Beyond Estimation TM
The Cost Reconciliation Tracker TM
Construction Cost Forecast
James Vermeulen, PQS, LEED AP – Co CEO
Blair Tennant, LEED AP – Project Manager
www.vermeulens.com
Toronto Boston Dallas Los Angeles
![Page 2: Beyond Estimation TM The Cost Reconciliation Tracker TM Construction Cost Forecast](https://reader035.fdocuments.in/reader035/viewer/2022062720/568134b4550346895d9bd326/html5/thumbnails/2.jpg)
2
Vermeulens is a Registered Provider with The American Institute of Architects Continuing Education Systems. Credit earned on completion of this program will be reported to CES Records for AIA members. Certificates of Completion for non-AIA members are available on request.
This program is registered with the AIA/CES for continuing professional education. As such, it does not include content that may be deemed or construed to be an approval or endorsement by the AIA of any material of construction or any method or manner of handling, using, distributing, or dealing in any material or product. Questions related to specific materials, methods, and services will be addressed at the conclusion of this presentation.
![Page 3: Beyond Estimation TM The Cost Reconciliation Tracker TM Construction Cost Forecast](https://reader035.fdocuments.in/reader035/viewer/2022062720/568134b4550346895d9bd326/html5/thumbnails/3.jpg)
3
Cost Reconciliation Tracker Present trends in median trade costs from January 2008 - Current
Quantify current cost reductions and provide future cost projections.
Construction Cost Inflation Understand historic trends in construction cost inflation
Where we were. Where we are. Where we are going.
Cost Drivers Examine the cost impact of: Volume, Commodities, Labor & Profit Margin
Economic Drivers Examine the cost impact of: Commodity Pricing, Equity Markets, Exchange Rates & Employment
LEARNING OBJECTIVES
![Page 4: Beyond Estimation TM The Cost Reconciliation Tracker TM Construction Cost Forecast](https://reader035.fdocuments.in/reader035/viewer/2022062720/568134b4550346895d9bd326/html5/thumbnails/4.jpg)
Where we were
4
![Page 5: Beyond Estimation TM The Cost Reconciliation Tracker TM Construction Cost Forecast](https://reader035.fdocuments.in/reader035/viewer/2022062720/568134b4550346895d9bd326/html5/thumbnails/5.jpg)
5
![Page 6: Beyond Estimation TM The Cost Reconciliation Tracker TM Construction Cost Forecast](https://reader035.fdocuments.in/reader035/viewer/2022062720/568134b4550346895d9bd326/html5/thumbnails/6.jpg)
6
![Page 7: Beyond Estimation TM The Cost Reconciliation Tracker TM Construction Cost Forecast](https://reader035.fdocuments.in/reader035/viewer/2022062720/568134b4550346895d9bd326/html5/thumbnails/7.jpg)
7
High/Low -4.1%
Low / Current +3.7%
Growth RatesQ3 09 +1.6%Q4 09 +4.9%Q1 10 +3.7%Q2 10 +1.7%Q3 10 +2.5%
![Page 8: Beyond Estimation TM The Cost Reconciliation Tracker TM Construction Cost Forecast](https://reader035.fdocuments.in/reader035/viewer/2022062720/568134b4550346895d9bd326/html5/thumbnails/8.jpg)
Cost Reconciliation Tracker TM
8
![Page 9: Beyond Estimation TM The Cost Reconciliation Tracker TM Construction Cost Forecast](https://reader035.fdocuments.in/reader035/viewer/2022062720/568134b4550346895d9bd326/html5/thumbnails/9.jpg)
9
Code Group VCC CM CM-VCC VCC CM CM-VCC
01 Allowances $1,156,805 $2,422,380 $1,265,575 $2,651,790 $2,672,730 $20,940
02 Site Work $2,636,810 $3,773,428 $1,136,618 $2,918,155 $2,882,279 ($35,876)
03 Concrete $5,840,270 $5,065,081 ($775,190) $5,065,361 $5,065,081 ($280)
04 Masonry $1,547,241 $1,767,385 $220,144 $1,615,526 $1,609,395 ($6,130)
05 Metals $17,945,452 $17,804,383 ($141,069) $15,675,089 $15,577,004 ($98,085)
06 Wood/Plastic $3,172,732 $3,831,671 $658,939 $3,694,276 $3,600,999 ($93,277)
07 Thermal/Moisture Protection $2,903,951 $3,046,873 $142,922 $3,099,398 $3,086,080 ($13,319)
08 Doors/Windows $17,219,666 $15,756,579 ($1,463,087) $15,214,307 $15,299,926 $85,619
09 Finishes $9,635,770 $9,399,224 ($236,546) $10,135,975 $10,137,758 $1,782
10 Specialties $1,335,983 $1,163,012 ($172,971) $1,410,825 $1,418,709 $7,884
11 Equipment $1,127,700 $1,852,358 $724,658 $1,692,000 $1,693,414 $1,414
12 Furnishings $784,846 $302,393 ($482,453) $559,342 $573,596 $14,255
13 Special Construction $300,000 $148,575 ($151,425) $150,000 $148,575 ($1,425)
14 Conveying Systems $4,858,875 $7,212,645 $2,353,770 $5,963,888 $5,993,138 $29,250
15 Mechanical $28,949,381 $35,232,816 $6,283,436 $29,127,187 $29,493,221 $366,034
16 Electrical $15,451,608 $16,700,277 $1,248,669 $16,476,313 $16,451,613 ($24,700)
17 Permits & Fees $19,075,543 $20,452,111 $1,376,568 $20,043,336 $20,051,467 $8,130
18 Contingencies $16,841,472 $14,102,030 ($2,739,443) $15,684,472 $15,697,176 $12,704
19 Enabling $22,704,456 $22,704,458 $2 $22,704,458 $22,704,458 $0
20 Total Construction Costs $173,488,558 $182,737,674 $9,249,116 $173,881,696 $174,156,616 $274,920
![Page 10: Beyond Estimation TM The Cost Reconciliation Tracker TM Construction Cost Forecast](https://reader035.fdocuments.in/reader035/viewer/2022062720/568134b4550346895d9bd326/html5/thumbnails/10.jpg)
10
115 Projects
![Page 11: Beyond Estimation TM The Cost Reconciliation Tracker TM Construction Cost Forecast](https://reader035.fdocuments.in/reader035/viewer/2022062720/568134b4550346895d9bd326/html5/thumbnails/11.jpg)
STRUCTURAL STEEL ($/TON)
11
$2,940 - $3,300 $3,260- $3,565
+9%
$180 Deviation
$3,120 Average
$150 Deviation
$3,410 Average
$2,785- $3,140
-13%
$2,965 Average
$2,410- $2,855
-11%
$2,635 Average
$2,385- $2,723
-1%
$2,610Average
$2,285- $2,530
$2,408Average
-9%
-29%
![Page 12: Beyond Estimation TM The Cost Reconciliation Tracker TM Construction Cost Forecast](https://reader035.fdocuments.in/reader035/viewer/2022062720/568134b4550346895d9bd326/html5/thumbnails/12.jpg)
CONCRETE SLAB ON DECK ($/SF)
12
$5.1 - $6.1
+2%
$5.1 - $6.3
-14%
$4.6 - $5.3
-8%
$4.3 - $4.8 $4.3 - $4.9
+3%
$4.5 - $5.3
-21%
+5%
![Page 13: Beyond Estimation TM The Cost Reconciliation Tracker TM Construction Cost Forecast](https://reader035.fdocuments.in/reader035/viewer/2022062720/568134b4550346895d9bd326/html5/thumbnails/13.jpg)
MASONRY - CMU ($/SF)
13
$16.0 - $17.9 $15.6 - $17.7 $14.7 - $16.7 $14.8 - $15.6 $12.8- $14.9 $15.8- $17.7
-18%
![Page 14: Beyond Estimation TM The Cost Reconciliation Tracker TM Construction Cost Forecast](https://reader035.fdocuments.in/reader035/viewer/2022062720/568134b4550346895d9bd326/html5/thumbnails/14.jpg)
ROOFING MEMBRANE ($/SF)
14
$13.2 - $16.5 $14.0 - $17.0 $14.8 - $16.9 $13.4 - $14.8
-11%
$12.7 - $15.0
-2% +8%
$13.2 - $15.1
+2%
-13%
![Page 15: Beyond Estimation TM The Cost Reconciliation Tracker TM Construction Cost Forecast](https://reader035.fdocuments.in/reader035/viewer/2022062720/568134b4550346895d9bd326/html5/thumbnails/15.jpg)
CURTAINWALL ($/SF)
15
$99- $118
+4%
$95- $114 $84- $101
-15%
$84- $96
-3%
$76- $88
-8%
$86- $96
+12%
-24%
![Page 16: Beyond Estimation TM The Cost Reconciliation Tracker TM Construction Cost Forecast](https://reader035.fdocuments.in/reader035/viewer/2022062720/568134b4550346895d9bd326/html5/thumbnails/16.jpg)
DRYWALL PARTITIONS ($/SF)
16
$7.1 - $8.2 $7.1- $7.9
-1%
$6.4- $7.4
-9%
$5.7- $6.8
-9%
$6.5- $7.2 +10%
$6.1- $6.8
-7%
-18%
![Page 17: Beyond Estimation TM The Cost Reconciliation Tracker TM Construction Cost Forecast](https://reader035.fdocuments.in/reader035/viewer/2022062720/568134b4550346895d9bd326/html5/thumbnails/17.jpg)
ELEVATORS ($/STOP)
17
$31,500 - $37,000
$58,000 - $70,000
![Page 18: Beyond Estimation TM The Cost Reconciliation Tracker TM Construction Cost Forecast](https://reader035.fdocuments.in/reader035/viewer/2022062720/568134b4550346895d9bd326/html5/thumbnails/18.jpg)
PLUMBING – BRANCH PIPE ($/LF)
18
$26- $29 $28 - $30
+4%
$26 - $29
-4%
$25 - $27
-5%
$24 - $25
-7%
$24 - $26
+4%
-16%
![Page 19: Beyond Estimation TM The Cost Reconciliation Tracker TM Construction Cost Forecast](https://reader035.fdocuments.in/reader035/viewer/2022062720/568134b4550346895d9bd326/html5/thumbnails/19.jpg)
DUCTWORK ($/LBS)
19
$7.4 - $8.4 $7.8 - $8.5
+3%
$7.0 - $7.9
-8%
$6.8 - $7.5
-4%
$7.1- $7.4
+1%
$7.0- $7.4
-1%
-12%
![Page 20: Beyond Estimation TM The Cost Reconciliation Tracker TM Construction Cost Forecast](https://reader035.fdocuments.in/reader035/viewer/2022062720/568134b4550346895d9bd326/html5/thumbnails/20.jpg)
CONTROLS ($/PT)
20
$1,130 - $1,270
+3%
$1,110 - $1,220 $1,000 - $1,110
-12%
$1,000 - $1,090
-1%
$970 - $1,050
-1%
$951 - $1,040
-5%
-17%
![Page 21: Beyond Estimation TM The Cost Reconciliation Tracker TM Construction Cost Forecast](https://reader035.fdocuments.in/reader035/viewer/2022062720/568134b4550346895d9bd326/html5/thumbnails/21.jpg)
ELECTRICAL FEEDER ($/LF)
21
$127 - $141
+6%
$114 - $139 $97 - $114
-21%
$93 - $112
-3%
$100 - $114
+4%
$96 - $105
-6%
-25%
![Page 22: Beyond Estimation TM The Cost Reconciliation Tracker TM Construction Cost Forecast](https://reader035.fdocuments.in/reader035/viewer/2022062720/568134b4550346895d9bd326/html5/thumbnails/22.jpg)
GENERAL REQUIREMENTS \ CONDITIONS
22
7.7% - 11.5% 7.4% - 11.2%
-3%
8.3% - 10.9%
+4%
8.3% - 9.7%
-6%
8.2% - 9.6%
-1%
8.4% - 11.3%
+12%
-10%
![Page 23: Beyond Estimation TM The Cost Reconciliation Tracker TM Construction Cost Forecast](https://reader035.fdocuments.in/reader035/viewer/2022062720/568134b4550346895d9bd326/html5/thumbnails/23.jpg)
GENERAL REQUIREMENTS \ CONDITIONS
23
1.4%
1.1%1.3% 1.3%
1.5%
1.0%
0.6%
![Page 24: Beyond Estimation TM The Cost Reconciliation Tracker TM Construction Cost Forecast](https://reader035.fdocuments.in/reader035/viewer/2022062720/568134b4550346895d9bd326/html5/thumbnails/24.jpg)
CONTRACTOR’S FEE (%DIRECTS)
24
2.8% - 3.4% 2.8% - 3.5%
+2%
2.6% - 3.3%
-6%
2.6% - 3.1%
-3%
2.4% - 3.1%
-4%
2.0% - 2.7%
-15%
-25%
![Page 25: Beyond Estimation TM The Cost Reconciliation Tracker TM Construction Cost Forecast](https://reader035.fdocuments.in/reader035/viewer/2022062720/568134b4550346895d9bd326/html5/thumbnails/25.jpg)
ESCALATION CONTINGENCY (% DIRECTS)
25
6% - 8%
![Page 26: Beyond Estimation TM The Cost Reconciliation Tracker TM Construction Cost Forecast](https://reader035.fdocuments.in/reader035/viewer/2022062720/568134b4550346895d9bd326/html5/thumbnails/26.jpg)
COST RECONCILIATION
TRACKER SUMMARY
26
![Page 27: Beyond Estimation TM The Cost Reconciliation Tracker TM Construction Cost Forecast](https://reader035.fdocuments.in/reader035/viewer/2022062720/568134b4550346895d9bd326/html5/thumbnails/27.jpg)
27
TRADE 2008 PEAK – BOTTOM 2010
Concrete -21%
Masonry -18%
Steel -29%
Roofing -13%
Curtainwall -24%
Drywall -18%
Plumbing -16%
Ductwork -12%
Controls -17%
Feeder -25%
GC’s & GR’s -10%
Contractor’s Fee -25%
TRADE SUMMARY
![Page 28: Beyond Estimation TM The Cost Reconciliation Tracker TM Construction Cost Forecast](https://reader035.fdocuments.in/reader035/viewer/2022062720/568134b4550346895d9bd326/html5/thumbnails/28.jpg)
28
TYPICAL INSTITUTIONAL PROJECT – DIRECT TRADE COST
CONSTRUCTION COST IMPACT
Assumes trade-weighted average of individual percentage trade reduction
Peak 2008 – Bottom 2010
-14%
![Page 29: Beyond Estimation TM The Cost Reconciliation Tracker TM Construction Cost Forecast](https://reader035.fdocuments.in/reader035/viewer/2022062720/568134b4550346895d9bd326/html5/thumbnails/29.jpg)
WHITING-TURNER CONTRACTING
29
Peak 2008 – Q3 2010
-13.2%
![Page 30: Beyond Estimation TM The Cost Reconciliation Tracker TM Construction Cost Forecast](https://reader035.fdocuments.in/reader035/viewer/2022062720/568134b4550346895d9bd326/html5/thumbnails/30.jpg)
30
BUDGET EXAMPLE
Q3 2008 - $100M
14% Escalation Q2 2010 - $114M
14% Market AdjQ2 2010 - $86M5%
Bids @
Cost
Q2 2010 - $82M
-25%
-5%
-28%
![Page 31: Beyond Estimation TM The Cost Reconciliation Tracker TM Construction Cost Forecast](https://reader035.fdocuments.in/reader035/viewer/2022062720/568134b4550346895d9bd326/html5/thumbnails/31.jpg)
31
Recession Bottom Growth
Design Contingency
Preliminary Design 10% - 15% same same
Schematic Design 6% - 9% same same
Design Development 3% - 6% same same
Contract Documents 0% - 3% same same
Construction Contingency 3% - 5% same same
Escalation Contingency negative zero 4% - 8%
Bidding Contingency -5% to 0% -5% to 0% 0% to +5%
Project Contingency (Owner) 15% - 10% 15% - 10% 10% - 5%
CONTINGENCY
![Page 32: Beyond Estimation TM The Cost Reconciliation Tracker TM Construction Cost Forecast](https://reader035.fdocuments.in/reader035/viewer/2022062720/568134b4550346895d9bd326/html5/thumbnails/32.jpg)
WHEN WILL
THE
WINDOW CLOSE ?
32
![Page 33: Beyond Estimation TM The Cost Reconciliation Tracker TM Construction Cost Forecast](https://reader035.fdocuments.in/reader035/viewer/2022062720/568134b4550346895d9bd326/html5/thumbnails/33.jpg)
33
COST DRIVERS
Volume
Commodity Pricing
Labor Productivity
Profit Margins
![Page 34: Beyond Estimation TM The Cost Reconciliation Tracker TM Construction Cost Forecast](https://reader035.fdocuments.in/reader035/viewer/2022062720/568134b4550346895d9bd326/html5/thumbnails/34.jpg)
34
• MaterialRaw Goods
• Markup Overhead, Equipment, Profit: (Manufacturer & Contractor)
STRUCTURAL STEEL PRICING
![Page 35: Beyond Estimation TM The Cost Reconciliation Tracker TM Construction Cost Forecast](https://reader035.fdocuments.in/reader035/viewer/2022062720/568134b4550346895d9bd326/html5/thumbnails/35.jpg)
35
US DOLLAR RISK HEDGE
High/Low -26%
Low / Mar 09 +18%
Mar09/Current -11%
![Page 36: Beyond Estimation TM The Cost Reconciliation Tracker TM Construction Cost Forecast](https://reader035.fdocuments.in/reader035/viewer/2022062720/568134b4550346895d9bd326/html5/thumbnails/36.jpg)
36
US DOLLAR RISK HEDGE
Low / High +123%
High / Mar 09 -58%
Mar09/Current +91%
![Page 37: Beyond Estimation TM The Cost Reconciliation Tracker TM Construction Cost Forecast](https://reader035.fdocuments.in/reader035/viewer/2022062720/568134b4550346895d9bd326/html5/thumbnails/37.jpg)
37
![Page 38: Beyond Estimation TM The Cost Reconciliation Tracker TM Construction Cost Forecast](https://reader035.fdocuments.in/reader035/viewer/2022062720/568134b4550346895d9bd326/html5/thumbnails/38.jpg)
38
US DOLLAR IMPACT ON COMMODITIES
Low/High +164%
High/ Mar 09 -56%
Mar09/Current +57%
![Page 39: Beyond Estimation TM The Cost Reconciliation Tracker TM Construction Cost Forecast](https://reader035.fdocuments.in/reader035/viewer/2022062720/568134b4550346895d9bd326/html5/thumbnails/39.jpg)
39
![Page 40: Beyond Estimation TM The Cost Reconciliation Tracker TM Construction Cost Forecast](https://reader035.fdocuments.in/reader035/viewer/2022062720/568134b4550346895d9bd326/html5/thumbnails/40.jpg)
40
![Page 41: Beyond Estimation TM The Cost Reconciliation Tracker TM Construction Cost Forecast](https://reader035.fdocuments.in/reader035/viewer/2022062720/568134b4550346895d9bd326/html5/thumbnails/41.jpg)
41
![Page 42: Beyond Estimation TM The Cost Reconciliation Tracker TM Construction Cost Forecast](https://reader035.fdocuments.in/reader035/viewer/2022062720/568134b4550346895d9bd326/html5/thumbnails/42.jpg)
42
![Page 43: Beyond Estimation TM The Cost Reconciliation Tracker TM Construction Cost Forecast](https://reader035.fdocuments.in/reader035/viewer/2022062720/568134b4550346895d9bd326/html5/thumbnails/43.jpg)
43
CONSTRUCTION EMPLOYMENT
High/Low Total – 6% Construction – 28%
Low/Current Total + 1% Construction +0.3%
![Page 44: Beyond Estimation TM The Cost Reconciliation Tracker TM Construction Cost Forecast](https://reader035.fdocuments.in/reader035/viewer/2022062720/568134b4550346895d9bd326/html5/thumbnails/44.jpg)
44
$140B Stimulus Package
CONSTRUCTION VOLUME
High/Low
Total –35% Infra –11% Res –66% Non Res –37%
Low/Current
Total +2% Infra +11% Res +6% Non Res +0.5%
![Page 45: Beyond Estimation TM The Cost Reconciliation Tracker TM Construction Cost Forecast](https://reader035.fdocuments.in/reader035/viewer/2022062720/568134b4550346895d9bd326/html5/thumbnails/45.jpg)
45
![Page 46: Beyond Estimation TM The Cost Reconciliation Tracker TM Construction Cost Forecast](https://reader035.fdocuments.in/reader035/viewer/2022062720/568134b4550346895d9bd326/html5/thumbnails/46.jpg)
46
CONSTRUCTION COST INDEX
Trendline Avg
W-T 3.5%ENR 3.0%Gov 2.6%
% Decline(Peak – Current)
W-T -11.6%Gov -4.9%ENR +2.5%
![Page 47: Beyond Estimation TM The Cost Reconciliation Tracker TM Construction Cost Forecast](https://reader035.fdocuments.in/reader035/viewer/2022062720/568134b4550346895d9bd326/html5/thumbnails/47.jpg)
47
![Page 48: Beyond Estimation TM The Cost Reconciliation Tracker TM Construction Cost Forecast](https://reader035.fdocuments.in/reader035/viewer/2022062720/568134b4550346895d9bd326/html5/thumbnails/48.jpg)
48
![Page 49: Beyond Estimation TM The Cost Reconciliation Tracker TM Construction Cost Forecast](https://reader035.fdocuments.in/reader035/viewer/2022062720/568134b4550346895d9bd326/html5/thumbnails/49.jpg)
49
![Page 50: Beyond Estimation TM The Cost Reconciliation Tracker TM Construction Cost Forecast](https://reader035.fdocuments.in/reader035/viewer/2022062720/568134b4550346895d9bd326/html5/thumbnails/50.jpg)
50
![Page 51: Beyond Estimation TM The Cost Reconciliation Tracker TM Construction Cost Forecast](https://reader035.fdocuments.in/reader035/viewer/2022062720/568134b4550346895d9bd326/html5/thumbnails/51.jpg)
51
![Page 52: Beyond Estimation TM The Cost Reconciliation Tracker TM Construction Cost Forecast](https://reader035.fdocuments.in/reader035/viewer/2022062720/568134b4550346895d9bd326/html5/thumbnails/52.jpg)
52
![Page 53: Beyond Estimation TM The Cost Reconciliation Tracker TM Construction Cost Forecast](https://reader035.fdocuments.in/reader035/viewer/2022062720/568134b4550346895d9bd326/html5/thumbnails/53.jpg)
53
Indicator Bottom Increase •Equities March 09 +91%
•Commodities March 09 +57%
•GDP Q2 09 + 4%
•Employment Dec 09 + 1 %
•Non Res Volume Oct 10 +0.5%
Economic Summary
![Page 54: Beyond Estimation TM The Cost Reconciliation Tracker TM Construction Cost Forecast](https://reader035.fdocuments.in/reader035/viewer/2022062720/568134b4550346895d9bd326/html5/thumbnails/54.jpg)
54
COST DRIVERS
Volume
Commodity Pricing
Labor Productivity
Profit Margins
2009 2010 2011
![Page 55: Beyond Estimation TM The Cost Reconciliation Tracker TM Construction Cost Forecast](https://reader035.fdocuments.in/reader035/viewer/2022062720/568134b4550346895d9bd326/html5/thumbnails/55.jpg)
55
![Page 56: Beyond Estimation TM The Cost Reconciliation Tracker TM Construction Cost Forecast](https://reader035.fdocuments.in/reader035/viewer/2022062720/568134b4550346895d9bd326/html5/thumbnails/56.jpg)
56
•Peak 2008 to Bottom 2010: -14.0%
•1st Half 2011: + 2.0% + 1.0% + 0.0%•2nd Half 2011: + 2.5% + 1.5% + 0.5%
Cost Outlook
High
VolumeModerate
Volume Low
Volume
![Page 57: Beyond Estimation TM The Cost Reconciliation Tracker TM Construction Cost Forecast](https://reader035.fdocuments.in/reader035/viewer/2022062720/568134b4550346895d9bd326/html5/thumbnails/57.jpg)
57
1. Major Economic Indicators have bottomed.
2. Construction Prices are bottoming.
3. Cost Escalation must be factored into construction budgets moving forward.
Summary
![Page 58: Beyond Estimation TM The Cost Reconciliation Tracker TM Construction Cost Forecast](https://reader035.fdocuments.in/reader035/viewer/2022062720/568134b4550346895d9bd326/html5/thumbnails/58.jpg)
58
•CM Selection Must Have Full Estimate and Schedules
•Negotiate GMP Post Bid Buyout
•Continue Design & Preconstruction
•Watch Equity Markets for Sustained Rebound
Recommendations
![Page 59: Beyond Estimation TM The Cost Reconciliation Tracker TM Construction Cost Forecast](https://reader035.fdocuments.in/reader035/viewer/2022062720/568134b4550346895d9bd326/html5/thumbnails/59.jpg)
59
•Track Record
•Project Volume & Benchmarking
•Consensus Approach in Reconciliation
•The Reconciliation Tracker
•Conceptual Estimating
•Brand
•Trusted Advisor
Why Vermeulens