixtures were supplied and installed by the construction team.
EXPERIENCE
Rizzoli Bookstorepasadena, ca
OwnerRizzoli Bookstore
ArchitectMeyer & Gifford
Duration5 weeks
Throughout the 5,000 sf, the elegance of rich cherry fixtures and walnut flooring contribute to the warmth of a private study.
Stately columns, brass handrails and lush imported carpeting are reminiscent of turn of the century America, remaining faithful to early 1900’s building facade. The millwork package was provided and installed by Build Group.
This project was completed after only seven weeks of construction.
EXPERIENCE
Hog Island Oyster Companysan francisco, ca
OwnerHog Island Oyster Company
ArchitectCCS Architecture
Duration12 weeks
Build Group, Inc. completed construction on the $1.2 million renovation of Hog Island Oyster Company’s restaurant space in the historic San Francisco Ferry Building.
At 3,800 sf, the facility’s new space was reconfigured to triple the existing restaurant and add 1,100 square feet of outdoor dining space. The new 130-seat restaurant features a full-service kitchen and bar, custom concrete bar counters, and reclaimed cypress millwork throughout. The ceiling, designed by CCS Architecture, was constructed to replicate the hull of a boat.
One of the toughest challenges on this job was coordinating the installation of the plumbing work. Since the Ferry Building is located on a pier, all plumbing work needed to be done by boat under the pier which required an extensive amount of coordination. In addition, work had to be completed in and around a fully-occupied building. Weekly meetings were held with the ferry building to constantly update them on our schedule. Any disruptive or noisy work was done off-hours to avoid any interference to the adjacent tenants.
EXPERIENCE
M.Y. China, Signature Restaurantsan francisco, ca
OwnerM.Y. China
ArchitectBCV Architects
Duration23 weeks
This project included construction of a new signature restaurant at Westfield’s San Francisco Centre. Based on television chef Martin Yan’s recipes, M.Y. China offers a 181-seat, high-end, high-class, exhibition style eating experience. Custom eucalyptus woodwork, laser cut metal screens, and antique Chinese furnishings set the scene for a sophisticated meal.
The eye-catching centerpiece of the restaurants circular bar, is an antique 1,800 pound bell that was imported in from China.
TEAM
TEAM
TEAM
Team Meet a few of our incredible team members.
Collectively, our principals have over 193 years of experience in the construction industry with the majority of this experience in the Bay Area. Our leadership team knows the complexities of building in San Francisco particularly the intricacies of permitting with the City and local agencies. Resumes have been provided on the following pages.
TEAM
Principal John Santori
Education B.S. Biochemistry, University of California, Berkeley
Nespresso, Union Square Flagship San Francisco, CA 8,600 sf high-end retail tenant improvement
JINS San Francisco, CA 4,300 sf, TI build-out, high-end case work, new front facade, ardex polished concrete floors, back of the house conference rooms and bathrooms, specialty show case room
Carolina Herrera San Francisco, CA $1.3 million, high-end retail build-out in Union Square
Burberry Brit, Westfield Centre San Francisco, CA Wood flooring, high-finish millwork, 12-week schedule, large format interior storefront
Gucci, Union Square Flagship San Francisco, CA 16,000 sf, four levels, 40% of ground floor concrete was removed and replaced for ADA compliance
Gucci, Ala Moana Shopping Center Honolulu, HI 7,732 sf, flagship store
John Vavartos, Union Square Flagship San Francisco, CA 6,500 sf, two level flagship, $2 million
Talbots, 26 Stores Throughout West Coast 12,000 sf, flagship store
H & M, Powell St., Union Square San Francisco, CA 40,000 sf, new high-end flagship, $4.5 million
Jimmy Choo, Union Square Flagship San Francisco, CA 2,300 sf tenant build-out, flagship store with high-end finishes
Tori Burch, Westfield Centre San Francisco, CA 1,381 sf tenant build-out, high-end finishes throughout
Bliss Spa at W Hotel Hollywood, CA 5,000 sf build out of high-end spa on the 4th floor of new W Hotel including 12 spa treatment rooms, sauna, steam rooms and a retail area
Villa Florence Hotel San Francisco, CA 125,000 sf hotel remodel in historic building
Hyatt Regency Embarcadero San Francisco, CA Remodel of public areas, club rooms and suites
Donatello Hotel, Union Square San Francisco, CA
Rizzoli’s Bookstore, 5 locations Pasadena, CA 5,000 sf, new high-end flagship, $1.2 million
Rizzoli’s Bookstore Pasadena, CA 5,000 sf retail build-out, stately columns, brass handrails, lush imported carpeting remaining faithful to early 1900’s building facade
Betsy Johnson, Westfield Centre San Francisco, CA 1,100 sf tenant build out, signature retail project, creative re-use of existing elements, eight weeks
Relevant Experience
John is a 30 year veteran with specialized expertise in high-end retail, signature restaurants and seismic upgrades. He helps lead Build Group Retail, Hospitality, Fine Interiors divisions, specializing in business development to assist clients in making deals pencil. John joined Build Group in 2007 through the acquisition of his company, Fine Line Group. He founded Fine Line Group in 1979 and grew the company to become a leading firm with unparalleled knowledge of Union Square and an uncompromising commitment to quality.
TEAM
Director of Operations Mark Izdepski
Education / Credentials BS IET Purdue University West Lafayette, Indiana
Continual Education: OSHA Certified, Continuing Education with Insurance Carriers, Safety, Laws and Regulations, Business Practices, Advanced Building Codes, Improving Construction Productivity, Workers Compensation
Tiffany & Co., Retail Stores San Diego, Rodeo, Topanga, Ala Moana - Waikiki, HI, Santa Barbara, Carmel, and 25 other locations
Cartier, Van Cleef & Arpels, Retail Stores Nationwide
Fendi, Retail Stores Las Vegas, NV
Armani Exchange, Retail Stores San Francisco, Pasadena, San Diego, San Jose, Nationwide
Giorgio Armani, Retail Stores Desert Hills, Miami, Manhasset, Nationwide
COACH, Retail Stores Nationwide
Lacoste, Retail Stores +60 stores Nationwide
Michael Kors, Retail Stores Denver, Miami, Nationwide
St John Knit, Retail Stores Nationwide
Versace, Retail Stores Las Vegas, NV Nationwide
Gucci, Retail Stores Two Rodeo Drive, CA San Francisco, Nationwide
Hermes Las Vegas, NV $8 million, in Bellagio Hotel, high-end jewelry retail store
Louis Vuitton Dallas, TX Las Vegas
Escada Rodeo Drive, CA Scottsdale, AZ, Nationwide
Yves Saint Laurent Houston, TX
Prada Desert Hills, CA South Coast Plaza, Costa Mesa, CA Beverly Center - Los Angeles, CA
Mikimoto Rodeo Drive, CA South Coast Plaza, Costa Mesa, CA Nationwide
Tory Burch San Francisco, CA San Diego, CA, Nationwide
Loro Piana Caesars - Las Vegas, Rodeo Drive, Bal Harbour Shops, Florida, Nationwide
Hugo Boss Nationwide
Kenneth Cole Nationwide
Kachina Point Retirement Center Sedona, AZ
Relevant Experience
Mark is an experienced construction professional with over 30 years specializing in high-end retail, hospitality and restaurant construction. Mark is Director of Operations of Build Groups Fine Interiors division. He is responsible for leading Build Groups highly competent teams of construction professionals guaranteeing on time on budget projects for our many repeat clients. Other responsibilities include facilitating the companies Safety Program and Customer Service & Satisfaction initiatives.
TEAM
Project Manager Tim Ferguson
Hotel Renoir San Francisco, CA 83,300 sf seismic upgrade & remodel, seven-stories, 135 rooms
Mary Helen Rogers Senior Community San Francisco, CA $30 million, eight-story concrete building, ground-floor lobby, one level below grade parking
Edith Witt Senior Center San Francisco, CA $35 million, 11-story concrete structure, one level below grade parking structure
Villa Serena Tampa, FL $68 million, 29 four-story condominium structures, wood frame over concrete podium
The Arbor Assisted Living Facility Fort Myers, FL $32 million, five-story concrete building, two-story amenity structure, one-story parking garage
Parkwood Place Independent Living Facility Fort Myers, FL $38 million, eight-story concrete structure, two-story parking garage
Capital One Buildings J, K, and Parking Structure Tampa, FL $62 million, two, four-story call center buildings, three-story parking garage
Relevant Experience
Tim Ferguson is a detail oriented Project Manager with more than 17 years of experience. He has a proven record in driving the completion of large-scale, multimillion dollar projects. Tim has a superior ability to develop a projects budget, with a demonstrated excellence in establishing parameters and managing numerous teams to complete projects under budget and within deadlines.
TEAM
SuperintendentJeff Lucero
Relevant Experience
Jeff Lucero is a Superintendent with more than 26 years of tenant improvement and construction experience. Jeff is known for his strong scheduling and completion record. With his long record of building in San Francisco, Jeff has developed an in-depth knowledge of city building codes and Title 19 & 24. He has extensive experience in high-end finishes, as well as framing, electrical, plumbing, door frames, door hardware, mill work, finish carpentry and tile.
Gucci, Union Square Flagship San Francisco, CA 16,000 sf, four levels, 40% of ground floor concrete was removed and replaced for ADA compliance
Bottega Veneta, Union Square Flagship San Francisco, CA 2,700 sf build out of flagship store on Union Square
Loro Piana, Union Square Flagship San Francisco, CA 3,000 sf build out of flagship store on Union Square
Pan Pacific Hotel, Union Square Flagship San Francisco, CA 3,000 sf, conversion of upper floors to conference rooms
Tory Burch, Westfield Centre San Francisco, CA 1,000 sf tenant build out
Dome Obscura, Westfield Centre San Francisco, CA Preparation of the historic Westfield dome for a light show
Brobeck Phleger Law Offices Palo Alto, CA 16,000 sf office remodel of high-end law firm
Wells Fargo, 550 California Street San Francisco, CA 15,000 sf tenant improvement
Orrick, Harrington Law Offices Menlo Park, CA 16,000 & 4,500 sf total remodel of three level store
Hopper’s Grain Warehouse San Francisco, CA 30,000 sf total seismic upgrade of a historical building with high-tech offices
Panda Express, Westfield Centre San Francisco, CA Restaurant tenant build out
Lupicia Tea, Westfield Centre San Francisco, CA 1,003 sf retail tenant build out
Sakru Japan, Westfield Centre San Francisco, CA 1,670 sf restaurant tenant build out
Bellini Cafe, Westfield Centre San Francisco, CA Relocation and rebuild of cafe
Cafe Central, Westfield Centre San Francisco, CA Restaurant tenant build out
Kokkari Estiatorio at Jackson Square San Francisco, CA 8,000 sf new construction of a signature restaurant on two levels
Miscellaneous Westfield Landlord Work Westfield San Francisco Centre San Francisco, CA
PRICING
PRICING
Pricing Proposal documents.
Proposal has been provided on the following page.
April14,2015
BarneysNewYorkSanFrancisco,CA
QualificationsandExclusions
WearepleasedtosubmitourProposalforBarneysNewYork–SanFranciscobasedontheplansdated3.17.15IntheamountofFourMillion,SixHundredThirtySixThousand,andOneHundredTwoDollars(4,636,102.00).Wehaveincludedour pricingdetailforyouruse.
Qualifications:
Division01000‐GeneralRequirements
Basedona33weekconstructionschedule
Division02000–SiteWork DemolitionperPlansandSpecifications
Division03000–Concrete
ConcreteWorkasshown ConcreteToppings
Division05000–MiscellaneousMetals
StructuralSteelperplans Steeldecking MetalStairsandRailing OrnamentalPanelsatexterior.16GA
Division06000‐WoodandPlastics
RoughCarpentry Backing,BlockingandPlywoodasShown MillworkofOwnerSuppliedMaterials
Division07000–ThermalandMoistureProtection Insulation
Division08000‐DoorsandWindows
Doors,FramesandHardwareperdrawings OverheadFireDoorsasSpecified AccessDoors Glazing–perplans
Division09000–Finishes
MetalStudFramingandDrywallperPlansandSpecifications FurnishandInstallTileatrestroom StoneFlooringInstallation CarpetFlooringinstallation.SupplyPadOnly Painting
SprayGypboardceilingsandexposedceilingsandpipes SprayDoorsandframesperschedule SprayPrimewallsforwallcoverings Installownersuppliedwallcoverings
WallCoverings:InstallOwnerSuppliedwallcoverings
Division10000–Specialties Mirrorsperplans Bathaccessories
Division14000–ConveyingSystems OtisElevatorGen2ElevatorSystem DemolitionofExistingElevator
Division15000–Mechanical
FireSprinklers–DesignBuildSystem PlumbingSystemasShown HVACSystemasShown
Division16000–Electrical
ElectricalSafeOff TemporaryPowerIncluded ElectricalperthePlansandSpecifications FireAlarmDesign F/Atesting TemporaryPower Lowvoltageconduitandwire
Division22000–Cleaning
Sweepandmophardorceramictile Vacuumcarpetareas Dustdoors,frames,hardware,baseboards,ceilinglightfixtures,cabinetry,wallsandwall features,etc.
Exclusions:
Permits,inspectionfees,testingfees,andarchitectural/engineeringfees Wehavenotincludedanyconstructioncontingency Anyunforeseenconditionsandworknotshownontheplans Anyearthquakeliabilityordamageinsurance BuildersRiskInsuranceassumedprovidedbyOwner Abatement–Noprovisionsforinspectionsorreportsarefiguredinthisproposal Performancepaymentisexcluded Bonding Anyworknotprovidedinattachedestimate BarricadeGraphics ExteriorSignage SeismicUpgradesofexistingstructuralconditions SecurityoftheBuilding Overtime
Ifyouhaveanyquestionsregardingtheproposalpleasefeelfreetocontactmeat 925.223.7566
Thankyoufortheopportunitytoearnyourwork,
EricOwenBuildGroup
SCHEDULE
SCHEDULE
Schedule our approach
ID Task Mode
Task Name Duration Start Finish Predecessors
1 Preconstruction 190 days Mon 6/1/15 Fri 2/19/16
2 Building Permit 1 day Mon 6/1/15 Mon 6/1/15
3 Barney's Selects Build Group (BG) 1 day Mon 6/1/15 Mon 6/1/15
4 Barney's gives an LOI to BG 1 day Mon 6/1/15 Mon 6/1/15
5 Barney's and BG finalize Lump Sum Contract 2 days Tue 6/2/15 Wed 6/3/15
6 Fine Interiors Group (FIG) contracts with Subcontractors 5 days Thu 6/4/15 Wed 6/10/15
7
8 Value Engineering (Option)
9 Build Group contracts with MEP & Drywall Contractor 3 days Thu 6/4/15 Mon 6/8/15
10 Architect conferences with Build Group about VE options 1 day Tue 6/9/15 Tue 6/9/15 9
11 BG budgets VE options 3 days Thu 6/11/15 Mon 6/15/15 10
12 Barney's reviews and selects VE options 2 days Tue 6/16/15 Wed 6/17/15 11
13 Contract amount is readjusted for approved VE options 1 day Thu 6/18/15 Thu 6/18/15 12
14 Fine Interiors Group (FIG) contracts with balance of Subcontractors 3 days Fri 6/19/15 Tue 6/23/15 13
15
16 Submittals
17 HVAC
18 Ductwork
19 Shop Drawings 10 days Thu 6/11/15 Wed 6/24/15 6
20 Engineer Approves Shop Drawings 5 days Wed 6/17/15 Tue 6/23/15
21 Fabrication of ductwork 8 days Tue 6/23/15 Thu 7/2/15
22 Linear Diffusers
23 Shop Drawings 2 days Thu 6/11/15 Fri 6/12/15 6
24 Engineer Approves Shop Drawings 5 days Mon 6/15/15 Fri 6/19/15 23
25 Fabrication of Diffusers 5 days Mon 6/22/15 Fri 6/26/15 24
26 Equipment
27 Submitt Cut Sheets for Equipment 3 days Thu 6/11/15 Mon 6/15/15 6
28 Engineer Approves Cut Sheets 1 day Tue 6/16/15 Tue 6/16/15 27
29 Order Equipment 15 days Wed 6/17/15 Tue 7/7/15 28
30 Plumbing
31 Submitt Cut Sheets for Plumbing Fixtures 5 days Thu 6/11/15 Wed 6/17/15 6
32 Architect Approves Cut Sheets 5 days Thu 6/18/15 Wed 6/24/15 31
33 Order Plumbing Fixtures 10 days Thu 6/25/15 Wed 7/8/15 32
34 Fire Protection
35 Submitt Cut Sheets for FP Fixtures 5 days Thu 6/11/15 Wed 6/17/15 6
36 Engineer Approves Cut Sheets 5 days Thu 6/18/15 Wed 6/24/15 35
37 Order FP Fixtures 7 days Thu 6/25/15 Fri 7/3/15 36
38 Electrical
39 Submitt Cut Sheets for Lighting Fixtures (Owner Provided) 5 days Thu 6/11/15 Wed 6/17/15 6
40 Engineer & Architect Approves Cut Sheets 5 days Thu 6/18/15 Wed 6/24/15 39
41 Order Light Fixtures 20 days Thu 6/25/15 Wed 7/22/15 40
42 Ship Light Fixtures directly to site 7 days Mon 8/24/15 Tue 9/1/15
43 Glazing
44 Storefront
45 Shop Drawings 7 days Thu 6/11/15 Fri 6/19/15 6
46 Architect & Engineer Approves Shop Drawings 5 days Mon 6/22/15 Fri 6/26/15 45
47 Fabricate Storefront panels 25 days Mon 8/10/15 Fri 9/11/15 46
48 Millwork (Owner Provided)
49 Perimeter Fixturing
50 Shop Drawings 5 days Thu 6/11/15 Wed 6/17/15 6
51 Architect approves Shop Drawings 5 days Thu 6/18/15 Wed 6/24/15 50
52 Millwork Fabrication 30 days Thu 6/25/15 Wed 8/5/15 51
53 Ship Millwork to S.F. 7 days Mon 11/23/15 Tue 12/1/15
54 Loose Fixturing
55 Shop Drawings 5 days Thu 6/11/15 Wed 6/17/15 6
56 Architect approves Shop Drawings 5 days Thu 6/18/15 Wed 6/24/15 55
57 Millwork Fabrication 30 days Thu 6/25/15 Wed 8/5/15 56
58 Ship Millwork S.F. 7 days Mon 11/23/15 Tue 12/1/15
59 Door Hardware
60 Submitt Cut Sheets for Door Hardware 5 days Thu 6/11/15 Wed 6/17/15 6
61 Architect Approves Cut Sheets 6 days Thu 6/18/15 Thu 6/25/15 60
62 Order Door Hardware 21 days Fri 6/26/15 Fri 7/24/15 61
63 Stone & Tile
64 Submit Stone Sample 5 days Thu 6/11/15 Wed 6/17/15 6
6/1 Barney's Selects Build Group (BG)
1 day
6/1 Barney's gives an LOI to BG
1 day
6/2 Barney's and BG finalize Lump Sum Contract
2 days
6/4 Fine Interiors Group (FIG) contracts with Subcontractors
5 days
6/4 Build Group contracts with MEP & Drywall Contractor
3 days
6/9 Architect conferences with Build Group about VE options
1 day
6/11 BG budgets VE options
3 days
6/16 Barney's reviews and selects VE options
2 days
6/18 Contract amount is readjusted for approved VE options
1 day
6/19 Fine Interiors Group (FIG) contracts with balance of Subcontractors
3 days
6/11 Shop Drawings10 days
6/17 Engineer Approves Shop Drawings5 days
6/23 Fabrication of ductwork8 days
6/11 Shop Drawings2 da
6/15 Engineer Approves Shop Drawings5 days
6/22 Fabrication of Diffusers5 days
6/11 Submitt Cut Sheets for Equipment3 days
6/16 Engineer Approves Cut Sheets1
6/17 Order Equipment15 days
6/11 Submitt Cut Sheets for Plumbing Fixtures5 days
6/18 Architect Approves Cut Sheets5 days
6/25 Order Plumbing Fixtures10 days
6/11 Submitt Cut Sheets for FP Fixtures5 days
6/18 Engineer Approves Cut Sheets5 days
6/25 Order FP Fixtures7 days
6/11 Submitt Cut Sheets for Lighting Fixtures (Owner Provided)5 days
6/18 Engineer & Architect Approves Cut Sheets5 days
6/25 Order Light Fixtures20 days
8/24 Ship Light Fixtures directly to site7 days
6/11 Shop Drawings7 days
6/22 Architect & Engineer Approves Shop Drawings5 days
8/10 Fabricate Storefront panels25 days
6/11 Shop Drawings 5 days
6/18 Architect approves Shop Drawings5 days
6/25 Millwork Fabrication30 days
11/23 Ship Millwork to S.F.7 days
6/11 Shop Drawings
5 days
6/18 Architect approves Shop Drawings
5 days
6/25 Millwork Fabrication
30 days
11/23 Ship Millwork S.F.
7 days
6/11 Submitt Cut Sheets for Door Hardware
5 days
6/18 Architect Approves Cut Sheets
6 days
6/26 Order Door Hardware
21 days
6/11 Submit Stone Sample
5 days
M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T WMay 24, '15 May 31, '15 Jun 7, '15 Jun 14, '15 Jun 21, '15 Jun 28, '15 Jul 5, '15 Jul 12, '15 Jul 19, '15 Jul 26, '15 Aug 2, '15 Aug 9, '15 Aug 16, '15 Aug 23, '15 Aug 30, '15 Sep 6, '15 Sep 13, '15 Sep 20, '15 Sep 27, '15 Oct 4, '15 Oct 11, '15 Oct 18, '15 Oct 25, '15 Nov 1, '15 Nov 8, '15 Nov 15, '15 Nov 22, '15 Nov 29, '15 Dec 6, '15 Dec 13, '15 Dec 20, '15 Dec 27, '15 Jan 3, '16 Jan 10, '16 Jan 17, '16 Jan 24, '16 Jan 31, '16 Feb 7, '16 Feb 14, '16 Feb 21, '
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration‐only
Manual Summary Rollup
Manual Summary
Start‐only
Finish‐only
Deadline
Progress
Barney's New York ‐ San Francisco FlagshipFINE INTERIORS GROUP (BUILD GROUP)
SUBJECT TO CHANGE
Tue 4/14/15 Page 1
Project: Loro Piana Schedule 3.11Date: Tue 4/14/15
ID Task Mode
Task Name Duration Start Finish Predecessors
65 Architect approves Stone Sample 5 days Thu 6/18/15 Wed 6/24/15 64
66 Order Stone 21 days Mon 11/23/15Mon 12/21/15 65
67 Ship Stone to S.F. 7 days Mon 11/23/15 Tue 12/1/15
68 Carpet (Owner Provided)
69 Submit Carpet Sample 5 days Thu 6/11/15 Wed 6/17/15 6
70 Architect approves Carpet Sample 5 days Thu 6/18/15 Wed 6/24/15 69
71 Order Carpet 21 days Mon 6/1/15 Mon 6/29/15
72 Ship Carpet & Rugs to S.F. 7 days Tue 12/1/15 Wed 12/9/15
73 Demolition Permit
74 Demolition 21 days Tue 7/7/15 Tue 8/4/15
75
76 Construction
77 Rough In Construction 65 days Tue 7/7/15 Mon 10/5/15
78 Mobilization 5 days Tue 7/7/15 Mon 7/13/15
79 Safeoffs 2 days Thu 7/9/15 Fri 7/10/15
80 Electrical; Safe‐off 1 day Thu 7/9/15 Thu 7/9/15 78FS‐3 days
81 Plumbing & HVAC; Safe‐off 1 day Thu 7/9/15 Thu 7/9/15 78FS‐3 days
82 Temporary Utilities; (Power, Lighting) 2 days Thu 7/9/15 Fri 7/10/15 78FS‐3 days
83 Barricade 6 days Tue 7/7/15 Tue 7/14/15
84 Frame & Plywood Wood Barricade on stockton 3 days Tue 7/7/15 Thu 7/9/15
85 Paint Barricade 2 days Mon 7/13/15 Tue 7/14/15 84
86 Structural Work 41 days Wed 7/8/15 Wed 9/2/15
87 Main Level Concrete 24 days Wed 7/8/15 Mon 8/10/15
88 Footings & Install Rebar 4 days Wed 7/8/15 Mon 7/13/15 78FS‐4 days
89 Footing Inspection 1 day Tue 7/14/15 Tue 7/14/15 88
90 Pour Footings 1 day Wed 7/22/15 Wed 7/22/15 91
91 Structural steel / Pandeck install 5 days Wed 7/15/15 Tue 7/21/15 89
92 Steel stairs 14 days Wed 7/22/15 Mon 8/10/15 91
93 Storefront 7 days Mon 8/24/15 Tue 9/1/15
94 Install Steel Panels 7 days Mon 8/24/15 Tue 9/1/15
95 Concrete entry work 1 day Wed 9/2/15 Wed 9/2/15 94
96 Recessed mat work 2 days Wed 9/2/15 Thu 9/3/15 94
97 Layout 6 days Mon 8/3/15 Mon 8/10/15
98 Layout Walls 2 days Mon 8/3/15 Tue 8/4/15
99 Layout Millwork (Millworker to confirm) 2 days Wed 8/5/15 Thu 8/6/15 98
100 Layout Lighting 2 days Fri 8/7/15 Mon 8/10/15 99
101 Drywall Framing 14 days Wed 8/5/15 Mon 8/24/15 98
102 HVAC Duct Installation 8 days Wed 8/5/15 Fri 8/14/15 98
103 Rough in Electrical 21 days Tue 8/25/15 Tue 9/22/15 101
104 Rough in Plumbing 14 days Tue 8/25/15 Fri 9/11/15 101
105 Rough in Sprinklers 21 days Tue 8/25/15 Tue 9/22/15 101
106 Install Backing 7 days Tue 8/25/15 Wed 9/2/15 101
107 Install Door Frames 2 days Tue 8/25/15 Wed 8/26/15 101
108 Frame in Ceilings 14 days Tue 8/25/15 Fri 9/11/15 101
109 Install Linear Diffusers 4 days Mon 9/14/15 Thu 9/17/15 108
110 Install Lighting 14 days Mon 9/14/15 Thu 10/1/15 108
111 Install All Low Voltage Wiring 7 days Mon 9/14/15 Tue 9/22/15 108
112 Install Life Safety 7 days Mon 9/14/15 Tue 9/22/15 108
113 Rough Inspections 2 days Fri 10/2/15 Mon 10/5/15 110
114
115 Finish Construction 138 days Fri 7/31/15 Tue 2/9/16
116 Sheetrock Walls and Ceiling 7 days Wed 9/23/15 Thu 10/1/15 112
117 Tape, Top & Finish Walls & Ceiling 14 days Fri 10/2/15 Wed 10/21/15 116
118 Finish Electrical 10 days Thu 10/22/15 Wed 11/4/15 117
119 Bathrooms 11 days Thu 10/22/15 Thu 11/5/15
120 Thickset 1 day Thu 10/22/15 Thu 10/22/15 117
121 Install Stone Floor 2 days Fri 10/23/15 Mon 10/26/15 120
122 Install Thinset Tile at Walls 4 days Tue 10/27/15 Fri 10/30/15 121
123 Install Finish Plumbing 3 days Mon 11/2/15 Wed 11/4/15 122
124 Install Mirrors 1 day Thu 11/5/15 Thu 11/5/15 123
125 Install Bathroom Accessories 1 day Thu 11/5/15 Thu 11/5/15 123
126 Main Entrance 47 days Tue 10/27/15 Wed 12/30/15
127 Measure for Stair Glazing 1 day Tue 10/27/15 Tue 10/27/15 121
128 Install Glass & Mirrors 5 days Wed 10/28/15 Tue 11/3/15 127
129 Install Entry Door Hardware 1 day Wed 11/4/15 Wed 11/4/15 128
6/18 Architect approves Stone Sample
5 days
11/23 Order Stone
21 days
6/11 Submit Carpet Sample
5 days
6/18 Architect approves Carpet Sample
5 days
6/1 Order Carpet
21 days
7/7 Demolition
21 days
M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T WMay 24, '15 May 31, '15 Jun 7, '15 Jun 14, '15 Jun 21, '15 Jun 28, '15 Jul 5, '15 Jul 12, '15 Jul 19, '15 Jul 26, '15 Aug 2, '15 Aug 9, '15 Aug 16, '15 Aug 23, '15 Aug 30, '15 Sep 6, '15 Sep 13, '15 Sep 20, '15 Sep 27, '15 Oct 4, '15 Oct 11, '15 Oct 18, '15 Oct 25, '15 Nov 1, '15 Nov 8, '15 Nov 15, '15 Nov 22, '15 Nov 29, '15 Dec 6, '15 Dec 13, '15 Dec 20, '15 Dec 27, '15 Jan 3, '16 Jan 10, '16 Jan 17, '16 Jan 24, '16 Jan 31, '16 Feb 7, '16 Feb 14, '16 Feb 21, '
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration‐only
Manual Summary Rollup
Manual Summary
Start‐only
Finish‐only
Deadline
Progress
Barney's New York ‐ San Francisco FlagshipFINE INTERIORS GROUP (BUILD GROUP)
SUBJECT TO CHANGE
Tue 4/14/15 Page 2
Project: Loro Piana Schedule 3.11Date: Tue 4/14/15
ID Task Mode
Task Name Duration Start Finish Predecessors
130 Install Signage 4 days Fri 12/25/15 Wed 12/30/15 138
131 Main Entry Flooring 50 days Thu 10/22/15 Wed 12/30/15
132 Install Stone Floor 14 days Thu 10/22/15 Tue 11/10/15 117
133 Grout & Seal 5 days Tue 11/24/15 Mon 11/30/15 132
134 Install Carpet 5 days Thu 10/22/15 Wed 10/28/15 117
135 Install Millwork 21 days Tue 12/1/15 Tue 12/29/15
136 Install Perimeter Fixturing 15 days Tue 12/1/15 Mon 12/21/15 133
137 Painting 10 days Thu 10/22/15 Wed 11/4/15 117
138 Install Loose Fixturing 3 days Tue 12/22/15 Thu 12/24/15 136
139 Final Inspections 1 day Fri 12/25/15 Fri 12/25/15 138
140 TCO 1 day Wed 1/13/16 Wed 1/13/16 141
141 Punchlist 10 days Wed 12/30/15 Tue 1/12/16 142
142 Install Furniture 3 days Fri 12/25/15 Tue 12/29/15 138
143 Stock Store 10 days Thu 1/14/16 Wed 1/27/16 140
144 Train Personel 10 days Thu 1/28/16 Wed 2/10/16 143
145 Grand Opening 1 day Thu 2/11/16 Thu 2/11/16 144
146 TCO 1 day Wed 12/30/15Wed 12/30/15 142
147 Punchlist 10 days Wed 12/30/15 Tue 1/12/16 142
148 Install Furniture 5 days Wed 1/13/16 Tue 1/19/16 147
149 Stock Store 10 days Wed 1/20/16 Tue 2/2/16 148
150 Train Personel 5 days Wed 2/3/16 Tue 2/9/16 149
151 Grand Opening 0 days Tue 2/9/16 Tue 2/9/16 150
12/30 TCO
1 day
12/30 Punchlist
10 days
1/13 Install Furniture
5 days
1/20 Stock Store
10 days
2/3 Train Personel
5 days
2/9
M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T WMay 24, '15 May 31, '15 Jun 7, '15 Jun 14, '15 Jun 21, '15 Jun 28, '15 Jul 5, '15 Jul 12, '15 Jul 19, '15 Jul 26, '15 Aug 2, '15 Aug 9, '15 Aug 16, '15 Aug 23, '15 Aug 30, '15 Sep 6, '15 Sep 13, '15 Sep 20, '15 Sep 27, '15 Oct 4, '15 Oct 11, '15 Oct 18, '15 Oct 25, '15 Nov 1, '15 Nov 8, '15 Nov 15, '15 Nov 22, '15 Nov 29, '15 Dec 6, '15 Dec 13, '15 Dec 20, '15 Dec 27, '15 Jan 3, '16 Jan 10, '16 Jan 17, '16 Jan 24, '16 Jan 31, '16 Feb 7, '16 Feb 14, '16 Feb 21, '
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration‐only
Manual Summary Rollup
Manual Summary
Start‐only
Finish‐only
Deadline
Progress
Barney's New York ‐ San Francisco FlagshipFINE INTERIORS GROUP (BUILD GROUP)
SUBJECT TO CHANGE
Tue 4/14/15 Page 3
Project: Loro Piana Schedule 3.11Date: Tue 4/14/15