Bg response to invitation to bid barneys 041415

34
457 minna street, suite 100, san francisco, ca 94103 www.buildgc.com Build Group Barneys New York - Men’s Expansion APRIL 15, 2015

description

 

Transcript of Bg response to invitation to bid barneys 041415

Page 1: Bg response to invitation to bid barneys 041415

457 minna street, suite 100, san francisco, ca 94103www.buildgc.com

BuildGroupBarneys New York - Men’s Expansion

APRIL 15, 2015

Page 2: Bg response to invitation to bid barneys 041415

TABLE OF CONTENTS

TEAM 1

EXPERIENCE 2

PRICING 3

SCHEDULE 4

457 minna street, suite 100, san francisco, ca 94103www.buildgc.com

Page 3: Bg response to invitation to bid barneys 041415

EXPERIENCE

EXPERIENCE

Page 4: Bg response to invitation to bid barneys 041415

EXPERIENCE

Experience Let’s show you our stuff!

High-End RetailFine Interiors Group is an extensive tenant build-out team. This division focuses solely on meeting the needs of tenant improvement clients, primarily on high-end retail spaces and restaurants. Fine Interiors Group has completed tenant build-outs for clients including Gucci, John Varvatos, Burberry, Nespresso, and Coach.

On the following pages, we have provided a sampling of our client relationships.

H&M | Union Square | San Francisco

Page 5: Bg response to invitation to bid barneys 041415

EXPERIENCE

TenantImprovements A snapshot of brands we have worked with.

Page 6: Bg response to invitation to bid barneys 041415

EXPERIENCE

* Flagship Store

MINNA

1 Metropolitain Club 2 Postrio 3 Donatello Hotel 4 449 Powell 5 Villa Florence Hotel 6 Dr. Marten 7 400 Sutter 8 Hyatt Union Square 9 I. Magnin | Macy’s10 Liberty House | Macy’s11 Gucci*12a Celine*12b Loro Piana*13 Wolford14 Gumps15 Tailored Man 16 Scheuer Linens

Fine Interiors Group/Build Group Offices

Completed Projects

Current Projects

UNIONSQUARE

SUTTER

POST

STOC

KTON

GEARY

POW

ELL

O’FARRELL

ELLIS

GR

ANT

KEARNY

MARKET

MISSIONFIFTH

FOURTH

THIRD

MASO

N

1

2 3

4

5

67

8

9

10

11

12a12b

13

14

15 16

17

24

2549

26

27

3545

36

37

38 39

40

41

42

23

28

29

30

31

32

33

34

1819

20

2122

43

46

47

48

44

San Francisco Retail Experience

17 239 Grant18 Coach Leather*19 Talbots*20 Rizzoli Bookstore*21 100 Grant22 Bottega Veneta*23 Compuserve24 H & M25 H & M*26 Axelle Gallery27 Benetton*28 Pan Pacific Hotel29 Allison Hotel30 Post Street Hotel31 Carolina Herrera*32 Nikko Hotel33 Sisley*

34 Anne Fontaine*35 Longchamp*36 Christofle*37 200 Powell38 152 Geary Street39 46 Geary Street40 533 Sutter Street41 John Varvatos*42 UGG43 Ritz Carleton Spa44 Jimmy Choo*45 77 Maiden Lane Spa46 Westfield Centre - 55+ Retail Stores47 Metreon & City View48 Nespresso*49 Jins Eyewear (under construction)

Page 7: Bg response to invitation to bid barneys 041415

EXPERIENCE

Bay Area Ports

San Francisco

Oakland

Alameda

UNION SQUARE

PIER STORAGE

Convienient Storage from Port of Oakland

Our Fine Interiors Group San Francisco location has storage space at Pier 50. This is an added benefit for our retail partners looking to ship in merchindise to the Port of Oakland.

Fine Interiors Group San Francisco Office

Union Square

Pier 50 Storage Space

Page 8: Bg response to invitation to bid barneys 041415

EXPERIENCE

John Varvatos, Flagshipunion square, san francisco, ca

OwnerJohn Varvatos

ArchitectDucDuc (New York)Pollack Associates (SF)

Duration16 weeks

The seventh and the largest of the John Varvatos stores, the San Francisco flagship features two floors of sophisticated interiors, showcasing the Varvatos casual to formal menswear attire. Solid walnut floors are throughout this design/build project.

The construction team coordinated with both architects on the East and West coasts and met a very aggressive schedule.

In addition to the remodel of the interior space, there team also completed a full seismic upgrade on the building.

Page 9: Bg response to invitation to bid barneys 041415

EXPERIENCE

JINS, Flagship union square, san francisco, ca

OwnerJINS

ArchitectKwan Henmi Architects

Project Duration15 weeks

The 4,300 sf build-out includes various elements that represent the clients ‘fully-customized’ products. The store includes high-end case work, new facade, ardex polished concrete floors, and back of the house conference rooms and bathrooms.

The focal point of the store is the specialty showcase room that will be used to produce all products on-site. The room was built with epoxy flooring and is encased in glass.

Page 10: Bg response to invitation to bid barneys 041415

EXPERIENCE

Nespresso, Flagshipunion square, san francisco, ca

OwnerNespresso

ArchitectGoring & Straja Architects

Duration19 weeks

The first signature Nespresso in San Francisco, this Union Square build-out features a modern design in a 100-year-old building. A complete structural rebuild of the first and second floors was constructed to make way for café and retail spaces. The team remained on a tight schedule while coordinating vendors from across the U.S. and Europe that completed high-end finishes. Architectural features include a floating staircase leading customers from the upper café area into the lower retail space.

Page 11: Bg response to invitation to bid barneys 041415

EXPERIENCE

Kate Spade, Retail Storewestfield, san francisco, ca

OwnerKate Spade, NY

ArchitectFreebaim, Smith & Crane

Project Duration8 weeks

The 2,700 sf Kate Spade retail outlet is located in the Westfield San Francisco Centre Mall. The project included wall-to-wall demolition of the existing store in order to redesign with updated corporate aesthetics and branding. The updates include luxury, high-end brass finishes on all fixtures and fit-outs along with a detailed store front system.

Page 12: Bg response to invitation to bid barneys 041415

EXPERIENCE

Club Monaco, Retail Storewestfield, san francisco, ca

OwnerClub Monaco

ArchitectAtelier Design, LLC

Project Duration22 weeks

Build Group provided the complete build-out of Club Monaco’s retail store in Union Square. Phase One involved the complete demolition of the existing 4,924 sf store. A portion of the Phase Two redesign work involved the high-end finishes, millwork, and hand-painted custom case work that the client is recognized for. Additionally, our team installed white oak wood floors that are a staple of this location. Build Group installed two, custom painted 12-foot-tall entrance doors, while upgrading the store’s facade.

Page 13: Bg response to invitation to bid barneys 041415

EXPERIENCE

H&M, Flagshipunion square, san francisco, ca

OwnerH&M

ArchitectTEK Architects

Duration20 weeks

H&M’s flagship store in a historic building on Powell St. features new escalators, large video display screens, all new stone flooring, 42 high-end dressing rooms, new restrooms, employee locker rooms, and kitchen, as well as a carefully restored historical ceiling, entry, and 400 linear feet of new sidewalk.

The Post Street store features all new stone flooring, a new glass balcony overlooking the entry, a grand staircase, new exterior sidewalks, new restrooms, and 20 high-end dressing rooms.

Both stores were completed one month ahead of schedule.

Page 14: Bg response to invitation to bid barneys 041415

EXPERIENCE

Gucci, Flagshiphonolulu, hawaii

OwnerGucci

ArchitectGensler

Duration20 weeks (fast-track schedule)

This project was Gucci’s first design-build turnkey. The store remained in business throughout the entire construction period, and was completed three weeks ahead of schedule with zero change orders.

The store location is set along the city’s waterfront and included a structural upgrade to the building, with a two-story high ornamental storefront finished with stainless steel panels. The store also included imported Italian millwork in high lacquered rosewood. All fixtures were supplied and installed by the construction team.

Page 15: Bg response to invitation to bid barneys 041415

EXPERIENCE

Rizzoli Bookstorepasadena, ca

OwnerRizzoli Bookstore

ArchitectMeyer & Gifford

Duration5 weeks

Throughout the 5,000 sf, the elegance of rich cherry fixtures and walnut flooring contribute to the warmth of a private study.

Stately columns, brass handrails and lush imported carpeting are reminiscent of turn of the century America, remaining faithful to early 1900’s building facade. The millwork package was provided and installed by Build Group.

This project was completed after only seven weeks of construction.

Page 16: Bg response to invitation to bid barneys 041415

EXPERIENCE

Hog Island Oyster Companysan francisco, ca

OwnerHog Island Oyster Company

ArchitectCCS Architecture

Duration12 weeks

Build Group, Inc. completed construction on the $1.2 million renovation of Hog Island Oyster Company’s restaurant space in the historic San Francisco Ferry Building.

At 3,800 sf, the facility’s new space was reconfigured to triple the existing restaurant and add 1,100 square feet of outdoor dining space. The new 130-seat restaurant features a full-service kitchen and bar, custom concrete bar counters, and reclaimed cypress millwork throughout. The ceiling, designed by CCS Architecture, was constructed to replicate the hull of a boat.

One of the toughest challenges on this job was coordinating the installation of the plumbing work. Since the Ferry Building is located on a pier, all plumbing work needed to be done by boat under the pier which required an extensive amount of coordination. In addition, work had to be completed in and around a fully-occupied building. Weekly meetings were held with the ferry building to constantly update them on our schedule. Any disruptive or noisy work was done off-hours to avoid any interference to the adjacent tenants.

Page 17: Bg response to invitation to bid barneys 041415

EXPERIENCE

M.Y. China, Signature Restaurantsan francisco, ca

OwnerM.Y. China

ArchitectBCV Architects

Duration23 weeks

This project included construction of a new signature restaurant at Westfield’s San Francisco Centre. Based on television chef Martin Yan’s recipes, M.Y. China offers a 181-seat, high-end, high-class, exhibition style eating experience. Custom eucalyptus woodwork, laser cut metal screens, and antique Chinese furnishings set the scene for a sophisticated meal.

The eye-catching centerpiece of the restaurants circular bar, is an antique 1,800 pound bell that was imported in from China.

Page 18: Bg response to invitation to bid barneys 041415

TEAM

TEAM

Page 19: Bg response to invitation to bid barneys 041415

TEAM

Team Meet a few of our incredible team members.

Collectively, our principals have over 193 years of experience in the construction industry with the majority of this experience in the Bay Area. Our leadership team knows the complexities of building in San Francisco particularly the intricacies of permitting with the City and local agencies. Resumes have been provided on the following pages.

Page 20: Bg response to invitation to bid barneys 041415

TEAM

Principal John Santori

Education B.S. Biochemistry, University of California, Berkeley

Nespresso, Union Square Flagship San Francisco, CA 8,600 sf high-end retail tenant improvement

JINS San Francisco, CA 4,300 sf, TI build-out, high-end case work, new front facade, ardex polished concrete floors, back of the house conference rooms and bathrooms, specialty show case room

Carolina Herrera San Francisco, CA $1.3 million, high-end retail build-out in Union Square

Burberry Brit, Westfield Centre San Francisco, CA Wood flooring, high-finish millwork, 12-week schedule, large format interior storefront

Gucci, Union Square Flagship San Francisco, CA 16,000 sf, four levels, 40% of ground floor concrete was removed and replaced for ADA compliance

Gucci, Ala Moana Shopping Center Honolulu, HI 7,732 sf, flagship store

John Vavartos, Union Square Flagship San Francisco, CA 6,500 sf, two level flagship, $2 million

Talbots, 26 Stores Throughout West Coast 12,000 sf, flagship store

H & M, Powell St., Union Square San Francisco, CA 40,000 sf, new high-end flagship, $4.5 million

Jimmy Choo, Union Square Flagship San Francisco, CA 2,300 sf tenant build-out, flagship store with high-end finishes

Tori Burch, Westfield Centre San Francisco, CA 1,381 sf tenant build-out, high-end finishes throughout

Bliss Spa at W Hotel Hollywood, CA 5,000 sf build out of high-end spa on the 4th floor of new W Hotel including 12 spa treatment rooms, sauna, steam rooms and a retail area

Villa Florence Hotel San Francisco, CA 125,000 sf hotel remodel in historic building

Hyatt Regency Embarcadero San Francisco, CA Remodel of public areas, club rooms and suites

Donatello Hotel, Union Square San Francisco, CA

Rizzoli’s Bookstore, 5 locations Pasadena, CA 5,000 sf, new high-end flagship, $1.2 million

Rizzoli’s Bookstore Pasadena, CA 5,000 sf retail build-out, stately columns, brass handrails, lush imported carpeting remaining faithful to early 1900’s building facade

Betsy Johnson, Westfield Centre San Francisco, CA 1,100 sf tenant build out, signature retail project, creative re-use of existing elements, eight weeks

Relevant Experience

John is a 30 year veteran with specialized expertise in high-end retail, signature restaurants and seismic upgrades. He helps lead Build Group Retail, Hospitality, Fine Interiors divisions, specializing in business development to assist clients in making deals pencil. John joined Build Group in 2007 through the acquisition of his company, Fine Line Group. He founded Fine Line Group in 1979 and grew the company to become a leading firm with unparalleled knowledge of Union Square and an uncompromising commitment to quality.

Page 21: Bg response to invitation to bid barneys 041415

TEAM

Director of Operations Mark Izdepski

Education / Credentials BS IET Purdue University West Lafayette, Indiana

Continual Education: OSHA Certified, Continuing Education with Insurance Carriers, Safety, Laws and Regulations, Business Practices, Advanced Building Codes, Improving Construction Productivity, Workers Compensation

Tiffany & Co., Retail Stores San Diego, Rodeo, Topanga, Ala Moana - Waikiki, HI, Santa Barbara, Carmel, and 25 other locations

Cartier, Van Cleef & Arpels, Retail Stores Nationwide

Fendi, Retail Stores Las Vegas, NV

Armani Exchange, Retail Stores San Francisco, Pasadena, San Diego, San Jose, Nationwide

Giorgio Armani, Retail Stores Desert Hills, Miami, Manhasset, Nationwide

COACH, Retail Stores Nationwide

Lacoste, Retail Stores +60 stores Nationwide

Michael Kors, Retail Stores Denver, Miami, Nationwide

St John Knit, Retail Stores Nationwide

Versace, Retail Stores Las Vegas, NV Nationwide

Gucci, Retail Stores Two Rodeo Drive, CA San Francisco, Nationwide

Hermes Las Vegas, NV $8 million, in Bellagio Hotel, high-end jewelry retail store

Louis Vuitton Dallas, TX Las Vegas

Escada Rodeo Drive, CA Scottsdale, AZ, Nationwide

Yves Saint Laurent Houston, TX

Prada Desert Hills, CA South Coast Plaza, Costa Mesa, CA Beverly Center - Los Angeles, CA

Mikimoto Rodeo Drive, CA South Coast Plaza, Costa Mesa, CA Nationwide

Tory Burch San Francisco, CA San Diego, CA, Nationwide

Loro Piana Caesars - Las Vegas, Rodeo Drive, Bal Harbour Shops, Florida, Nationwide

Hugo Boss Nationwide

Kenneth Cole Nationwide

Kachina Point Retirement Center Sedona, AZ

Relevant Experience

Mark is an experienced construction professional with over 30 years specializing in high-end retail, hospitality and restaurant construction. Mark is Director of Operations of Build Groups Fine Interiors division. He is responsible for leading Build Groups highly competent teams of construction professionals guaranteeing on time on budget projects for our many repeat clients. Other responsibilities include facilitating the companies Safety Program and Customer Service & Satisfaction initiatives.

Page 22: Bg response to invitation to bid barneys 041415

TEAM

Project Manager Tim Ferguson

Hotel Renoir San Francisco, CA 83,300 sf seismic upgrade & remodel, seven-stories, 135 rooms

Mary Helen Rogers Senior Community San Francisco, CA $30 million, eight-story concrete building, ground-floor lobby, one level below grade parking

Edith Witt Senior Center San Francisco, CA $35 million, 11-story concrete structure, one level below grade parking structure

Villa Serena Tampa, FL $68 million, 29 four-story condominium structures, wood frame over concrete podium

The Arbor Assisted Living Facility Fort Myers, FL $32 million, five-story concrete building, two-story amenity structure, one-story parking garage

Parkwood Place Independent Living Facility Fort Myers, FL $38 million, eight-story concrete structure, two-story parking garage

Capital One Buildings J, K, and Parking Structure Tampa, FL $62 million, two, four-story call center buildings, three-story parking garage

Relevant Experience

Tim Ferguson is a detail oriented Project Manager with more than 17 years of experience. He has a proven record in driving the completion of large-scale, multimillion dollar projects. Tim has a superior ability to develop a projects budget, with a demonstrated excellence in establishing parameters and managing numerous teams to complete projects under budget and within deadlines.

Page 23: Bg response to invitation to bid barneys 041415

TEAM

SuperintendentJeff Lucero

Relevant Experience

Jeff Lucero is a Superintendent with more than 26 years of tenant improvement and construction experience. Jeff is known for his strong scheduling and completion record. With his long record of building in San Francisco, Jeff has developed an in-depth knowledge of city building codes and Title 19 & 24. He has extensive experience in high-end finishes, as well as framing, electrical, plumbing, door frames, door hardware, mill work, finish carpentry and tile.

Gucci, Union Square Flagship San Francisco, CA 16,000 sf, four levels, 40% of ground floor concrete was removed and replaced for ADA compliance

Bottega Veneta, Union Square Flagship San Francisco, CA 2,700 sf build out of flagship store on Union Square

Loro Piana, Union Square Flagship San Francisco, CA 3,000 sf build out of flagship store on Union Square

Pan Pacific Hotel, Union Square Flagship San Francisco, CA 3,000 sf, conversion of upper floors to conference rooms

Tory Burch, Westfield Centre San Francisco, CA 1,000 sf tenant build out

Dome Obscura, Westfield Centre San Francisco, CA Preparation of the historic Westfield dome for a light show

Brobeck Phleger Law Offices Palo Alto, CA 16,000 sf office remodel of high-end law firm

Wells Fargo, 550 California Street San Francisco, CA 15,000 sf tenant improvement

Orrick, Harrington Law Offices Menlo Park, CA 16,000 & 4,500 sf total remodel of three level store

Hopper’s Grain Warehouse San Francisco, CA 30,000 sf total seismic upgrade of a historical building with high-tech offices

Panda Express, Westfield Centre San Francisco, CA Restaurant tenant build out

Lupicia Tea, Westfield Centre San Francisco, CA 1,003 sf retail tenant build out

Sakru Japan, Westfield Centre San Francisco, CA 1,670 sf restaurant tenant build out

Bellini Cafe, Westfield Centre San Francisco, CA Relocation and rebuild of cafe

Cafe Central, Westfield Centre San Francisco, CA Restaurant tenant build out

Kokkari Estiatorio at Jackson Square San Francisco, CA 8,000 sf new construction of a signature restaurant on two levels

Miscellaneous Westfield Landlord Work Westfield San Francisco Centre San Francisco, CA

Page 24: Bg response to invitation to bid barneys 041415

PRICING

Page 25: Bg response to invitation to bid barneys 041415

PRICING

Pricing Proposal documents.

Proposal has been provided on the following page.

Page 26: Bg response to invitation to bid barneys 041415

 

     

 

April14,2015 

BarneysNewYorkSanFrancisco,CA

 QualificationsandExclusions

 WearepleasedtosubmitourProposalforBarneysNewYork–SanFranciscobasedontheplansdated3.17.15IntheamountofFourMillion,SixHundredThirtySixThousand,andOneHundredTwoDollars(4,636,102.00).Wehaveincludedour pricingdetailforyouruse.

 Qualifications:

 Division01000‐GeneralRequirements

Basedona33weekconstructionschedule 

Division02000–SiteWork DemolitionperPlansandSpecifications

Division03000–Concrete

ConcreteWorkasshown ConcreteToppings

 Division05000–MiscellaneousMetals

StructuralSteelperplans Steeldecking MetalStairsandRailing OrnamentalPanelsatexterior.16GA

 Division06000‐WoodandPlastics

RoughCarpentry Backing,BlockingandPlywoodasShown MillworkofOwnerSuppliedMaterials

Division07000–ThermalandMoistureProtection Insulation

 Division08000‐DoorsandWindows

Doors,FramesandHardwareperdrawings OverheadFireDoorsasSpecified AccessDoors Glazing–perplans

 

Page 27: Bg response to invitation to bid barneys 041415

 

Division09000–Finishes

MetalStudFramingandDrywallperPlansandSpecifications FurnishandInstallTileatrestroom StoneFlooringInstallation CarpetFlooringinstallation.SupplyPadOnly Painting

SprayGypboardceilingsandexposedceilingsandpipes SprayDoorsandframesperschedule SprayPrimewallsforwallcoverings Installownersuppliedwallcoverings

WallCoverings:InstallOwnerSuppliedwallcoverings 

Division10000–Specialties Mirrorsperplans Bathaccessories

Division14000–ConveyingSystems OtisElevatorGen2ElevatorSystem DemolitionofExistingElevator

 Division15000–Mechanical

FireSprinklers–DesignBuildSystem PlumbingSystemasShown HVACSystemasShown

 Division16000–Electrical

ElectricalSafeOff TemporaryPowerIncluded ElectricalperthePlansandSpecifications FireAlarmDesign F/Atesting TemporaryPower Lowvoltageconduitandwire

 Division22000–Cleaning

Sweepandmophardorceramictile Vacuumcarpetareas Dustdoors,frames,hardware,baseboards,ceilinglightfixtures,cabinetry,wallsandwall features,etc.

 

Page 28: Bg response to invitation to bid barneys 041415

 

Exclusions:

Permits,inspectionfees,testingfees,andarchitectural/engineeringfees Wehavenotincludedanyconstructioncontingency Anyunforeseenconditionsandworknotshownontheplans Anyearthquakeliabilityordamageinsurance BuildersRiskInsuranceassumedprovidedbyOwner Abatement–Noprovisionsforinspectionsorreportsarefiguredinthisproposal Performancepaymentisexcluded Bonding Anyworknotprovidedinattachedestimate BarricadeGraphics ExteriorSignage SeismicUpgradesofexistingstructuralconditions SecurityoftheBuilding Overtime

 

Ifyouhaveanyquestionsregardingtheproposalpleasefeelfreetocontactmeat 925.223.7566 

Thankyoufortheopportunitytoearnyourwork,

 EricOwenBuildGroup

Page 29: Bg response to invitation to bid barneys 041415
Page 30: Bg response to invitation to bid barneys 041415

SCHEDULE

Page 31: Bg response to invitation to bid barneys 041415

SCHEDULE

Schedule our approach

Page 32: Bg response to invitation to bid barneys 041415

ID Task Mode

Task Name Duration Start Finish Predecessors

1 Preconstruction 190 days Mon 6/1/15 Fri 2/19/16

2  Building Permit 1 day Mon 6/1/15 Mon 6/1/15

3 Barney's Selects Build Group (BG) 1 day Mon 6/1/15 Mon 6/1/15

4 Barney's gives an LOI to BG 1 day Mon 6/1/15 Mon 6/1/15

5 Barney's and BG finalize Lump Sum Contract 2 days Tue 6/2/15 Wed 6/3/15

6 Fine Interiors Group (FIG) contracts with Subcontractors 5 days Thu 6/4/15 Wed 6/10/15

7

8  Value Engineering (Option)

9  Build Group contracts with MEP & Drywall Contractor  3 days Thu 6/4/15 Mon 6/8/15

10 Architect conferences with Build Group about VE options 1 day Tue 6/9/15 Tue 6/9/15 9

11  BG budgets VE options 3 days Thu 6/11/15 Mon 6/15/15 10

12 Barney's reviews and selects VE options 2 days Tue 6/16/15 Wed 6/17/15 11

13 Contract amount is readjusted for approved VE options 1 day Thu 6/18/15 Thu 6/18/15 12

14 Fine Interiors Group (FIG) contracts with balance of Subcontractors 3 days Fri 6/19/15 Tue 6/23/15 13

15

16  Submittals

17  HVAC

18  Ductwork 

19  Shop Drawings 10 days Thu 6/11/15 Wed 6/24/15 6

20  Engineer Approves Shop Drawings 5 days Wed 6/17/15 Tue 6/23/15

21  Fabrication of ductwork 8 days Tue 6/23/15 Thu 7/2/15

22 Linear Diffusers

23  Shop Drawings 2 days Thu 6/11/15 Fri 6/12/15 6

24  Engineer Approves Shop Drawings 5 days Mon 6/15/15 Fri 6/19/15 23

25  Fabrication of Diffusers 5 days Mon 6/22/15 Fri 6/26/15 24

26  Equipment 

27  Submitt Cut Sheets for Equipment 3 days Thu 6/11/15 Mon 6/15/15 6

28  Engineer Approves Cut Sheets 1 day Tue 6/16/15 Tue 6/16/15 27

29  Order Equipment 15 days Wed 6/17/15 Tue 7/7/15 28

30  Plumbing 

31  Submitt Cut Sheets for Plumbing Fixtures 5 days Thu 6/11/15 Wed 6/17/15 6

32  Architect Approves Cut Sheets 5 days Thu 6/18/15 Wed 6/24/15 31

33  Order Plumbing Fixtures 10 days Thu 6/25/15 Wed 7/8/15 32

34  Fire Protection

35  Submitt Cut Sheets for FP Fixtures 5 days Thu 6/11/15 Wed 6/17/15 6

36  Engineer Approves Cut Sheets 5 days Thu 6/18/15 Wed 6/24/15 35

37  Order FP Fixtures 7 days Thu 6/25/15 Fri 7/3/15 36

38  Electrical

39  Submitt Cut Sheets for Lighting Fixtures (Owner Provided) 5 days Thu 6/11/15 Wed 6/17/15 6

40  Engineer & Architect Approves Cut Sheets 5 days Thu 6/18/15 Wed 6/24/15 39

41  Order Light Fixtures 20 days Thu 6/25/15 Wed 7/22/15 40

42  Ship Light Fixtures directly to site 7 days Mon 8/24/15 Tue 9/1/15

43  Glazing

44  Storefront 

45  Shop Drawings 7 days Thu 6/11/15 Fri 6/19/15 6

46  Architect & Engineer Approves Shop Drawings 5 days Mon 6/22/15 Fri 6/26/15 45

47  Fabricate Storefront panels 25 days Mon 8/10/15 Fri 9/11/15 46

48  Millwork (Owner Provided)

49  Perimeter Fixturing

50  Shop Drawings  5 days Thu 6/11/15 Wed 6/17/15 6

51  Architect approves Shop Drawings 5 days Thu 6/18/15 Wed 6/24/15 50

52  Millwork Fabrication 30 days Thu 6/25/15 Wed 8/5/15 51

53  Ship Millwork to S.F. 7 days Mon 11/23/15 Tue 12/1/15

54  Loose Fixturing

55  Shop Drawings  5 days Thu 6/11/15 Wed 6/17/15 6

56  Architect approves Shop Drawings 5 days Thu 6/18/15 Wed 6/24/15 55

57  Millwork Fabrication 30 days Thu 6/25/15 Wed 8/5/15 56

58  Ship Millwork S.F. 7 days Mon 11/23/15 Tue 12/1/15

59  Door Hardware 

60  Submitt Cut Sheets for Door Hardware 5 days Thu 6/11/15 Wed 6/17/15 6

61  Architect Approves Cut Sheets 6 days Thu 6/18/15 Thu 6/25/15 60

62  Order Door Hardware 21 days Fri 6/26/15 Fri 7/24/15 61

63  Stone & Tile

64  Submit Stone Sample 5 days Thu 6/11/15 Wed 6/17/15 6

6/1 Barney's Selects Build Group (BG)

1 day

6/1 Barney's gives an LOI to BG

1 day

6/2 Barney's and BG finalize Lump Sum Contract

2 days

6/4 Fine Interiors Group (FIG) contracts with Subcontractors

5 days

6/4  Build Group contracts with MEP & Drywall Contractor 

3 days

6/9 Architect conferences with Build Group about VE options

1 day

6/11  BG budgets VE options

3 days

6/16 Barney's reviews and selects VE options

2 days

6/18 Contract amount is readjusted for approved VE options

1 day

6/19 Fine Interiors Group (FIG) contracts with balance of Subcontractors

3 days

6/11  Shop Drawings10 days

6/17  Engineer Approves Shop Drawings5 days

6/23  Fabrication of ductwork8 days

6/11  Shop Drawings2 da

6/15  Engineer Approves Shop Drawings5 days

6/22  Fabrication of Diffusers5 days

6/11  Submitt Cut Sheets for Equipment3 days

6/16  Engineer Approves Cut Sheets1

6/17  Order Equipment15 days

6/11  Submitt Cut Sheets for Plumbing Fixtures5 days

6/18  Architect Approves Cut Sheets5 days

6/25  Order Plumbing Fixtures10 days

6/11  Submitt Cut Sheets for FP Fixtures5 days

6/18  Engineer Approves Cut Sheets5 days

6/25  Order FP Fixtures7 days

6/11  Submitt Cut Sheets for Lighting Fixtures (Owner Provided)5 days

6/18  Engineer & Architect Approves Cut Sheets5 days

6/25  Order Light Fixtures20 days

8/24 Ship Light Fixtures directly to site7 days

6/11  Shop Drawings7 days

6/22  Architect & Engineer Approves Shop Drawings5 days

8/10 Fabricate Storefront panels25 days

6/11  Shop Drawings 5 days

6/18  Architect approves Shop Drawings5 days

6/25 Millwork Fabrication30 days

11/23  Ship Millwork to S.F.7 days

6/11  Shop Drawings 

5 days

6/18  Architect approves Shop Drawings

5 days

6/25 Millwork Fabrication

30 days

11/23  Ship Millwork S.F.

7 days

6/11  Submitt Cut Sheets for Door Hardware

5 days

6/18  Architect Approves Cut Sheets

6 days

6/26  Order Door Hardware

21 days

6/11  Submit Stone Sample

5 days

M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T WMay 24, '15 May 31, '15 Jun 7, '15 Jun 14, '15 Jun 21, '15 Jun 28, '15 Jul 5, '15 Jul 12, '15 Jul 19, '15 Jul 26, '15 Aug 2, '15 Aug 9, '15 Aug 16, '15 Aug 23, '15 Aug 30, '15 Sep 6, '15 Sep 13, '15 Sep 20, '15 Sep 27, '15 Oct 4, '15 Oct 11, '15 Oct 18, '15 Oct 25, '15 Nov 1, '15 Nov 8, '15 Nov 15, '15 Nov 22, '15 Nov 29, '15 Dec 6, '15 Dec 13, '15 Dec 20, '15 Dec 27, '15 Jan 3, '16 Jan 10, '16 Jan 17, '16 Jan 24, '16 Jan 31, '16 Feb 7, '16 Feb 14, '16 Feb 21, '

Task

Split

Milestone

Summary

Project Summary

External Tasks

External Milestone

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration‐only

Manual Summary Rollup

Manual Summary

Start‐only

Finish‐only

Deadline

Progress

Barney's New York ‐ San Francisco FlagshipFINE INTERIORS GROUP (BUILD GROUP)

SUBJECT TO CHANGE

Tue 4/14/15 Page 1

Project: Loro Piana Schedule 3.11Date: Tue 4/14/15

Page 33: Bg response to invitation to bid barneys 041415

ID Task Mode

Task Name Duration Start Finish Predecessors

65  Architect approves Stone Sample 5 days Thu 6/18/15 Wed 6/24/15 64

66  Order Stone 21 days Mon 11/23/15Mon 12/21/15 65

67 Ship Stone to S.F. 7 days Mon 11/23/15 Tue 12/1/15

68  Carpet (Owner Provided)

69  Submit Carpet Sample 5 days Thu 6/11/15 Wed 6/17/15 6

70  Architect approves Carpet Sample 5 days Thu 6/18/15 Wed 6/24/15 69

71  Order Carpet 21 days Mon 6/1/15 Mon 6/29/15

72 Ship Carpet & Rugs to S.F. 7 days Tue 12/1/15 Wed 12/9/15

73 Demolition Permit

74 Demolition  21 days Tue 7/7/15 Tue 8/4/15

75

76 Construction

77  Rough In Construction 65 days Tue 7/7/15 Mon 10/5/15

78  Mobilization 5 days Tue 7/7/15 Mon 7/13/15

79  Safeoffs 2 days Thu 7/9/15 Fri 7/10/15

80  Electrical; Safe‐off 1 day Thu 7/9/15 Thu 7/9/15 78FS‐3 days

81  Plumbing & HVAC; Safe‐off 1 day Thu 7/9/15 Thu 7/9/15 78FS‐3 days

82  Temporary Utilities; (Power, Lighting) 2 days Thu 7/9/15 Fri 7/10/15 78FS‐3 days

83  Barricade  6 days Tue 7/7/15 Tue 7/14/15

84  Frame & Plywood Wood Barricade on stockton 3 days Tue 7/7/15 Thu 7/9/15

85  Paint Barricade 2 days Mon 7/13/15 Tue 7/14/15 84

86  Structural Work  41 days Wed 7/8/15 Wed 9/2/15

87 Main Level Concrete  24 days Wed 7/8/15 Mon 8/10/15

88 Footings & Install Rebar 4 days Wed 7/8/15 Mon 7/13/15 78FS‐4 days

89 Footing Inspection 1 day Tue 7/14/15 Tue 7/14/15 88

90 Pour Footings 1 day Wed 7/22/15 Wed 7/22/15 91

91 Structural steel / Pandeck install 5 days Wed 7/15/15 Tue 7/21/15 89

92 Steel stairs 14 days Wed 7/22/15 Mon 8/10/15 91

93  Storefront  7 days Mon 8/24/15 Tue 9/1/15

94 Install Steel Panels 7 days Mon 8/24/15 Tue 9/1/15

95 Concrete entry work 1 day Wed 9/2/15 Wed 9/2/15 94

96 Recessed mat work 2 days Wed 9/2/15 Thu 9/3/15 94

97  Layout 6 days Mon 8/3/15 Mon 8/10/15

98  Layout Walls  2 days Mon 8/3/15 Tue 8/4/15

99  Layout Millwork (Millworker to confirm) 2 days Wed 8/5/15 Thu 8/6/15 98

100  Layout Lighting 2 days Fri 8/7/15 Mon 8/10/15 99

101  Drywall Framing 14 days Wed 8/5/15 Mon 8/24/15 98

102  HVAC Duct Installation 8 days Wed 8/5/15 Fri 8/14/15 98

103  Rough in Electrical 21 days Tue 8/25/15 Tue 9/22/15 101

104  Rough in Plumbing 14 days Tue 8/25/15 Fri 9/11/15 101

105  Rough in Sprinklers 21 days Tue 8/25/15 Tue 9/22/15 101

106  Install Backing 7 days Tue 8/25/15 Wed 9/2/15 101

107  Install Door Frames 2 days Tue 8/25/15 Wed 8/26/15 101

108  Frame in Ceilings  14 days Tue 8/25/15 Fri 9/11/15 101

109  Install Linear Diffusers 4 days Mon 9/14/15 Thu 9/17/15 108

110  Install Lighting 14 days Mon 9/14/15 Thu 10/1/15 108

111  Install All Low Voltage Wiring 7 days Mon 9/14/15 Tue 9/22/15 108

112  Install Life Safety 7 days Mon 9/14/15 Tue 9/22/15 108

113  Rough Inspections 2 days Fri 10/2/15 Mon 10/5/15 110

114

115  Finish Construction 138 days Fri 7/31/15 Tue 2/9/16

116  Sheetrock Walls and Ceiling 7 days Wed 9/23/15 Thu 10/1/15 112

117  Tape, Top & Finish Walls & Ceiling 14 days Fri 10/2/15 Wed 10/21/15 116

118  Finish Electrical 10 days Thu 10/22/15 Wed 11/4/15 117

119  Bathrooms  11 days Thu 10/22/15 Thu 11/5/15

120 Thickset 1 day Thu 10/22/15 Thu 10/22/15 117

121 Install Stone Floor 2 days Fri 10/23/15 Mon 10/26/15 120

122 Install Thinset Tile at Walls 4 days Tue 10/27/15 Fri 10/30/15 121

123  Install Finish Plumbing 3 days Mon 11/2/15 Wed 11/4/15 122

124  Install Mirrors 1 day Thu 11/5/15 Thu 11/5/15 123

125  Install Bathroom Accessories 1 day Thu 11/5/15 Thu 11/5/15 123

126 Main Entrance 47 days Tue 10/27/15 Wed 12/30/15

127 Measure for Stair Glazing  1 day Tue 10/27/15 Tue 10/27/15 121

128 Install Glass & Mirrors 5 days Wed 10/28/15 Tue 11/3/15 127

129 Install Entry Door Hardware 1 day Wed 11/4/15 Wed 11/4/15 128

6/18  Architect approves Stone Sample

5 days

11/23  Order Stone

21 days

6/11  Submit Carpet Sample

5 days

6/18  Architect approves Carpet Sample

5 days

6/1  Order Carpet

21 days

7/7 Demolition 

21 days

M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T WMay 24, '15 May 31, '15 Jun 7, '15 Jun 14, '15 Jun 21, '15 Jun 28, '15 Jul 5, '15 Jul 12, '15 Jul 19, '15 Jul 26, '15 Aug 2, '15 Aug 9, '15 Aug 16, '15 Aug 23, '15 Aug 30, '15 Sep 6, '15 Sep 13, '15 Sep 20, '15 Sep 27, '15 Oct 4, '15 Oct 11, '15 Oct 18, '15 Oct 25, '15 Nov 1, '15 Nov 8, '15 Nov 15, '15 Nov 22, '15 Nov 29, '15 Dec 6, '15 Dec 13, '15 Dec 20, '15 Dec 27, '15 Jan 3, '16 Jan 10, '16 Jan 17, '16 Jan 24, '16 Jan 31, '16 Feb 7, '16 Feb 14, '16 Feb 21, '

Task

Split

Milestone

Summary

Project Summary

External Tasks

External Milestone

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration‐only

Manual Summary Rollup

Manual Summary

Start‐only

Finish‐only

Deadline

Progress

Barney's New York ‐ San Francisco FlagshipFINE INTERIORS GROUP (BUILD GROUP)

SUBJECT TO CHANGE

Tue 4/14/15 Page 2

Project: Loro Piana Schedule 3.11Date: Tue 4/14/15

Page 34: Bg response to invitation to bid barneys 041415

ID Task Mode

Task Name Duration Start Finish Predecessors

130 Install Signage 4 days Fri 12/25/15 Wed 12/30/15 138

131 Main Entry Flooring 50 days Thu 10/22/15 Wed 12/30/15

132 Install Stone Floor  14 days Thu 10/22/15 Tue 11/10/15 117

133 Grout & Seal 5 days Tue 11/24/15 Mon 11/30/15 132

134 Install Carpet  5 days Thu 10/22/15 Wed 10/28/15 117

135  Install Millwork  21 days Tue 12/1/15 Tue 12/29/15

136  Install Perimeter Fixturing  15 days Tue 12/1/15 Mon 12/21/15 133

137  Painting 10 days Thu 10/22/15 Wed 11/4/15 117

138  Install Loose Fixturing  3 days Tue 12/22/15 Thu 12/24/15 136

139  Final Inspections  1 day Fri 12/25/15 Fri 12/25/15 138

140 TCO 1 day Wed 1/13/16 Wed 1/13/16 141

141 Punchlist 10 days Wed 12/30/15 Tue 1/12/16 142

142 Install Furniture 3 days Fri 12/25/15 Tue 12/29/15 138

143 Stock Store 10 days Thu 1/14/16 Wed 1/27/16 140

144 Train Personel 10 days Thu 1/28/16 Wed 2/10/16 143

145 Grand Opening 1 day Thu 2/11/16 Thu 2/11/16 144

146 TCO 1 day Wed 12/30/15Wed 12/30/15 142

147 Punchlist 10 days Wed 12/30/15 Tue 1/12/16 142

148 Install Furniture 5 days Wed 1/13/16 Tue 1/19/16 147

149 Stock Store 10 days Wed 1/20/16 Tue 2/2/16 148

150 Train Personel 5 days Wed 2/3/16 Tue 2/9/16 149

151 Grand Opening 0 days Tue 2/9/16 Tue 2/9/16 150

12/30 TCO

1 day

12/30 Punchlist

10 days

1/13 Install Furniture

5 days

1/20 Stock Store

10 days

2/3 Train Personel

5 days

2/9

M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T WMay 24, '15 May 31, '15 Jun 7, '15 Jun 14, '15 Jun 21, '15 Jun 28, '15 Jul 5, '15 Jul 12, '15 Jul 19, '15 Jul 26, '15 Aug 2, '15 Aug 9, '15 Aug 16, '15 Aug 23, '15 Aug 30, '15 Sep 6, '15 Sep 13, '15 Sep 20, '15 Sep 27, '15 Oct 4, '15 Oct 11, '15 Oct 18, '15 Oct 25, '15 Nov 1, '15 Nov 8, '15 Nov 15, '15 Nov 22, '15 Nov 29, '15 Dec 6, '15 Dec 13, '15 Dec 20, '15 Dec 27, '15 Jan 3, '16 Jan 10, '16 Jan 17, '16 Jan 24, '16 Jan 31, '16 Feb 7, '16 Feb 14, '16 Feb 21, '

Task

Split

Milestone

Summary

Project Summary

External Tasks

External Milestone

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration‐only

Manual Summary Rollup

Manual Summary

Start‐only

Finish‐only

Deadline

Progress

Barney's New York ‐ San Francisco FlagshipFINE INTERIORS GROUP (BUILD GROUP)

SUBJECT TO CHANGE

Tue 4/14/15 Page 3

Project: Loro Piana Schedule 3.11Date: Tue 4/14/15